NRP : 02411640000030
Kelas : Manpro - B
1. Given the project information below, what is the probability of completing the National
Holiday Toy project in 93 time units?
Jawab
𝑂𝑇+4 ×𝑀𝑇+𝑃𝑇
AT = 6
Dimana,
AT : Actual time
OT : Optimum time
MT : Most probable time
PT : Presimistic time
𝑏−𝑎 2
Varians = ( )
6
Dimana,
b : Presimistic time
a : Optimum time
AON Network
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
93−86
Z=
√9+4+9+25+1+1
7
Z= =1
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,84. Dengan nilai z = 1,
maka probabilitasnya adalah 0,84 yang berarti terdapat peluang 84% menyelesaikan proyek
sebelum 86 unit waktu.
2. The Global Tea and Organic Juice companies have merged. The following information
has been collected for the “Consolidation Project.”
𝑂𝑇+4 ×𝑀𝑇+𝑃𝑇
AT = 6
Contoh perhitungan pada ativitas 1:
16+4 ×19 +28
AT = = 20
6
Act time
Act Description Predecessor a opt m ml b pess
te
𝑏−𝑎 2
Varians = ( )
6
Contoh perhitungan pada ativitas 1:
28−16 2
Varians = ( ) =4
6
Act Variance
Act Description Predecessor a opt m ml b pess
time te [(b-a)/6]^2
Te = 114
Critical path = 1,5,6,8,12,14,15
d. What is the probability of completing the project by day 112? Within 116 days?
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
112−114
Z=
√4+25+1+9+9+1
−2
Z= = -0,28
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,39. Dengan nilai z = -
0,28, maka probabilitasnya adalah 0,39 yang berarti terdapat peluang 39% menyelesaikan
proyek sebelum 114 unit waktu.
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
116−114
Z=
√4+25+1+9+9+1
+2
Z= = +0.28
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,61. Dengan nilai z =
+0,28, maka probabilitasnya adalah 0,61 yang berarti terdapat peluang 61% menyelesaikan
proyek sebelum 114 unit waktu.