Overview:
Currently, there are two subcontractors hired by E&M contractor namely, Silian Technial Co.
1. Mr. Tang
Mr. tang is hired for carrying out the work in power house including installation auxiliary system,
turbine, generator, spiral casing, draft tube.
Moreover, it Mr. tang is also responsible for installation of earthing system at power house,
weir, intake and sandtrap.
Tang’s team is as follows
Sr. No Name Capacity/Role
1 Tang Supervisor/Manager/ SubContractor
2 Cheng Role not defined
3 Yu Role not defined
4 Ma Role not defined
5 Ha Role not defined
6 Tauheed Role not defined
7 Saleem Labor/helper
8 Faizan Role not defined
9 Wakeel Role not defined
10 Behrooz Role not defined
11 Waheed Labor
12 Naveed Role not defined
It also stated that the contractor was asked to submit the role/capacity of Tang’s team. The
contractor refused to submit above mentioned team’s capacity and said that they will only
submit it JV’s Project Manager. (Conversation recorded and available).
Moreover, Tang’s behavior with MC staff is aggressive and tang threatened MC supervision staff
at site on his first visit to site.
Work at Power House:
5 persons were working at house from Tang’s team. It was observed that they were doing work
at very slow pace. It took them 3 days (From March 23, 2018 to March 26, 2018) to install
drainage pipes of butterfly valve and spiral casing & earthing strip at unit # 3. Civil work at
power house had to stop 3 days due to substandard/poor quality work by tang’s team.
It is futher stated that Wang Jiangwei of Silian Technical Co. indulged in a heated argument with
MC Supervision E&M staff due to MC asked his team to rectify faulty work and unapproved their
faulty work.
2. Mr. Ha
Mr. Ha is responsible for installation of embedded parts of gates & trash rack and electric hoists
and other embedded parts such as flushing pipes etc. at weir, intake and sand trap.
Ha’s team is as follows
Sr. No Name Capacity/Role
1 Ha Subcontractor/ fitter/fabricator
2 Lon Role not defined/ No contribution in work
3 Salif Qualified welder
4 Waqas Labor
5 Hayat Labor
It should be noted that Ha’s work force has remained the same and Ha has not hired more
workforce despite of letters written to JV for slow progress at undersluice gates embedded
parts.
b) Labour:
Contractor's Site installation team is short staffed and lacks qualified labor for specific task. The
installation team only consists of 5 persons. The team cannot carryout multiple tasks in parallel at
a time e.g. rust cleaning, installation, leveling, welding etc.
c) Work Quality:
Work quality is also a factor causing delay in achieving the planned progress. The Contractor
carried out different activities by their own following no standard procedure, specification and
employer requirements to assure the required quality of work. On instructions issued by MC staff
for the rectification of the poor quality of work instead the installation staff always show
resistance and threaten the MC staff. No test has been carried out at site for the confirmation of
the work quality like welding test etc. Also the installation team did not respond to the NCR
issued by MC supervisory staff and carry out the work in their own way. This results in
substandard and poor Quality of work.
CONCLUSION: