PROJECT

PLANNING
TECHNIQUES

EXAMPLES:
Satellite
Project

Parviz F. Rad
Vittal Anantatmula
MGT 270 Directed Computation John Hood

Section 1
WBS Level 3 Resources and Costs (1 of 2)
Total
Total
Total Effort Resource Total Total Effort Resource Resource Materials Total WBS
Duration Tools & Machinery Duration Tools & Materials & Installed Total Effort
WBS Element Labor Resource Intensity (Intensity X Cost/ Labor Intensity (Intensity X Cost/ Intensity Duration Cost/ & Installed Element
(Hours) Resource (Hours) Machinery Equipment (Intensity X Duration)
Duration) Unit Cost Duration) Unit Unit Equipment Cost
Cost
Cost
1.0 Lightweight Communications Satellite Project Total Project Cost 46,167,965
1.1 Project Management Total Cost for 1.1 Project Management 34,203,980
1.1.1 Project Management Total Labor Resource Cost for 1.1.1 750,140 Total Tools & Machinery Resource Cost for 1.1.1 0 Total Materials & Installed Equipment Resource Cost for 1.1.1 0 750,140
1.1.1.1 Project Plan General Manager / Group Director 1 20 20 worker-hrs 200 4,000 4,000
Division Director 1 20 20 worker-hrs 170 3,400 3,400
Business Manager 1 20 20 worker-hrs 120 2,400 2,400
Program Manager 1 20 20 worker-hrs 165 3,300 3,300
Project Manager 1 192 192 worker-hrs 160 30,720 30,720
Software Manager 1 96 96 worker-hrs 150 14,400 14,400
Administrative Assistant 1 176 176 worker-hrs 30 5,280 5,280
Chief Systems Engineer 1 96 96 worker-hrs 160 15,360 15,360
1.1.1.2 Risk Management Project Manager 1 96 96 worker-hrs 160 15,360 15,360
Plan Chief Systems Engineer 1 48 48 worker-hrs 160 7,680 7,680
Administrative Assistant 1 80 80 worker-hrs 30 2,400 2,400
Software Manager 1 48 48 worker-hrs 150 7,200 7,200
1.1.1.3 Configuration Configuration Manager 1 96 96 worker-hrs 125 12,000 12,000
Control Plan Software Manager 1 96 96 worker-hrs 150 14,400 14,400
Administrative Assistant 1 80 80 worker-hrs 30 2,400 2,400
Systems Engineer 1 96 96 worker-hrs 140 13,440 13,440
1.1.1.4 Spacecraft Sell-Off Program Manager 1 600 600 worker-hrs 165 99,000 99,000
Report Project Manager 1 960 960 worker-hrs 160 153,600 153,600
Software Manager 1 300 300 worker-hrs 150 45,000 45,000
Chief Systems Engineer 1 600 600 worker-hrs 160 96,000 96,000
Factory Supervisor 1 300 300 worker-hrs 120 36,000 36,000
Test Engineer 1 1200 1200 worker-hrs 110 132,000 132,000
Administrative Assistant 1 1160 1160 worker-hrs 30 34,800 34,800
1.1.2 Systems Engineering Total Labor Resource Cost for 1.1.2 4,577,280 Total Tools & Machinery Resource Cost for 1.1.2 0 Total Materials & Installed Equipment Resource Cost for 1.1.2 0 4,577,280
1.1.2.1 Systems Engineering Project Manager 1 96 96 worker-hrs 160 15,360 15,360
Plan Chief Systems Engineer 1 192 192 worker-hrs 160 30,720 30,720
Administrative Assistant 1 176 176 worker-hrs 30 5,280 5,280
Software Manager 1 192 192 worker-hrs 150 28,800 28,800
1.1.2.2 Requirements Chief Systems Engineer 1 96 96 worker-hrs 160 15,360 15,360
Verification Plan Systems Engineer 1 192 192 worker-hrs 140 26,880 26,880
Project Manager 1 160 160 worker-hrs 160 25,600 25,600
Software Engineer 2 192 384 worker-hrs 130 49,920 49,920
Administrative Assistant 1 176 176 worker-hrs 30 5,280 5,280
1.1.2.3 Spacecraft Analysis Development Engineer 7 1152 8064 worker-hrs 120 967,680 967,680
& Design Reports Software Engineer 6 1152 6912 worker-hrs 130 898,560 898,560
Quality Assurance Engineer 1 576 576 worker-hrs 60 34,560 34,560
Systems Engineer 1 1120 1120 worker-hrs 140 156,800 156,800
Administrative Assistant 2 1120 2240 worker-hrs 30 67,200 67,200
1.1.2.4 Interface Control Configuration Manager 1 384 384 worker-hrs 125 48,000 48,000
Document Software Manager 1 384 384 worker-hrs 150 57,600 57,600
Systems Engineer 1 384 384 worker-hrs 140 53,760 53,760
Administrative Assistant 2 320 640 worker-hrs 30 19,200 19,200
1.1.2.5 Subsystem Development Engineer 6 576 3456 worker-hrs 120 414,720 414,720
Specifications Software Engineer 6 576 3456 worker-hrs 130 449,280 449,280
Administrative Assistant 2 560 1120 worker-hrs 30 33,600 33,600
1.1.2.6 Spacecraft Senior Manufacturing Technician 1 192 192 worker-hrs 100 19,200 19,200
Manufacturing Quality Assurance Engineer 1 96 96 worker-hrs 60 5,760 5,760
Plan Safety Director 1 96 96 worker-hrs 80 7,680 7,680
Administrative Assistant 2 160 320 worker-hrs 30 9,600 9,600
1.1.2.7 Parts, Materials, Supply Chain Manager 1 192 192 worker-hrs 80 15,360 15,360
& Processes Plan Safety Director 1 144 144 worker-hrs 80 11,520 11,520
Configuration Manager 1 192 192 worker-hrs 125 24,000 24,000
Administrative Assistant 2 160 320 worker-hrs 30 9,600 9,600
1.1.2.8 Layouts & Drawings Development Engineer 7 960 6720 worker-hrs 120 806,400 806,400
Systems Engineer 1 960 960 worker-hrs 140 134,400 134,400
Project Manager 1 480 480 worker-hrs 160 76,800 76,800
Administrative Assistant 2 880 1760 worker-hrs 30 52,800 52,800
1.1.3 Integration & Test Total Labor Resource Cost for 1.1.3 3,810,560 Total Tools & Machinery Resource Cost for 1.1.3 4,706,000 Total Materials & Installed Equipment Resource Cost for 1.1.3 20,360,000 28,876,560
1.1.3.1 Spacecraft Safety Director 1 240 240 worker-hrs 80 19,200 19,200
Integration & Test Systems Engineer 1 192 192 worker-hrs 140 26,880 26,880
Plan Test Engineer 4 960 3840 worker-hrs 110 422,400 422,400
1.1.3.2 Subsystem Test Safety Director 1 112 112 worker-hrs 80 8,960 8,960
Plans Development Engineer 2 160 320 worker-hrs 120 38,400 38,400
Test Engineer 4 192 768 worker-hrs 110 84,480 84,480
1.1.3.3 Subsystem Test Development Engineer 6 440 2640 worker-hrs 120 316,800 Unit & Subsystem Test Equipment 9 440 3960 equipment-hrs 550 2,178,000 Class 10,000 Clean Room 1 464 464 room-hrs 5000 2320000 4,814,800
Reports Test Engineer 5 480 2400 worker-hrs 110 264,000 Test Stand Set 2 440 880 equipment-hrs 100 88,000 Class 100,000 Clean Room 1 440 440 room-hrs 1000 440000 792,000
Test Technician 8 400 3200 worker-hrs 80 256,000 Calibration Equipment Set 4 440 1760 equipment-hrs 200 352,000 608,000
1.1.3.4 Spacecraft Test Factory Supervisor 1 300 300 worker-hrs 120 36,000 Vehicle Test Equipment 1 1160 1160 equipment-hrs 1000 1,160,000 Thermal Vacuum Chamber 1 400 400 chamber-hrs 20000 8000000 9,196,000
Reports Development Engineer 6 1184 7104 worker-hrs 120 852,480 Calibration Equipment Set 4 1160 4640 equipment-hrs 200 928,000 Acoustic Chamber 1 80 80 chamber-hrs 15000 1200000 2,980,480
Test Engineer 5 1200 6000 worker-hrs 110 660,000 Anechoic Chamber 1 160 160 chamber-hrs 50000 8000000 8,660,000
Test Technician 8 1184 9472 worker-hrs 80 757,760 Class 100,000 Clean Room 1 400 400 room-hrs 1000 400000 1,157,760
Administrative Assistant 2 1120 2240 worker-hrs 30 67,200 67,200

3
MGT 270 Directed Computation John Hood

WBS Level 3 Resources and Costs (2 of 2)


Total
Total
Total Effort Resource Total Total Effort Resource Resource Materials Total WBS
Duration Tools & Machinery Duration Tools & Materials & Installed Total Effort
WBS Element Labor Resource Intensity (Intensity X Cost/ Labor Intensity (Intensity X Cost/ Intensity Duration Cost/ & Installed Element
(Hours) Resource (Hours) Machinery Equipment (Intensity X Duration)
Duration) Unit Cost Duration) Unit Unit Equipment Cost
Cost
Cost
1.2 Spacecraft Payload Total Cost for 1.2 Spacecraft Payload 6,195,080
1.2.1 Payload Electronics Total Labor Resource Cost for 1.2.1 140,160 Total Tools & Machinery Resource Cost for 1.2.1 264,000 Total Materials & Installed Equipment Resource Cost for 1.2.1 3,947,600 4,351,760
1.2.1.1 Transmitters Senior Manufacturing Technician 2 96 192 worker-hrs 100 19,200 Unit & Subsystem Test Equipment 1 96 96 equipment-hrs 550 52,800 Transmitter Unit Slices 20 - 20 transmitter unit slices 70000 1,400,000 1,472,000
Electrical Unit Attachment Kits 4 - 4 unit attachment kits 500 2,000 2,000
Electrical Unit Cases 4 - 4 electrical unit cases 500 2,000 2,000
1.2.1.2 Receivers Senior Manufacturing Technician 2 96 192 worker-hrs 100 19,200 Unit & Subsystem Test Equipment 1 96 96 equipment-hrs 550 52,800 Receiver Unit Slices 16 - 16 receiver unit slices 46000 736,000 808,000
Electrical Unit Attachment Kits 4 - 4 unit attachment kits 500 2,000 2,000
Electrical Unit Cases 4 - 4 electrical unit cases 500 2,000 2,000
1.2.1.3 Payload Processor Senior Manufacturing Technician 2 192 384 worker-hrs 100 38,400 Unit & Subsystem Test Equipment 1 192 192 equipment-hrs 550 105,600 Communication Processors 2 - 2 processors 350000 700,000 844,000
Software Engineer 2 192 384 worker-hrs 130 49,920 Integrated Circuit Board 4 - 4 board-square feet 25000 100,000 149,920
Electrical Unit Attachment Kits 2 - 2 unit attachment kits 500 1,000 1,000
Electrical Unit Cases 2 - 2 electrical unit cases 500 1,000 1,000
1.2.1.4 Transmit & Receive Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Test Equipment 1 96 96 equipment-hrs 550 52,800 Reflectors 4 - 4 reflectors 100000 400,000 466,240
Antennas Sub-Reflectors & Feeds 8 - 8 sub-reflectors & feeds 75000 600,000 600,000
Transmitter & Receiver Cables 8 - 8 cable-feet 200 1,600 1,600
1.2.2 Data Handling Electronics Total Labor Resource Cost for 1.2.2 89,920 Total Tools & Machinery Resource Cost for 1.2.2 70,400 Total Materials & Installed Equipment Resource Cost for 1.2.2 1,683,000 1,843,320
1.2.2.1 Data Storage Device Senior Manufacturing Technician 3 80 240 worker-hrs 100 24,000 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 Data Storage Memory Slices 8 - 8 memory slices 180000 1,440,000 1,499,200
Software Engineer 2 96 192 worker-hrs 130 24,960 Electrical Unit Cases 2 - 2 electrical unit cases 500 1,000 25,960
Electrical Unit Attachment Kits 2 - 2 unit attachment kits 500 1,000 1,000
1.2.2.2 Data Encryption Senior Manufacturing Technician 2 80 160 worker-hrs 100 16,000 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 Encryption Devices 2 - 2 devices 40000 80,000 131,200
Device Software Engineer 2 96 192 worker-hrs 130 24,960 Encryption Keys 4 - 4 encryption keys 40000 160,000 184,960
Electrical Unit Attachment Kits 2 - 2 unit attachment kits 500 1,000 1,000
1.3 Spacecraft Bus Total Cost for 1.3 Spacecraft Bus 5,768,905
1.3.1 Structures Subsystem Total Labor Resource Cost for 1.3.1 60,480 Total Tools & Machinery Resource Cost for 1.3.1 37,800 Total Materials & Installed Equipment Resource Cost for 1.3.1 43,000 141,280
1.3.1.1 Primary Bus Manufacturing Technician 5 96 480 worker-hrs 70 33,600 Vehicle Integration Fixture 1 88 88 fixture-hours 50 4,400 Pre-Fab Structure 200 - 200 structure-pounds 100 20000 58,000
Structure Composite Curing Equipment 1 20 20 equipment-hrs 1000 20,000 Carbon Matrix Composites 20 - 20 composites-square feet 500 10000 30,000
1.3.1.2 Secondary Bus Manufacturing Technician 4 96 384 worker-hrs 70 26,880 Vehicle Integration Fixture 1 88 88 fixture-hours 50 4,400 Pre-Fab Structure 50 - 50 structure-pounds 100 5000 36,280
Structure Metal Fabrication Equipment 1 18 18 equipment-hrs 500 9,000 Aluminum Sheet Metal 40 - 40 aluminum-square feet 200 8000 17,000
1.3.2 Guidance, Navigation, & Control Subsystem Total Labor Resource Cost for 1.3.2 142,720 Total Tools & Machinery Resource Cost for 1.3.2 158,400 Total Materials & Installed Equipment Resource Cost for 1.3.2 1,050,200 1,351,320
1.3.2.1 Spacecraft Control Senior Manufacturing Technician 1 160 160 worker-hrs 100 16,000 Unit & Subsystem Test Equipment 1 160 160 equipment-hrs 550 88,000 Guidance & Navigation Processor 2 - 2 processors 275000 550000 654,000
Processor Software Engineer 4 192 768 worker-hrs 130 99,840 Integrated Circuit Board 2 - 2 board-square feet 25000 50000 149,840
Electrical Unit Attachment Kits 1 - 1 unit attachment kits 500 500 500
Electrical Unit Cases 1 - 1 electrical unit cases 500 500 500
1.3.2.2 Magnetometers Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 Magnetometer Magnet Kits 4 - 4 magnetometer kits 74500 298000 346,640
GNC Sensor Attachment Kit 2 - 2 sensor attachment kit 175 350 350
Magnetometer Cases 2 - 2 magnetometer cases 500 1000 1,000
1.3.2.3 Sun Sensor Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 Sun Sensors 2 - 2 sensors 70000 140000 188,640
Sun Sensor Electronics 2 - 2 sensor electronics 4000 8000 8,000
GNC Sensor Attachment Kit 2 - 2 sensor attachment kit 175 350 350
Sun Sensor Case 2 - 2 sensor cases 750 1500 1,500
1.3.3 Thermal Control Subsystem Total Labor Resource Cost for 1.3.3 53,760 Total Tools & Machinery Resource Cost for 1.3.3 8,800 Total Materials & Installed Equipment Resource Cost for 1.3.3 340,340 402,900
1.3.3.1 Blankets Manufacturing Technician 4 96 384 worker-hrs 70 26,880 Vehicle Integration Fixture 1 88 88 fixture-hours 50 4,400 Thermal Blankets 32 - 32 blanket-square feet 550 17600 48,880
Blanket Support Structure 40 - 40 structure-square feet 200 8000 8,000
Blanket Adhesive 34 - 34 adhesive-square feet 10 340 340
Heaters & Switches 40 - 40 heaters & switches 250 10000 10,000
1.3.3.2 Radiators Manufacturing Technician 4 96 384 worker-hrs 70 26,880 Vehicle Integration Fixture 1 88 88 fixture-hours 50 4,400 Radiator Quartz Mirror Material 50 - 50 quartz-square feet 5000 250000 281,280
Radiator Backing Structure 54 54 structure-square feet 1000 54000 54,000
Radiator Attachment Kit 2 - 2 radiator attachment kit 200 400 400
1.3.4 Electrical Power Subsystem Total Labor Resource Cost for 1.3.4 209,280 Total Tools & Machinery Resource Cost for 1.3.4 114,400 Total Materials & Installed Equipment Resource Cost for 1.3.4 3,136,825 3,460,505
1.3.4.1 Solar Arrays Manufacturing Technician 8 192 1536 worker-hrs 70 107,520 Unit & Subsystem Test Equipment 1 80 80 equipment-hrs 550 44,000 Dual Junction Solar Cells 500 - 500 solar cells 150 75,000 226,520
worker-hrs Solar Array Backing Structure 250 - 250 structure-square feet 100 25,000 25,000
Solar Cell Adhesive 275 - 275 adhesive-square feet 15 4,125 4,125
Solar Cell Cover Glass 260 - 260 glass-square feet 20 5,200 5,200
Titanium Material 20 - 20 titanium-pounds 1500 30,000 30,000
1.3.4.2 Battery Senior Manufacturing Technician 2 192 384 worker-hrs 100 38,400 Unit & Subsystem Test Equipment 1 96 96 equipment-hrs 550 52,800 Medium Capacity Battery Cells 32 - 32 battery cells 50000 1,600,000 1,691,200
Battery Cell Thermal Sleeves 32 - 32 thermal sleeves 10000 320,000 320,000
Wiring Harness 30 - 30 harness-feet 150 4,500 4,500
1.3.4.3 Power Electronics Senior Manufacturing Technician 4 96 384 worker-hrs 100 38,400 Unit & Subsystem Test Equipment 1 32 32 equipment-hrs 550 17,600 Power Management Processor 2 - 2 processors 175000 350,000 406,000
& Wiring Harness Software Engineer 2 96 192 worker-hrs 130 24,960 Power Distribution Unit Slices 32 - 32 power unit slices 20000 640,000 664,960
Electrical Unit Cases 8 - 8 electrical unit cases 500 4,000 4,000
Electrical Unit Attachment Kits 8 - 8 unit attachment kits 500 4,000 4,000
Wiring Harness 500 - 500 harness-feet 150 75,000 75,000
1.3.5 Telemetry & Command Subsystem Total Labor Resource Cost for 1.3.5 45,120 Total Tools & Machinery Resource Cost for 1.3.5 70,400 Total Materials & Installed Equipment Resource Cost for 1.3.5 182,100 297,620
1.3.5.1 Omni Antennas Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 Omni Antennas 2 - 2 antennas 25000 50000 98,640
Wiring Harness 6 - 6 harness-feet 150 900 900
1.3.5.2 Telemetry & Senior Manufacturing Technician 2 96 192 worker-hrs 100 19,200 Unit & Subsystem Test Equipment 1 64 64 equipment-hrs 550 35,200 T&C Transmitter slices 8 - 8 transmitter slices 10000 80000 134,400
Command Electronics Software Engineer 1 96 96 worker-hrs 130 12,480 Transmitter & Receiver Cables 6 - 6 cable-feet 200 1200 13,680
Electrical Unit Attachment Kits 4 - 4 unit attachment kits 500 2000 2,000
T&C Receiver Slices 8 - 8 receiver slices 6000 48000 48,000
1.3.6 Propulsion Subsystem Total Labor Resource Cost for 1.3.6 26,880 Total Tools & Machinery Resource Cost for 1.3.6 4,000 Total Materials & Installed Equipment Resource Cost for 1.3.6 84,400 115,280
1.3.6.1 Thrusters Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Fixtures 1 80 80 fixture-hours 25 2,000 Small Thrusters 4 - 4 thrusters 5000 20,000 35,440
Thruster Pressure Sensors 8 - 8 pressure sensors 50 400 400
Thruster Catalyst 2 - 2 catalyst-cubic feet 1000 2,000 2,000
1.3.6.2 Propellant & Manufacturing Technician 2 96 192 worker-hrs 70 13,440 Unit & Subsystem Fixtures 1 80 80 fixture-hours 25 2,000 Propellant Tanks 40 - 40 tank-cubic feet 500 20,000 35,440
Pressurant Tanks Propellant Tank Baffles 4 - 4 tank baffles 100 400 400
Pressurant Tank 8 - 8 tank-cubic feet 200 1,600 1,600
Lines, Valves, & Filters 8 - 8 lines, valves, & filters 5000 40,000 40,000

4
MGT 270 Directed Computation John Hood

Section 2
WBS Level 2 Resources and Costs (1 of 2)

Total Tools Total Total Total


Total Total Effort Resource Total Total Effort Resource Resource Total WBS
Tools & Machinery & Tools & Materials & Installed Materials & Total Effort Materials &
WBS Element Labor Resource Labor (Intensity X Cost/ Labor (Intensity X Cost/ Cost/ Element
Resource Machinery Machinery Equipment Equipment (Intensity X Duration) Equipment
Resource Duration) Unit Cost Duration) Unit Unit Costs
Resource Cost Resource Cost

1.0 Lightweight Communications Satellite Project Total Project Cost 46,167,965


1.1 Project Management Total Labor Resource Cost for 1.1 9,137,980 Total Tools & Machinery Resource Cost for 1.1 4,706,000 Total Materials & Installed Equipment Resource Cost for 1.1 20,360,000 34,203,980
1.1.1 Project Management Total Labor Resource Cost for 1.1.1 750,140 Total Tools & Machinery Resource Cost for 1.1.1 0 Total Materials & Installed Equipment Resource Cost for 1.1.1 0 750,140
Management Staff
General Manager/Group Director 1 20 worker-hrs 200 4,000
Division Director 1 20 worker-hrs 170 3,400
Business Manager 1 20 worker-hrs 120 2,400
Program Manager 1 620 worker-hrs 165 102,300
Project Manager 1 1248 worker-hrs 160 199,680
Software Manager 1 540 worker-hrs 150 81,000
Configuration Manager 1 96 worker-hrs 125 12,000
Analysis, Engineering, & Test Staff
Chief Systems Engineer 1 744 worker-hrs 160 119,040
Systems Engineer 1 96 worker-hrs 140 13,440
Test Engineer 1 1200 worker-hrs 110 132,000
Manufacturing Staff
Factory Supervisor 1 300 worker-hrs 120 36,000
Administrative Support Staff
Administrative Assistant 1 1496 worker-hrs 30 44,880
1.1.2 Systems Engineering Total Labor Resource Cost for 1.1.2 4,577,280 Total Tools & Machinery Resource Cost for 1.1.2 0 Total Materials & Installed Equipment Resource Cost for 1.1.2 0 4,577,280
Management Staff
Project Manager 1 736 worker-hrs 160 117,760
Software Manager 1 576 worker-hrs 150 86,400
Configuration Manager 1 576 worker-hrs 125 72,000
Supply Chain Manager 1 192 worker-hrs 80 15,360
Analysis, Engineering, & Test Staff
Chief Systems Engineer 1 288 worker-hrs 160 46,080
Systems Engineer 2 2656 worker-hrs 140 371,840
Development Engineer 1 18240 worker-hrs 120 2,188,800
Software Engineer 8 10752 worker-hrs 130 1,397,760
Manufacturing Staff
Senior Manufacturing Technician 1 192 worker-hrs 100 19,200
Administrative Support Staff
Administrative Assistant 2 6752 worker-hrs 30 202,560
Quality Assurance Engineer 1 672 worker-hrs 60 40,320
Safety Director 2 240 worker-hrs 80 19,200
1.1.3 Integration & Test Total Labor Resource Cost for 1.1.3 3,810,560 Total Tools & Machinery Resource Cost for 1.1.3 4,706,000 Total Materials & Installed Equipment Resource Cost for 1.1.3 20,360,000 28,876,560
Analysis, Engineering, & Test Staff Lab Equipment Installed Equipment
Systems Engineer 1 192 worker-hrs 140 26,880 Test Stand Set 2 880 equipment-hrs 100 88,000 Thermal Vacuum Chamber 1 400 chamber-hrs 20000 8,000,000
Development Engineer 6 10064 worker-hrs 120 1,207,680 Unit & Subsystem Test Equipment 1 3960 equipment-hrs 550 2,178,000 Acoustic Chamber 1 80 chamber-hrs 15000 1,200,000
Test Engineer 5 13008 worker-hrs 110 1,430,880 Calibration Equipment Set 1 6400 equipment-hrs 200 1,280,000 Anechoic Chamber 1 160 chamber-hrs 50000 8,000,000
Test Technician 8 12672 worker-hrs 80 1,013,760 Satellite Factory Equipment Class 100,000 Clean Room 1 840 room-hrs 1000 840,000
Manufacturing Staff Vehicle Test Equipment 1 1160 equipment-hrs 1000 1,160,000 Class 10,000 Clean Room 1 464 room-hrs 5000 2,320,000
Factory Supervisor 1 300 worker-hrs 120 36,000
Administrative Support Staff
Adminstrative Assistant 2 2240 worker-hrs 30 67,200
Safety Director 1 352 worker-hrs 80 28,160
1.2 Spacecraft Payload Total Labor Resource Cost for 1.2 230,080 Total Tools & Machinery Resource Cost for 1.2 334,400 Total Materials & Installed Equipment Resource Cost for 1.2 5,630,600 6,195,080
1.2.1 Payload Electronics Total Labor Resource Cost for 1.2.1 140,160 Total Tools & Machinery Resource Cost for 1.2.1 264,000 Total Materials & Installed Equipment Resource Cost for 1.2.1 3,947,600 4,351,760
Analysis, Engineering, & Test Staff Lab Equipment Electrical Power Components
Software Engineer 2 384 worker-hrs 130 49,920 Unit & Subsystem Test Equipment 3 480 equipment-hrs 550 264,000 Electrical Unit Cases - 10 electrical unit cases 500 5,000
Manufacturing Staff Electrical Unit Attachment Kits - 10 unit attachment kits 500 5,000
Senior Manufacturing Technician 4 768 worker-hrs 100 76,800 Integrated Circuit Board - 4 board-square feet 25000 100,000
Manufacturing Technician 2 192 worker-hrs 70 13,440 Communications Components
Transmitter Unit Slices - 20 transmitter unit slices 70000 1,400,000
Receiver Unit Slices - 16 receiver unit slices 46000 736,000
Reflectors - 4 reflectors 100000 400,000
Sub-Reflectors & Feeds - 8 sub-reflectors & feeds 75000 600,000
Communications Processor - 2 processors 350000 700,000
Transmitter & Receiver Cables - 8 cable-feet 200 1,600
1.2.2 Data Handling Electronics Total Labor Resource Cost for 1.2.2 89,920 Total Tools & Machinery Resource Cost for 1.2.2 70,400 Total Materials & Installed Equipment Resource Cost for 1.2.2 1,683,000 1,843,320
Analysis, Engineering, & Test Staff Lab Equipment Electrical Power Components
Software Engineer 2 384 worker-hrs 130 49,920 Unit & Subsystem Test Equipment 1 128 equipment-hrs 550 70,400 Electrical Unit Cases - 2 electrical unit cases 500 1,000
Manufacturing Staff Electrical Unit Attachment Kits - 4 unit attachment kits 500 2,000
Senior Manufacturing Technician 3 400 worker-hrs 100 40,000 Communications Components
Encryption Devices - 2 devices 40000 80,000
Encryption Keys - 4 encryption keys 40000 160,000
Data Storage Memory Slices - 8 memory slices 180000 1,440,000

5
MGT 270 Directed Computation John Hood

WBS Level 2 Resources and Costs (2 of 2)

Total Tools Total Total Total


Total Total Effort Resource Total Total Effort Resource Resource Total WBS
Tools & Machinery & Tools & Materials & Installed Materials & Total Effort Materials &
WBS Element Labor Resource Labor (Intensity X Cost/ Labor (Intensity X Cost/ Cost/ Element
Resource Machinery Machinery Equipment Equipment (Intensity X Duration) Equipment
Resource Duration) Unit Cost Duration) Unit Unit Costs
Resource Cost Resource Cost

1.3 Spacecraft Bus Total Labor Resource Cost for 1.2 538,240 Total Tools & Machinery Resource Cost for 1.3 393,800 Total Materials & Installed Equipment Resource Cost for 1.3 4,836,865 5,768,905
1.3.1 Structures Subsystem Total Labor Resource Cost for 1.3.1 60,480 Total Tools & Machinery Resource Cost for 1.3.1 37,800 Total Materials & Installed Equipment Resource Cost for 1.3.1 43,000 141,280
Manufacturing Staff Satellite Factory Equipment Spacecraft Structual Materials
Manufacturing Technician 5 864 worker-hrs 70 60,480 Vehicle Integration Fixture 1 176 fixture-hrs 50 8,800 Pre-Fab Structure - 250 structure-pounds 100 25,000
Composite Curing Equipment 1 20 equipment-hrs 1000 20,000 Carbon Matrix Composites - 20 composites-square feet 500 10,000
Metal Fabrication Equipment 1 18 equipment-hrs 500 9,000 Aluminum Sheet Metal - 40 aluminum-square feet 200 8,000
1.3.2 Guidance, Navigation, & Control Subsystem
Total Labor Resource Cost for 1.3.2 142,720 Total Tools & Machinery Resource Cost for 1.3.2 158,400 Total Materials & Installed Equipment Resource Cost for 1.3.2 1,050,200 1,351,320
Analysis, Engineering, & Test Staff Lab Equipment Guidance, Navigation & Control Components
Software Engineer 4 768 worker-hrs 130 99,840 Unit & Subsystem Test Equipment 2 288 equipment-hrs 550 158,400 Sun Sensor Case - 2 sensor cases 750 1,500
Manufacturing Staff Sun Sensor - 2 sensors 70000 140,000
Senior Manufacturing Technician 1 160 worker-hrs 100 16,000 Sun Sensor Electronics - 2 sensor electronics 4000 8,000
Manufacturing Technician 4 384 worker-hrs 70 26,880 Magnetometer Magnet Kits - 4 magnetometer kits 74500 298,000
Magnetometer Cases - 2 magnetometer cases 500 1,000
GNC Sensor Attachment Kit - 4 sensor attachment kit 175 700
Guidance & Navigation Processor - 2 processors 275000 550,000
Electrical Power Components
Electrical Unit Cases - 1 electrical unit cases 500 500
Electrical Unit Attachment Kits - 1 unit attachment kits 500 500
Integrated Circuit Board - 2 board-square feet 25000 50,000
1.3.3 Thermal Control Subsystem Total Labor Resource Cost for 1.3.3 53,760 Total Tools & Machinery Resource Cost for 1.3.3 8,800 Total Materials & Installed Equipment Resource Cost for 1.3.3 340,340 402,900
Manufacturing Staff Satellite Factory Equipment Thermal Control Components
Manufacturing Technician 4 768 worker-hrs 70 53,760 Vehicle Integration Fixture 1 176 fixture-hrs 50 8,800 Thermal Blankets - 32 blanket-square feet 550 17,600
Blanket Support Structure - 40 structure-square feet 200 8,000
Blanket Adhesive - 34 adhesive-square feet 10 340
Heaters & Switches - 40 heaters & switches 250 10,000
Radiator Quartz Mirror Material - 50 quartz-square feet 5000 250,000
Radiator Backing Structure - 54 structure-square feet 1000 54,000
Radiator Attachment Kit - 2 radiator attachment kit 200 400
1.3.4 Electrical Power Subsystem Total Labor Resource Cost for 1.3.4 209,280 Total Tools & Machinery Resource Cost for 1.3.4 114,400 Total Materials & Installed Equipment Resource Cost for 1.3.4 3,136,825 3,460,505
Analysis, Engineering, & Test Staff Lab Equipment Electrical Power Components
Software Engineer 2 192 worker-hrs 130 24,960 Unit & Subsystem Test Equipment 2 208 equipment-hrs 550 114,400 Power Distribution Unit Slices - 32 power unit slices 20000 640,000
Manufacturing Staff Electrical Unit Cases - 8 electrical unit cases 500 4,000
Senior Manufacturing Technician 4 768 worker-hrs 100 76,800 Electrical Unit Attachment Kits - 8 unit attachment kits 500 4,000
Manufacturing Technician 8 1536 worker-hrs 70 107,520 Dual Junction Solar Cells - 500 solar cells 150 75,000
Solar Array Backing Structure - 250 structure-square feet 100 25,000
Solar Cell Adhesive - 275 adhesive-square feet 15 4,125
Solar Cell Cover Glass - 260 glass-square feet 20 5,200
Medium Capacity Battery Cells - 32 battery cells 50000 1,600,000
Battery Cell Thermal Sleeves - 32 thermal sleeves 10000 320,000
Power Management Processor - 2 processors 175000 350,000
Wiring Harness - 530 harness-feet 150 79,500
Spacecraft Structural Materials
Titanium Material - 20 titanium-pounds 1500 30,000
1.3.5 Telemetry & Command Subsystem Total Labor Resource Cost for 1.3.5 45,120 Total Tools & Machinery Resource Cost for 1.3.5 70,400 Total Materials & Installed Equipment Resource Cost for 1.3.5 182,100 297,620
Analysis, Engineering, & Test Staff Lab Equipment Telemetry & Command Components
Software Engineer 1 96 worker-hrs 130 12,480 Unit & Subsystem Test Equipment 2 128 equipment-hrs 550 70,400 T&C Transmitter slices - 8 transmitter slices 10000 80,000
Manufacturing Staff T&C Receiver Slices - 8 receiver slices 6000 48,000
Senior Manufacturing Technician 2 192 worker-hrs 100 19,200 Omni Antennas - 2 antennas 25000 50,000
Manufacturing Technician 2 192 worker-hrs 70 13,440 Electrical Power Components -
Electrical Unit Attachment Kits - 4 unit attachment kits 500 2,000
Wiring Harness - 6 harness-feet 150 900
Communications Components
Transmitter & Receiver Cables - 6 cable-feet 200 1,200
1.3.6 Propulsion Subsystem Total Labor Resource Cost for 1.3.6 26,880 Total Tools & Machinery Resource Cost for 1.3.6 4,000 Total Materials & Installed Equipment Resource Cost for 1.3.6 84,400 115,280
Manufacturing Staff Lab Equipment Propulsion Components
Manufacturing Technician 4 384 worker-hrs 70 26,880 Unit & Subsystem Fixtures 1 160 fixture-hrs 25 4,000 Small Thrusters - 4 thrusters 5000 20,000
Thruster Pressure Sensors - 8 pressure sensors 50 400
Thruster Catalyst - 2 catalyst-cubic feet 1000 2,000
Propellant Tanks - 40 tank-cubic feet 500 20,000
Propellant Tank Baffles - 4 tank baffles 100 400
Pressurant Tank - 8 tank-cubic feet 200 1,600
Lines, Valves, & Filters - 8 lines, valves, & filters 5000 40,000

6
MGT 270 Directed Computation John Hood

Section 3
WBS Level 1 Resources and Costs (1 of 2)

Total Tools Total Total Total


Total Total Effort Resource Total Total Effort Resource Resource Total WBS
Tools & Machinery & Tools & Materials & Installed Materials & Total Effort Materials &
WBS Element Labor Resource Labor (Intensity X Cost/ Labor (Intensity X Cost/ Cost/ Element
Resource Machinery Machinery Equipment Equipment (Intensity X Duration) Equipment
Resource Duration) Unit Cost Duration) Unit Unit Costs
Resource Cost Resource Cost

1.0 Lightweight Communications Satellite Project Total Project Cost 46,167,965


1.1 Project Management Total Labor Resource Cost for 1.1 9,137,980 Total Tools & Machinery Resource Cost for 1.1 4,706,000 Total Materials & Installed Equipment Resource Cost for 1.1 20,360,000 34,203,980
Management Staff Lab Equipment Installed Equipment
General Manager/Group Director 1 20 worker-hrs 200 4,000 Test Stand Set 2 880 equipment-hrs 100 88,000 Thermal Vacuum Chamber 1 400 chamber-hrs 20000 8,000,000
Division Director 1 20 worker-hrs 170 3,400 Unit & Subsystem Test Equipment 1 3960 equipment-hrs 550 2,178,000 Acoustic Chamber 1 80 chamber-hrs 15000 1,200,000
Business Manager 1 20 worker-hrs 120 2,400 Calibration Equipment Set 1 6400 equipment-hrs 200 1,280,000 Anechoic Chamber 1 160 chamber-hrs 50000 8,000,000
Program Manager 1 620 worker-hrs 165 102,300 Satellite Factory Equipment Class 100,000 Clean Room 1 840 room-hrs 1000 840,000
Project Manager 1 1984 worker-hrs 160 317,440 Vehicle Test Equipment 1 1160 equipment-hrs 1000 1,160,000 Class 10,000 Clean Room 1 464 room-hrs 5000 2,320,000
Software Manager 1 1116 worker-hrs 150 167,400
Configuration Manager 1 672 worker-hrs 125 84,000
Supply Chain Manager 1 192 worker-hrs 80 15,360
Analysis, Engineering, & Test Staff
Chief Systems Engineer 1 1032 worker-hrs 160 165,120
Systems Engineer 2 2944 worker-hrs 140 412,160
Development Engineer 7 28304 worker-hrs 120 3,396,480
Software Engineer 8 10752 worker-hrs 130 1,397,760
Test Engineer 6 14208 worker-hrs 110 1,562,880
Test Technician 8 12672 worker-hrs 80 1,013,760
Manufacturing Staff
Factory Supervisor 1 600 worker-hrs 120 72,000
Senior Manufacturing Technician 1 192 worker-hrs 100 19,200
Administrative Support Staff
Administrative Assistant 3 10488 worker-hrs 30 314,640
Quality Assurance Engineer 1 672 worker-hrs 60 40,320
Safety Director 2 592 worker-hrs 80 47,360
1.2 Spacecraft Payload Total Labor Resource Cost for 1.2 230,080 Total Tools & Machinery Resource Cost for 1.2 334,400 Total Materials & Installed Equipment Resource Cost for 1.2 5,630,600 6,195,080
Analysis, Engineering, & Test Staff Lab Equipment Electrical Power Components
Software Engineer 4 768 worker-hrs 130 99,840 Unit & Subsystem Test Equipment 4 608 equipment-hrs 550 334,400 Electrical Unit Cases - 12 electrical unit cases 500 6,000
Manufacturing Staff Electrical Unit Attachment Kits - 14 unit attachment kits 500 7,000
Senior Manufacturing Technician 7 1168 worker-hrs 100 116,800 Integrated Circuit Board - 4 board-square feet 25000 100,000
Manufacturing Technician 2 192 worker-hrs 70 13,440 Communications Components
Transmitter Unit Slices - 20 transmitter unit slices 70000 1,400,000
Receiver Unit Slices - 16 receiver unit slices 46000 736,000
Reflectors - 4 reflectors 100000 400,000
Sub-Reflectors & Feeds - 8 sub-reflectors & feeds 75000 600,000
Communications Processor - 2 processors 350000 700,000
Transmitter & Receiver Cables - 8 cable-feet 200 1,600
Encryption Devices - 2 devices 40000 80,000
Encryption Keys - 4 encryption keys 40000 160,000
Data Storage Memory Slices - 8 memory slices 180000 1,440,000

7
MGT 270 Directed Computation John Hood

WBS Level 1 Resources and Costs (2 of 2)

Total Tools Total Total Total


Total Total Effort Resource Total Total Effort Resource Resource Total WBS
Tools & Machinery & Tools & Materials & Installed Materials & Total Effort Materials &
WBS Element Labor Resource Labor (Intensity X Cost/ Labor (Intensity X Cost/ Cost/ Element
Resource Machinery Machinery Equipment Equipment (Intensity X Duration) Equipment
Resource Duration) Unit Cost Duration) Unit Unit Costs
Resource Cost Resource Cost

1.3 Spacecraft Bus Total Labor Resource Cost for 1.2 538,240 Total Tools & Machinery Resource Cost for 1.3 393,800 Total Materials & Installed Equipment Resource Cost for 1.3 4,824,865 5,768,905
Analysis, Engineering, & Test Staff Satellite Factory Equipment Spacecraft Structual Materials
Software Engineer 7 1056 worker-hrs 130 137,280 Vehicle Integration Fixture 2 352 fixture-hrs 50 17,600 Pre-Fab Structure - 250 structure-pounds 100 25,000
Manufacturing Staff Composite Curing Equipment 1 20 equipment-hrs 1000 20,000 Carbon Matrix Composites - 20 composites-square feet 500 10,000
Senior Manufacturing Technician 7 1120 worker-hrs 100 112,000 Metal Fabrication Equipment 1 18 equipment-hrs 500 9,000 Aluminum Sheet Metal - 40 aluminum-square feet 200 8,000
Manufacturing Technician 21 4128 worker-hrs 70 288,960 Lab Equipment Titanium Material - 20 titanium-pounds 1500 30,000
Unit & Subsystem Test Equipment 6 624 equipment-hrs 550 343,200 Electrical Power Components
Unit & Subsystem Fixtures 1 160 fixture-hrs 25 4,000 Power Distribution Unit Slices - 32 power unit slices 20000 640,000
Electrical Unit Cases - 9 electrical unit cases 500 4,500
Electrical Unit Attachment Kits - 13 unit attachment kits 500 6,500
Dual Junction Solar Cells - 500 solar cells 150 75,000
Solar Array Backing Structure - 250 structure-square feet 100 25,000
Solar Cell Adhesive - 275 adhesive-square feet 15 4,125
Solar Cell Cover Glass - 260 glass-square feet 20 5,200
Medium Capacity Battery Cells - 32 battery cells 50000 1,600,000
Battery Cell Thermal Sleeves - 32 thermal sleeves 10000 320,000
Power Management Processor - 2 processors 175000 350,000
Wiring Harness - 536 harness-feet 150 80,400
Integrated Circuit Board - 2 board-square feet 25000 50,000
Guidance, Navigation & Control Components
Sun Sensor Case - 2 sensor cases 750 1,500
Sun Sensor - 2 sensors 70000 140,000
Sun Sensor Electronics - 2 sensor electronics 4000 8,000
Magnetometer Magnet Kits - 4 magnetometer kits 74500 298,000
Magnetometer Cases - 2 magnetometer cases 500 1,000
GNC Sensor Attachment Kit - 4 sensor attachment kit 175 700
Guidance & Navigation Processor - 2 processors 275000 550,000
Thermal Control Components
Thermal Blankets - 32 blanket-square feet 550 17,600
Blanket Support Structure - 40 structure-square feet 200 8,000
Blanket Adhesive - 34 adhesive-square feet 10 340
Heaters & Switches - 40 heaters & switches 250 10,000
Radiator Quartz Mirror Material - 50 quartz-square feet 5000 250,000
Radiator Backing Structure - 54 structure-square feet 1000 54,000
Radiator Attachment Kit - 2 radiator attachment kit 200 400
Telemetry & Command Components
T&C Transmitter slices - 8 transmitter slices 10000 80,000
T&C Receiver Slices - 8 receiver slices 6000 48,000
Omni Antennas - 2 antennas 25000 50,000
Communications Components
Transmitter & Receiver Cables - 6 cable-feet 200 1,200
Propulsion Components
Small Thrusters - 4 thrusters 5000 20,000
Thruster Pressure Sensors - 8 pressure sensors 50 400
Thruster Catalyst - 2 catalyst-cubic feet 1000 2,000
Propellant Tanks - 40 tank-cubic feet 200 8,000
Propellant Tank Baffles - 4 tank baffles 100 400
Pressurant Tank - 8 tank-cubic feet 200 1,600
Lines, Valves, & Filters - 8 lines, valves, & filters 5000 40,000

8
MGT 270 Directed Computation John Hood

Section 4
WBS Level 0 Total Project Resources and Cost

Total Tools Total Tools Total Total


Total Total Effort Total Effort Total WBS
Resource Total Labor Tools & Machinery & Resource & Materials & Installed Materials & Total Effort Materials &
WBS Element Labor Resource Labor (Intensity X (Intensity X Cost/Unit Element
Cost/Unit Cost Resource Machinery Cost/ Unit Machinery Equipment Equipment (Intensity X Duration) Equipment
Resource Duration) Duration) Cost
Resource Cost Resource Cost

1.0 Lightweight Communications Satellite Total Labor Resource Cost for 1.0 9,906,300 Total Tools & Machinery Resource Cost for 1.0 5,434,200 Total Materials & Installed Equipment Resource Cost for 1.0 30,827,465 46,167,965
Management Staff Lab Equipment Installed Equipment
General Manager/Group Director 1 20 worker-hrs 200 4,000 Test Stand Set 2 880 equipment-hrs 100 88,000 Thermal Vacuum Chamber 1 400 chamber-hrs 20000 8,000,000
Division Director 1 20 worker-hrs 170 3,400 Unit & Subsystem Test Equipment 11 5192 equipment-hrs 550 2,855,600 Acoustic Chamber 1 80 chamber-hrs 15000 1,200,000
Business Manager 1 20 worker-hrs 120 2,400 Calibration Equipment Set 1 6400 equipment-hrs 200 1,280,000 Anechoic Chamber 1 160 chamber-hrs 50000 8,000,000
Program Manager 1 620 worker-hrs 165 102,300 Satellite Factory Equipment Class 100,000 Clean Room 1 840 room-hrs 1000 840,000
Project Manager 1 1984 worker-hrs 160 317,440 Vehicle Test Equipment 1 1160 equipment-hrs 1000 1,160,000 Class 10,000 Clean Room 1 464 room-hrs 5000 2,320,000
Software Manager 1 1116 worker-hrs 150 167,400 Unit & Subsystem Fixtures 1 160 fixture-hrs 25 4,000 Communications Components
Configuration Manager 1 672 worker-hrs 125 84,000 Composite Curing Equipment 1 20 equipment-hrs 1000 20,000 Transmitter Unit Slices - 20 transmitter unit slices 70000 1,400,000
Supply Chain Manager 1 192 worker-hrs 80 15,360 Metal Fabrication Equipment 1 18 equipment-hrs 500 9,000 Receiver Unit Slices - 16 receiver unit slices 46000 736,000
Analysis, Engineering, & Test Staff Vehicle Integration Fixture 2 352 fixture-hrs 50 17,600 Reflectors - 4 reflectors 100000 400,000
Chief Systems Engineer 1 1032 worker-hrs 160 165,120 Sub-Reflectors & Feeds - 8 sub-reflectors & feeds 75000 600,000
Systems Engineer 2 2944 worker-hrs 140 412,160 Communications Processor - 2 processors 350000 700,000
Development Engineer 7 28304 worker-hrs 120 3,396,480 Transmitter & Receiver Cables - 14 cable-feet 200 2,800
Software Engineer 8 12576 worker-hrs 130 1,634,880 Encryption Devices - 2 devices 40000 80,000
Test Engineer 6 14208 worker-hrs 110 1,562,880 Encryption Keys - 4 encryption keys 40000 160,000
Test Technician 8 12672 worker-hrs 80 1,013,760 Data Storage Memory Slices - 8 memory slices 180000 1,440,000
Manufacturing Staff Spacecraft Structual Materials
Factory Supervisor 1 600 worker-hrs 120 72,000 Pre-Fab Structure - 250 structure-pounds 100 25,000
Senior Manufacturing Technician 14 2480 worker-hrs 100 248,000 Carbon Matrix Composites - 20 composites-square feet 500 10,000
Manufacturing Technician 23 4320 worker-hrs 70 302,400 Aluminum Sheet Metal - 40 aluminum-square feet 200 8,000
Administrative Support Staff Titanium Material - 20 titanium-pounds 1500 30,000
Administrative Assistant 3 10488 worker-hrs 30 314,640 Electrical Power Components
Quality Assurance Engineer 1 672 worker-hrs 60 40,320 Power Distribution Unit Slices - 32 power unit slices 20000 640,000
Safety Director 2 592 worker-hrs 80 47,360 Electrical Unit Cases - 21 electrical unit cases 500 10,500
Electrical Unit Attachment Kits - 27 unit attachment kits 500 13,500
Dual Junction Solar Cells - 500 solar cells 150 75,000
Solar Array Backing Structure - 250 structure-square feet 100 25,000
Solar Cell Adhesive - 275 adhesive-square feet 15 4,125
Solar Cell Cover Glass - 260 glass-square feet 20 5,200
Medium Capacity Battery Cells - 32 battery cells 50000 1,600,000
Battery Cell Thermal Sleeves - 32 thermal sleeves 10000 320,000
Power Management Processor - 2 processors 175000 350,000
Wiring Harness - 536 harness-feet 150 80,400
Integrated Circuit Board - 6 board-square feet 25000 150,000
Guidance, Navigation & Control Components
Sun Sensor Case - 2 sensor cases 750 1,500
Sun Sensor - 2 sensors 70000 140,000
Sun Sensor Electronics - 2 sensor electronics 4000 8,000
Magnetometer Magnet Kits - 4 magnetometer kits 74500 298,000
Magnetometer Cases - 2 magnetometer cases 500 1,000
GNC Sensor Attachment Kit - 4 sensor attachment kit 175 700
Guidance & Navigation Processor - 2 processors 275000 550,000
Thermal Control Components
Thermal Blankets - 32 blanket-square feet 550 17,600
Blanket Support Structure - 40 structure-square feet 200 8,000
Blanket Adhesive - 34 adhesive-square feet 10 340
Heaters & Switches - 40 heaters & switches 250 10,000
Radiator Quartz Mirror Material - 50 quartz-square feet 5000 250,000
Radiator Backing Structure - 54 structure-square feet 1000 54,000
Radiator Attachment Kit - 2 radiator attachment kit 200 400
Telemetry & Command Components
T&C Transmitter slices - 8 transmitter slices 10000 80,000
T&C Receiver Slices - 8 receiver slices 6000 48,000
Omni Antennas - 2 antennas 25000 50,000
Propulsion Components
Small Thrusters - 4 thrusters 5000 20,000
Thruster Pressure Sensors - 8 pressure sensors 50 400
Thruster Catalyst - 2 catalyst-cubic feet 1000 2,000
Propellant Tanks - 40 tank-cubic feet 500 20,000
Propellant Tank Baffles - 4 tank baffles 100 400
Pressurant Tank - 8 tank-cubic feet 200 1,600
Lines, Valves, & Filters - 8 lines, valves, & filters 5000 40,000

9
MGT 270 Directed Computation John Hood

Quantity
Unit of Cost Quantity
Item Available for
Measure (Dollars) in Group
New Project
1.2 Analysis, Engineering, & Test Staff
1.2.1 Chief Systems Engineer Hour 160 10 1
1.2.2 Systems Engineer Hour 140 10 2
1.2.3 Senior Development Engineer Hour 130 8 3
1.2.4 Development Engineer Hour 120 40 8
1.2.5 Software Engineer Hour 130 40 8
1.2.6 Test Engineer Hour 110 30 6
1.2.7 Test Technician Hour 80 50 10
1.3 Manufacturing Staff
1.3.1 Factory Supervisor Hour 120 2 0.5
1.3.2 Senior Manufacturing Technician Hour 100 26 3
1.3.3 Manufacturing Technician Hour 70 50 10
1.4 Administrative Support Staff
1.4.1 Administrative Assistant Hour 30 12 4
1.4.2 Quality Assurance Engineer Hour 60 8 1
1.4.3 System Administrator Hour 70 8 2
1.4.4 Safety Director Hour 80 8 1
2.0 Tools & Machinery
2.1 Lab Equipment
2.1.1 Test Stand Set Hour 100 8 1
2.1.2 Fabrication Machinery Hour 350 4 1
2.1.3 Unit & Subsystem Test Equipment Hour 550 8 1
2.1.4 Calibration Equipment Set Hour 200 8 1
2.1.5 Unit & Subsystem Fixtures Hour 25 8 1
2.2 Satellite Factory Equipment
2.2.1 Vehicle Integration Fixtures Hour 50 8 1
2.2.2 Vehicle Test Equipment Hour 1000 8 1
2.3 Office Equipment
2.3.1 Desktop Computers Each 1400 350 90
2.3.2 Laptop Computers Each 1800 35 8
2.3.3 Workstations Each 3000 30 6
3.0 Materials & Installed Equipment
3.1 Installed Equipment
3.1.1 Thermal Vacuum Chamber Hour 20000 1 1
3.1.2 Acoustic Chamber Hour 15000 1 1
3.1.3 Anechoic Chamber Hour 50000 1 1
3.1.4 Class 100,000 Clean Room Hour 1000 5 1
3.1.5 Class 10,000 Clean Room Hour 5000 2 1
3.1.6 Class 100 Clean Bench Hour 2000 2 0
3.1.7 Composite Curing Equipment Hour 1000 5 1
3.1.8 Metal Fabrication Equipment Hour 500 5 1
3.2 Spacecraft Structural Materials
3.2.1 Pre-Fabricated Bus Structure Pound 100 10000 450
3.2.2 Non-Deployable Mechanisms Each 5000 150 24
3.2.3 Deployable Mechanisms Each 2000 75 15
3.2.4 Carbon Matrix Composites Sq. Foot 500 1000 130
3.2.5 Titanium Material Pound 1500 1200 120
3.2.6 Aluminum Sheet Metal Sq. Foot 200 50000 5000
3.2.7 Inconel Material Sq. Foot 500 3000 250

17
MGT 270 Directed Computation John Hood

Quantity
Unit of Cost Quantity
Item Available for
Measure (Dollars) in Group
New Project
3.3 Electrical Power Components
3.3.1 Power Distribution Unit Slices Each 20000 250 50
3.3.2 Electrical Unit Cases Each 500 100 25
3.3.3 Electrical Unit Attachment Hardware Kits Each 500 100 25
3.3.4 Power Conditioning Unit Slices Each 18000 250 50
3.3.5 Single Junction Solar Cells Each 75 5000 1000
3.3.6 Dual Junction Solar Cells Each 150 3000 850
3.3.7 Solar Array Backing Structure Sq. Foot 100 10000 1000
3.3.8 Solar Cell Adhesive Sq. Foot 15 10000 1000
3.3.9 Solar Cell Cover Glass Sq. Foot 20 10000 1000
3.3.10 Large Capacity Battery Cells Each 75000 100 40
3.3.11 Medium Capacity Battery Cells Each 50000 90 30
3.3.12 Small Capacity Battery Cells Each 35000 110 35
3.3.13 Battery Cell Thermal Sleeves Each 10000 120 40
3.3.14 Integrated Circuit Board Sq. Foot 25000 450 80
3.3.15 Power Management Processor Each 175000 45 4
3.3.16 Wiring Harness Foot 150 10500 1200
3.4 Thermal Control Components
3.4.1 Straight Heat Pipes Each 20000 150 15
3.4.2 Curved Heat Pipes Each 25000 50 10
3.4.3 Heat Pipe Transition Joints Each 500 35 10
3.4.4 Heat Pipe Attachment Hardware Kits Each 250 55 15
3.4.5 Heat Pipe Wicks Each 2000 210 40
3.4.6 Thermal Blankets Sq. Foot 550 5600 500
3.4.7 Thermal Blanket Support Structure Sq. Foot 200 6000 500
3.4.8 Thermal Blanket Adhesive Sq. Foot 10 6500 500
3.4.9 Radiator Quartz Mirror Material Sq. Foot 5000 1500 120
3.4.10 Radiator Backing Structure Sq. Foot 1000 1500 120
3.4.11 Radiator Attachment Hardware Kits Each 200 100 14
3.4.12 Louver Hinges & Support Structure Kits Each 250 110 15
3.4.13 Louver Bearings Each 15 400 80
3.4.14 Louvers Sq. Foot 7500 4 0
3.4.15 Heaters & Switches Each 250 4000 230
3.5 Communications Components
3.5.1 Transmitter Unit Slices Each 70000 200 40
3.5.2 Receivers Unit Slices Each 46000 225 40
3.5.3 Reflectors Each 100000 30 6
3.5.4 Sub-Reflectors & Feeds Each 75000 60 12
3.5.5 Encryption Devices Each 40000 35 4
3.5.6 Encryption Keys Each 40000 40 8
3.5.7 Communications Processor Each 350000 20 3
3.5.8 Transmitter & Receiver Cables Foot 200 5000 200
3.5.9 Data Storage Memory Slices Each 180000 225 15
3.6 Telemetry & Command Components
3.6.1 T&C Transmitter Slices Each 10000 500 20
3.6.2 T&C Receiver Slices Each 6000 250 15
3.6.3 Omni Antennas Each 25000 60 3

18
MGT 270 Directed Computation John Hood

Quantity
Unit of Cost Quantity
Item Available for
Measure (Dollars) in Group
New Project
3.7 Guidance, Navigation & Control
3.7.1 Control Moment Gyros Each 150000 4 0
3.7.2 Control Moment Gyro Electronics Each 50000 4 0
3.7.3 Torque Rods Each 150000 30 0
3.7.4 Star Tracker Catalog Each 50000 45 0
3.7.5 Star Trackers Each 150000 50 0
3.7.6 Sun Sensor Case Each 750 110 6
3.7.7 Sun Sensor Each 70000 100 5
3.7.8 Sun Sensor Electronics Each 4000 100 5
3.7.9 Inertial Reference Units Each 250000 50 0
3.7.10 Earth Sensors Each 50000 70 5
3.7.11 Magnetometer Magnet Kits Each 74500 50 5
3.7.12 Magnetometer Case Each 500 50 5
3.7.13 Reaction Wheels Each 80000 50 0
3.7.14 GNC Sensor Attachment Hardware Kit Each 175 150 15
3.7.15 Guidance & Navigation Processors Each 275000 30 3
3.8 Propulsion Components
3.8.1 Large Thrusters Each 45000 40 0
3.8.2 Medium Thrusters Each 20000 50 2
3.8.3 Small Thrusters Each 5000 60 8
3.8.4 Thruster Pressure Sensors Each 50 50 10
3.8.5 Thruster Catalyst Cu. Foot 1000 100 10
3.8.6 Propellant Tanks Cu. Foot 500 30 6
3.8.7 Pressurant Tanks Cu. Foot 200 45 3
3.8.8 Propellant Tank Baffles Each 100 30 6
3.8.9 Propellant Tank Diaphragms Each 200 35 6
3.8.10 Lines, Valves, & Filters Each 5000 1000 100
3.8.11 Hydrazine Propellant Pound 1000 10000 800
3.8.12 Helium Pressurant Pound 10 5000 150

RBS Notes:

1.0 Labor: Personnel are organized and allocated on a position title basis.

2.0 Tools & Machinery: A certain number of each item in this section is usually dedicated full time to an
individual project. Items in this section are also typically transportable between various project
workspaces. Office equipment is usually considered part of project overhead, unless the project requires a
unique piece of office equipment.

3.0 Materials & Installed Equipment: The equipment in this section shared among all the projects in the
group. The equipment is also typically fixed in location.

19
MGT 270 Directed Computation John Hood

The Lightweight Communications Satellite Project Objectives

Using a combination of previously space - qualified and new development hardware and software Space
Technologies Corporation will design, assemble, integrate, and test a lightweight communications satellite
for a commercial communications provider.

Work Breakdown Structure

The Work Breakdown Structure (WBS) for the Lightweight Communications Satellite Project is
presented below. This WBS has been extended down to Level Four. Below each of lowest - level WBS
elements are numerous activity-based tasks that must be accomplished to produce or deliver the item
specified at the fourth level of the WBS. For example, WBS element 1.1.3.4 Spacecraft Test Reports,
encompasses all the spacecraft-level testing that must be accomplished to produce the finished test
reports. These activities would include the spacecraft thermal vacuum test and the acoustic test, along
with various other activities associated with testing the entire integrated spacecraft.

1.0 Lightweight Communications Satellite Project


1.1 Project Management
1.1.1 Project Management
1.1.1.1 Project Plan
1.1.1.2 Risk Management Plan
1.1.1.3 Configuration Control Plan
1.1.1.4 Spacecraft Sell-off Report
1.1.2 Systems Engineering
1.1.2.1 Systems Engineering Plan
1.1.2.2 Requirements Verification Plan
1.1.2.3 Spacecraft Analysis & Design Reports
1.1.2.4 Interface Control Document
1.1.2.5 Subsystem Specifications
1.1.2.6 Spacecraft Manufacturing Plan
1.1.2.7 Parts, Materials, Processes Plan
1.1.2.8 Layouts & Drawings
1.1.3 Integration & Test
1.1.3.1 Spacecraft Integration & Test Plan
1.1.3.2 Subsystem Test Plans
1.1.3.3 Subsystem Test Reports
1.1.3.4 Spacecraft Test Reports

22
MGT 270 Directed Computation John Hood

1.2 Spacecraft Payload


1.2.1 Payload Electronics
1.2.1.1 Transmitters
1.2.1.2 Receivers
1.2.1.3 Payload Processor
1.2.1.4 Transmit & Receive Antennas
1.2.2 Data Handling Electronics
1.2.2.1 Data Storage Device
1.2.2.2 Data Encryption Device
1.3 Spacecraft Bus
1.3.1 Structures Subsystem
1.3.1.1 Primary Bus Structure
1.3.1.2 Secondary Bus Structure
1.3.2 Guidance, Navigation, & Control Subsystem
1.3.2.1 Spacecraft Control Processor
1.3.2.2 Magnetometers
1.3.2.3 Sun Sensor
1.3.3 Thermal Control Subsystem
1.3.3.1 Blankets
1.3.3.2 Radiators
1.3.4 Electrical Power Subsystem
1.3.4.1 Solar Arrays
1.3.4.2 Battery
1.3.4.3 Power Electronics & Wiring Harness
1.3.5 Telemetry & Command Subsystem
1.3.5.1 Omni Antennas
1.3.5.2 Telemetry & Command Electronics
1.3.6 Propulsion Subsystem
1.3.6.1 Thrusters
1.3.6.2 Propellant & Pressurant Tanks

23
MGT 270 Directed Computational John Hood

The critical path is shown in red on the network diagram, and the six gates are outlined with double lines. Note that the major milestone
reviews are scheduled for 0 days. In practice, each review is will last one day and will be held on the last day of its last predecessor task. These
gates are called out to provide an overall structure and logic to the Microsoft Project schedule. Labor resources required to support project
reviews are included as a part of labor overhead. Because the network diagram is somewhat large, it is reproduced over the next two pages.

Network Diagram with Optimum Durations and Float (1 of 2)

7. Interface Control Doc. 8. Require. Verif. Plan 9. Sys. Require. Review 11. S/C I&T Plan 12. PDR
48d 1.1.2.4 24d 1.1.2.2 0d Gate 2 120d 1.1.3.1 0d Gate 3
11/6/02 1/10/03 1/13/03 2/13/03 2/13/03 2/13/03 2/14/03 7/31/03 7/31/03 7/31/03
2. Risk Management Plan 0d 72d 0d 72d 0d 72d 0d 72d 0d 72d
12d 1.1.1.2
6/7/02 6/24/02
1. Project Plan 0d 0d 4. Integ. Baseline Review 5. Sys. Engineering Plan 6. Subsystem Specs
24d 1.1.1.1 0d Gate 1 24d 1.1.2.1 72d 1.1.2.5
5/6/02 6/6/02 6/24/02 6/24/02 6/25/02 7/26/02 7/29/02 11/5/02
0d 0d 3. Config. Control Plan 0d 0d 0d 0d 0d 0d
12d 1.1.1.3
6/7/02 6/24/02
0d 0d 10. S/C Anal. & Design Rpt. 13. Layouts & Drawings 15. S/C Manuf. Plan
144d 1.1.2.3 120d 1.1.2.8 24d 1.1.2.6
11/6/02 5/26/03 5/27/03 11/10/03 11/11/03 12/12/03
0d 0d 0d 0d 0d 0d

16. PMP Plan


24d 1.1.2.7
11/11/03 12/12/03
0d 0d

6
MGT 270 Directed Computational John Hood

Network Diagram with Optimum Duration and Float (2 of 2)


22. Data Storage Device 23. Data Encrypt. Device
12d 1.2.2.1 12d 1.2.2.2
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

26. Magnetometers
12d 1.3.2.2
12/15/03 12/30/03
0d 0d 28. S/C Control Processor
24d 1.3.2.1
12/31/03 2/2/04
27. Sun Sensor 0d 0d
12d 1.3.2.3
12/15/03 12/30/03
0d 0d

32. Battery
24d 1.3.4.2
12/15/03 1/15/04
0d 0d 33. Power Electronics
12d 1.3.4.3
1/16/04 2/2/04
31. Solar Arrays 0d 0d
24d 1.3.4.1
12/15/03 1/15/04
0d 0d

36. Thrusters 37. Prop. & Press. Tanks


12d 1.3.6.1 12d 1.3.6.2
12/15/03 12/3/03 12/31/03 1/15/04
0d 12d 0d 12d

14. Subsys. Test Plans 17. CDR 38. Subsys. Test Reports 39. S/C I&T Read. Review 40. S/C Test Reports
24d 1.1.3.2 0d Gate 4 60d 1.1.3.3 0d Gate 5 150d 1.1.3.4
8/1/03 9/3/03 12/12/03 12/12/03 2/3/04 4/26/04 4/26/04 4/26/04 4/27/04 11/22/04
72d 72d 0d 0d 0d 0d 0d 0d 0d 0d 42. Launch Read. Review
0d Gate 6
11/22/04 11/22/04
34. Omni Antennas 35. T & C Electronics 41. S/C Sell Off Report 0d 0d
12d 1.3.5.1 12d 1.3.5.2 150d 1.1.1.4
12/15/03 12/30/03 12/31/03 1/15/04 12/15/03 7/9/04
0d 12d 12d 12d 96d 96d

29. Radiators 30. Blankets


12d 1.3.3.2 12d 1.3.3.1
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

24. Primary Bus Struc. 25. Secondary Bus Struc.


12d 1.3.1.1 12d 1.3.1.2
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

18. P/L Transmitter


12d 1.2.1.1
12/15/03 12/30/03
0d 0d

19. P/L Receiver 21. P/L Processor


12d 1.2.1.2 24d 1.2.1.3
12/15/03 12/30/03 12/31/03 2/2/04
0d 0d 0d 0d

20. P/L Antennas


12d 1.2.1.4
12/15/03 12/30/03
0d 0d

7
MGT 270 Directed Computational John Hood

Section 3
Precedence Table

This table contains a complete list of all the lowest-level WBS elements (Level Three), their optimum
durations (based on the original elemental estimates made in previous assignments), along with each
task’s predecessor(s) and successor(s). This table was produced in Microsoft Project and imported to
Excel so it could be easily manipulated.

WBS Element Task Name Duration Predecessors Successors


1 1.1.1.1 Project Plan 24d 2,3
2 1.1.1.2 Risk Management Plan 12d 1 4
3 1.1.1.3 Configuration Control Plan 12d 1 4
4 Gate 1 Integrated Baseline Review (IBR) 0d 2,3 5
5 1.1.2.1 Systems Engineering Plan 24d 4 6
6 1.1.2.5 Subsystem Specifications 72d 5 7,10
7 1.1.2.4 Interface Control Document 48d 6 8
8 1.1.2.2 Requirements Verification Plan 24d 7 9
9 Gate 2 System Requirements Review (SRR) 0d 8 11
10 1.1.2.3 Spacecraft Analysis & Design Reports 144d 6 12,13
11 1.1.3.1 Spacecraft Integration & Test Plan 120d 9 12
12 Gate 3 Preliminary Design Review (PDR) 0d 10,11 14
13 1.1.2.8 Layouts & Drawings 120d 10 15,16
14 1.1.3.2 Subsystem Test Plans 24d 12 17
15 1.1.2.6 Spacecraft Manufacturing Plan 24d 13 17
16 1.1.2.7 Parts, Materials, & Processes Plan 24d 13 17
18,19,20,22,24,26,
27,29,31,32,34,36,
17 Gate 4 Critical Design Review (CDR) 0d 14,15,16 41
18 1.2.1.1 Payload Transmitter 12d 17 21
19 1.2.1.2 Payload Receiver 12d 17 21
20 1.2.1.4 Payload Antennas 12d 17 21
21 1.2.1.3 Payload Processor 24d 18,19,20 38
22 1.2.2.1 Data Storage Device 12d 17 23
23 1.2.2.2 Data Encryption Device 12d 22 38
24 1.3.1.1 Primary Bus Structure 12d 17 25
25 1.3.1.2 Secondary Bus Structure 12d 24 38
26 1.3.2.2 Magnetometers 12d 17 28
27 1.3.2.3 Sun Sensor 12d 17 28
28 1.3.2.1 Spacecraft Control Processor 24d 26,27 38
29 1.3.3.2 Radiators 12d 17 30
30 1.3.3.1 Blankets 12d 29 38
31 1.3.4.1 Solar Arrays 24d 17 33
32 1.3.4.2 Battery 24d 17 33
33 1.3.4.3 Power Electronics 12d 31,32 38
34 1.3.5.1 Omni Antennas 12d 17 35
35 1.3.5.2 Telemetry & Command Electronics 12d 34 38
36 1.3.6.1 Thrusters 12d 17 37
37 1.3.6.2 Propellant & Pressurant Tanks 12d 36 38
21,23,25,28,30,33,
38 1.1.3.3 Subsystem Test Reports 60d 35,37 39
39 Gate 5 Spacecraft Integration & Test Readiness Review (TRR) 0d 38 40
40 1.1.3.4 Spacecraft Test Reports 150d 39 42
41 1.1.1.4 Spacecraft Sell Off Report 150d 17 42
42 Gate 6 Launch Readiness Review (LRR) 0d 40,41

10
MGT 270 Directed Computational John Hood

Section 4
Calendar Schedule

The schedule presented below was generated with Microsoft Project. The network diagram presented
earlier was generated from this Microsoft Project schedule. The schedule itself was generated relative to
the given project start date of 6 May 2002 and the estimated optimum durations. The optimum durations
themselves were based upon the resource requirements determined in previous assignments. Other than
the project start date and the previously determined elemental duration estimates, there are no other
constraints within this schedule. No RBS resource constraints have been introduced at this point.

2002 2003 2004


ID WBS Task Name Start Finish Q2 '02 Q3 '02 Q4 '02 Q1 '03 Q2 '03 Q3 '03 Q4 '03 Q1 '04 Q2 '04 Q3 '04 Q4 '04
1 1.1.1.1 Project Plan Mon 5/6/02 Thu 6/6/02

2 1.1.1.2 Risk Management Plan Fri 6/7/02 Mon 6/24/02

3 1.1.1.3 Configuration Control Plan Fri 6/7/02 Mon 6/24/02

4 Gate 1 Integrated Baseline Review (IBR) Mon 6/24/02 Mon 6/24/02 6/24

5 1.1.2.1 Systems Engineering Plan Tue 6/25/02 Fri 7/26/02

6 1.1.2.5 Subsystem Specifications Mon 7/29/02 Tue 11/5/02

7 1.1.2.4 Interface Control Document Wed 11/6/02 Fri 1/10/03

8 1.1.2.2 Requirements Verification Plan Mon 1/13/03 Thu 2/13/03

9 Gate 2 System Requirements Review (SRR) Thu 2/13/03 Thu 2/13/03 2/13

10 1.1.2.3 Spacecraft Analysis & Design Reports Wed 11/6/02 Mon 5/26/03

11 1.1.3.1 Spacecraft Integration & Test Plan Fri 2/14/03 Thu 7/31/03

12 Gate 3 Preliminary Design Review (PDR) Thu 7/31/03 Thu 7/31/03 7/31

13 1.1.2.8 Layouts & Drawings Tue 5/27/03 Mon 11/10/03

14 1.1.3.2 Subsystem Test Plans Fri 8/1/03 Wed 9/3/03

15 1.1.2.6 Spacecraft Manufacturing Plan Tue 11/11/03 Fri 12/12/03

16 1.1.2.7 Parts, Materials, & Processes Plan Tue 11/11/03 Fri 12/12/03

17 Gate 4 Critical Design Review (CDR) Fri 12/12/03 Fri 12/12/03 12/12

18 1.2.1.1 Payload Transmitter Mon 12/15/03 Tue 12/30/03

19 1.2.1.2 Payload Receiver Mon 12/15/03 Tue 12/30/03

20 1.2.1.4 Payload Antennas Mon 12/15/03 Tue 12/30/03

21 1.2.1.3 Payload Processor Wed 12/31/03 Mon 2/2/04

22 1.2.2.1 Data Storage Device Mon 12/15/03 Tue 12/30/03

23 1.2.2.2 Data Encryption Device Wed 12/31/03 Thu 1/15/04

24 1.3.1.1 Primary Bus Structure Mon 12/15/03 Tue 12/30/03

25 1.3.1.2 Secondary Bus Structure Wed 12/31/03 Thu 1/15/04

26 1.3.2.2 Magnetometers Mon 12/15/03 Tue 12/30/03

27 1.3.2.3 Sun Sensor Mon 12/15/03 Tue 12/30/03

28 1.3.2.1 Spacecraft Control Processor Wed 12/31/03 Mon 2/2/04

29 1.3.3.1 Radiators Mon 12/15/03 Tue 12/30/03

30 1.3.3.2 Blankets Wed 12/31/03 Thu 1/15/04

31 1.3.4.1 Solar Arrays Mon 12/15/03 Thu 1/15/04

32 1.3.4.2 Battery Mon 12/15/03 Thu 1/15/04

33 1.3.4.3 Power Electronics Fri 1/16/04 Mon 2/2/04

34 1.3.5.1 Omni Antennas Mon 12/15/03 Tue 12/30/03

35 1.3.5.2 Telemetry & Command Electronics Wed 12/31/03 Thu 1/15/04

36 1.3.6.1 Thrusters Mon 12/15/03 Tue 12/30/03

37 1.3.6.2 Propellant & Pressurant Tanks Wed 12/31/03 Thu 1/15/04

38 1.1.3.3 Subsystem Test Reports Tue 2/3/04 Mon 4/26/04

39 Gate 5 S/C Integration & Test Readiness Review Mon 4/26/04 Mon 4/26/04 4/26

40 1.1.3.4 Spacecraft Test Reports Tue 4/27/04 Mon 11/22/04

41 1.1.1.4 Spacecraft Sell Off Report Mon 12/15/03 Fri 7/9/04

42 Gate 6 Launch Readiness Review (LRR) Mon 11/22/04 Mon 11/22/04

11
MGT 270 Directed Computational John Hood

Introduction

The various resource utilization and cash flow charts shown below were generated in Microsoft Project.
They were exported to Microsoft Excel for easier manipulation. These charts are based on optimum task
durations developed in earlier assignments and without regard to any resource constraints. The RBS,
WBS, and elemental estimates developed in earlier assignments have not been changed for this
assignment.

Resource Utilization for the Five Most Used Resources

The five most used resources for the Lightweight Communications Satellite Project are: (1) Development
Engineer, (2) Test Engineer, (3) Test Technician, (4) Software Engineer, and (5) Administrative Assistant.
The following five charts show how each resource is expended from project start (May 2002) through
project completion (November 2004). For each of these five charts, the X-axis shows project time in
months, and the Y-axis shows monthly worker-hours.

Chart 1. Development Engineer Resource Expenditure

1600
1496

1400
1288 1232 1288 1288
1232 1232 1232
1200 1152
1176 1176
1104 1120 1104 1056
1056 1056 1056 1056
1008 1008 1008
1000
912

816
800
672

600

400 336

200 144

0 0 0 0
0

The trend for the usage of the Development Engineer resource is clearly bi-modal. This reflects the fact
that Development Engineers in this project environment are heavily involved up-front in the initial design
of the spacecraft. They are not typically involved in the actual manufacture of the spacecraft, which is
why they are not utilized in the December 2003 and January 2004 timeframe. Their usage peaks again at
the end of the project as they verify that the as-built configuration conforms to the as-designed
configuration. This activity culminates in the release of the Spacecraft Sell Off Report.

2
MGT 270 Directed Computational John Hood

Chart 2. Test Engineer Resource Expenditure

1200
1104
1056 1056
1008
1000
936
920 880
880
840

800 704
736
704
672 672 672
640

600

400 352

200 176

96 104

0 0 0 0 0 0 0 0 0 0 0
0

Like the Development Engineer resource, the Test Engineer resource is also bi-modal, although this
resource is spread over a slightly different time period. Test Engineers are involved in the middle of the
program as test plans are developed. Their involvement declines as Layouts and Drawings are produced,
and final manufacturing plans are developed. Once the vehicle is integrated, the Test Engineer activity
again peaks as they become intimately involved in the testing of the satellite. They maintain a high level
of activity as final test reports are generated.

3
MGT 270 Directed Computational John Hood

Chart 3. Test Technician Resource Expenditure

1600
1472 1408 1408
1408 1408
1400 1344 1344

1216
1200

1000
896

800 768

600

400

200

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0

Test Technicians are only involved in the actual testing of the spacecraft. They do not play any role in test
planning. Therefore, all their activity occurs toward the end of the project as the spacecraft enters the test
phase. Their utilization continues through the end of the project as the test reports are written.

4
MGT 270 Directed Computational John Hood

Chart 4. Software Engineer Resource Expenditure

1600
1496

1400 1344

1200
1104 1104
1056 1056 1056
1008 1008 1008
1000
864

800

600

400
264

200 144
64
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0

The Software Engineer resource also shows a bi-modal trend. Software Engineers are heavily involved in
initial design and development efforts. They must ensure early in the project that the various software
requirements are understood. Then during spacecraft manufacture, they must finish writing the software
code, install that code, and test it to ensure it meets the requirements.

5
MGT 270 Directed Computational John Hood

Chart 5. Administrative Assistant Resource Expenditure

800

704
700

592
600
528
504
500 488
448

400 368 376 368 368


352 352 352 352 352
336 336 336 336 336
304 296
288
300
240
208
192
200 160
176
160
184

96
100

The Administrative Assistant Resource is required throughout the entire project. This resource peaks
during major project planning phases and when the significant project reports and documents are
generated.

6
MGT 270 Directed Computational John Hood

Chart 6. Top Five Resources for WBS Element 1.1 – Development Engineer
1600
1496

1400
1288 1232 1288 1288
1232 1232 1232
1176 1176
1200 1152
1120
1104 1104 1056 1056
1056 1056 1056
1008 1008 1008
1000
912

816
800
672

600

400 336

200 144

0 0 0 0
0

Development Engineer

In Chart 6 above, note the bi-modal spread of this resource. As explained earlier, Development Engineers
are involved in the initial design of the spacecraft. They are not typically involved in the actual
manufacture, which is why they are not utilized in the December 2003 and January 2004 timeframe. Their
usage peaks again at the end of the project as they verify that the as-built configuration conforms to the
as-designed configuration. This activity culminates in release of the Spacecraft Sell Off Report.

8
MGT 270 Directed Computational John Hood

The next chart shows the second and third most-used resources for WBS Element 1.1 Project
Management. This chart is somewhat truncated for clarity because prior to February 2003 neither of these
resources are utilized.

Chart 7. Top Five Resources for WBS Element 1.1 – Test Engineer and Test Technician

1600
1472 1408 1408
1408 1408
1400 1344 1344

1216
1200
1104
1056 1048
1008
1000 920 936
880 880 896
840
800 768
736
704 704
672 672 672
640
600

400 352

176
200
96 104

00 0 0 0 0 0 0 0 0 00 00 0 0
0

Test Engineer Test Technician

Chart 7 above shows the bi-modal nature of utilization for the Test Engineer resource. As explained
previously, Test Engineers are involved early in the program as test plans are developed. Their
involvement declines as layouts and drawings are produced and final manufacturing plans are developed
(October-November 2003 timeframe). Once the vehicle is integrated, the Test Engineer activity again
peaks as they become involved in the actual testing of the satellite. They maintain a high level of activity
as final test reports are generated. In contrast, Test Technicians are only involved in the actual testing of
the spacecraft. They also participate in the release of the test reports. This activity carries them through to
the end of the project.

9
MGT 270 Directed Computational John Hood

The fourth and fifth most used resources within WBS element 1.1 Project Management are shown below
in Chart 8.

Chart 8. Top Five Resources for WBS Element 1.1 – Software Engineer and Administrative Assistant

1600

1400 1344

1200
1104 1104
1056 1056 1056
1008 1008 1008
1000
864

800
704

592
600
488 504 528
448
368
400
352 376 352 368 368 352 352
336 336 336 336 352 336
288 304 296
240
176 160 184
200 144
98
48
00 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0

Software Engineer Adminstrative Assistant

To support WBS element 1.1, the Software Engineer resource is used early in the program to identify
software requirements and ensure that the design satisfies these requirements. Recall from Chart 4 that the
Software Engineer resource was bi-modal when the utilization of this resource was looked at from an
overall project perspective. The second peak occurred in the December 2003 and January 2004 period.
This peak does not appear in this chart because that particular activity supports WBS element 1.2
Spacecraft Payload. Note that utilization of the Administrative Assistant resource is required throughout
the project. The peaks in this resource utilization correspond to the generation of major project reports.

10
MGT 270 Directed Computational John Hood

The top five resources used in support of WBS element 1.2 Spacecraft Payload activities are shown in
Chart 9 below. This chart is truncated for clarity. None of these resources are utilized for WBS element
1.2 prior to December 2003 or after February 2004.

Chart 9. Top Five Resources for WBS Element 1.2 Spacecraft Payload

700
656

600
528
496
500

400

300 272

224
192
200 176

100
40
20 16
0 0 0 0 0 0 0 0 8 0 0 0 0 0 0
0
Nov-03 Dec-03 Jan-04 Feb-04 Mar-04

Senior Mnaufacturing Technician Software Engineer


Manufacturing Technician Unit & Subsystem Test Equipment
Transmitter Slices

All the top five resources for 1.2 Spacecraft Payload are utilized only during the period between
December 2003 to February 2004. This period corresponds to the manufacture of the satellite payload.

11
MGT 270 Directed Computational John Hood

The top five resources used in support of WBS element 1.3 Spacecraft Bus activities are shown in Chart
10 below. This chart is truncated for clarity. None of these resources are utilized for WBS element 1.3
prior to December 2003 or after February 2004.

Chart 10. Top Five Resources for WBS Element 1.3 Spacecraft Bus

3000

2544
2500

2000

1584

1500

968
1000 856

500
500 408
312
232

0 0 0 0 0 40 36 0 32 48 0 0 0 0 0 0 0
0
Nov-03 Dec-03 Jan-04 Feb-04 Mar-04
Manufacturing Technician Senior Manufacturing Technician
Software Engineer Unit & Subsystem Test Equipment
Wiring Harness

All the top five resources for 1.3 Spacecraft Bus are utilized only during the period between December
2003 to February 2004. This period corresponds to the manufacture of the satellite bus subsystems.

12
MGT 270 Directed Computational John Hood

Project Cash Flow

Chart 11 shows total monthly cash flow for the entire project. The X-axis shows project time in months
and the Y-axis shows costs in dollars.

Chart 11. Project Cash Flow

$12,000,000.00

$10,000,000.00

$8,000,000.00

$6,000,000.00

$4,000,000.00

$2,000,000.00

$0.00

Note the peak cost expenditure in December 2003. This corresponds to the manufacture of the spacecraft.
Immediately after this, costs are reduced until they peak again in May 2004. This corresponds to the
testing of the spacecraft. As mentioned in previous assignments, the spacecraft test phase is usually the
most expensive part of the project.

13
MGT 270 Directed Computational John Hood

Project Cash Flow at WBS Level 1

These last three charts show how the cash flow is distributed over time for each of the three WBS Level - 1
elements. For all three charts, the X-axis shows project time in months, and the Y-axis shows costs in
dollars. Chart 12 shows the cash flow for WBS element 1.1, Project Management.

Chart 12. Cash Flow for WBS Element 1.1 Project Management

12000000

10000000

8000000

6000000

4000000

2000000

The cash flow trend shown in Chart 12 above is very similar to the one shown in Chart 11 for the entire
project except, that there is no peak in December 2003. This peak is part of the WBS elements 1.2 and 1.3
and is captured in Charts 13 and 14 below.

14
MGT 270 Directed Computational John Hood

Chart 13. Cash Flow for WBS Element 1.2 Spacecraft Payload

7000000

6000000

5000000

4000000

3000000

2000000

1000000

WBS element 1.2, Spacecraft Payload, only covers the relatively short time period of December 2003 to
January 2004 when the spacecraft payload is assembled. Thus there is only one very high cash flow peak
in Chart 13 above. As can be seen in Chart 14 below, WBS element 1.3, Spacecraft Bus, exhibits a similar
trend. As in the case of the payload, the satellite bus is also assembled during December 2003 through
January 2004. Therefore, all the costs are concentrated in this short time period.

15
MGT 270 Directed Computational John Hood

Chart 14. Cash Flow for WBS Element 1.3 Spacecraft Bus

4500000

4000000

3500000

3000000

2500000

2000000

1500000

1000000

500000

16
MGT 270 Directed Computational John Hood

Table 2 below shows a summary of the compressed activities, a description of the proposed changes in
those activities to achieve the required schedule compression, the original and compressed durations, the
original and new total effort required, and the resulting increase in cost.

Table 2. Summary of Compression Activities


Original Total Labor Proposed Total Labor
Desription of Proposed Original Compressed Total Cost
WBS Element WBS Element Description Effort (Intensity X Effort (Intensity X
Changes Duration Duration Increase
Duration) Duration)

Carry out required tasks and


Includes all tasks and activities activities using a 2 shift (16
required to verify and test all hour) workday instead of the
Subsystem Test
1.1.3.3 spacecraft subsystems. originally proposed 1 shift (8 60 days 30 days 8,240 worker-hours 16,480 worker-hours $1,255,200
Reports
Culminates in the release of hour) workday. Second shift
Subsystem Test Reports for works at an overtime rate of
each subsystem. 1.5x original labor rate.
Includes all tasks and activities
required to assemble all Carry out required tasks and
subsystems into a complete activities using a 2 shift (16
Spacecraft Test satellite. Also includes all hour) workday instead of the
1.1.3.4 150 days 75 days 24,816 worker-hours 49,632 worker-hours $3,506,160
Report efforts required to verify and originally proposed 1 shift (8
test the complete satellite and hour) workday. Second shift
culminates in the release of the works at an overtime rate of
Spacecraft Test Report. 1.5x original labor rate.
Includes all tasks and activities
required to validate that the
spacecraft was developed,
manufactured, assembled, and
tested properly. This effort
ensures that the spacecraft's
Spacecraft Sell Off
1.1.1.4 "as designed" configuration and Carry out required tasks and 150 days 120 days 2,360 worker-hours 4,720 worker-hours $250,200
Report
"as built" configuration are activities using a 2 shift (16
consistent with each other and hour) workday instead of the
that the spacecraft meets all originally proposed 1 shift (8
customer requirements. hour) workday. Second shift
Culminates in the release of the works at an overtime rate of
Spacecraft Sell Off Report. 1.5x original labor rate.
Totals 360 days 225 days 35,416 worker-hours 70,832 worker-hours $5,011,560

Table 3 provides a little more detail in terms of where the additional labor must be applied to achieve the
5 month reduction in the schedule. This table also shows more detail in terms of the additional costs. Note
that the Total Additional Resource Cost includes a 1.5 X normal labor rate scaling factor to account for
the overtime incurred in the second shift. Also note that the Duration column only reflects the amount of
effort brought in to allow for a second shift. It is not new scope.

Table 3. Additional Resources Required to Achieve Schedule Compression


Total Total WBS
Duration Total Effort (Intensity Resource
WBS Element Resource Intensity Additional Element
(Hours) X Duration) Cost / Unit
Resource Cost Cost
1.1.3.3 Subsystem Test Reports 1,255,200
Development Engineer 6 440 2640 worker-hours 120 475,200
Test Engineer 5 480 2400 worker-hours 110 396,000
Test Technician 8 400 3200 worker-hours 80 384,000
1.1.3.4 Spacecraft Test Reports 3,506,160
Development Engineer 6 1184 7104 worker-hours 120 1,278,720
Test Engineer 5 1200 6000 worker-hours 110 990,000
Test Technician 8 1184 9472 worker-hours 80 1,136,640
Administrative Assistant 2 1120 2240 worker-hours 30 100,800
1.1.1.4 Spacecraft Sell Off Report 250,200
Test Engineer 1 1200 1200 worker-hours 110 198,000
Administrative Assistant 1 1160 1160 worker-hours 30 52,200
Total Additional Cost for Proposed Schedule Compression 5,011,560

3
MGT 270 Directed Computational John Hood

As can be seen from Tables 2 and 3 above, the additional resources are concentrated in only three WBS
Level 3 elements: (1) 1.1.3.3 Subsystem Test Reports, (2) 1.1.3.4 Spacecraft Test Reports, and (3) 1.1.1.4
Spacecraft Sell Off Report. WBS element 1.1.3.3 represents all the subsystem-level testing that must
occur before the subsystems are assembled (integrated) together to form the satellite. WBS element
1.1.3.4 contains all the activities that must be accomplished to integrate and test the entire spacecraft.
Finally, WBS element 1.1.1.4 represents the effort that must be accomplished to verify the spacecraft was
developed, built, and tested correctly, and that it meets all requirements. There are many labor resources
applied to this last WBS element. However only the two resources (Test Engineer and Administrative
Assistant) that actually drive the task duration have been applied to a double shift schedule. Chart 1 below
shows the new compressed schedule from Microsoft Project.

Chart 1. Proposed Compressed Schedule


2002 2003 2004
ID Task Name Start Finish Duration Q2 '02 Q3 '02 Q4 '02 Q1 '03 Q2 '03 Q3 '03 Q4 '03 Q1 '04 Q2 '04 Q3 '04 Q4 '04
1 Project Plan Mon 5/6/02 Thu 6/6/02 24d

2 Risk Management Plan Fri 6/7/02 Mon 6/24/02 12d

3 Configuration Control Plan Fri 6/7/02 Mon 6/24/02 12d

4 Integrated Baseline Review (IBR) Mon 6/24/02 Mon 6/24/02 0d 6/24

5 Systems Engineering Plan Tue 6/25/02 Fri 7/26/02 24d

6 Subsystem Specifications Mon 7/29/02 Tue 11/5/02 72d

7 Interface Control Document Wed 11/6/02 Fri 1/10/03 48d

8 Requirements Verification Plan Mon 1/13/03 Thu 2/13/03 24d

9 System Requirements Review (SRR) Thu 2/13/03 Thu 2/13/03 0d 2/13

10 Spacecraft Analysis & Design Reports Wed 11/6/02 Mon 5/26/03 144d

11 Spacecraft Integration & Test Plan Fri 2/14/03 Thu 7/31/03 120d

12 Preliminary Design Review (PDR) Thu 7/31/03 Thu 7/31/03 0d 7/31

13 Layouts & Drawings Tue 5/27/03 Mon 11/10/03 120d

14 Subsystem Test Plans Fri 8/1/03 Wed 9/3/03 24d

15 Spacecraft Manufacturing Plan Tue 11/11/03 Fri 12/12/03 24d

16 Parts, Materials, & Processes Plan Tue 11/11/03 Fri 12/12/03 24d

17 Critical Design Review (CDR) Fri 12/12/03 Fri 12/12/03 0d 12/12

18 Payload Transmitter Mon 12/15/03 Tue 12/30/03 12d

19 Payload Receiver Mon 12/15/03 Tue 12/30/03 12d

20 Payload Antennas Mon 12/15/03 Tue 12/30/03 12d

21 Payload Processor Wed 12/31/03 Mon 2/2/04 24d

22 Data Storage Device Mon 12/15/03 Tue 12/30/03 12d

23 Data Encryption Device Wed 12/31/03 Thu 1/15/04 12d

24 Primary Bus Structure Mon 12/15/03 Tue 12/30/03 12d

25 Secondary Bus Structure Wed 12/31/03 Thu 1/15/04 12d

26 Magnetometers Mon 12/15/03 Tue 12/30/03 12d

27 Sun Sensor Mon 12/15/03 Tue 12/30/03 12d

28 Spacecraft Control Processor Wed 12/31/03 Mon 2/2/04 24d

29 Radiators Mon 12/15/03 Tue 12/30/03 12d

30 Blankets Wed 12/31/03 Thu 1/15/04 12d

31 Solar Arrays Mon 12/15/03 Thu 1/15/04 24d

32 Battery Mon 12/15/03 Thu 1/15/04 24d

33 Power Electronics Fri 1/16/04 Mon 2/2/04 12d

34 Omni Antennas Mon 12/15/03 Tue 12/30/03 12d

35 Telemetry & Command Electronics Wed 12/31/03 Thu 1/15/04 12d

36 Thrusters Mon 12/15/03 Tue 12/30/03 12d

37 Propellant & Pressurant Tanks Wed 12/31/03 Thu 1/15/04 12d

38 Subsystem Test Reports Tue 2/3/04 Mon 3/15/04 30d

39 S/C Integration & Test Readiness Review Mon 3/15/04 Mon 3/15/04 0d 3/15

40 Spacecraft Test Reports Tue 3/16/04 Mon 6/28/04 75d

41 Spacecraft Sell Off Report Mon 12/15/03 Fri 5/28/04 120d

42 Launch Readiness Review (LRR) Mon 6/28/04 Mon 6/28/04 0d

4
MGT 270 Directed Computational John Hood

Project Critical Path

The project’s critical path has not changed. It has only gotten shorter as can be seen in the Microsoft Project schedule presented in Chart 1
above. The next two pages depict a network diagram of the compressed schedule. The project critical path is depicted in red, and the changes
associated with the compressed tasks are shown in blue.

Network Diagram with Critical Path (1 of 2)


7. Interface Control Doc. 8. Require. Verif. Plan 9. Sys. Require. Review 11. S/C I&T Plan 12. PDR
48d 1.1.2.4 24d 1.1.2.2 0d Gate 2 120d 1.1.3.1 0d Gate 3
11/6/02 1/10/03 1/13/03 2/13/03 2/13/03 2/13/03 2/14/03 7/31/03 7/31/03 7/31/03
2. Risk Management Plan 0d 72d 0d 72d 0d 72d 0d 72d 0d 72d
12d 1.1.1.2
6/7/02 6/24/02
1. Project Plan 0d 0d 4. Integ. Baseline Review 5. Sys. Engineering Plan 6. Subsystem Specs
24d 1.1.1.1 0d Gate 1 24d 1.1.2.1 72d 1.1.2.5
5/6/02 6/6/02 6/24/02 6/24/02 6/25/02 7/26/02 7/29/02 11/5/02
0d 0d 3. Config. Control Plan 0d 0d 0d 0d 0d 0d
12d 1.1.1.3
6/7/02 6/24/02
0d 0d 10. S/C Anal. & Design Rpt. 13. Layouts & Drawings 15. S/C Manuf. Plan
144d 1.1.2.3 120d 1.1.2.8 24d 1.1.2.6
11/6/02 5/26/03 5/27/03 11/10/03 11/11/03 12/12/03
0d 0d 0d 0d 0d 0d

16. PMP Plan


24d 1.1.2.7
11/11/03 12/12/03
0d 0d

5
MGT 270 Directed Computational John Hood
Network Diagram with Critical Path (2 of 2)

22. Data Storage Device 23. Data Encrypt. Device


12d 1.2.2.1 12d 1.2.2.2
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

26. Magnetometers
12d 1.3.2.2
12/15/03 12/30/03
0d 0d 28. S/C Control Processor Note the only changes to the original baseline schedule
24d 1.3.2.1
12/31/03 2/2/04
27. Sun Sensor 0d 0d
are in these three tasks. Specific effects of these changes
12d 1.3.2.3
12/15/03 12/30/03 are shown in blue.
0d 0d

32. Battery
24d 1.3.4.2
12/15/03 1/15/04
0d 0d 33. Power Electronics
12d 1.3.4.3
1/16/04 2/2/04
31. Solar Arrays 0d 0d
24d 1.3.4.1
12/15/03 1/15/04
0d 0d

36. Thrusters 37. Prop. & Press. Tanks


12d 1.3.6.1 12d 1.3.6.2
12/15/03 12/3/03 12/31/03 1/15/04
0d 12d 0d 12d

14. Subsys. Test Plans 17. CDR 38. Subsys. Test Reports 39. S/C I&T Read. Review 40. S/C Test Reports
24d 1.1.3.2 0d Gate 4 30d 1.1.3.3 0d Gate 5 75d 1.1.3.4
8/1/03 9/3/03 12/12/03 12/12/03 2/3/04 3/15/04 3/15/04 3/15/04 3/16/04 6/28/04
72d 72d 0d 0d 0d 0d 0d 0d 0d 0d 42. Launch Read. Review
0d Gate 6
6/28/04 6/28/04
34. Omni Antennas 35. T & C Electronics 41. S/C Sell Off Report 0d 0d
12d 1.3.5.1 12d 1.3.5.2 120d 1.1.1.4
12/15/03 12/30/03 12/31/03 1/15/04 12/15/03 5/28/04
0d 12d 12d 12d 21d 21d

29. Radiators 30. Blankets


12d 1.3.3.2 12d 1.3.3.1
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

24. Primary Bus Struc. 25. Secondary Bus Struc.


12d 1.3.1.1 12d 1.3.1.2
12/15/03 12/30/03 12/31/03 1/15/04
0d 12d 12d 12d

18. P/L Transmitter


12d 1.2.1.1
12/15/03 12/30/03
0d 0d

19. P/L Receiver 21. P/L Processor


12d 1.2.1.2 24d 1.2.1.3
12/15/03 12/30/03 12/31/03 2/2/04
0d 0d 0d 0d

20. P/L Antennas


12d 1.2.1.4
12/15/03 12/30/03
0d 0d

6
MGT 270 Directed Computational John Hood

Table 1. Scope Change Impacts on Task Duration


Original New Duration
Scope Change
WBS Task Duration (Days)
(%)
(Days) (Actual)
1 1.1.1.1 Project Plan - 24 24
2 1.1.1.2 Risk Management Plan - 12 12
3 1.1.1.3 Configuration Control Plan - 12 12
Gate 1 Integrated Baseline Review (IBR) - 0 0
4 1.1.2.1 Systems Engineering Plan - 24 24
5 1.1.2.5 Subsystem Specifications - 72 94
6 1.1.2.4 Interface Control Document - 48 61
7 1.1.2.2 Requirements Verification Plan - 24 24
Gate 2 System Requirements Review (SRR) - 0 0
8 1.1.2.3 Spacecraft Analysis & Design Reports - 144 149
9 1.1.3.1 Spacecraft Integration & Test Plan +7 120 127
Gate 3 Preliminary Design Review (PDR) - 0 -
10 1.1.2.8 Layouts & Drawings +7 120 128
11 1.1.3.2 Subsystem Test Plans +7 24 26
12 1.1.2.6 Spacecraft Manufacturing Plan +7 24 26
13 1.1.2.7 Parts, Materials, & Processes Plan +15 24 28
Gate 4 Critical Design Review (CDR) - 0 0
14 1.2.1.1 Payload Transmitter -15 12 10
15 1.2.1.2 Payload Receiver +7 12 13
16 1.2.1.4 Payload Antennas +7 12 13
17 1.2.1.3 Payload Processor +35 24 33
18 1.2.2.1 Data Storage Device +7 12 13
19 1.2.2.2 Data Encryption Device +7 12 13
20 1.3.1.1 Primary Bus Structure +7 12 13
21 1.3.1.2 Secondary Bus Structure +7 12 13
22 1.3.2.2 Magnetometers +7 12 13
23 1.3.2.3 Sun Sensor +15 12 13
24 1.3.2.1 Spacecraft Control Processor -15 24 20
25 1.3.3.1 Radiators +7 12 13
26 1.3.3.2 Blankets +7 12 13
27 1.3.4.1 Solar Arrays +35 24 33
28 1.3.4.2 Battery +7 24 26
29 1.3.4.3 Power Electronics +7 12 13
30 1.3.5.1 Omni Antennas +7 12 13
31 1.3.5.2 Telemetry & Command Electronics +7 12 13
32 1.3.6.1 Thrusters +7 12 13
33 1.3.6.2 Propellant & Pressurant Tanks +15 12 14
34 1.1.3.3 Subsystem Test Reports -15 60 51
Gate 5 S/C Integration & Test Readiness Review - 0 0
35 1.1.3.4 Spacecraft Test Reports +7 150 160
36 1.1.1.4 Spacecraft Sell Off Report +7 150 157
Gate 6 Launch Readiness Review (LRR) - 0 0
1a 1.1.1.1(a) Revise Project Plan +7 0 1
2a 1.1.1.2(a) Revise Risk Management Plan +7 0 1
3a 1.1.1.3(a) Revise Configuration Control Plan +15 0 2
4a 1.1.2.1(a) Revise Systems Engineering Plan -15 0 -
5a 1.1.2.5(a) Revise Subsystem Specifications +7 0 5
6a 1.1.2.4(a) Revise Interface Control Document +7 0 4
7a 1.1.2.2(a) Revise Requirements Verification Plan +35 0 8
8a 1.1.2.3(a) Revise Spacecraft Analysis & Design Reports +7 0 10
Totals 932 1,011

3
MGT 270 Directed Computational John Hood

Table 2. Scope Change Impacts on Effort and Cost


Original Effort Change in Effort Change in New BAC
WBS Task Original BAC
(Worker-Hours) (Worker-Hours) BAC (Actual)

1 1.1.1.1 Project Plan 640 - 78,860 0 78,000


2 1.1.1.2 Risk Management Plan 272 - 32,640 0 33,500
3 1.1.1.3 Configuration Control Plan 368 - 42,240 0 42,000
Gate 1 Integrated Baseline Review (IBR) 0 0 0 0 0
4 1.1.2.1 Systems Engineering Plan 656 - 80,160 0 83,000
5 1.1.2.5 Subsystem Specifications 8,032 - 897,600 0 1,161,600
6 1.1.2.4 Interface Control Document 1,792 - 178,560 0 221,720
7 1.1.2.2 Requirements Verification Plan 1,008 - 123,040 0 124,000
Gate 2 System Requirements Review (SRR) 0 0 0 0 0
8 1.1.2.3 Spacecraft Analysis & Design Reports 18,912 - 2,124,800 0 2,300,600
9 1.1.3.1 Spacecraft Integration & Test Plan 4,272 299 468,480 32,794 501,274
Gate 3 Preliminary Design Review (PDR) 0 0 0 0 0
10 1.1.2.8 Layouts & Drawings 9,920 694 1,070,400 74,928 1,145,328
11 1.1.3.2 Subsystem Test Plans 1,200 84 131,840 9,229 141,069
12 1.1.2.6 Spacecraft Manufacturing Plan 704 49 42,240 2,957 45,197
13 1.1.2.7 Parts, Materials, & Processes Plan 848 127 60,480 9,072 69,552
Gate 4 Critical Design Review (CDR) 0 0 0 0 0
14 1.2.1.1 Payload Transmitter 192 -30 1,476,000 -221,400 1,254,600
15 1.2.1.2 Payload Receiver 192 13 812,000 56,840 868,840
16 1.2.1.4 Payload Antennas 192 13 1,067,840 74,749 1,142,589
17 1.2.1.3 Payload Processor 768 269 995,920 348,572 1,344,492
18 1.2.2.1 Data Storage Device 432 30 1,526,160 106,831 1,632,991
19 1.2.2.2 Data Encryption Device 352 25 317,160 22,201 339,361
20 1.3.1.1 Primary Bus Structure 480 34 88,000 6,160 94,160
21 1.3.1.2 Secondary Bus Structure 384 27 53,280 3,730 57,010
22 1.3.2.2 Magnetometers 192 13 347,990 24,359 372,349
23 1.3.2.3 Sun Sensor 192 29 198,490 29,774 228,264
24 1.3.2.1 Spacecraft Control Processor 928 -139 804,840 -120,726 684,114
25 1.3.3.1 Radiators 384 27 335,680 23,498 359,178
26 1.3.3.2 Blankets 384 27 67,220 4,705 71,925
27 1.3.4.1 Solar Arrays 1,536 538 290,845 101,796 392,641
28 1.3.4.2 Battery 384 27 2,015,700 141,099 2,156,799
29 1.3.4.3 Power Electronics 576 40 1,153,960 80,777 1,234,737
30 1.3.5.1 Omni Antennas 192 13 99,540 6,968 106,508
31 1.3.5.2 Telemetry & Command Electronics 288 20 198,080 13,866 211,946
32 1.3.6.1 Thrusters 192 13 37,840 2,649 40,489
33 1.3.6.2 Propellant & Pressurant Tanks 192 29 77,440 11,616 89,056
34 1.1.3.3 Subsystem Test Reports 8,240 -1,236 6,214,800 -932,220 5,282,580
Gate 5 S/C Integration & Test Readiness Review 0 0 0 0 0
35 1.1.3.4 Spacecraft Test Reports 25,116 1,758 22,061,440 1,544,301 23,605,741
36 1.1.1.4 Spacecraft Sell Off Report 5,120 358 596,400 41,748 638,148
Gate 6 Launch Readiness Review (LRR) 0 0 0 0 0
1a 1.1.1.1(a) Revise Project Plan 0 45 0 5,520 5,520
2a 1.1.1.2(a) Revise Risk Management Plan 0 20 0 2,285 2,285
3a 1.1.1.3(a) Revise Configuration Control Plan 0 55 0 6,336 6,336
4a 1.1.2.1(a) Revise Systems Engineering Plan 0 - 0 - -
5a 1.1.2.5(a) Revise Subsystem Specifications 0 562 0 62,832 62,832
6a 1.1.2.4(a) Revise Interface Control Document 0 125 0 12,499 12,499
7a 1.1.2.2(a) Revise Requirements Verification Plan 0 353 0 43,064 43,064
8a 1.1.2.3(a) Revise Spacecraft Analysis & Design Reports 0 1,324 0 148,736 148,736
Totals 95,532 5,665 46,167,965 1,782,143 48,436,628

Methodology used to calculate new effort resulting from changes in scope – Consider the case of
WBS Element 1.1.2.5, Subsystem Specifications. Although this task has already been completed, new
scope to the original effort has been added. Therefore a new WBS Element 1.1.2.5(a), Revise Subsystem
Specifications, has been added. The original task required 8032 worker-hours of effort within the Labor
resource area, and the scope was increased 7%. Thus the additional effort required is 562 worker-hours
(8032 x 0.07 = 562).

4
MGT 270 Directed Computational John Hood
2002 2003 2004 2005
Figure 1. ID Task Name Q2 '02 Q3 '02 Q4 '02 Q1 '03 Q2 '03 Q3 '03 Q4 '03 Q1 '04 Q2 '04 Q3 '04 Q4 '04 Q1 '05 Q2 '05 Q3 '05 Q4 '05 Q1 '06
1 Project Plan
Project Gantt Chart (Revised Scope)
2 Risk Management Plan

3 Configuration Control Plan

4 Integrated Baseline Review (IBR) 6/24


New tasks are shown in blue in the 5 Systems Engineering Plan

Task Name field. 6 Subsystem Specifications

7 Interface Control Document

8 Requirements Verification Plan

9 System Requirements Review (SRR) 4/3


Critical tasks are shown in red. 10 Spacecraft Analysis & Design Reports

11 Revise Project Plan

12 Revise Risk Management Plan

13 Revise Configuration Control Plan

14 Revise Subsystem Specifications

15 Revise Interface Control Document

16 Revise Requirements Verification Plan

17 Revise Spacecraft Analysis and Design Reports

18 Spacecraft Integration & Test Plan

19 Preliminary Design Review (PDR) 9/29

20 Layouts & Drawings

21 Subsystem Test Plans

22 Spacecraft Manufacturing Plan

23 Parts, Materials, & Processes Plan

24 Critical Design Review (CDR) 2/5

25 Payload Transmitter

26 Payload Receiver

27 Payload Antennas

28 Payload Processor

29 Data Storage Device

30 Data Encryption Device

31 Primary Bus Structure

32 Secondary Bus Structure

33 Magnetometers

34 Sun Sensor

35 Spacecraft Control Processor

36 Radiators

37 Blankets

38 Solar Arrays

39 Battery

40 Power Electronics

41 Omni Antennas

42 Telemetry & Command Electronics

43 Thrusters

44 Propellant & Pressurant Tanks

45 Subsystem Test Reports

46 S/C Integration & Test Readiness Review 6/30

47 Spacecraft Test Reports

48 Spacecraft Sell Off Report

49 Launch Readiness Review (LRR)


MGT 270 Directed Computational John Hood
2002 2003 2004 2005
Figure 2. ID Task Name Q2 '02 Q3 '02 Q4 '02 Q1 '03 Q2 '03 Q3 '03 Q4 '03 Q1 '04 Q2 '04 Q3 '04 Q4 '04 Q1 '05 Q2 '05 Q3 '05 Q4 '05 Q1 '06
Project Gantt Chart 1 Project Plan

(Original Baseline) 2 Risk Management Plan

3 Configuration Control Plan

4 Integrated Baseline Review (IBR) 6/24


Critical tasks are in red. 5 Systems Engineering Plan

6 Subsystem Specifications

7 Interface Control Document

8 Requirements Verification Plan

9 System Requirements Review (SRR) 2/13

10 Spacecraft Analysis & Design Reports

11 Spacecraft Integration & Test Plan

12 Preliminary Design Review (PDR) 7/31

13 Layouts & Drawings

14 Subsystem Test Plans

15 Spacecraft Manufacturing Plan

16 Parts, Materials, & Processes Plan

17 Critical Design Review (CDR) 12/12

18 Payload Transmitter

19 Payload Receiver

20 Payload Antennas

21 Payload Processor

22 Data Storage Device

23 Data Encryption Device

24 Primary Bus Structure

25 Secondary Bus Structure

26 Magnetometers

27 Sun Sensor

28 Spacecraft Control Processor

29 Radiators

30 Blankets

31 Solar Arrays

32 Battery

33 Power Electronics

34 Omni Antennas

35 Telemetry & Command Electronics

36 Thrusters

37 Propellant & Pressurant Tanks

38 Subsystem Test Reports

39 S/C Integration & Test Readiness Review 4/26

40 Spacecraft Test Reports

41 Spacecraft Sell Off Report

42 Launch Readiness Review (LRR)

8
MGT 270 Directed Computational John Hood

Introduction

This assignment recalculates overall project costs and schedule impacts based upon revised resource costs
for the Lightweight Communications Satellite project. Table 1 below shows the change in resource costs
based upon the new data.

Table 1. Resource Cost Changes


Original Revised
Unit of Cost Change in Cost
Item Measure (Dollars) Cost (%) (Dollars)
1.0 Labor
1.1 Management Staff
1 1.1.1 General Manager / Group Director Hour 200 11% 222
2 1.1.2 Division Director Hour 170 11% 188.7
3 1.1.3 Business Manager Hour 120 11% 133.2
4 1.1.4 Program Manager Hour 150 11% 166.5
5 1.1.5 Project Manager Hour 130 11% 144.3
6 1.1.6 Software Manager Hour 150 11% 166.5
7 1.1.7 Configuration Manager Hour 125 11% 138.75
8 1.1.8 Supply Chain Manager Hour 80 11% 88.8
1.2 Analysis, Engineering, & Test Staff
9 1.2.1 Chief Systems Engineer Hour 160 11% 177.6
10 1.2.2 Systems Engineer Hour 140 11% 155.4
11 1.2.3 Senior Development Engineer Hour 130 7% 139.1
12 1.2.4 Development Engineer Hour 120 7% 128.4
13 1.2.5 Software Engineer Hour 130 7% 139.1
14 1.2.6 Test Engineer Hour 110 7% 117.7
15 1.2.7 Test Technician Hour 80 7% 85.6
1.3 Manufacturing Staff
16 1.3.1 Factory Supervisor Hour 120 7% 128.4
17 1.3.2 Senior Manufacturing Technician Hour 100 7% 107
18 1.3.3 Manufacturing Technician Hour 70 7% 74.9
1.4 Administrative Support Staff
19 1.4.1 Administrative Assistant Hour 30 7% 32.1
20 1.4.2 Quality Assurance Engineer Hour 60 7% 64.2
21 1.4.3 System Administrator Hour 70 -1% 69.3
22 1.4.4 Safety Director Hour 80 -1% 79.2
2.0 Tools & Machinery
2.1 Lab Equipment
23 2.1.1 Test Stand Set Hour 100 -1% 99
24 2.1.2 Fabrication Machinery Hour 350 -1% 346.5
25 2.1.3 Unit & Subsystem Test Equipment Hour 550 -1% 544.5
26 2.1.4 Calibration Equipment Set Hour 200 -1% 198
27 2.1.5 Unit & Subsystem Fixtures Hour 25 -1% 24.75
2.2 Satellite Factory Equipment
28 2.2.1 Vehicle Integration Fixtures Hour 50 -1% 49.5
29 2.2.2 Vehicle Test Equipment Hour 1000 -1% 990
2.3 Office Equipment
30 2.3.1 Desktop Computers Each 1400 -1% 1386
31 2.3.2 Laptop Computers Each 1800 3% 1854
32 2.3.3 Workstations Each 3000 3% 3090

2
MGT 270 Directed Computational John Hood

Table 1. Resource Cost Changes (Continued)


Original Revised
Unit of Cost Change in Cost
Item Measure (Dollars) Cost (%) (Dollars)
3.0 Materials & Installed Equipment
3.1 Installed Equipment
33 3.1.1 Thermal Vacuum Chamber Hour 20000 3% 20600
34 3.1.2 Acoustic Chamber Hour 15000 3% 15450
35 3.1.3 Anechoic Chamber Hour 50000 3% 51500
36 3.1.4 Class 100,000 Clean Room Hour 1000 3% 1030
37 3.1.5 Class 10,000 Clean Room Hour 5000 3% 5150
38 3.1.6 Class 100 Clean Bench Hour 2000 3% 2060
39 3.1.7 Composite Curing Equipment Hour 1000 3% 1030
40 3.1.8 Metal Fabrication Equipment Hour 500 3% 515
3.2 Spacecraft Structural Materials
41 3.2.1 Pre-Fabricated Bus Structure Pound 100 3% 103
42 3.2.2 Non-Deployable Mechanisms Each 5000 3% 5150
43 3.2.3 Deployable Mechanisms Each 2000 3% 2060
44 3.2.4 Carbon Matrix Composites Sq. Foot 500 3% 515
45 3.2.5 Titanium Material Pound 1500 3% 1545
46 3.2.6 Aluminum Sheet Metal Sq. Foot 200 3% 206
47 3.2.7 Inconel Material Sq. Foot 500 3% 515
3.3 Electrical Power Components
49 3.3.1 Power Distribution Unit Slices Each 20000 3% 20600
50 3.3.2 Electrical Unit Cases Each 500 3% 515
51 3.3.3 Electrical Unit Attachment Hardware Kits Each 500 3% 515
52 3.3.4 Power Conditioning Unit Slices Each 18000 3% 18540
53 3.3.5 Single Junction Solar Cells Each 75 3% 77.25
54 3.3.6 Dual Junction Solar Cells Each 150 3% 154.5
55 3.3.7 Solar Array Backing Structure Sq. Foot 100 3% 103
56 3.3.8 Solar Cell Adhesive Sq. Foot 15 3% 15.45
57 3.3.9 Solar Cell Cover Glass Sq. Foot 20 3% 20.6
58 3.3.10 Large Capacity Battery Cells Each 75000 3% 77250
59 3.3.11 Medium Capacity Battery Cells Each 50000 3% 51500
60 3.3.12 Small Capacity Battery Cells Each 35000 3% 36050
61 3.3.13 Battery Cell Thermal Sleeves Each 10000 3% 10300
62 3.3.14 Integrated Circuit Board Sq. Foot 25000 3% 25750
63 3.3.15 Power Management Processor Each 175000 3% 180250
64 3.3.16 Wiring Harness Foot 150 3% 154.5
3.4 Thermal Control Components
65 3.4.1 Straight Heat Pipes Each 20000 3% 20600
66 3.4.2 Curved Heat Pipes Each 25000 3% 25750
67 3.4.3 Heat Pipe Transition Joints Each 500 3% 515
68 3.4.4 Heat Pipe Attachment Hardware Kits Each 250 3% 257.5
69 3.4.5 Heat Pipe Wicks Each 2000 3% 2060
70 3.4.6 Thermal Blankets Sq. Foot 550 3% 566.5
71 3.4.7 Thermal Blanket Support Structure Sq. Foot 200 3% 206
72 3.4.8 Thermal Blanket Adhesive Sq. Foot 10 3% 10.3
73 3.4.9 Radiator Quartz Mirror Material Sq. Foot 5000 3% 5150
74 3.4.10 Radiator Backing Structure Sq. Foot 1000 3% 1030
75 3.4.11 Radiator Attachment Hardware Kits Each 200 3% 206
76 3.4.12 Louver Hinges & Support Structure Kits Each 250 3% 257.5
77 3.4.13 Louver Bearings Each 15 3% 15.45
78 3.4.14 Louvers Sq. Foot 7500 3% 7725
79 3.4.15 Heaters & Switches Each 250 3% 257.5

3
MGT 270 Directed Computational John Hood

Table 1. Resource Cost Changes (Continued)


Original Revised
Unit of Cost Change in Cost
Item Measure (Dollars) Cost (%) (Dollars)
3.5 Communications Components
80 3.5.1 Transmitter Unit Slices Each 70000 3% 72100
81 3.5.2 Receivers Unit Slices Each 46000 3% 47380
82 3.5.3 Reflectors Each 100000 3% 103000
83 3.5.4 Sub-Reflectors & Feeds Each 75000 3% 77250
84 3.5.5 Encryption Devices Each 40000 3% 41200
85 3.5.6 Encryption Keys Each 40000 3% 41200
86 3.5.7 Communications Processor Each 350000 3% 360500
87 3.5.8 Transmitter & Receiver Cables Foot 200 3% 206
88 3.5.9 Data Storage Memory Slices Each 180000 3% 185400
3.6 Telemetry & Command Components
89 3.6.1 T&C Transmitter Slices Each 10000 3% 10300
90 3.6.2 T&C Receiver Slices Each 6000 3% 6180
91 3.6.3 Omni Antennas Each 25000 3% 25750
3.7 Guidance, Navigation & Control
92 3.7.1 Control Moment Gyros Each 150000 3% 154500
93 3.7.2 Control Moment Gyro Electronics Each 50000 3% 51500
94 3.7.3 Torque Rods Each 150000 3% 154500
95 3.7.4 Star Tracker Catalog Each 50000 3% 51500
96 3.7.5 Star Trackers Each 150000 3% 154500
97 3.7.6 Sun Sensor Case Each 750 3% 772.5
98 3.7.7 Sun Sensor Each 70000 3% 72100
99 3.7.8 Sun Sensor Electronics Each 4000 3% 4120
100 3.7.9 Inertial Reference Units Each 250000 3% 257500
101 3.7.10 Earth Sensors Each 50000 3% 51500
102 3.7.11 Magnetometer Magnet Kits Each 74500 3% 76735
103 3.7.12 Magnetometer Case Each 500 3% 515
104 3.7.13 Reaction Wheels Each 80000 3% 82400
105 3.7.14 GNC Sensor Attachment Hardware Kit Each 175 3% 180.25
106 3.7.15 Guidance & Navigation Processors Each 275000 3% 283250
3.8 Propulsion Components
107 3.8.1 Large Thrusters Each 45000 3% 46350
108 3.8.2 Medium Thrusters Each 20000 3% 20600
109 3.8.3 Small Thrusters Each 5000 3% 5150
110 3.8.4 Thruster Pressure Sensors Each 50 3% 51.5
111 3.8.5 Thruster Catalyst Cu. Foot 1000 3% 1030
112 3.8.6 Propellant Tanks Cu. Foot 500 3% 515
113 3.8.7 Pressurant Tanks Cu. Foot 200 3% 206
114 3.8.8 Propellant Tank Baffles Each 100 3% 103
115 3.8.9 Propellant Tank Diaphragms Each 200 3% 206
116 3.8.10 Lines, Valves, & Filters Each 5000 3% 5150
117 3.8.11 Hydrazine Propellant Pound 1000 3% 1030
118 3.8.12 Helium Pressurant Pound 10 3% 10.3

The project schedule is included in an appendix. The schedule also shows the current status of each task.