Вы находитесь на странице: 1из 8

RINCIAN ANGGARAN BIAYA (RAB)

PAGAR BATAKO DAN BRC BAGIAN SELATAN


PALU CITY SQUARE

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Ls 1.00 1,500,000.00 1,500,000.00
2 Pengukuran dan Pasang Buowplank Ls 1.00 2,250,000.00 2,250,000.00
3 Administrasi dan Dokumentasi Ls 1.00 3,500,000.00 3,500,000.00
Sub Total 7,250,000.00
II Pekerjaan Tanah / Pasir
1 Galian Tanah Kontruksi M³ 113.20 46,900.00 5,309,080.00
2 Urugan Kembali Bekas Galian M³ 28.30 21,350.00 604,205.00
3 Urugan Pasir Bawah Galian M³ 15.30 85,260.00 1,304,478.00
Sub Total 7,217,763.00
III Pekerjaan Pagar Batako Type I = 60 mtr
1 Pasangan Batu Kosong M³ 7.20 458,134.20 3,298,566.24
2 Pasangan Pondasi Batu Kali M³ 18.90 838,734.00 15,852,072.60
3 Pasangan Dinding Batako M² 103.68 125,617.00 13,023,970.56
4 Plesteran Dinding M² 207.36 55,784.00 11,567,370.24
5 Acian Dinding M² 207.36 32,383.00 6,714,938.88
6 Plesteran Pondasi M² 36.00 55,784.00 2,008,224.00
7 Acian Pondasi M² 36.00 32,383.00 1,165,788.00
8 Sloof 15/20 beton K 225 M³ 1.73 5,445,373.36 9,420,495.91
9 Kolom 20/20 beton K 225 M³ 3.90 6,151,185.16 23,989,622.11
10 Ring Balok 15/20 beton K 225 M³ 1.73 5,445,373.36 9,420,495.91
Sub Total 96,461,544.44
IV Pekerjaan Pagar Batako Type II = 32,50 mtr
1 Pasangan Batu Kosong M³ 3.90 458,134.20 1,786,723.38
2 Pasangan Pondasi Batu Kali M³ 13.16 838,734.00 11,037,739.44
3 Pasangan Batako M² 56.16 125,617.00 7,054,650.72
4 Plesteran Dinding M² 112.32 55,784.00 6,265,658.88
5 Acian Dinding M² 112.32 32,383.00 3,637,258.56
6 Plesteran Pondasi M² 26.00 55,784.00 1,450,384.00
7 Acian Pondasi M² 26.00 32,383.00 841,958.00
8 Sloof 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
9 Kolom 20/20 beton K 225 M³ 2.33 6,151,185.16 14,332,261.41
10 Ring Balok 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
Sub Total 56,643,936.30
V Pekerjaan Pagar Batako Type III = 140 mtr
1 Pasangan Batu Kosong M³ 16.80 458,134.20 7,696,654.56
2 Pasangan Pondasi Batu Kali M³ 56.70 838,734.00 47,556,217.80
3 Pasangan Batako M² 239.40 125,617.00 30,072,709.80
4 Plesteran Dinding M² 478.80 55,784.00 26,709,379.20
5 Acian Dinding M² 478.80 32,383.00 15,504,980.40
6 Plesteran Pondasi M² 98.00 55,784.00 5,466,832.00
7 Acian Pondasi M² 98.00 32,383.00 3,173,534.00
8 Sloof 15/20 beton K 225 M³ 3.57 5,445,373.36 19,439,982.88
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6

9 Kolom 20/20 beton K 225 M³ 5.88 6,151,185.16 36,168,968.72


10 Ring Balok 15/20 beton K 225 M³ 3.57 5,445,373.36 19,439,982.88
Sub Total 211,229,242.24
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6

VI Pekerjaan Pagar BRC Ø 8 = 277,5 mtr


1 Pekerjaan Pondasi Setempat K 225 M³ 4.00 6,793,380.80 27,173,523.20
2 Pekerjaan Pondasi Menerus M³ 59.00 838,734.00 49,485,306.00
3 Pekerjaan Sloof 15/20 M³ 8.33 5,445,373.36 45,332,733.19
4 Pekerjaan Pagar BRC 240 X 170 Lbr 277.50 536,632.72 148,915,580.58
Sub Total 270,907,142.97
VII Pekerjaan Lain-lain
1 Pembersihan Akhir Lahan Ls 1.00 1,000,000.00 1,000,000.00
0.00
Sub Total 1,000,000.00
Total Harga Pekerjaan 650,709,628.95
REKAPITULASI ANGGARAN BIAYA
PAGAR BATAKO DAN BRC BAGIAN SELATAN
PALU CITY SQUARE TAHUN 2015
No. Uraian Pekerjaan Jumlah Harga
1 2 3

I Pekerjaan Persiapan 7,250,000.00


II Pekerjaan Tanah / Pasir 7,217,763.00

III Pekerjaan Pagar Batako Type I = 60 mtr 96,461,544.44

IV Pekerjaan Pagar Batako Type II = 32,50 mtr 56,643,936.30


V Pekerjaan Pagar Batako Type III = 140 mtr 211,229,242.24
VI Pekerjaan Pagar BRC Ø 8 = 277,5 mtr 270,907,142.97
VII Pekerjaan Lain-lain 1,000,000.00

Total Harga Pekerjaan 650,709,628.95


PPn 10% 65,070,962.89
Total Harga Pekerjaan + PPn 10% 715,780,591.84
Dibulatkan 715,780,000.00

Terbilang : " Tujuh Ratus Lima Belas Juta Tujuh Ratus Delapan Puluh Ribu Rupiah "
ANALISA HARGA SATUAN

PEKERJAAN : PAGAR BATAKO DAN BRC BAGIAN SELATAN


LOKASI : PALU CITY SQUARE
THN. ANGGARAN : 2015

No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

I Pekerjaan Tanah, Pondasi dan Pasangan Dinding


1 1 M³ Galian Tanah
Pekerja Org 0.550 74,250.00 40,837.50
Mandor Org 0.055 112,000.00 6,160.00
Total Harga Rp. 46,997.50

2 1 M³ Urugan Kembali Bekas Galian


Pekerja Org 0.250 74,250.00 18,562.50
Mandor Org 0.025 112,000.00 2,800.00
Total Harga Rp. 21,362.50

3 1 M³ Urugan Sirtu Bawah Galian


Pekerja Org 0.100 74,250.00 7,425.00
Mandor Org 0.020 112,000.00 2,240.00
Sirtu M³ 1.200 182,000.00 218,400.00
Total Harga Rp. 228,065.00

4 1 M³ Urugan Tanah Bawah Galian


Pekerja Org 0.100 74,250.00 7,425.00
Mandor Org 0.020 112,000.00 2,240.00
Tanah Urug M³ 1.200 63,000.00 75,600.00
Total Harga Rp. 85,265.00

5 1 M³ Urugan Pasir Bawah Pondasi/Lantai


Pekerja Org 0.300 74,250.00 22,275.00
Mandor Org 0.100 112,000.00 11,200.00
Pasir Urug M³ 1.200 175,000.00 210,000.00
Total Harga Rp. 243,475.00

6 1 M³ Pasangan Batu Kosong (Aanstamping)


Batu Kali/Belah M³ 1.200 231,490.00 277,788.00
Pasir urug M³ 0.432 175,000.00 75,600.00
Pekerja Org 0.780 74,200.00 57,876.00
Tukang Org 0.390 98,000.00 38,220.00
Kepala Tukang Org 0.039 109,800.00 4,282.20
Mandor Org 0.039 112,000.00 4,368.00
Total Harga Rp. 458,134.20

7 1 M³ Pasangan Batu Kali 1 : 4


Batu Kali/Belah M³ 1.100 231,490.00 254,639.00
Semen PC Zak 3.260 85,000.00 277,100.00
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Pasir Pasang M³ 0.520 203,000.00 105,560.00


Pekerja Org 1.500 74,200.00 111,300.00
Tukang Batu Org 0.750 98,000.00 73,500.00
Kepala Tukang Org 0.075 109,800.00 8,235.00
Mandor Org 0.075 112,000.00 8,400.00
Total Harga Rp. 838,734.00

8 1 M² Pasangan Dinding Batako


Batu Bata Bh 25.000 2,500.00 62,500.00
Semen PC Zak 0.230 85,000.00 19,550.00
Pasir Pasang M³ 0.043 203,000.00 8,729.00
Pekerja Org 0.300 74,200.00 22,260.00
Tukang Org 0.100 98,000.00 9,800.00
Kepala Tukang Org 0.010 109,800.00 1,098.00
Mandor Org 0.015 112,000.00 1,680.00
Total Harga Rp. 125,617.00

9 1 M² Plesteran
Semen PC Zak 0.125 85,000.00 10,625.00
Pasir M³ 0.024 203,000.00 4,872.00
Pekerja Org 0.300 74,200.00 22,260.00
Tukang Org 0.150 98,000.00 14,700.00
Kepala Tukang Org 0.015 109,800.00 1,647.00
Mandor Org 0.015 112,000.00 1,680.00
Total Harga Rp. 55,784.00

10 1 M² Acian
Semen PC Zak 0.065 85,000.00 5,525.00
Pekerja Org 0.200 74,200.00 14,840.00
Tukang Org 0.100 98,000.00 9,800.00
Kepala Tukang Org 0.010 109,800.00 1,098.00
Mandor Org 0.010 112,000.00 1,120.00
Total Harga Rp. 32,383.00

II Pekerjaan Beton
1 1 M² Rabat Beton
Semen PC Zak 4.360 85,000.00 370,600.00
Pasir M³ 0.520 203,000.00 105,560.00
Batu Pecah 2/3 M³ 0.870 350,000.00 304,500.00
Pekerja Org 1.650 74,200.00 122,430.00
Tukang Org 0.250 98,000.00 24,500.00
Kepala Tukang Org 0.050 109,800.00 5,490.00
Mandor Org 0.080 112,000.00 8,960.00
Total Harga Rp. 942,040.00

2 1 M³ Beton Mutu fc' = 19,3 Mpa (K 225)


Semen PC Zak 7.420 85,000.00 630,700.00
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Pasir M³ 0.499 203,000.00 101,297.00


Batu Pecah 2/3 M³ 0.776 350,000.00 271,600.00
Air M³ 0.215 28,000.00 6,020.00
Pekerja Org 1.650 74,200.00 122,430.00
Tukang Org 0.275 98,000.00 26,950.00
Kepala Tukang Org 0.028 109,800.00 3,074.40
Mandor Org 0.083 112,000.00 9,296.00
Total Harga Rp. 1,171,367.40

3 10 Kg Pekerjaan Pembesian
Besi Beton Kg 11.000 19,500.00 214,500.00
Kawat Beton M³ 0.300 25,000.00 7,500.00
Pekerja Org 0.070 74,200.00 5,194.00
Tukang Besi Org 0.070 98,000.00 6,860.00
Kepala Tukang Org 0.007 109,800.00 768.60
Mandor Org 0.004 112,000.00 448.00
Total Harga Rp. 235,270.60
Per Kg Besi Rp. 23,527.06

4 1 M² Pekerjaan Begesting
Kayu Kelas III M³ 0.030 1,500,000.00 45,000.00
Paku Biasa Kg 0.400 20,000.00 8,000.00
Mould Oil Ltr 0.200 40,000.00 8,000.00
Multiplex 6mm Lbr 0.350 130,000.00 45,500.00
Kayu Doken Btg 0.500 18,000.00 9,000.00
Pekerja Org 0.300 74,200.00 22,260.00
Tukang Org 0.260 98,000.00 25,480.00
Kepala Tukang Org 0.026 109,800.00 2,854.80
Mandor Org 0.005 112,000.00 560.00
Total Harga Rp. 166,654.80

5 1 M³ Pekerjaan Plat Beton Bertulang K 225


Beton Bertulang M³ 1.000 1,171,367.40 1,171,367.40
Bekesting M² 6.000 166,654.80 999,928.80
Pembesian Kg 200.000 23,527.06 4,705,412.00
Total Harga Rp. 6,876,708.20

6 1 M³ Pekerjaan Sloof /Ring Balk K 225


Beton Bertulang M³ 1.000 1,171,367.40 1,171,367.40
Bekesting M² 4.470 166,654.80 744,946.96
Pembesian Kg 150.000 23,527.06 3,529,059.00
Total Harga Rp. 5,445,373.36

7 1 M³ Pekerjaan Kolom K 255


Beton Bertulang M³ 1.000 1,171,367.40 1,171,367.40
Bekesting M² 4.470 166,654.80 744,946.96
Pembesian Kg 180.000 23,527.06 4,234,870.80
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Total Harga Rp. 6,151,185.16

8 1 M³ Pekerjaan Pondasi Beton Bertulang K 225


Beton Bertulang M³ 1.000 1,171,367.40 1,171,367.40
Bekesting M² 5.500 166,654.80 916,601.40
Pembesian Kg 200.000 23,527.06 4,705,412.00
Total Harga Rp. 6,793,380.80

9 1 M³ Pekerjaan Pondasi Beton Bertulang K 175


Beton Bertulang M³ 1.000 1,171,367.40 1,171,367.40
Bekesting M² 5.500 166,654.80 916,601.40
Pembesian Kg 150.000 23,527.06 3,529,059.00
Total Harga Rp. 5,617,027.80

III Pekerjaan BRC


1 1 M¹ Pagar BRC 175
Beton K 175 untuk Pondasi M³ 0.026 5,617,027.80 146,042.72
BRC t = 175 mm + Assesories Lbr 1.000 238,000.00 238,000.00
Tiang Pagar BRC Ø2" Galvanis Unit 1.000 91,000.00 91,000.00
Pekerja Org 0.550 74,200.00 40,810.00
Tukang Batu Org 0.100 98,000.00 9,800.00
Kepala Tukang Org 0.100 109,800.00 10,980.00
Total Harga Rp. 536,632.72

2 1 M² Pintu Pagar BRC t = 2 cm


BRC t = 2 cm + Assesories M² 1.000 450,000.00 450,000.00
Pekerja Org 0.750 74,200.00 55,650.00
Tukang Batu Org 0.350 98,000.00 34,300.00
Kepala Tukang Org 0.350 109,800.00 38,430.00
Total Harga Rp. 578,380.00