COMMENTS RESOLUTION

SHEET [ CRS ]
CONTRACT NUMBER : GC14104300 QP PROJECT NUMBER 3788
CONTRACT TITLE : EPIC FOR NEW SOUR GAS COMPRESSOR AT NGL-3 PLANT, MESAIEED
QP EXTERNAL TRANSMITTAL REFERENCE : EDM/GC14104300/EXT/TN/2828 DATE 05-05-16
DOCUMENT NUMBER : 3788-M3MP-1-19-0017 DOCUMENT REVISION 0
DOCUMENT TITLE : Method Statement for Installation of Temporary Supports for Valve Assembly in Cooler Area
No. QP COMMENTS CONTRACTOR RESPONSE
All weld joints carried out for the purpose of providing temporary
10 support to be approved after conducting proper inspection tests. Noted and added. See Item 8.7

In JSA -
1. Activity no.3 - Add: No simultaneous works below the 1. Activity no.3 has been revised,
scaffolding.
2. Activity no.6 - Add: in control measures for electrocution, 2. Note, and added. See Activity no.6
ensure proper earthing to the equipment and records to be
kept at site. All power tools to be double insulated. 3. Added in Activity no.6.
1 3. Activity no.6 - In Hazards column, add sharp edges.
4. 4. Add activity - refixing of existing support to the newly cast 4. Noted, please see revised activity no.08
concrete. Include the corresponding hazards and control
measures. 5. Noted, new section added. Please see activity no.09
5. 5. Include waste management as separate activity.
In JSA -
1. Activity no.3 - Add: No simultaneous works below the
scaffolding.
2. Activity no.6 - Add: in control measures for electrocution,
ensure proper earthing to the equipment and records to be
2 kept at site. All power tools to be double insulated. Comments repeated (See CONTRACTOR response above in No#02)
3. Activity no.6 - In Hazards column, add sharp edges.
4. Add activity - refixing of existing support to the newly cast
concrete. Include the corresponding hazards and control
measures.
5. 5. Include waste management as separate activity.
 Cutting, demolition of the existing pavement below and very
near the existing pipes, cable trays, and structures shall be - Noted. Please see Item 8.11
done manually.
- All equipment will be inspected prior to mobilization and will be indicated in
 For any use of Mechanical equipment for the works, It shall be
permit. Approval of permit will be considered as approval of operations to
discussed on site and after QP NGL Safety &
3 commence work.
Operations approval the work may proceed.
 A Full time Safety Officer shall be placed on this area - A full time safety Office will be placed in the area during working period.
specifically to monitor the Safe work procedure.
- Approval of this method statement and permit will be considered as approval
 Finally, this shall be subject to approval from the End User.
from end user.

In Section :-
1. Upon completion of the inspection stated in item # 7, all - Noted and incorporated. Please see Item 8.10 & 8.15
existing anchor bolts connecting the supports to the existing
pavement slab shall be removed prior to pavement breaking.
These bolts shall be cast in during the reinstatement of the
same pavement.
- Noted and incorporated. Please see Item 8.16
2. Concrete chipped and the post drilled bolt holes made on
4 existing pavement as per item # 4 of this section shall be
repaired and re-instated with approved concrete repair grout
and mortar after removal of the temporary supports.
3. Cast in site temporary pipe support foundation / sleeper (item - Temporary foundation will be demolished and debris disposed in designated
# 2) shall be provided with proper lifting hooks or sleeves to area. Please see item 8.17
enable removal of this foundation after the removal of the
temporary supports.

Maximum member weight is 400 Kg.

Item 5 states: Beams will be placed manually? Shifting of beams under the pipe rack to the location by using Manual Hydraulic
5 Please specify the weight of these beams. trolley, Placing the Temporary supports to its location by using lifting tools (Slings,
Ropes, etc.) & Manual Hydraulic trolley. Please see item 8.4
Also consider adding: "...or by use of mechanical aids (chain blocks)". Due to the existing services and the space constraint, mechanical lifting is not possible.

6 7.3 If there is a likelihood that the excavation could reach 1.2m


depth, then it is much better to focus on the higher severity risk and IP-OPS-027 - Gas Operations-Confined Space will be followed. Please see 7.3.6
6
treat this activity as a confined space and have all the standard
controls in place i.e. all personnel shall undergo confined space
training, gas monitoring, access/egress, emergency response etc.

Please add: Detailed review of the latest as-built under-ground


7 information/drawings with QP Asset Holder. Noted and incorporated. Please see Item 7.1.4

Add Vibrator to the list of equipment Added. Please see Item 6.1.13. Works will be carried out as per Approved Method
8
statement for concrete works referred in Item 3.

Due to the existing services lifting operations cannot be carried out using equipment.
Item 7.2.4, Contractor to include Approved lifting plan prior to work Hence, lifting will be manual means only.
start.
b) Item 8.0.9, Contractor to include Surround equipment as-built Approved project survey bench mark will be used to record level. Please see Item 8.9
elevation, to provide survey report reference to monitor if any
settlement occurred during construction & completion of work.
9 c) Item 8.0, Contractor to include requirements for civil activities for Works will be carried out as per Approved Method statement for Earthworks referred
compaction test for formation level prior to blinding & backfilling layer in Item 3. Please see Item 8.14
by layer as per projects specs requirements.
d) Temporary support requires design calculations & approval by Document approved in Code-2. AFC document will be available prior to
engineer prior to implementation / execution. commencement of work.