Академический Документы
Профессиональный Документы
Культура Документы
Training
1
Please keep your cell phone in Vibration/Silent Mode
PROJECT
MANAGEMENT
2
So what is a Project then ?
3
Definitions of Project
A Project is a Human Activity that achieves a clear Objective against
a Time Scale.
4
PROJECT IS A
TEMPORARY
ENDEAVOUR
UNDERTAKEN TO CREATE
A UNIQUE
PRODUCT
OR SERVICE
5
Any ‘WORK’ which is undertaken for
the ‘betterment’ of ‘human life’ with
the help of ‘resources’, and completed
in a given ‘time’ can be called as a
‘PROJECT’.
6
PROJECT IS A SET OF
INTERRELATED TASKS
THAT ARE UNDERTAKEN
BY AN ORGANIZATION
•To meet defined objectives,
•Has an agreed start and finish time,
•Is constrained by cost and
•Has specified performance
requirements and resources
(THE ASSOCIATION OF PROJECT MANAGERS, U.K.)
7
PROJECT MANAGEMENT IS THE
APPLICATION OF KNOWLEDGE,
SKILLS, TOOLS AND TECHNIQUES
TO PROJECT ACTIVITIES
8
Benefits of Microsoft Project Training
9
THIS INVOLVES BALANCING OF COMPETING
DEMANDS AMONG:-
QUALITY
&
PERFORMANCE
PROJECT SCOPE
10
Project Traingle
11
12
What Does Project Management Facilitate?
13
PROJECT MANAGEMENT OVERVIEW
Projects are being undertaken and managed by
human civilizations since centuries. Some of the
well known examples are:
• Building of pyramids in Egypt
• Building of Aqueducts in Rome
• Building of TajMahal in India
• Shifting of capital from Delhi to Daulatabad
14
The Project Manager should aim to achieve his mission by
DEVELOPMENT
& DEFINATION
PR O PO SAL
EVALUATION
SCOPE
AUTHORIZATION
SCHEDULE
BUDGET
RESOURCES
P LA N N I N G
ORGANIZATION
DETAIL
STAGES OF A PROJECT
SANCTION
ENGINEERING
& DESIGN
PROCUREMENT
MANUFACTURING
& CONSTRUCTION
TRIALS
I M PLE M E NTAT I O N
& COMMISSIONING
DOCUMENTATION
SNAG LIST &
FAILURE ANALYSIS
LEARNINGS
HAND OVER
OPERATION &
CLOSING
MAINTENANCE
17
What is Project Life Cycle ?
Collectively project phases are termed as Project Life
Cycle
18
What is essentially defined in Project Life Cycle ?
19
Characteristics of Project Phases
What is a Deliverable?
A deliverable is a tangible, verifiable work product, e.g.
feasibility study, a detailed design, a working prototype etc.
20
MAIN CAUSES OF A PROJECT FAILURE
Inadequate Project Formulation
Poor field investigations
Inadequate information
Inaccurate cost estimations
Lack of experience
Inadequate Project Analysis
Poor Decisions
21
MANAGEMENT FAILURES
Planning Failure
Organizational Failure
Resource Failure
Directional Failure
Controlling Failure
Coordination Failure
Other Failures
22
What is Project Management ?
23
What is a Project Management Framework ?
24
PROJECT MANAGEMENT KNOWLEDGE
AREAS RECOGNIZED BY PMI
25
Project Management Component Processes
26
An Overview
Of
Microsoft Project
R.SRINIVASAN
27
Different Versions of Microsoft Project 2007
28
Features of Microsoft Project 2007
29
Features of Microsoft Project 2007
Timesheet Lock Downs
Protect Saved Baselines
Risk Management
Define Timesheet Views
Multiple Timesheet Approvers
Enterprise File Open Dialog
Delete Resources
Document Check-in/Check-Out
Document Versions
Pick Lists and Look up Tables in Enterprise Custom Fields
Microsoft Outlook Integration
Renamed Custom Fields Appear on Views Page
30
Other Similar Products
Computer Associates – Super project
Sure Trak Project Manager (primavera)
Virtual Boss
Ajera
Micro Planner X-Pert and Micro Planner Manager
Smartworks - Project Planner 4.8
Primavera
Fast Track Schedule
BUGTRACK
Evolve
Prolog
PertMaster
31
PROJECT INTERFACE
32
33
34
Topics
WHAT IS PROJECT 2007? LINKING TASKS WITHIN A PROJECT
WHAT IS A PROJECT? UNLINKING TASKS WITHIN A PROJECT
7HY USE PROJECT 2003? USING LAG TIME AND LEAD TIME
OPENING MICROSOFT PROJECT 2003 SPLITTING A TASK
INTERFACE OVERVIEW CALENDAR TYPES
USING TASK PANES, MENUS AND TOOLBARS SETTING UP THE CALENDAR
CLOSING MICROSOFT PROJECT 2003 CREATING A NEW CALENDAR
MENU OVERVIEW CHANGING CALENDAR VIEWS
USING STANDARD & FORMATTING TOOLBAR ADJUSTING THE TIMESCALE
USING THE PROJECT GUIDE BASELINE BASICS
OPENING PROJECT FILES SAVING A BASELINE
SAVING PROJECT FILES FOR THE FIRST TIME VIEWING A BASELINE
RE-SAVING A PROJECT FILE CLEARING A BASELINE
SWITCHING BETWEEN OPEN PROJECTS SETTING AN INTERIM PLAN
CLOSING PROJECT FILES VIEWING AN INTERIM PLAN
USING THE HELP MENU & HELP TASK PANE CLEARING AN INTERIM PLAN
USING THE OFFICE ASSISTANT WHAT IS THE CRITICAL PATH?
USING THE TYPE A QUESTION BOX HOW DOES PROJECT DETERMINE THE CRITICAL PATH?
GETTING HELP IN A DIALOG BOX VIEWING THE CRITICAL PATH
PLANNING YOUR PROJECT SHORTENING THE CRITICAL PATH
CREATING A PROJECT CHECKING SPELLING IN A PROJECT
ENTERING PROJECT INFORMATION SELECTING TEXT
SETTING WORKING TIME CUTTING, COPYING, AND PASTING
ENTERING NEW TASKS USING UNDO AND REDO
CHANGING A TASK’S DURATION INSERTING PAGE BREAKS
MOVING A TASK USING ZOOM
INSERTING A TASK USING THE VIEW BAR
DELETING A TASK USING BASIC VIEWS
OPENING THE TASK INFORMATION DIALOG USING ADVANCED VIEWS
TASK TYPES USING THE FIND DIALOG
SETTING MILESTONES SETTING PAGE OPTIONS
CREATING RECURRING TASKS SETTING MARGINS
CREATING SUBTASKS SETTING HEADERS
CREATING SUMMARY TASKS SETTING FOOTERS
TYPES OF CONSTRAINTS MODIFYING THE LEGEND
CREATING A CONSTRAINT CHANGING VIEW SETTINGS
SETTING TASK DEADLINES OPENING PRINT PREVIEW
CONSTRAINTS VS. DEADLINES USING PRINT PREVIEW
USING PRINT COMMANDS
USING THE TASK ENTRY VIEW USING THE PRINT DIALOG
USING THE TASK USAGE VIEW USING THE PROJECT GUIDE FOR PRINTING WIZARD
USING THE TRACKING GANTT VIEW
ABOUT TASK INDICATORS
LINK TYPES
35
Learning Methodology
Defining Tasks
Resources
Tracking
Reporting
49
Best Learning Approach
The FIRST STEP is to Plan and schedule the project's tasks.
✓ Define the project
✓ Define general working times
✓ List the tasks in the project
✓ Organize tasks into phases
✓ Schedule tasks
✓ Link to or attach more task information
✓ Add columns of custom information
✓ Set deadlines and constraint tasks
✓ Identify risks to the project
✓ Add documents to the project
✓ Publish project information to the Web
After planning the tasks, we have to define the RESOURCES to build the
project's team and assign people to tasks.
50
Best Learning Approach
51
Best Learning Approach
52
Best Learning Approach
53
Indicators
Types of Indicators
Misc Indicators
Constraint Indicators
Task Type Indicators
Work Group Indicators
Contour Indicators
54
TASKS
55
Tasks
There are four major types of tasks:
1. Summary tasks – Main tasks which contain
subtasks
2. Subtasks - are smaller tasks that are a part of a
summary task
3. Recurring tasks - are tasks that occur at regular
intervals
4. Milestones - are tasks that are set to zero
duration and are like key phases in the project.
56
Summary & Sub Tasks
57
DEPENDENCIES
58
Linking Tasks
59
Logical Task Relationships
There are four Types of task relationships in Project
60
Linking Tasks
1. All tasks in a Project plan start
at the project start date unless
we specify.
2. With no task dependencies or
constraints applied, the project
finish date is the same as the
longest task's finish date.
3. Task dependencies, like Finish-
to-Start dependency between
the first and second tasks, can
change the project's scheduled
finish date.
61
Task Types
62
CONSTRAINTS
63
Constraints
64
WORK CONTOURS
65
Work Contours
This is the default flat work contour where each unit's work is
spread evenly across the duration of the task.
66
Types of Work Contours
Flat: The default contour with an even distribution of work.
Back-loaded: Peak activity happens at the end of the project.
To change the work contour for an assignment in either Task Usage View
or the Resource Usage View, double-click an assignment to open the
Assignment Information Dialog box and choose a contour from the Work
Contour drop-down list.
67
VIEWS
68
Views
69
To access the Task Information Dialog Box
70
To enter a Task Note
71
To create a Milestone
72
To access the Assign Resources Dialog Box
73
To assign a Resource in the Gantt Table View
1. Open a view.
2. Select the task, resource or assignment that you want to add a
hyperlink to and use Insert Menu -> Hyperlink to open the
Insert Hyperlink Dialog box
3. Enter a Web site URL or a filename from Microsoft Word or
Excel in the Type the File or Web Page Name Box.
4. Enter information in the Text to Display and Screen Tip to
Display when the user moves the mouse over the hyperlink
indicator.
5. The Bookmark button enables you to insert hyperlinks to other
Microsoft Project’s files.
6. Click OK.
76
Project Management
Tools
77
Project Management Tools include
Financial Tools
Cause and Effect Charts
PERT Charts
GANTT Charts
Run Charts
78
PERT
79
PERT Duration Calculation
80
Definitions
CPM is best suited for project which are having
definite boundaries, i.e., task/activity based, and
with one time deterministic duration.
81
Project Network Analysis
The basic purpose remains the same, i.e., of time planning for
the project, controlling the objectives of the project by using
network techniques.
82
Comparison between PDM and ADM
Precedence Diagram Method (PDM)
- Also called Activity on Node (AON).
- Four types of logical relationships:
- Finish to Start: The predecessor activity must finish before the successor
activity can start.
- Finish to Finish: The predecessor activity must finish before the successor
activity can finish.
- Start to Start: The predecessor activity must start before the successor
activity can start.
- Start to Finish: The predecessor activity must start before the successor
activity can finish.
- Also can show lead or lag time.
- Lead is the same as negative lag.
Arrow Diagram Method (ADM)
- (AOA) Also called Activity on Arrow
- Arrows represent activities while nodes represent the dependencies
- May require the use of dummy activities to define all logical relationships
correctly
- Only shows "Finish to start" relationships
83
Differences Between CPM & PERT
Fields of application vary.
CPM is activity oriented whereas PERT is an event
oriented.
CPM uses one time estimate whereas PERT uses three time
estimate.
In CPM activity durations were related to cost, whereas in
PERT it was their probable time of occurrence.
CPM enabled optimization of resources as the activity
duration were defined in terms of resources employed. This
was not possible in PERT.
Interpretation of CPM was easier whereas PERT required a
statistician to interpret the results.
84
To perform a PERT analysis to estimate a task's duration.
On the View menu, point to Toolbars, and then click PERT Analysis.
On the PERT Analysis toolbar, click PERT Entry Sheet .
For each task, enter the optimistic, expected, and pessimistic durations in
the Optimistic Dur., Expected Dur., and Pessimistic Dur. fields,
respectively. (If a task's duration is not expected to vary, enter the expected
duration in all three fields).
Click Calculate PERT to calculate the estimated durations. (Microsoft
Office Project 2003 estimates a single project duration based on a weighted
average of the three duration values for each task).
To view the optimistic, expected, and pessimistic durations, on the PERT
Analysis toolbar, click Optimistic Gantt , Expected Gantt , or Pessimistic
Gantt .
To view the end dates of the three resulting schedules, on the Tools menu,
click Options.
Click the View tab, and then select the Show project summary task box.
85
OVER ALLOCATION
86
Resolve Over allocations
To delay a task
Split a task
Assign additional or different resources
87
Tasks Leveling
Three leveling orders are:
1. ID: Higher ID tasks are delayed (It would be useful to enter
tasks in order of importance).
88
Overallocated resources will be in BOLD RED color and a
LEVELLING ICON appears in the information column.
89
Overallocation
90
Unleveling
91
FILTERS
92
Filtering & Auto Filter
93
VIEWING COSTS
94
To Assign a Fixed Cost for a Task
95
Viewing Costs
The Summary Table gives you a quick look at cost and work.
96
Assigning the resource cost table to a task
98
Review Resource Cost Variances
99
Review Assignment Cost Variances
100
View Costs per task
101
View Costs per Resource
102
View Project Costs
103
Using Per Use Costs
104
FORMATTING
105
Grid Lines
When information is displayed across rows and columns, the appropriate
placement of gridlines is very useful in obtaining a good view.
Format – Gridlines , The different lines for Gantt Chart Rows are displayed in a
row.
106
USING
COPY PICTURE
WIZARD
107
Using Copy Picture Command & Wizard
108
3. Copy Picture Wizard
1. Adjust Dates
2. Analyze Timescaled data in Excel
3. Copy Picture to Office Wizard
4. PERT Analysis
5. Visio WBS Chart Wizard
6. XML Reporting Wizard
109
Company Microsoft Corporation
Title delete
LINK TO EXCEL
111
Custom Fields in Tables
113
To print Gantt Charts
114
BASELINE
115
After building and refining the project to the point where we are
confident that we can start the project, we save a baseline.
If we save baseline task information at that point, at later points
throughout the project we can compare your current progress against
your initial plan.
Once we save a baseline, the five key information about Work, Cost,
Duration, Start and Finish date, are saved for each task in the project.
116
MULTIPLE
BASE LINES
117
Viewing Multiple Baselines
Format > Bar Styles... In the Bar Styles form, scroll down to a blank
row and click in the Name cell.
Type in a name for example - Interim1.
Click in the Appearance cell and give it a color / pattern.
Click in the Show For...Tasks cell and using the drop-down arrow,
select Normal.
In the Row cell select 2.
In the from cell select Start1 and in the To cell select Finish1.
This will show the first Interim baseline, assuming when you created it
from Tools > Tracking > Save Baseline you selected the data to be
copied from Start/Finish to Start1/Finish1.
Repeat the same procedure for Start2/Finish2 but change the Row to 3
(you can have up to 4 rows - make them all thin bars to save space on
the screen).
118
TRACKING
119
Tracking Work
The variance fields show the difference between the current value
and the baseline value for each task.
A positive variance means that your task will take longer to
complete than originally scheduled.
120
Tracking Work
121
To update the percentage of a task is complete
Indicating the percentage that a task is complete helps you track actual
progress. By specifying a percentage of completion between 0 (for a task
that hasn't started) and 100 (for a task that is finished), you can compare
planned progress to actual progress.
123
Progress of Tasks
124
Adding progress lines to the Gantt Chart
125
To define progress lines
1. Choose Tools, Tracking – Progress lines to open the Progress
Lines Dialog box.
2. Select the Always Display Current Progress line checkbox.
3. Click At Project Status Date or At Current Date to indicate
where you want the project lines to appear.
4. Select Display Project Lines at Recurring Intervals Checkbox;
then check Daily, Weekly, Monthly to specify a time that you
want to display the progress lines
5. Turn on Display Selected Progress lines and select dates.
6. Check the Line styles tab and select line type, color, and
progress point shape, point color for the current and all
progress lines.
7. Click OK to close the dialog box and apply the project lines.
126
MACROS
127
Changing All Entered Durations
128
REPORTS
129
To create a New Report
1. To create a new report, click New in the Custom
Reports dialog box.
2. Project offers four formats to base your new
report
on: Task, Resource, Monthly Calendar, and
Crosstab.
3. Select the report type you would like to create
from the Define New Report dialog box and click
OK.
4. Depending on the type you select, the appropriate
dialog box appears to assist you in building your
report.
130
To print a Report
131
WBS
132
Definition : WBS
134
What is a Work Breakdown Structure ?
Each item in WBS is assigned a unique identifier,
collectively known as Codes of Accounts.
135
Work Break Down Structure ( WBS )
Project
Sub-Project
Task
Sub-Task
Work Package
Activity
Operations
136
137
EVA
138
Earned Value Analysis
139
Three task-related values used to calculate variances and ratios
3. Actual cost of work performed – (ACWP) or Actual Cost incurred for tasks
(actual cost * actual hours)
140
The three values are used to calculate two variances
and two ratios that are:
141
Definitions
Actual Cost: The cost that has actually been incurred to date
for a task, resource. For example, if the only resource
assigned to a task gets paid Rs. 20 per hour and has worked
for two hours, the actual cost to date for the task is Rs. 40)
142
BCWS – Budgeted Cost of Work Scheduled
143
ACWP – Actual Cost of Work Performed
BCWP – Budgeted Cost of Work Performed
144
Key Values of Earned Value Analysis
Chart showing a steady accumulation of cost over the lifetime of a project
145
Once the work on the project has begun
Chart of the key values of earned value analysis
In this case, the value of the work performed is less than the
amount spent to perform that work.
146
Cost Variance
147
Schedule Variance
SV = BCWP - BCWS.
148
Cost Performance Index & Schedule Performance Index
149
Earned Value Indicators
Earned value indicators will help us to determine if there is enough money
left in the budget and if the project will finish on time.
Cost Performance Index (CPI) & Schedule Performance Index (SPI) can
be greater than 1 or less than 1.
A value that's greater than 1 indicates that the project is ahead of
schedule or under budget.
150
Performance Measurement Technique
151
152
153
154
155
156
157
158
159
160
161
IMPORTANT
162
AUTO SAVE
163
Automatically repair Project
164
To create a link between tasks that cross projects
165
To Change the project's currency settings
1. On the Tools menu, click Options, and then click the View
tab.
2. In the Symbol box, type the symbol of the currency you
want to use.
3. In the Placement box, select the position you want the
currency symbol to occupy.
4. In the Decimal digits box, type the number of digits after
the decimal you want to display.
166
Set the default working folder
167
ORGANIZER
168
Using the Organizer
Using this tool you can copy, rename, or delete the following elements:
Views
Reports
Visual Basic for Applications modules
Forms (predefined and custom forms)
Tables
Filters
Calendars
Toolbars (including menu bars)
Export/import maps
Fields (including custom fields)
Groups
169
Steps
1. On the Tools menu, click Organizer.
2. If you want to change the enterprise global template, you
need to open this template before you can change elements
using the Organizer.
3. Click the tab you want.
4. In the Global.mpt or Global (+ cached Enterprise list, click
the element you want to copy, delete, or rename. Only
someone with administrative privileges can change the
enterprise global template.
1. To copy a project element, click the file in the available in box
on the right to which you want to copy the element, and then
click Copy.
2. To delete a project element, click Delete, and then click Yes.
3. To rename a project element, click Rename, and then type a
new name for the element.
170
CUSTOMIZATION
171
Create a custom toolbar
1. You can rearrange and modify toolbar buttons, menus, and menu
commands by using the mouse or you can use the Rearrange
Commands dialog box which is accessible using a keyboard menu.
These tasks are identified as (keyboard accessible).
2. On the Tools menu, point to Customize, and then click Toolbars.
3. On the Toolbars tab, click New.
4. In the Toolbar name box, type the name you want, and then click OK.
5. Click the Commands tab.
6. Do one of the following:
7. Add a button to the toolbar
1. Click a category in the Categories box.
2. Drag the command you want from the Commands box to the
displayed toolbar.
172
Next
Add a button to the toolbar (keyboard accessible)
Click Rearrange Commands.
Click Toolbar, and then click the new toolbar in the Toolbar list.
Click Add.
In the Categories list, click a category.
In the Commands list, click the command you want.
Add a built-in menu to the toolbar
In the Categories box, click Built-in Menus.
Drag the menu you want from the Commands box to the displayed
toolbar.
Add a built-in menu to the toolbar (keyboard accessible)
Click Rearrange Commands.
Click Toolbar, and then click the new toolbar in the Toolbar list.
Click Add.
In the Categories list, click Built-in Menus .
In the Commands list, click the menu you want.
173
TEMPLATES
174
Available templates
Commercial Construction template
Engineering template
Home Move template
Infrastructure Deployment template
Microsoft Active Directory Deployment template
Microsoft Exchange 2000 Deployment template
Microsoft Office 2003 Deployment template
Microsoft SharePoint Portal Server "v2.0" Deployment template
Microsoft Windows XP Deployment template
MSF Application Development template
New Business template
New Product template
Office Move template
Project Office template
Residential Construction template
175
MASTER PROJECT
176
MASTER / CONSOLIDATED PROJECT
177
PROJECT SERVER
178
Project Server
179
Microsoft Office Enterprise Project Management
(EMP) Solution
180
Critical Path Method (CPM)
181
Project Time Management – Schedule Development
(Contd…)
182
Project Time Management – Schedule Development
183
Outputs for Schedule Development
184
Project Network Diagram
There are many other acceptable ways to display date information on a project network diagram
185
Bar (Gantt) Chart
There are many other acceptable ways to display project information on a bar chart.
186
Time-Scaled Network Diagram
There are many other acceptable ways to display project information on a time-scaled
network diagram
187
Milestone Chart
There are many other acceptable ways to display project information on a milestone chart.
188
Thank You
189