Client: Vingroup
Main duties:
Supervise daily construction works of the
Contractors to comply with the signed contracts
between the parties, achive the best quanlity
and make sure safety during work.
Inspecting completed construction works.
Control construction shedule of the project,
construction material and machinary.
Review and approve shop drawing and also
constructed quantity from the contracts.
Manage and control labor safety and
environmental sanitation in the site.
The Landmark 2 are a luxury apartment that
include 50 superstructure floors and 3
basements which constructed by top down
method. The basement slab is flat slab with
capital and drop at the column top. Average
area of a superstructure slab is approximately
1600m2, 622 units.The structural superstructure
is reinforcement concrete core and wall system.
Main duties:
Manage and operate all works on the site such
as: material, manpower, construction machinary
and equipment, schedule, subcontracts…
Review and approve shop drawing, statement
construction methods.
Manage and control labor safety and
environmental sanitation in the site.
Meeting to the parties, approve and sign
constructed volume.
Key characteristics: The project have 1330
Trang 2/5
Nguyen Van Hung
Client: P&G
Main duties:
Manage and operate all works on the site such
as: material, manpower, construction machinary
and equipment, schedule, subcontracts…
Review and approve shop drawing, statement
construction methods.
Manage and control labor safety and
environmental sanitation in the site.
Meeting to the parties, approve and sign
constructed volume.
Main Features of the project: two factory of
45mx60m that is steel building, and a
wastewater treatment system with capacity of
20.000m3/day.
Client: ViettinBank.
Main duties:
Manage and operate all works on the site such
as: material, manpower, construction machinary
and equipment, schedule, subcontracts
Review and approve shop drawing, statement
construction methods.
Manage and control labor safety and
environmental sanitation in the site.
Meeting to the parties, approve and sign
constructed volume for subcontracts.
Organize and invite consultant supervision and
relative parties to inspect for construction items,
Trang 3/5
Nguyen Van Hung
completed phase.
Information project: ViettinBank tower have 23
floors and Cinco building of 35 floors. Europa
Windows undertake to construct aluminium
glass items and curtain wall. Used glasses are
laminate, tempered, sound and temperature
isolate box glass.