HARGA SEWA
NO. PERALATAN SATUAN ALAT KET.
(Rp)
24 Molen hr 250,000
2 Mandor Hr 200,000
10 T u k a n g c a t Hr 175,000
11 K e p . t k . c a t Hr 185,000
12 T u k a n g p l i t u r Hr 175,000
13 T u k a n g g a l i Hr 150,000
20 M a n d o r P i p a Hr 200,000
21 T k . P i p a Hr 175,000
22 P e k e r j a . P i p a Hr 185,000
23 T k . l e i d e n g Hr 175,000
25 Geologist Hr 60,000
26 Administrasi Hr 50,000
27 Logistik Hr 50,000
29 Mekanik Hr 60,000
30 C r e w Hr 50,000
32 P e n j a g a m a l a m Hr 40,000
33 Pengemudi Hr 40,000
Jepara, Februari 2015
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
4 ASBES PLAT
. 100cm X 100 cm X 4 mm bh 25,700
PC polos 30 X 30 cm bh 2,900
20 X 20 cm bh 1,500
PC warna 30 X 30 cm bh 3,000
20 X 20 cm bh 1,900
Teraso 30 X 30 cm bh 3,800
V.BAHAN CETAK
1 BUIS BETON
Ø 20 cm - 100 cm bh 53,000
Ø 30 cm - 100 cm bh 79,000
Ø 60 cm - 100 cm bh 169,100
Ø 80 cm - 100 cm bh 248,000
Ø 100 cm - 100 cm bh 340,000
U 15 cm - 100 cm bh 36,500
U 20 cm - 100 cm bh 46,200
U 30 cm - 100 cm bh 58,700
225,000
2 LUBANG ANGIN (ROSTER)
Roster Tanah Merah bh 3,300
Roster Beton bh 9,500
Roster Kayu bh 17,700
VI . B A H A N B E S I
1 BESI BETON besi beton polos/Ulir kg 9,180
besi beton prestress kg 16,000
VII . B A H A N P I P A
1 Pipa PVC AW
Pipa PVC DN 20 ( ½" ) AW m' 5,100
Pipa PVC DN 25 ( ¾" ) AW m' 6,600
Pipa PVC DN 32 ( 1" ) AW m' 8,500
Pipa PVC DN 40 ( 1½" ) AW m' 10,000
Pipa PVC DN 63 ( 2" ) AW m' 17,000
Pipa PVC DN 90 ( 3" ) AW m' 32,300
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
VIII . B A H A N L A N G I T - L A N G I T
1 List Kayu Profil m' 15,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 64,300
3 PLY WOOD
Teak wood
. 90 X 210 X 4 mm lbr 72,200
Tripleks
. 120 X 240 X 3 mm lbr 47,500
. 120 X 240 X 4 mm lbr 55,000
. 120 X 240 X 6 mm lbr 69,700
Multipleks
. 120 X 240 X 9 mm lbr 102,000
Formika ukuran pintu lbr 58,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 29,000
Dempul plamur kg 28,700
Ambril/amplas lbr 13,100
Cat dasar kg 33,000
cat kayu kg 51,700
Kuas bh 11,500
Sirlak ons 20,000
Spiritus ltr 11,600
Vernish ltr 40,000
2 TEMBOK
Kalkarium kg 5,500
Kapur sirih kg 5,200
Plamur kg 17,500
Undercoat/cat dasar kg 45,000
Cat Tembok Decolite kg 18,000
Mowilex Dalam Ruangan kg 52,600
Mowilex Luar Ruangan kg 80,000
3 BESI
Menie kg 29,000
Cat besi kg 57,600
Minyak cat/Afduner ltr 18,000
Residu (teer/aspal) drum 68,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 71,200
5 mm m2 85,000
8 mm m3 140,000
8 LAIN - LAIN
Kran Air bh 36,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
X V . PAVING BLOCK
1 Blok pafing tebal 6 cm lokal m2 55,300
2 Blok pafing tebal 8 cm lokal m2 75,000
3 Blok pafing warna tebal 6 cm lokal m2 51,000
4 Blok pafing warna tebal 8 cm lokal m2 57,500
5 Blok pafing blok tebal 6 cm K.225 m2 60,000
6 Blok pafing blok tebal 8 cm K.300 m2 94,000
7 Blok pafing blok tebal 8 cm K.400 m2 108,000
8 KANSTEEN m' 13,500
9 BATACO bh 3,700
10 Glass blox bh 20,600
XVI. L A I N - L A I N
1 Rel Pintu dorong bh 183,000
2 Naco per Daun bh 11,000
3 Rolling door Besi m2 350,000
4 Rolling door Almunium m2 415,000
5 Awning Almunium m2 190,000
6 Profil Alumunium m' 103,200
7 Alumunium strip m' 34,300
8 Besi Hollow 40x40x2 m' 11,300
9 ASPAL.
Aspal Ex Pertamina kg 13,500
10 K A C A
Cermin tebal 5 mm m2 230,000
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
26 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' A.5.1.1.33 323,323.13
27 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' A.5.1.1.34 181,785.19
32,970,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
118,589,572.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
2,482,500.00
TOTAL Rp. 154,042,072.00
Overhead 2.5% 3,851,051.80
TOTAL BIAYA 157,893,123.80
16,875,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
M
A Aspal untuk campuran 3.4285 1,371.40 kg M061 13,500.00 18,513,900.00
T Pasir beton 0.0172 6.86 m3 M041 270,300.00 1,854,258.00
E Abu batu (filler) 0.0039 1.57 m3 M027 172,700.00 271,139.00
R Aspal untuk prime coat 0.2514 100.57 kg M061 13,500.00 1,357,695.00
I Minyak bakar 0.5575 223.00 Ltr M065 13,500.00 3,010,500.00
A
L
25,007,492.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
470,000.00
TOTAL Rp. 42,352,492.00
Overhead 2.5% 1,058,812.30
TOTAL BIAYA 43,411,304.30
###
945000
259050
759850
0.4290322581
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMELIHARAAN PRASARANA FISIK
DESA SLAGI KECAMATAN PAKIS AJI KABUPATEN JEPARA
PEKERJAAN : REHABILITASI JALAN ASPAL
LOKASI : RT 01 RW 01
TAHUN ANGGARAN : 2015
VOLUME : 200 x 2,75 = 550 m2
Jepara, 2015
MENYETUJUI :
KETUA BPD SLAGI PETINGGI SLAGI
Konsultan
RETNO KUSUMAWATI, ST
DAFTAR ANALISIS HARGA SATUAN PEKERJAAN
(AHSP)
KABUPATEN JEPARA
TAHUN 2015
SWAKELOLA
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A Tenaga
AHSP-SDA Pekerja L.01 OH 0.0750 150,000.00 11,250.00
Mandor L.04 OH 0.0075 200,000.00 1,500.00
12,750.00
B Bahan
Minyak tanah ltr 0.010 13,500.00 135.00
135.00
C PERALATAN
D Jumlah A + B + C 12,885.00
E Overhead 2.5% 322.13
F Harga Satuan Pekerjaan (D+E) 13,207.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
2 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 270,300.00 25,137.90
168,973.40
C PERALATAN
D Jumlah A + B + C 303,673.40
E Overhead 2.5% 7,591.84
F Harga Satuan Pekerjaan (D+E) 311,265.24
3 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 270,300.00 27,570.60
165,272.60
C PERALATAN
D Jumlah A + B + C 299,972.60
E Overhead 2.5% 7,499.32
F Harga Satuan Pekerjaan (D+E) 307,471.92
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
4 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 270,300.00 32,976.60
165,461.60
C PERALATAN
D Jumlah A + B + C 300,161.60
E Overhead 2.5% 7,504.04
F Harga Satuan Pekerjaan (D+E) 307,665.64
5 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 270,300.00 10,812.00
84,273.70
C PERALATAN
D Jumlah A + B + C 151,623.70
E Overhead 2.5% 3,790.59
F Harga Satuan Pekerjaan (D+E) 155,414.29
6 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Muntilan m3 0.043 270,300.00 11,622.90
81,037.90
C PERALATAN
D Jumlah A + B + C 148,387.90
E Overhead 2.5% 3,709.70
F Harga Satuan Pekerjaan (D+E) 152,097.60
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
7 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 270,300.00 12,163.50
79,012.30
C PERALATAN
D Jumlah A + B + C 146,362.30
E Overhead 2.5% 3,659.06
F Harga Satuan Pekerjaan (D+E) 150,021.36
8 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 270,300.00 13,244.70
78,175.90
C PERALATAN
D Jumlah A + B + C 145,525.90
E Overhead 2.5% 3,638.15
F Harga Satuan Pekerjaan (D+E) 149,164.05
9 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 270,300.00 13,515.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
75,880.00
C PERALATAN
D Jumlah A + B + C 143,230.00
E Overhead 2.5% 3,580.75
F Harga Satuan Pekerjaan (D+E) 146,810.75
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
10 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Terawang / Roster Buah 30 3,300.00 99,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Muntilan m3 0.035 270,300.00 9,460.50
123,970.50
C PERALATAN
D Jumlah A + B + C 191,320.50
E Overhead 2.5% 4,783.01
F Harga Satuan Pekerjaan (D+E) 196,103.51
11 A.4.4.1.2.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Pasang lokal m3 0.091 142,800.00 12,994.80
165,854.30
C PERALATAN
D Jumlah A + B + C 300,554.30
E Overhead 2.5% 7,513.86
F Harga Satuan Pekerjaan (D+E) 308,068.16
12 A.4.4.1.3.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang lokal m3 0.093 142,800.00 13,280.40
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
157,115.90
C PERALATAN
D Jumlah A + B + C 291,815.90
E Overhead 2.5% 7,295.40
F Harga Satuan Pekerjaan (D+E) 299,111.30
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
13 A.4.4.1.4.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang lokal m3 0.102 142,800.00 14,565.60
152,267.60
C PERALATAN
D Jumlah A + B + C 286,967.60
E Overhead 2.5% 7,174.19
F Harga Satuan Pekerjaan (D+E) 294,141.79
14 A.4.4.1.5.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Pasang lokal m3 0.122 142,800.00 17,421.60
149,906.60
C PERALATAN
D Jumlah A + B + C 284,606.60
E Overhead 2.5% 7,115.17
F Harga Satuan Pekerjaan (D+E) 291,721.77
15 A.4.4.1.8.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang lokal m3 0.04 142,800.00 5,712.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
79,173.70
C PERALATAN
D Jumlah A + B + C 146,523.70
E Overhead 2.5% 3,663.09
F Harga Satuan Pekerjaan (D+E) 150,186.79
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
16 A.4.4.1.9.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang lokal m3 0.043 142,800.00 6,140.40
75,555.40
C PERALATAN
D Jumlah A + B + C 142,905.40
E Overhead 2.5% 3,572.64
F Harga Satuan Pekerjaan (D+E) 146,478.04
17 A.4.4.1.10.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Pasang lokal m3 0.045 142,800.00 6,426.00
73,274.80
C PERALATAN
D Jumlah A + B + C 140,624.80
E Overhead 2.5% 3,515.62
F Harga Satuan Pekerjaan (D+E) 144,140.42
18 A.4.4.1.11.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang lokal m3 0.049 142,800.00 6,997.20
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
71,928.40
C PERALATAN
D Jumlah A + B + C 139,278.40
E Overhead 2.5% 3,481.96
F Harga Satuan Pekerjaan (D+E) 142,760.36
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
19 A.4.4.1.12.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang lokal m3 0.05 142,800.00 7,140.00
69,505.00
C PERALATAN
D Jumlah A + B + C 136,855.00
E Overhead 2.5% 3,421.38
F Harga Satuan Pekerjaan (D+E) 140,276.38
20 A.4.4.1.23.1 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Terawang / Roster Buah 30 3,300.00 99,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Pasang lokal m3 0.035 142,800.00 4,998.00
119,508.00
C PERALATAN
D Jumlah A + B + C 186,858.00
E Overhead 2.5% 4,671.45
F Harga Satuan Pekerjaan (D+E) 191,529.45
21 A.4.4.1.2.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Muntilan m3 0.091 270,300.00 24,597.30
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
150,556.80
C PERALATAN
D Jumlah A + B + C 285,256.80
E Overhead 2.5% 7,131.42
F Harga Satuan Pekerjaan (D+E) 292,388.22
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
22 A.4.4.1.3.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 270,300.00 25,137.90
142,073.40
C PERALATAN
D Jumlah A + B + C 276,773.40
E Overhead 2.5% 6,919.34
F Harga Satuan Pekerjaan (D+E) 283,692.74
23 A.4.4.1.4.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 270,300.00 27,570.60
138,372.60
C PERALATAN
D Jumlah A + B + C 273,072.60
E Overhead 2.5% 6,826.82
F Harga Satuan Pekerjaan (D+E) 363,072.60
24 A.4.4.1.5.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 270,300.00 32,976.60
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
138,561.60
C PERALATAN
D Jumlah A + B + C 273,261.60
E Overhead 2.5% 6,831.54
F Harga Satuan Pekerjaan (D+E) 280,093.14
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
25 A.4.4.1.8.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 270,300.00 10,812.00
70,823.70
C PERALATAN
D Jumlah A + B + C 138,173.70
E Overhead 2.5% 3,454.34
F Harga Satuan Pekerjaan (D+E) 141,628.04
26 A.4.4.1.9.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Muntilan m3 0.043 270,300.00 11,622.90
67,587.90
C PERALATAN
D Jumlah A + B + C 134,937.90
E Overhead 2.5% 3,373.45
F Harga Satuan Pekerjaan (D+E) 138,311.35
27 A.4.4.1.10.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 270,300.00 12,163.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
65,562.30
C PERALATAN
D Jumlah A + B + C 132,912.30
E Overhead 2.5% 3,322.81
F Harga Satuan Pekerjaan (D+E) 136,235.11
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
28 A.4.4.1.11.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 270,300.00 13,244.70
64,725.90
C PERALATAN
D Jumlah A + B + C 132,075.90
E Overhead 2.5% 3,301.90
F Harga Satuan Pekerjaan (D+E) 135,377.80
29 A.4.4.1.12.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 270,300.00 13,515.00
62,430.00
C PERALATAN
D Jumlah A + B + C 129,780.00
E Overhead 2.5% 3,244.50
F Harga Satuan Pekerjaan (D+E) 133,024.50
30 A.4.4.1.2.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.091 142,800.00 12,994.80
138,954.30
C PERALATAN
D Jumlah A + B + C 273,654.30
E Overhead 2.5% 6,841.36
F Harga Satuan Pekerjaan (D+E) 280,495.66
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
31 A.4.4.1.3.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang Lokal m3 0.093 142,800.00 13,280.40
130,215.90
C PERALATAN
D Jumlah A + B + C 264,915.90
E Overhead 2.5% 6,622.90
F Harga Satuan Pekerjaan (D+E) 271,538.80
32 A.4.4.1.4.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang Lokal m3 0.102 142,800.00 14,565.60
125,367.60
C PERALATAN
D Jumlah A + B + C 260,067.60
E Overhead 2.5% 6,501.69
F Harga Satuan Pekerjaan (D+E) 350,067.60
33 A.4.4.1.5.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.122 142,800.00 17,421.60
123,006.60
C PERALATAN
D Jumlah A + B + C 257,706.60
E Overhead 2.5% 6,442.67
F Harga Satuan Pekerjaan (D+E) 264,149.27
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
34 A.4.4.1.8.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang Lokal m3 0.04 142,800.00 5,712.00
65,723.70
C PERALATAN
D Jumlah A + B + C 133,073.70
E Overhead 2.5% 3,326.84
F Harga Satuan Pekerjaan (D+E) 136,400.54
35 A.4.4.1.9.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang Lokal m3 0.043 142,800.00 6,140.40
62,105.40
C PERALATAN
D Jumlah A + B + C 129,455.40
E Overhead 2.5% 3,236.39
F Harga Satuan Pekerjaan (D+E) 132,691.79
36 A.4.4.1.10.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.045 142,800.00 6,426.00
59,824.80
C PERALATAN
D Jumlah A + B + C 127,174.80
E Overhead 2.5% 3,179.37
F Harga Satuan Pekerjaan (D+E) 130,354.17
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
37 A.4.4.1.11.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang Lokal m3 0.049 142,800.00 6,997.20
58,478.40
C PERALATAN
D Jumlah A + B + C 125,828.40
E Overhead 2.5% 3,145.71
F Harga Satuan Pekerjaan (D+E) 128,974.11
38 A.4.4.1.12.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang Lokal m3 0.05 142,800.00 7,140.00
56,055.00
C PERALATAN
D Jumlah A + B + C 123,405.00
E Overhead 2.5% 3,085.13
F Harga Satuan Pekerjaan (D+E) 126,490.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 7.7760 1,410.00 10,964.16
Pasir Muntilan m3 0.0230 270,300.00 6,216.90
17,181.06
C PERALATAN
D Jumlah A + B + C 94,206.06
E Overhead 2.5% 2,355.15
F Harga Satuan Pekerjaan (D+E) 96,561.21
19 A.4.4.2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang batu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Portland Semen Kg 3.1080 1,410.00 4,382.28
4,382.28
C PERALATAN
D Jumlah A + B + C 43,087.28
E Overhead 2.5% 1,077.18
F Harga Satuan Pekerjaan (D+E) 44,164.46
20 A.4.4.2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
PP Muntilan m3 0.0120 270,300.00 3,243.60
12,183.00
C PERALATAN
D Jumlah A + B + C 89,208.00
E Overhead 2.5% 2,230.20
F Harga Satuan Pekerjaan (D+E) 91,438.20
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
21 A.4.4.2.26.1 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Lokal
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
PP Lokal m3 0.0120 142,800.00 1,713.60
10,653.00
C PERALATAN
D Jumlah A + B + C 87,678.00
E Overhead 2.5% 2,191.95
F Harga Satuan Pekerjaan (D+E) 89,869.95
2 A.4.6.1.2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu kamfer
A Tenaga
Pekerja L.01 OH 6.0000 150,000.00 900,000.00
Tukang Kayu L.02 OH 18.0000 175,000.00 3,150,000.00
Kepala Tukang L.03 OH 1.8000 185,000.00 333,000.00
Mandor L.04 OH 0.3000 200,000.00 60,000.00
4,443,000.00
B Bahan
Kayu Klas II (kamfer) m3 1.2000 8,116,300.00 9,739,560.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
9,768,360.00
C PERALATAN
D Jumlah A + B + C 14,211,360.00
E Overhead 2.5% 355,284.00
F Harga Satuan Pekerjaan (D+E) 14,566,644.00
5 A.4.6.1.6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu jati, papan m3 0.0240 16,875,000.00 405,000.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
408,840.00
C PERALATAN
D Jumlah A + B + C 1,001,240.00
E Overhead 2.5% 25,031.00
F Harga Satuan Pekerjaan (D+E) 1,026,271.00
6 A.4.6.1.6.1 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu kamfer m3 0.0240 8,116,300.00 194,791.20
Lem Kayu kg 0.3000 12,800.00 3,840.00
198,631.20
C PERALATAN
D Jumlah A + B + C 791,031.20
E Overhead 2.5% 19,775.78
F Harga Satuan Pekerjaan (D+E) 810,806.98
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.6.1.8 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm)
A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Kayu L.02 OH 2.1000 175,000.00 367,500.00
Kepala Tukang L.03 OH 0.2100 185,000.00 38,850.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
518,350.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 72,200.00 72,200.00
281,891.50
C PERALATAN
D Jumlah A + B + C 800,241.50
E Overhead 2.5% 20,006.04
F Harga Satuan Pekerjaan (D+E) 820,247.54
8 A.4.6.1.9 Pembuatan&Pemasangan 1 m2 Pintu Plywood rangkap, rangka expose kayu klas I atau II
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0256 8,116,300.00 207,777.28
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 72,200.00 72,200.00
286,761.28
C PERALATAN
D Jumlah A + B + C 879,161.28
E Overhead 2.5% 21,979.03
F Harga Satuan Pekerjaan (D+E) 901,140.31
9 A.4.6.1.10 Pembuatan & Pemasangan 1 m2 Jalusi mati Kosen Kayu Klas I atau II
A Tenaga
Pekerja L.01 OH 0.6700 150,000.00 100,500.00
Tukang Kayu L.02 OH 2.0000 175,000.00 350,000.00
Kepala Tukang L.03 OH 0.2000 185,000.00 37,000.00
Mandor L.04 OH 0.3350 200,000.00 67,000.00
554,500.00
B Bahan
Kayu Klas I Bengkirai) m3 0.0600 8,648,600.00 518,916.00
Paku Biasa 1/2" - 1" Kg 0.1500 12,800.00 1,920.00
520,836.00
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 1,075,336.00
E Overhead 2.5% 26,883.40
F Harga Satuan Pekerjaan (D+E) 1,102,219.40
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.6.1.11 Pembuatan & Pemasangan 1 m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu Klas I (Bengkirai) m3 0.0250 8,648,600.00 216,215.00
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 72,200.00 72,200.00
292,639.00
C PERALATAN
D Jumlah A + B + C 885,039.00
E Overhead 2.5% 22,125.98
F Harga Satuan Pekerjaan (D+E) 907,164.98
11 A.4.6.1.12 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II
A Tenaga
Pekerja L.01 OH 0.8500 150,000.00 127,500.00
Tukang Kayu L.02 OH 2.5500 175,000.00 446,250.00
Kepala Tukang L.03 OH 0.2550 185,000.00 47,175.00
Mandor L.04 OH 0.0430 200,000.00 8,600.00
629,525.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.0800 12,800.00 1,024.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 72,200.00 72,200.00
Formika Lbr 0.5000 58,000.00 29,000.00
305,515.50
C PERALATAN
D Jumlah A + B + C 935,040.50
E Overhead 2.5% 23,376.01
F Harga Satuan Pekerjaan (D+E) 958,416.51
19 A.4.6.1.20 Pemasangan 1 m2 Rangka Langit-langit (60x60) cm, kayu Klas II atau III
A Tenaga
Pekerja L.01 OH 0.2000 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.3000 175,000.00 52,500.00
Kepala Tukang L.03 OH 0.0300 185,000.00 5,550.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
90,050.00
B Bahan
Kayu Klas II (Kruing) m3 0.0163 6,582,500.00 107,294.75
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
110,494.75
C PERALATAN
D Jumlah A + B + C 200,544.75
E Overhead 2.5% 5,013.62
F Harga Satuan Pekerjaan (D+E) 205,558.37
21 A.4.6.1.22 Pemasangan 1 m' Listplank Uk. (3x30)cm Kayu klas I atau klas II
A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
54,700.00
B Bahan
Kayu klas I Bengkirai) m3 0.0110 8,648,600.00 95,134.60
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
95,774.60
C PERALATAN
D Jumlah A + B + C 150,474.60
E Overhead 2.5% 3,761.87
F Harga Satuan Pekerjaan (D+E) 154,236.47
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
22 A.4.6.1.23 Pemasangan 1 m2 Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.4500 175,000.00 78,750.00
Kepala Tukang L.03 OH 0.0450 185,000.00 8,325.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
111,175.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
186,230.00
C PERALATAN
D Jumlah A + B + C 297,405.00
E Overhead 2.5% 7,435.13
F Harga Satuan Pekerjaan (D+E) 304,840.13
3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 299.000 1,410.00 421,590.00
Pasir Beton kg 799.000 193.07 154,264.07
Kerikil (maksimum 30 mm) kg 1017.000 159.93 162,644.67
Air ltr 215.000 20.00 4,300.00
742,798.74
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 1,060,203.74
E Overhead 2.5% 26,505.09
F Harga Satuan Pekerjaan (D+E) 1,086,708.83
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A Tenaga
Pekerja L.01 OH 1.200 150,000.00 180,000.00
Tukang Batu L.02 OH 0.200 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.020 185,000.00 3,700.00
Mandor L.04 OH 0.060 200,000.00 12,000.00
230,700.00
B Bahan
Portland Semen Kg 230.000 1,410.00 324,300.00
Pasir Beton Kg 893.000 193.07 172,412.79
Kerikil (maksimum 30 mm) Kg 1027.000 159.93 164,243.93
Air ltr 200.000 20.00 4,000.00
664,956.71
C PERALATAN
D Jumlah A + B + C 895,656.71
E Overhead 2.5% 22,391.42
F Harga Satuan Pekerjaan (D+E) 918,048.13
5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 326.000 1,410.00 459,660.00
Pasir Beton Kg 760.000 193.07 146,734.29
Kerikil (maksimum 30 mm) Kg 1029.000 159.93 164,563.78
Air ltr 215.000 20.00 4,300.00
775,258.06
C PERALATAN
D Jumlah A + B + C 1,092,663.06
E Overhead 2.5% 27,316.58
F Harga Satuan Pekerjaan (D+E) 1,119,979.64
6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 352.000 1,410.00 496,320.00
Pasir Beton Kg 731.000 193.07 141,135.21
Kerikil (maksimum 30 mm) Kg 1031.000 159.93 164,883.63
Air ltr 215.000 20.00 4,300.00
806,638.84
C PERALATAN
D Jumlah A + B + C 1,124,043.84
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 28,101.10
F Harga Satuan Pekerjaan (D+E) 1,152,144.94
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 371.000 1,410.00 523,110.00
Pasir Beton Kg 698.000 193.07 134,763.86
Kerikil (maksimum 30 mm) Kg 1047.000 159.93 167,442.44
Air ltr 215.000 20.00 4,300.00
829,616.30
C PERALATAN
D Jumlah A + B + C 1,147,021.30
E Overhead 2.5% 28,675.53
F Harga Satuan Pekerjaan (D+E) 1,175,696.83
8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 384.000 1,410.00 541,440.00
Pasir Beton Kg 692.000 193.07 133,605.43
Kerikil (maksimum 30 mm) Kg 1039.000 159.93 166,163.04
Air ltr 215.000 20.00 4,300.00
845,508.47
C PERALATAN
D Jumlah A + B + C 1,162,913.47
E Overhead 2.5% 29,072.84
F Harga Satuan Pekerjaan (D+E) 1,191,986.30
9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 406.000 1,410.00 572,460.00
Pasir Beton kg 684.000 193.07 132,060.86
Kerikil (maksimum 30 mm) kg 1026.000 159.93 164,084.00
Air ltr 215.000 20.00 4,300.00
872,904.86
C PERALATAN
D Jumlah A + B + C 1,190,309.86
E Overhead 2.5% 29,757.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,220,067.60
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 413.000 1,410.00 582,330.00
Pasir Beton Kg 681.000 193.07 131,481.64
Kerikil (maksimum 30 mm) Kg 1021.000 159.93 163,284.37
Air ltr 215.000 20.00 4,300.00
881,396.01
C PERALATAN
D Jumlah A + B + C 1,198,801.01
E Overhead 2.5% 29,970.03
F Harga Satuan Pekerjaan (D+E) 1,228,771.04
21 A.4.1.1.37 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm
A Tenaga
Pekerja L.01 OH 0.200 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.500 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.050 185,000.00 9,250.00
Mandor L.04 OH 0.010 200,000.00 2,000.00
128,750.00
B Bahan
kayu randu tebal 2 cm m3 0.022 897,700.00 19,749.40
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
24,869.40
C PERALATAN
D Jumlah A + B + C 153,619.40
E Overhead 2.5% 3,840.49
F Harga Satuan Pekerjaan (D+E) 157,459.89
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
C PERALATAN
D Jumlah A + B + C 146,705.00
E Overhead 2.5% 3,667.63
F Harga Satuan Pekerjaan (D+E) 150,372.63
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
37,245.00
B Bahan
Seng Plaat 3" x 6" BJLS 28 Lbr 0.3000 80,000.00 24,000.00
Paku Biasa 1/2" - 1" Kg 0.0400 12,800.00 512.00
24,512.00
C PERALATAN
D Jumlah A + B + C 61,757.00
E Overhead 2.5% 1,543.93
F Harga Satuan Pekerjaan (D+E) 63,300.93
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
A Tenaga
Pekerja L.01 OH 0.030 150,000.00 4,500.00
18,845.00
B Bahan
28,398.00
C PERALATAN
D Jumlah A + B + C 47,243.00
E Overhead 2.5% 1,181.08
A Tenaga
Pekerja L.01 OH 0.100 150,000.00 15,000.00
B Bahan
Tripleks (4 mm) Lbr 0.375 55,000.00 20,625.00
21,009.00
C PERALATAN
D Jumlah A + B + C 56,359.00
253,253.00
C PERALATAN
D Jumlah A + B + C 536,053.00
25,675.00
B Bahan
Gypsum Board Lbr 0.364 64,300.00 23,405.20
C PERALATAN
D Jumlah A + B + C 50,510.20
A Tenaga
21,210.00
B Bahan
20,255.00
C PERALATAN
D Jumlah A + B + C 41,465.00
A Tenaga
21,210.00
B Bahan
18,515.00
C PERALATAN
D Jumlah A + B + C 39,725.00
A Tenaga
413,400.00
B Bahan
C PERALATAN
D Jumlah A + B + C 763,400.00
A Tenaga
155,540.00
B Bahan
434,000.00
C PERALATAN
D Jumlah A + B + C 589,540.00
A Tenaga
353,500.00
B Bahan
415,000.00
C PERALATAN
D Jumlah A + B + C 768,500.00
A Tenaga
15,190.50
B Bahan
C PERALATAN
D Jumlah A + B + C 133,260.50
A Tenaga
30,037.50
B Bahan
954,860.00
C PERALATAN
D Jumlah A + B + C 984,897.50
A Tenaga
30,290.00
B Bahan
842,655.00
C PERALATAN
D Jumlah A + B + C 872,945.00
A Tenaga
68,900.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Seng Plaat Lbr 1.0500 31,300.00 32,865.00
118,557.00
C PERALATAN
D Jumlah A + B + C 187,457.00
10 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm
A Tenaga
82,150.00
B Bahan
C PERALATAN
D Jumlah A + B + C 125,243.00
A Tenaga
123,825.00
B Bahan
156,500.00
C PERALATAN
D Jumlah A + B + C 280,325.00
SNI A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Keramik 40 x 40 cm Buah 6.6300 8,300.00 55,029.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 11,790.00 15,327.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
90,600.00
C PERALATAN
D Jumlah A + B + C 154,980.00
E Overhead 2.5% 3,874.50
F Harga Satuan Pekerjaan (D+E) 158,854.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
SNI A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Keramik 40 x 40 cm putih Buah 6.6300 7,800.00 51,714.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 11,790.00 15,327.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
87,285.00
C PERALATAN
D Jumlah A + B + C 151,665.00
E Overhead 2.5% 3,791.63
F Harga Satuan Pekerjaan (D+E) 155,456.63
D Jumlah A + B + C 170,376.50
E Overhead 2.5% 4,259.41
F Harga Satuan Pekerjaan (D+E) 174,635.91
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 167,876.50
E Overhead 2.5% 4,196.91
F Harga Satuan Pekerjaan (D+E) 172,073.41
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 150,000.00 10,500.00
Tukang Cat L.02 OH 0.1050 175,000.00 18,375.00
Kepala Tukang L.03 OH 0.0040 185,000.00 740.00
Mandor L.04 OH 0.0030 200,000.00 600.00
30,215.00
B Bahan
Cat Menie kg 0.2000 29,000.00 5,800.00
Plamuur kg 0.1500 28,700.00 4,305.00
Cat Dasar kg 0.1700 33,000.00 5,610.00
Cat Penutup kg 0.3500 51,700.00 18,095.00
Kuas bh 0.0100 11,500.00 115.00
Pengencer kg 0.0300 18,000.00 540.00
Amplas lbr 0.2000 13,100.00 2,620.00
37,085.00
C PERALATAN
D Jumlah A + B + C 67,300.00
E Overhead 2.5% 1,682.50
F Harga Satuan Pekerjaan (D+E) 68,982.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Decolite
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 18,000.00 4,680.00
10,930.00
C PERALATAN
D Jumlah A + B + C 26,720.50
E Overhead 2.5% 668.01
F Harga Satuan Pekerjaan (D+E) 27,388.51
11 A.4.7.1.10.1 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 52,600.00 13,676.00
19,926.00
C PERALATAN
D Jumlah A + B + C 35,716.50
E Overhead 2.5% 892.91
F Harga Satuan Pekerjaan (D+E) 36,609.41
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
12 A.4.7.1.10.2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 80,000.00 20,800.00
27,050.00
C PERALATAN
D Jumlah A + B + C 42,840.50
E Overhead 2.5% 1,071.01
F Harga Satuan Pekerjaan (D+E) 43,911.51
14 A.4.7.1.11.1 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0280 150,000.00 4,200.00
Tukang Cat L.02 OH 0.0420 175,000.00 7,350.00
Kepala Tukang L.03 OH 0.0042 185,000.00 777.00
Mandor L.04 OH 0.0030 200,000.00 600.00
12,927.00
B Bahan
Cat Dasar Kg 0.1200 45,000.00 5,400.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Cat Penutup 2 kali Kg 0.1800 52,600.00 9,468.00
14,868.00
C PERALATAN
D Jumlah A + B + C 27,795.00
E Overhead 2.5% 694.88
F Harga Satuan Pekerjaan (D+E) 28,489.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
15 A.4.7.1.11.2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0280 150,000.00 4,200.00
Tukang Cat L.02 OH 0.0420 175,000.00 7,350.00
Kepala Tukang L.03 OH 0.0042 185,000.00 777.00
Mandor L.04 OH 0.0030 200,000.00 600.00
12,927.00
B Bahan
Cat Dasar Kg 0.1200 45,000.00 5,400.00
Cat Penutup 2 kali Kg 0.1800 80,000.00 14,400.00
19,800.00
C PERALATAN
D Jumlah A + B + C 32,727.00
E Overhead 2.5% 818.18
F Harga Satuan Pekerjaan (D+E) 33,545.18
9 A.8.4.1.80 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan)
Galian tanah keras m3 0.075 160,310.00 12,023.25
Urugan tanah kembali m3 0.065 29,041.67 1,887.71
Buangan sisa galian m3 0.010 52,787.50 527.88
Pemasangan Pipa 1.000 28,788.52 28,788.52
Harga Satuan Pekerjaan 43,227.36
10 A.8.4.1.81 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan)
Galian tanah keras m3 0.100 160,310.00 16,031.00
Urugan tanah kembali m3 0.080 29,041.67 2,323.33
Buangan sisa galian m3 0.020 52,787.50 1,055.75
Pemasangan Pipa 1.000 41,717.50 41,717.50
Harga Satuan Pekerjaan 61,127.58
11 A.8.4.1.82 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 160,310.00 20,038.75
Urugan tanah kembali m3 0.095 29,041.67 2,758.96
Buangan sisa galian m3 0.030 52,787.50 1,583.63
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Pemasangan Pipa 1.000 49,312.75 49,312.75
Harga Satuan Pekerjaan 73,694.08
12 A.8.4.1.83 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 160,310.00 24,046.50
Urugan tanah kembali m3 0.120 29,041.67 3,485.00
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 80,272.88 80,272.88
Harga Satuan Pekerjaan 109,388.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.8.4.1.84 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan)
Galian tanah keras m3 0.300 160,310.00 48,093.00
Urugan tanah kembali m3 0.265 29,041.67 7,696.04
Buangan sisa galian m3 0.035 52,787.50 1,847.56
Pemasangan Pipa 1.000 107,420.00 107,420.00
Harga Satuan Pekerjaan 165,056.60
14 A.8.4.1.85 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 160,310.00 20,038.75
Urugan tanah kembali m3 0.095 29,041.67 2,758.96
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 61,602.50 61,602.50
Harga Satuan Pekerjaan 85,983.83
15 A.8.4.1.86 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 160,310.00 24,046.50
Urugan tanah kembali m3 0.120 29,041.67 3,485.00
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 82,978.88 82,978.88
Harga Satuan Pekerjaan 112,094.00
16 A.8.4.1.87 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan)
Galian tanah keras m3 0.175 160,310.00 28,054.25
Urugan tanah kembali m3 0.140 29,041.67 4,065.83
Buangan sisa galian m3 0.035 52,787.50 1,847.56
Pemasangan Pipa 1.000 115,825.00 115,825.00
Harga Satuan Pekerjaan 149,792.65
I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3
Crew pengeboran Hari 4.00 x 1.00 50,000.00 200,000.00
4
Pengemudi Hari 2.00 x 2.00 40,000.00 160,000.00
II. PERALATAN
1 Sewa kendaraan Hari 2.00 x 2.00 250,000.00 1,000,000.00
angkut ( truk )
JUMLAH 1,485,000.00
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 70.00 x 1.00 6,400.00 448,000.00
2 Olie mesin Ltr 5.00 x 1.00 33,600.00 168,000.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 400,000.00 400,000.00
JUMLAH 2,063,200.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 206,320.00
Overhead 2.5% 5,158.00
211,478.00
An.3 Jenis pekerjaan :Pemboran pilot hole diameter 6", 50 -- 100 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 6,400.00 480,000.00
2 Olie mesin Ltr 5.00 x 1.00 33,600.00 168,000.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 50.00 x 1.00 11,400.00 570,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
JUMLAH 2,184,200.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 218,420.00
Overhead 2.5% 5,460.50
223,880.50
An.4 Jenis pekerjaan :Pemboran pilot hole diameter 6", 100 -- 150 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 85.00 x 1.00 6,400.00 544,000.00
2 Olie mesin Ltr 6.00 x 1.00 33,600.00 201,600.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 60.00 x 1.00 11,400.00 684,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
JUMLAH 2,428,900.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 242,890.00
Overhead 2.5% 6,072.25
248,962.25
An.5 Jenis pekerjaan : Pekerjaan reaming, 0 -- 65 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 60.00 x 1.00 6,400.00 384,000.00
2 Olie mesin Ltr 4.00 x 1.00 33,600.00 134,400.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
JUMLAH 1,940,600.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 194,060.00
Overhead 2.5% 4,851.50
198,911.50
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 6,400.00 480,000.00
2 Olie mesin Ltr 6.00 x 1.00 33,600.00 201,600.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 55.00 x 1.00 11,400.00 627,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
JUMLAH 2,307,900.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 230,790.00
Overhead 2.5% 5,769.75
236,559.75
An.7 Jenis pekerjaan : Electric logging
I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
4
Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
II. PERALATAN
1 Recorder paper Unit 1.00 x 1.00 20,000.00 20,000.00
2 Alat tulis Unit 1.00 x 1.00 15,000.00 15,000.00
III. PERALATAN
Mesin peralatan logging Unit 1.00 x 1.00 700,000.00 700,000.00
Tranportasi peralatan logging Unit 1.00 x 1.00 150,000.00 150,000.00
JUMLAH 1,170,000.00
1 HARI RATA-RATA 50 M' ----> JADI PER METER 23,400.00
Overhead 2.5% 585.00
23,985.00
An.8 Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 8"
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 6,400.00 768,000.00
2 Olie mesin Ltr 3.00 x 1.00 33,600.00 100,800.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
Pipa jambang diameter 8" Mtr 60.00 x 578,400.00 34,704,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 36,587,000.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 609,783.33
Overhead 2.5% 15,244.58
625,027.92
DIBULATKAN 625,000.00
An.9 Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 6"
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 6" Mtr 30.00 x 310,000.00 9,300,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 10,503,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 350,115.33
Overhead 2.5% 8,752.88
358,868.22
DIBULATKAN 358,000.00
An.10 Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 6"
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 6 : Mtr 30.00 x 1,719,900.00 51,597,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 52,800,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,760,015.33
Overhead 2.5% 44,000.38
1,804,015.72
DIBULATKAN 1,804,000.00
An.8' Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 6" (GIP)
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 6,400.00 768,000.00
2 Olie mesin Ltr 3.00 x 1.00 33,600.00 100,800.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
5 Pipa jambang diameter 6" Mtr 60.00 x 323,200.00 19,392,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 21,275,000.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 354,583.33
Overhead 2.5% 8,864.58
363,447.92
DIBULATKAN 363,000.00
An.9' Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 4" (GIP)
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 4" Mtr 30.00 x 283,500.00 8,505,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 9,708,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 323,615.33
Overhead 2.5% 8,090.38
331,705.72
DIBULATKAN 331,000.00
An.10' Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 4"
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 4" : Mtr 30.00 x 1,181,300.00 35,439,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00
JUMLAH 36,642,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,221,415.33
Overhead 2.5% 30,535.38
1,251,950.72
DIBULATKAN 1,251,000.00
ANALISA BIAYA PEKERJAAN
LAPIS PENETRASI MAKADAM (LAPEN) 5 CM KODE
( MENGGUNAKAN BURUH ) K 618
32,970,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
118,589,572.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
2,482,500.00
TOTAL Rp. 154,042,072.00
Overhead 2.5% 3,851,051.80
TOTAL BIAYA 157,893,123.80
16,875,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
M
A Aspal untuk campuran 3.4285 1,371.40 kg M061 13,500.00 18,513,900.00
T Pasir beton 0.01715 6.86 m3 M041 270,300.00 1,854,258.00
E Abu batu (filler) 0.003925 1.57 m3 M027 172,700.00 271,139.00
R Aspal untuk prime coat 0.251425 100.57 kg M061 13,500.00 1,357,695.00
I Minyak bakar 0.5575 223.00 Ltr M065 13,500.00 3,010,500.00
A
L
25,007,492.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
470,000.00
TOTAL Rp. 42,352,492.00
Overhead 2.5% 1,058,812.30
TOTAL BIAYA 43,411,304.30
9,815,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
7,414,375.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
P
E Mesin gilas 3 roda 6 Ton 1.00 1 E 080 5.00 44,000.00 220,000.00
R Truck tangki air 68 HP 1.00 1 E 182 5.00 82,500.00 412,500.00
A
L
A
T
A
N
632,500.00
TOTAL Rp. 17,861,875.00
Overhead 2.5% 446,546.88
TOTAL BIAYA 18,308,421.88
1,190,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
27,500,800.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
1,663,500.00
TOTAL Rp. 30,354,300.00
Overhead 2.5% 758,857.50
TOTAL BIAYA 31,113,157.50
10,530,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
12,024,900.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
P
E Mesin gilas 3 roda 6 T 1.00 1 E 080 5.00 44,000.00 220,000.00
R Truck tangki air 68 HP 1.00 1 E 182 4.00 82,500.00 330,000.00
A
L
A
T
A
N
550,000.00
TOTAL Rp. 23,104,900.00
Overhead 2.5% 577,622.50
TOTAL BIAYA 23,682,522.50
15,625,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)
16,573,000.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
P
E Mesin gilas 3 roda 6 Ton 1.00 1 E 080 5.00 44,000.00 220,000.00
R
A
L
A
T
A
N
220,000.00
TOTAL Rp. 32,418,000.00
Overhead 2.5% 810,450.00
TOTAL BIAYA 33,228,450.00
TOTAL 121,998,875.25
PPn dan PPh (11.5 %) 14,029,870.65
JUMLAH TOTAL 136,028,745.91
DIBULATKAN 136,020,000.00
TERBILANG
Err:511
Ketua Sekretaris
MUSTA'IN
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN DRAINASE
LOKASI : RW. 03 DAN RW. 04
TAHUN ANGGARAN : 2015
VOLUME : …………………
B Bahan 49.00 m2
Ubin Keramik 40 x 40 cm putih 6.6300 324.87 Buah 7,800 2,533,986
Portland Semen 9.8000 480.2 Kg 1,410 677,082
Semen Warna 1.3000 63.7 Kg 11,790 751,023
Pasir Pasang 0.0450 2.205 m3 142,800 314,874
TOTAL 114,374,161.45
PPn dan PPh (11.5 %) 13,153,028.57
JUMLAH TOTAL 127,527,190.02
DIBULATKAN 127,520,000.00
TERBILANG
Err:511
Ketua Sekretaris
MUSTA'IN