DAFTAR HARGA SEWA PERALATAN

KABUPATEN JEPARA TAHUN 2015

HARGA SEWA
NO. PERALATAN SATUAN ALAT KET.
(Rp)

1 Dump Truck 3 ton Jam 71,500

2 Truk Tanki Air Jam 82,500

3 Truk Bak Terbuka hr 250,000

4 Bulldozer Jam 236,500

5 Motor Grader Jam 236,500

6 Wheel Loader Jam 192,500

7 Excavator Jam 275,000

8 Handle Crane 2 T hr 210,000

9 Trailler Jam 225,000

10 Mesin Gilas 3 roda 6 - 10 ton Jam 44,000

11 Mesin Gilas Roda Karet 8 - 10 ton Jam 57,700

12 Vibratory Roller Jam 170,500

13 Vibro roller 1 ton Jam 30,200

14 Water Pump Jam 20,000

15 Asphalt Sprayer Jam 50,000

16 Pick Up Jam 50,000

17 Asphalt Finisher Jam 550,000

18 Concrete Vibrator Jam 50,000

19 Compressor Jam 125,000

20 Concrete Mixer Jam 75,000

21 Stamper Jam 40,000

22 Genset Jam 180,000

23 Alat Pengecat Marka Jam 80,000

24 Molen hr 250,000

Jepara, Februari 2015


KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN
KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR UPAH TENAGA KERJA
KABUPATEN JEPARA TAHUN 2015

NO. JENIS BAHAN SATUAN HARGA SATUAN KET.


(Rp)
1 Pekerja Hr 150,000

2 Mandor Hr 200,000

3 Tukang listrik Hr 175,000

4 Tukang kayu Hr 175,000

5 Kep. tk. kayu Hr 185,000

6 Tukang batu Hr 175,000

7 Kep. tk. batu Hr 185,000

8 Tukang besi Hr 175,000

9 Kep. tk. besi Hr 185,000

10 T u k a n g c a t Hr 175,000

11 K e p . t k . c a t Hr 185,000

12 T u k a n g p l i t u r Hr 175,000

13 T u k a n g g a l i Hr 150,000

14 Tukang aspal Hr 175,000

15 Operator terlatih Hr 175,000

16 Operator semi terlatih Hr 150,000

17 Buruh tak terlatih Hr 150,000

18 Buruh semi terlatih Hr 150,000

19 Buruh terlatih Hr 150,000

20 M a n d o r P i p a Hr 200,000

21 T k . P i p a Hr 175,000

22 P e k e r j a . P i p a Hr 185,000

23 T k . l e i d e n g Hr 175,000

24 Site manager Hr 75,000

25 Geologist Hr 60,000

26 Administrasi Hr 50,000

27 Logistik Hr 50,000

28 Operator pemboran Hr 50,000

29 Mekanik Hr 60,000

30 C r e w Hr 50,000

31 Buruh lokal Hr 40,000

32 P e n j a g a m a l a m Hr 40,000

33 Pengemudi Hr 40,000
Jepara, Februari 2015

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR HARGA SATUAN BAHAN BANGUNAN
KABUPATEN JEPARA TAHUN 2015

HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

I. B A H A N DASAR Harga belum


1 BATU KALI termasuk PPN 10%
Pecah 15/20 m3 143,000
Pecah 5/7 m3 191,900
Pecah 3/5 m3 191,900
2 KERIKIL Timbun/Sirtu m3 82,500
Beton/Ciping 0,5/1 m3 189,400
Beton ,1/2 m3 217,100
Beton ,2/3 m3 215,900
Abu batu m3 172,700
3 BATU BATA Kudus bh 760
Kalipucang/Clering bh 530
4 PASIR Urug m3 82,000
Pasang lokal m3 142,800
Beton/Muntilan m3 270,300
5 TANAH Padas m3 56,500
Liat/tanah merah m3 41,700
6 KAPUR Pasang m3 402,800
Semen Merah m3 172,500
7 PORTLAND CEMENT
Semen PC kg 1,410
Semen Putih kg 2,120
Semen warna kg 11,790

II. B A H A N PENUTUP ATAP

1 GENTENG BETON Genteng Beton Warna standard bh 6,000


Kerpus Beton Warna Standard bh 13,500
2 GENTENG TANAH LIAT
Jatiwangi kecil tak berwarna bh 3,000
Jatiwangi besar tak berwarna bh 6,000
Genteng Pres Lokal bh 1,200
Nok kerpus Jatiwangi bh 13,500
Nok kerpus Lokal bh 5,000

3 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 72,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

. 225 cm X 102 cm X 5 mm bh 78,000


. 250 cm X 102 cm X 5 mm bh 87,000
. 200 cm X 102 cm X 6 mm bh 85,000
. 225 cm X 102 cm X 6 mm bh 93,000
. 250 cm X 102 cm X 6 mm bh 100,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 45,000
. 180 cm X 105 cm X 4 mm bh 52,000
. 210 cm X 105 cm X 4 mm bh 62,000
. 240 cm X 105 cm X 4 mm bh 70,000
. 270 cm X 105 cm X 4 mm bh 80,000
. 300 cm X 105 cm X 4 mm bh 88,000
NOK Jabes nok
. Kerpus Genteng bh 30,000
. Stel Besar bh 60,000

4 ASBES PLAT
. 100cm X 100 cm X 4 mm bh 25,700

5 FIBRE GLASS (JABES)


Fiber Glass Plat bh 29,800
Fiber Glass Gelombang bh 35,800
6 SENG PLAT
BJLS 0,18 lebar 55 cm m' 31,300
BJLS 0,28 lebar 55 cm m' 72,500
7 SENG GELOMBANG
BJLS 0,20 panjang 180 cm lbr 80,000
III . B A H A N K A Y U
1 JATI m3 16,875,000
2 KAMPER m3 8,116,300
3 KRUING m3 6,582,500
4 MERANTI m3 4,500,000
5 HUTAN m3 2,750,000
6 BENGKIRAI m3 8,648,600
7 DOLKEN
Kayu cetakan/Randu m3 897,700
Kayu bakar m3 160,000
Bambu bt 13,500

IV . BAHAN PENUTUP DINDING / LANTAI


1 UBIN (TEGEL BIASA)
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

PC polos 30 X 30 cm bh 2,900
20 X 20 cm bh 1,500
PC warna 30 X 30 cm bh 3,000
20 X 20 cm bh 1,900
Teraso 30 X 30 cm bh 3,800

2 KERAMIK 40 X 40 cm warna bh 8,300


40 X 40 cm putih bh 7,800
30 X 30 cm warna bh 4,100
30 X 30 cm putih bh 3,800
20 X 20 cm bh 2,000
2,500
3 Parquet Jati m2 210,000
4 Batu Paras/alam m2 105,000
5 Batu Tempel Hitam m2 105,000
6 GRANITO 40 x 40 cm bh 32,800
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

V.BAHAN CETAK
1 BUIS BETON
Ø 20 cm - 100 cm bh 53,000
Ø 30 cm - 100 cm bh 79,000
Ø 60 cm - 100 cm bh 169,100
Ø 80 cm - 100 cm bh 248,000
Ø 100 cm - 100 cm bh 340,000
U 15 cm - 100 cm bh 36,500
U 20 cm - 100 cm bh 46,200
U 30 cm - 100 cm bh 58,700
225,000
2 LUBANG ANGIN (ROSTER)
Roster Tanah Merah bh 3,300
Roster Beton bh 9,500
Roster Kayu bh 17,700

VI . B A H A N B E S I
1 BESI BETON besi beton polos/Ulir kg 9,180
besi beton prestress kg 16,000

2 BESI PLAT Besi Strip kg 20,200

3 BESI PROFIL Besi Profil kg 16,100

4 JARING - JARING BAJA


Kawat Bronjong/wiremesh kg 17,000
5 BESI SIKU L
L 50 X 50 X 5 m' 35,800
6 KAWAT - Ikat beton/bendrat kg 15,300
- Kawat Kasa m2 18,300
- Saringan pasir m2 15,000
- Kawat bronjong kg 17,000

VII . B A H A N P I P A
1 Pipa PVC AW
Pipa PVC DN 20 ( ½" ) AW m' 5,100
Pipa PVC DN 25 ( ¾" ) AW m' 6,600
Pipa PVC DN 32 ( 1" ) AW m' 8,500
Pipa PVC DN 40 ( 1½" ) AW m' 10,000
Pipa PVC DN 63 ( 2" ) AW m' 17,000
Pipa PVC DN 90 ( 3" ) AW m' 32,300
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Pipa PVC DN 110 ( 4" ) AW m' 50,800


Pipa PVC DN 160 ( 6" ) AW m' 93,500
Pipa PVC DN 200 ( 8" ) AW m' 151,500
Pipa PVC DN 250 ( 10" ) AW m' 287,500
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

VIII . B A H A N L A N G I T - L A N G I T
1 List Kayu Profil m' 15,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 64,300
3 PLY WOOD
Teak wood
. 90 X 210 X 4 mm lbr 72,200
Tripleks
. 120 X 240 X 3 mm lbr 47,500
. 120 X 240 X 4 mm lbr 55,000
. 120 X 240 X 6 mm lbr 69,700
Multipleks
. 120 X 240 X 9 mm lbr 102,000
Formika ukuran pintu lbr 58,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 29,000
Dempul plamur kg 28,700
Ambril/amplas lbr 13,100
Cat dasar kg 33,000
cat kayu kg 51,700
Kuas bh 11,500
Sirlak ons 20,000
Spiritus ltr 11,600
Vernish ltr 40,000

2 TEMBOK
Kalkarium kg 5,500
Kapur sirih kg 5,200
Plamur kg 17,500
Undercoat/cat dasar kg 45,000
Cat Tembok Decolite kg 18,000
Mowilex Dalam Ruangan kg 52,600
Mowilex Luar Ruangan kg 80,000

3 BESI
Menie kg 29,000
Cat besi kg 57,600
Minyak cat/Afduner ltr 18,000
Residu (teer/aspal) drum 68,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Fibre glass (tanki air)


kapasitas 550 liter. bh 780,000
kapasitas 1100 liter. bh 1,350,000
Lem Aica Aibon kg 35,000

X.BAHAN KACA
1 POLOS 3 mm m2 71,200
5 mm m2 85,000
8 mm m3 140,000

XI . BAHAN INSTALASI LISTRIK


Stop kontak Broco bh 15,200
Saklar tunggal Broco bh 14,200
Saklar ganda Broco bh 17,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM
Biasa 2 X slag bh 60,800
Kamar mandi 1 X slag bh 36,600

2 ENGSEL DAN GERENDEL


Engsel Angin bh 19,800
Engsel Jendela bh 14,100
Engsel Pintu kuningan bh 20,500
Espagnoled - bh 32,000
Grendel biasa bh 8,900
Kait Angin bh 5,500
Door Stop bh 35,000
Door Closer bh 93,300

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,192,800
2 KLOSET JONGKOK bh 134,700
3 WASTAFEL GANTUNG BULAT bh 292,700
4 TEMPAT SABUN TANAM bh 36,100
5 URINOIR bh 367,500
6 BAK MANDI FIBER bh 280,000
7 BAK CUCI PIRING STAINLES bh 176,100

8 LAIN - LAIN
Kran Air bh 36,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Seal tape bh 2,300


Floor drain bh 23,100
Water drain bh 60,000
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 5" kg 12,800
2 PAKU - sekrup kg 13,000
3 PAKU - sekrup fizzer bh 1,600
4 PAKU - sumbat / kait kg 25,000
5 MUR BAUT (kuda-kuda) kg 16,000
6 ANGKUR BAUT bh 14,000
7 LEM KAYU bh 12,800
8 Tali Ijuk kg 23,600
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

X V . PAVING BLOCK
1 Blok pafing tebal 6 cm lokal m2 55,300
2 Blok pafing tebal 8 cm lokal m2 75,000
3 Blok pafing warna tebal 6 cm lokal m2 51,000
4 Blok pafing warna tebal 8 cm lokal m2 57,500
5 Blok pafing blok tebal 6 cm K.225 m2 60,000
6 Blok pafing blok tebal 8 cm K.300 m2 94,000
7 Blok pafing blok tebal 8 cm K.400 m2 108,000
8 KANSTEEN m' 13,500
9 BATACO bh 3,700
10 Glass blox bh 20,600
XVI. L A I N - L A I N
1 Rel Pintu dorong bh 183,000
2 Naco per Daun bh 11,000
3 Rolling door Besi m2 350,000
4 Rolling door Almunium m2 415,000
5 Awning Almunium m2 190,000
6 Profil Alumunium m' 103,200
7 Alumunium strip m' 34,300
8 Besi Hollow 40x40x2 m' 11,300
9 ASPAL.
Aspal Ex Pertamina kg 13,500
10 K A C A
Cermin tebal 5 mm m2 230,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 178,000


Pagar BRC 120 A2 /lb 220,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 10,000
Pintu Lipat Besi m2 434,000
Sealent tube 22,500
Soda api kg 20,000
Sabun kg 15,000
Air ltr 20
Kuas bh 11,500
Premium ltr 6,600
Minyak Tanah ltr 13,500
Vynil 30x30 cm bh 6,500

XVII. INSTALASI AIR BERSIH PERDESAAN/PERKOTAAN


1 " Pipa PVC "SII, S 10
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Diameter nominal 1/2" m' 3,400


Diameter nominal 3/4" m' 5,000
Diameter nominal 1" m' 8,450
Diameter nominal 1 1/2" m' 19,100
2 " Pipa PVC "SII, S 12.5
Diameter nominal 2" m' 24,350
Diameter nominal 3" m' 50,900
Diameter nominal 4" m' 73,900
3 " Pipa Galvanis " medium
Diameter nominal 1/2" m' 19,900
Diameter nominal 3/4" m' 26,000
Diameter nominal 1" m' 40,000
Diameter nominal 1 1/2" m' 60,100
Diameter nominal 2" m' 80,100
Diameter nominal 3" m' 130,200
Diameter nominal 4" m' 190,300
Diameter nominal 6" m' 310,500
4 " Pipa HDPE " SDR 11(PN16)
Diameter nominal OD 40mm m' 20,400
Diameter nominal OD 50mm m' 31,650
Diameter nominal OD 63mm m' 50,050
Diameter nominal OD 75mm m' 69,900
Diameter nominal OD 90mm m' 101,300
5 " Stop valve "
Diameter nominal 3/4" Bh 35,100
Diameter nominal 1" Bh 58,500
Diameter nominal 1 1/2" Bh 101,600
Diameter nominal 2" Bh 171,900
6 " Gate valve "
Diameter nominal 3" Bh 445,400
Diameter nominal 4" Bh 570,400
Diameter nominal 6" Bh 1,015,100
7 " Reduser " SC/SC
Diameter nominal 160 x 110 mm Bh 164,200
Diameter nominal 110 x 90 mm Bh 76,200
Diameter nominal 63 x 50 mm Bh 26,050
Diameter nominal 50 x 40 mm Bh 10,850
Diameter nominal 40 x 25 mm Bh 8,150
Diameter nominal 25 x 20 mm Bh 3,050
8 " Tee all socket " PVC
Diameter nominal 100 x 100 mm Bh 179,100
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Diameter nominal 75 x 75 mm Bh 110,800


Diameter nominal 50 x 50 mm Bh 18,050
Diameter nominal 40 x 40 mm Bh 10,500
Diameter nominal 25 x 25 mm Bh 3,850
9 " Bend all socket " PVC
Diameter nominal 75 mm RRJ Bh 36,500
Diameter nominal 50 mm RRJ Bh 27,000
Diameter nominal 40 mm Bh 5,400
Diameter nominal 25 mm Bh 3,400
Diameter nominal 20 mm Bh 2,100
10 " Bend all socket " GI
Diameter nominal 2" Bh 10,400
Diameter nominal 1 1/2" Bh 8,300
Diameter nominal 1" Bh 5,400
Diameter nominal 3/4" Bh 3,100
11 " Clamp sadle " GI
Diameter nominal 3" x 3/4" Bh 23,400
Diameter nominal 2" x 3/4" Bh 15,600
Diameter nominal 1 1/2" x 3/4" Bh 12,400
Diameter nominal 1" x 3/4" Bh 12,400
12 " Valve socket " PVC
Diameter nominal 50 mm Bh 23,550
Diameter nominal 40 mm Bh 13,400
Diameter nominal 25 mm Bh 8,700
Diameter nominal 20 mm Bh 8,050
13 " Flange socket " PVC
Diameter nominal 50 mm Bh 143,200
Diameter nominal 63 mm Bh 179,400
Diameter nominal 110 mm Bh 448,400
Diameter nominal 160 mm Bh 691,200
14 " Faucet socket " PVC
Diameter nominal 50 mm Bh 47,850
Diameter nominal 40 mm Bh 35,750
Diameter nominal 25 mm Bh 20,050
Diameter nominal 20 mm Bh 15,900
15 " D o f " PVC
Diameter nominal 100 mm Bh 24,300
Diameter nominal 75 mm Bh 14,200
Diameter nominal 50 mm Bh 12,250
Diameter nominal 40 mm Bh 8,050
Diameter nominal 25 mm Bh 4,050
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Diameter nominal 20 mm Bh 3,050


16 " Water meter "
Diameter nominal 3" Bh 1,218,500
Diameter nominal 2" Bh 927,800
Diameter nominal 1" Bh 345,300
Diameter nominal 1/2" Bh 108,100
17 " Chek valve "
Diameter nominal 3" Bh 473,300
Diameter nominal 4" Bh 609,300
Diameter nominal 6" Bh 1,048,800
18 " Bend all flange " CI - 45'
Diameter nominal 3" Bh 89,700
Diameter nominal 4" Bh 124,100
Diameter nominal 6" Bh 199,900
19 " Air valve " CI
Diameter nominal 1" Bh 115,100
Diameter nominal 3/4" Bh 108,100
20 " Stred boox "
Diameter nominal 3" Bh 25,200
Diameter nominal 4" Bh 30,600
21 "Accessories"
Doble neple GI dia 3/4" Bh 1,800
Tee all socket GI dia 3/4" Bh 4,600
Valve socket GI dia 3/4" Bh 2,600
Kran stainless steel Bh 18,600
Verlop ring 1 " x 3/4" Bh 8,300
Sock GIP dia 1" Bh 3,300
Sock GIP dia 3/4" Bh 2,600
Tee faucet dia 20 mm PVC Bh 5,400
Bend faucet dia 20 mm PVC Bh 3,400
Submersible pump 5.5 KW/1 Phase Unit 29,508,000
Submersible pump 11 KW/3 Phase Unit 53,655,900
Panel submersible pump 5.5 KW Unit 2,864,600
Panel submersible pump 11 KW Unit 4,688,400
Submersible pump 2.2 KW/1 Phase Unit 22,325,600
Panel submersible pump 2.2 KW Unit 2,232,600
Bend all sock GIP diameter 3" Bh 21,400
Tee all sock GIP diameter 3" Bh 17,900
Pasang tangga bahan pipa GIP dn 1" Bh 198,500
Tutup man hole & tutup pengaman lengkap 3 mm Unit 297,700
Speed Kran DN 20 mm Bh 18,600
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)

Gate Valev DN 50 mm Bh 168,700


Flends diameter 150 mm Bh 99,200
Pelurus / Centering tiap 30 mm set 36,000
Reduser DN 100 x 150 mm set 509,300
Filter Grevel m3 180,000
Grouting m 480,300
Tangki fiberglas kapasitas 1 m3 m' 3,959,100
Tangki fiberglas kapasitas 2 m3 m' 4,688,400
22 "Pembuatan Sumur Produksi"
Solar ltr 6,400
Olie ltr 33,600
Bentonite kg 11,400
Veet/grease kg 33,100
Gravel pack m3 173,900
Kawat las btg 900
Pipa jambang diameter 8" ( GI) m' 578,400
Pipa jambang diameter 6" (GI) m' 323,200
Pipa buta diamter 6" ( GI ) m' 310,000
Pipa buta diamter 4" (GI ) m' 283,500
Pipa saringan stainless steel diameter 6" m' 1,719,900
Pipa saringan stainless steel diameter 4" m' 1,181,300

Jepara, Februari 2015

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR HARGA SATUAN PEKERJAAN KONSTRUKSI
KABUPATEN JEPARA TA. 2015
SWAKELOLA
(Ket : Harga belum termasuk PPN 10%)

HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)

I HARGA SATUAN PEKERJAAN PERSIAPAN A. 2.2.1


1 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m m' A.2.2.1.2 450,192.92
2 Pengukuran dan Pemasangan Bouwplank m' A.2.2.1.4 76,762.15
3 Membersihkan Lapangan dan Perataan m2 A.2.2.1.9 25,625.00
4 Bongkaran Beton Bertulang m3 A.2.2.1.13 2,186,632.50
5 Bongkaran Dinding Tembok Bata Merah m3 A.2.2.1.14 1,093,316.25
6 Bongkaran 1 m3 Pasangan Batu m3 A.2.2.1.17 322,362.50
7 Pembuatan Steger/Perancah dari Bambu m2 A.2.2.1.18 210,294.13
tebas tebang berupa memotong dan membersihkan lokasi dari tanaman diameter < 15cm
8 m2 A.2.2.1.19 13,207.13

II HARGA SATUAN PEKERJAAN TANAH A.2.3.1


1 Menggali Tanah Biasa Sedalam 1 m m3 A.2.3.1.1 120,437.50
2 Menggali Tanah Biasa Sedalam 2 m m3 A.2.3.1.2 147,600.00
3 Menggali Tanah Biasa Sedalam 3 m m3 A.2.3.1.3 175,172.50
4 Menggali Tanah Keras Sedalam 1 m m3 A.2.3.1.4 160,310.00
5 Menggali Tanah Cadas Sedalam 1 m m3 A.2.3.1.5 242,925.00
6 Menggali Tanah Lumpur Sedalam 1 m m3 A.2.3.1.6 193,725.00
7 Mengerjakan Striping Tebing Setinggi 1 m m2 A.2.3.1.7 8,712.50
8 MembuangTanah sejauh 30 m' m3 A.2.3.1.8 52,787.50
9 Pengurugan Kembali m3 A.2.3.1.9 29,041.67
10 Pemadatan Tanah (per 20 cm) m3 A.2.3.1.10 87,125.00
11 Urugan Pasir hurug m3 A.2.3.1.11 149,035.00
12 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan m2 A.2.3.1.13 171,277.50
13 Mengurug Sirtu Padat m3 A.2.3.1.14 145,037.50
15 Urugan tanah biasa dan dipadatkan (SNI) m3 A.2.3.1.15 90,123.13
16 Urugan tanah padas dan dipadatkan (SNI) m3 A.2.3.1.16 108,327.13
17 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) ttk A.2.3.1.17 36,545.48

III HARGA SATUAN PEKERJAAN PONDASI A.3.2.1.


1 Pemasangan Pondasi Batu Belah 1SP : 3 PP lokal m3 A.3.2.1.1 933,573.08
2 Pemasangan Pondasi Batu Belah 1SP : 3 PP muntilan m3 A.3.2.1.1.1 996,956.51
3 Pemasangan Pondasi Batu Belah 1SP : 4 PP lokal m3 A.3.2.1.2 882,331.28
4 Pemasangan Pondasi Batu Belah 1SP : 4 PP muntilan m3 A.3.2.1.2.1 950,288.78
5 Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal m3 A.3.2.1.3 846,822.41
6 Pemasangan Pondasi Batu Belah 1SP : 5 PP muntilan m3 A.3.2.1.3.1 917,916.41
7 Pemasangan Pondasi Batu Belah 1SP : 6 PP lokal m3 A.3.2.1.4 821,850.95
8 Pemasangan Pondasi Batu Belah 1SP : 6 PP muntilan m3 A.3.2.1.4.1 895,166.63
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
9 Pemasangan Pondasi Batu Belah 1SP : 8 PP lokal m3 A.3.2.1.5 787,640.96
10 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan m3 A.3.2.1.5.1 863,962.46
11 Pemasang Batu Kosong/Anstamping m3 A.3.2.1.9 417,471.23
12 Pasang Pondasi Sumuran diameter 100 cm m3 A.3.2.1.11 1,091,640.17
17 Pasang Pondasi Rolag Trashraam Bata Merah 1 Pc : 3 Ps (SNI) m3 A.3.2.1.12 1,624,019.23
18 Pasang suling-suling m' A.3.2.1.13 9,119.43
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
IV HARGA SATUAN PEKERJAAN PASANGAN DINDING A.4.4.1
Dinding dengan bata merah kudus
1 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.2 319,960.72
2 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.3 311,265.24
3 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.4 307,471.92
4 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.5 307,665.64
5 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.8 155,414.29
6 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.9 152,097.60
7 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.10 150,021.36
8 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.11 149,164.05
9 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 8PP Muntilan m2 A.4.4.1.12 146,810.75
10 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP Muntilan m2 A.4.4.1.23 196,103.51
11 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.2.1 308,068.16
12 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.3.1 299,111.30
13 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.4.1 294,141.79
14 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.5.1 291,721.77
15 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.8.1 150,186.79
16 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.9.1 146,478.04
17 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.10.1 144,140.42
18 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.11.1 142,760.36
19 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 8PP Lokal m2 A.4.4.1.12.1 140,276.38
20 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP Lokal m2 A.4.4.1.23.1 191,529.45
Dinding dengan bata merah Kalipucang
21 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.2.2 292,388.22
22 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.3.2 283,692.74
23 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.4.2 363,072.60
24 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.5.2 280,093.14
25 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.8.2 141,628.04
26 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.9.2 138,311.35
27 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.10.2 136,235.11
28 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.11.2 135,377.80
29 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP Muntilan m2 A.4.4.1.12.2 133,024.50
30 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.3.3 280,495.66
31 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.3.3 271,538.80
32 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.4.3 350,067.60
33 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.5.3 264,149.27
34 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.8.3 136,400.54
35 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.9.3 132,691.79
36 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.10.3 130,354.17
37 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.11.3 128,974.11
38 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP Lokal m2 A.4.4.1.12.3 126,490.13
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
V HARGA SATUAN PEKERJAAN PLESTERAN A.4.4.2
1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.3 96,561.21
2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.3.1 93,555.40
3 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.4 94,618.37
4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.4.1 91,481.87
5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.5 93,646.30
6 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.5.1 90,248.42
7 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.6 92,813.40
8 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.6.1 89,284.84
9 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.7 92,396.74
10 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.7.1 88,737.49
11 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.8 91,980.08
12 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.8.1 88,190.14
13 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.19 54,368.30
14 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.19.1 50,970.42
15 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm Pasir Muntilan m2 A.4.4.2.20 96,779.37
16 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm Pasir Lokal m2 A.4.4.2.20.1 95,080.44
17 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Muntilan m2 A.4.4.2.23 76,939.58
18 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Lokal m2 A.4.4.2.23.1 76,155.45
19 Pemasangan Finishing Siar Pasangan Dinding Bata Merah m2 A.4.4.2.24 44,164.46
20 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp Muntilan m2 A.4.4.2.26 91,438.20
21 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp Lokal m2 A.4.4.2.26.1 89,869.95
22 Pemasangan Acian m2 A.4.4.2.27 57,330.81

VI HARGA SATUAN PEKERJAAN K A Y U A.4.6.1


1 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu bengkirai m3 A.4.6.1.1 15,093,904.00
2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu Kamfer m3 A.4.6.1.2 14,566,644.00
3 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Jati m2 A.4.6.1.5 1,451,543.50
4 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Kamfer m2 A.4.6.1.5.1 1,092,436.80
5 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati m2 A.4.6.1.6 1,026,271.00
6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer m2 A.4.6.1.6.1 810,806.98
7 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Kamfer m2 A.4.6.1.8 820,247.54
8 Pembuatan&Pemasangan 1 m2 Pintu Plywood rangkap, rangka expose kayu Kamfer m2 A.4.6.1.9 901,140.31
9 Pembuatan & Pemasangan 1 m2 Jalusi mati Kosen Kayu Bengkirai m2 A.4.6.1.10 1,102,219.40
10 Pembuatan & Pemasangan 1 m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Bengkirai m2 A.4.6.1.11 907,164.98
11 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu kamfer m2 A.4.6.1.12 958,416.51
12 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu bengkirai m3 A.4.6.1.13 13,171,393.50
13 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing m3 A.4.6.1.13.1 10,841,865.75
14 Pemasangan 1 m3 konstruksi Gording, Kayu bengkirai m3 A.4.6.1.15 15,186,615.25
15 Pemasangan konstruksi 1 m3 Gording, Kayu Kruing m3 A.4.6.1.15.1 12,857,087.50
16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu bengkirai m2 A.4.6.1.16 195,534.49
17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu bengkirai m2 A.4.6.1.17 227,447.83
18 Pemasangan 1 m2 Rangka Langit-langit (50x1,00) m, kayu Kruing m2 A.4.6.1.19 204,467.51
19 Pemasangan 1 m2 Rangka Langit-langit (60x60) cm, kayu Kruing m2 A.4.6.1.20 205,558.37
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
20 Pemasangan 1 m' Listplank Uk. (3x20)cm Kayu Bengkirai m' A.4.6.1.21 153,119.50
21 Pemasangan 1 m' Listplank Uk. (3x30)cm Kayu Bengkirai m' A.4.6.1.22 154,236.47
22 Pemasangan 1 m2 Rangka Dinding Pemisah (60x120) cm Kayu Kruing m2 A.4.6.1.23 304,840.13
23 Pemasangan 1 m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Kruing m2 A.4.6.1.24 375,831.63
24 Pemasangan 1 m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kruing m2 A.4.6.1.25 386,004.75
25 Pemasangan 1 m2 Dinding Lambriziring dari Papan Kayu Jati m2 A.4.6.1.26 579,796.38
26 Pasang Kasau & Reng Kayu Bengkirai (SNI) m2 A.4.6.1.29 144,579.53
27 Pasang Kasau & Reng Kayu Kruing (SNI) m2 A.4.6.1.30 119,166.50
28 Pasang Papan sirip (SNI) m' A.4.6.1.31 79,850.06
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)

VII HARGA SATUAN PEKERJAAN BETON A.4.1.1


1 Membuat Beton mutu f'c=7,4 Mpa (K100) m3 A.4.1.1.1 1,022,458.07
2 Membuat Beton mutu f'c=9,8 Mpa (K125) m3 A.4.1.1.2 1,058,387.51
3 Membuat Beton mutu f'c=12,2 Mpa (K150) m3 A.4.1.1.3 1,086,708.83
4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K100) m3 A.4.1.1.4 918,048.13
5 Membuat Beton mutu f'c=14,5 MPa (K175) m3 A.4.1.1.5 1,119,979.64
6 Membuat Beton mutu f'c=16,9 MPa (K200) m3 A.4.1.1.6 1,152,144.94
7 Membuat Beton mutu f'c=19,3 MPa (K225) m3 A.4.1.1.7 1,175,696.83
8 Membuat Beton mutu f'c=21,7 MPa (K250) m3 A.4.1.1.8 1,191,986.30
9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275) m3 A.4.1.1.9 1,220,067.60
10 Membuat Beton mutu f'c=26,4 MPa (K300) m3 A.4.1.1.10 1,228,771.04
11 Pembesian dg Besi Polos atau Besi Ulir 1 kg A.4.1.1.17 12,661.83
12 Jaring Kawat baja/Wire Mesh 1 kg A.4.1.1.19 18,743.15
13 Memasang Bekisting untuk Pondasi m2 A.4.1.1.20 178,614.45
14 Memasang Bekisting untuk Sloof m2 A.4.1.1.21 183,215.16
15 Memasang Bekisting untuk Kolom m2 A.4.1.1.22 295,864.71
16 Memasang Bekisting untuk Balok m2 A.4.1.1.23 298,625.14
17 Memasang Bekisting untuk Lantai m2 A.4.1.1.24 351,214.71
18 Memasang Bekisting untuk Tangga m2 A.4.1.1.26 286,150.79
19 Membuat Kolom Penguat Beton Bertulang/kolom praktis (11 x 11) cm m' A.4.1.1.35 81,760.97
20 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' A.4.1.1.36 119,836.13
21 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 A.4.1.1.37 157,459.89

VIII HARGA SATUAN PEKERJAAN PENUTUP ATAP A.4.5.2


1 Pemasangan Atap Genteng Jatiwangi Kecil m2 A.4.5.2.1 116,452.81
2 Pemasangan Atap Genteng Kodok / lokal m2 A.4.5.2.2 70,422.63
3 Pemasangan Atap Genteng Jatiwangi Super / Besar m2 A.4.5.2.3 150,372.63
4 Pemasangan Genteng Bubung jatiwangi kecil m' A.4.5.2.4 187,010.84
5 Pemasangan Genteng Bubung Kodok / lokal m' A.4.5.2.5 143,448.34
6 Pemasangan Genteng Bubung Jatiwangi Besar m' A.4.5.2.6 173,173.34
7 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm m2 A.4.5.2.9 89,180.13
8 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm m2 A.4.5.2.10 84,198.63
9 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm m2 A.4.5.2.12 71,488.63
10 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm m2 A.4.5.2.15 72,329.13
11 Pemasangan 1 m’ bubung Asbes m' A.4.5.2.22 122,262.00
12 Pemasangan Atap Genteng Beton m2 A.4.5.2.30 120,677.35
13 Pemasangan Nok Genteng Beton m' A.4.5.2.34 186,732.04
14 Pemasangan Atap Seng Gelombang m2 A.4.5.2.38 89,492.75
15 Pemasangan Atap Nok Seng m' A.4.5.2.39 63,300.93

IX HARGA SATUAN PEKERJAAN LANGIT-LANGIT A.4.5.1


1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm m2 A.4.5.1.1 48,424.08
2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm m2 A.4.5.1.5 57,767.98
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
3 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm m2 A.4.5.1.6 549,454.33
4 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm m2 A.4.5.1.7 51,772.96
5 List Langit-Langit Kayu Profil m1 A.4.5.1.10 34,494.33
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
X HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG A.5.1.1
1 Memasang Closet Duduk / Mono Blok Unit A.5.1.1.1 2,035,360.95
2 Memasang Closet Jongkok Porselen Unit A.5.1.1.2 632,258.95
3 Memasang Urinoir Unit A.5.1.1.4 862,166.45
4 Memasang Wastafel Unit A.5.1.1.5 597,407.93
5 Pemasangan Bak Fibreglass vol.1 m3 Unit A.5.1.1.7 1,783,858.75
6 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit A.5.1.1.8 2,157,912.00
7 Pemasangan Bak Cuci Piring Stainless stell buah A.5.1.1.12 309,191.25
8 Pemasangan Floor Drain buah A.5.1.1.14 46,073.75
9 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm bh A.5.1.1.15 629,324.38
10 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm bh A.5.1.1.16 942,315.30
11 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm bh A.5.1.1.17 1,077,340.50
12 Pemasangan Pipa Galvanis Ø ½" m' A.5.1.1.18 63,304.00
13 Pemasangan Kran Ø ½" atau Ø ¾" bh A.5.1.1.19 118,856.44
14 Pemasangan Pipa Galvanis Ø ¾" m' A.5.1.1.20 72,995.38
15 Pemasangan Pipa Galvanis Ø 1" m' A.5.1.1.21 95,237.88

16 Pemasangan Pipa Galvanis Ø 1½ " m' A.5.1.1.22 148,814.63

17 Pemasangan Pipa Galvanis Ø 3" m' A.5.1.1.23 273,767.25

18 Pemasangan Pipa Galvanis Ø 4" m' A.5.1.1.24 369,251.13

19 Pemasangan Pipa PVC tipe AW Ø ½" m' A.5.1.1.25 25,947.88

20 Pemasangan Pipa PVC tipe AW Ø ¾" m' A.5.1.1.26 28,331.00

21 Pemasangan Pipa PVC tipe AW Ø 1" m' A.5.1.1.27 31,349.63

22 Pemasangan Pipa PVC tipe AW Ø 1½" m' A.5.1.1.28 42,655.38

23 Pemasangan Pipa PVC tipe AW Ø 2" m' A.5.1.1.29 53,776.63

24 Pemasangan Pipa PVC tipe AW Ø 3" m' A.5.1.1.31 91,365.94

25 Pemasangan Pipa PVC tipe AW Ø 4" m' A.5.1.1.32 120,757.81

26 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' A.5.1.1.33 323,323.13

27 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' A.5.1.1.34 181,785.19

28 Pemasangan Pipa Beton Ø 20 cm m' A.5.1.1.35 128,255.18

29 Pemasangan Pipa Beton Ø 100 cm m' A.5.1.1.36 704,643.22

XI HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM A.4.2.1


1 Pemasangan Besi Profil Kg A.4.2.1.1 42,501.63
2 Pemasangan Rangka Kuda-kuda Baja IWF kg A.4.2.1.2 40,718.13
3 Pemasangan Pintu Rolling Door Besi m2 A.4.2.1.7 782,485.00
4 Pemasangan Pintu Lipat (Folding Door) m2 A.4.2.1.8 604,278.50
5 Pemasangan Rolling Door Allumunium m2 A.4.2.1.10 787,712.50
6 Pemasangan Kusen Pintu Allumunium m' A.4.2.1.11 136,592.01
7 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 A.4.2.1.12 1,009,519.94
8 Pemasangan Pintu Kaca Rangka Allumunium m2 A.4.2.1.13 894,768.63
9 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m' A.4.2.1.18 192,143.43
10 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m' A.4.2.1.19 128,374.08
11 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon m2 A.4.2.1.21 287,333.13
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
XII HARGA SATUAN PEKERJAAN KUNCI dan KACA A.4.6.2
1 Pemasangan Kunci Tanam Biasa Buah A.4.6.2.2 164,051.25
2 Pemasangan Kunci Kamar Mandi Buah A.4.6.2.3 137,965.00
3 Pemasangan Kunci Selinder Buah A.4.6.2.4 162,770.00
4 Pemasangan Engsel Pintu Buah A.4.6.2.5 53,233.38
5 Pemasangan Engsel Jendela Kupu-kupu Buah A.4.6.2.6 35,926.25
6 Pemasangan Engsel Angin Buah A.4.6.2.7 75,440.00
7 Pemasangan Kait Angin Buah A.4.6.2.9 39,334.38
8 Pasang Door Closer Buah A.4.6.2.10 203,001.25
9 Pemasangan Kunci Selot Buah A.4.6.2.11 52,070.00
10 Pemasangan Door Stop Buah A.4.6.2.13 57,348.75
11 Pemasangan Rel Pintu Dorong Buah A.4.6.2.14 316,417.50
12 Pemasangan Kaca tebal 3 mm m2 A.4.6.2.16 112,488.63
13 Pemasangan Kaca tebal 5 mm m2 A.4.6.2.17 128,048.13
14 Pemasangan Kaca Cermin tebal 5 mm m2 A.4.6.2.18 291,535.63

XIII HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING A.4.4.3


1 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 A.4.4.3.2 122,312.23
2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 A.4.4.3.3 133,613.88
3 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 A.4.4.3.5 144,090.40
4 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 A.4.4.3.6 164,056.17
5 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 A.4.4.3.9 325,350.38
6 Pemasangan Lantai Keramik 30 x 30 cm warna m2 A.4.4.3.35 273,268.08
7 Pemasangan Lantai Keramik 30 x 30 cm putih m2 A.4.4.3.35.1 269,618.05
8 Pemasangan Lantai Keramik 40 x 40 cm warna m2 A.4.4.3.35.2 158,854.50
9 Pemasangan Lantai Keramik 40 x 40 cm putih m2 A.4.4.3.35.3 155,456.63
10 Pemasangan Lantai Keramik 20 x 20 cm m2 A.4.4.3.36 279,737.67
11 Pemasangan Lantai Parquet Jati m2 A.4.4.3.46 431,755.63
12 Pemasangan Dinding Keramik 10x20 cm, m2 A.4.4.3.53 340,485.42
11 Pemasangan Dinding Keramik 20x20 cm, m2 A.4.4.3.54 330,696.78
14 Pemasangan Dinding Batu Paras / Batu Tempel Hitam m2 A.4.4.3.58 324,710.26
15 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' A.4.4.3.63 64,387.94
14 Pasang blok pafing tebal 6 cm K.125 (SNI) m2 A.4.4.3.64 169,818.41
15 Blok paving tebal 6 cm dengan paving mutu K 225 (SNI) m2 A.4.4.3.65 174,635.91
16 Blok paving tebal 8 cm dengan paving mutu K 300 (SNI) m2 A.4.4.3.66 209,485.91
17 Blok paving warna tebal 6 cm K.125 (SNI) m2 A.4.4.3.67 165,410.91
18 Blok paving warna tebal 8 cm K.125 (SNI) m2 A.4.4.3.68 172,073.41
19 pasang saluran U-20 cm (SNI) m' A.4.4.3.69 352,240.99
20 pasang saluran U-30 cm (SNI) m' A.4.4.3.70 365,053.49
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
XIV HARGA SATUAN PEKERJAAN PENGECATAN A.4.7.1
1 Pengikisan / pengerokan Permukaan Cat Tembok Lama m2 A.4.7.1.1 24,702.50
2 Pencucian Bidang Permukaan Tembok yang Pernah dicat m2 A.4.7.1.2 24,446.25
3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual m2 A.4.7.1.3 25,471.25
4 Pengecatan Bidang Kayu Baru 2x cat m2 A.4.7.1.4 47,372.43
5 Pengecatan Bidang Kayu Baru 3x cat m2 A.4.7.1.5 68,982.50
6 Pelaburan Bidang Kayu dg Teak Oil m2 A.4.7.1.6 45,510.00
7 Pelaburan Bidang Kayu dg Politur m2 A.4.7.1.7 54,914.58
8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 A.4.7.1.8 17,824.75
9 Pelaburan Bidang Kayu dg Vernis m2 A.4.7.1.9 65,912.63
10 Pengecat Tembok Baru dengan Decolite m2 A.4.7.1.10 27,388.51
11 Pengecat Tembok Baru dengan Mowilex dalam ruangan m2 A.4.7.1.10.1 36,609.41
12 Pengecat Tembok Baru dengan Mowilex luar ruangan m2 A.4.7.1.10.2 43,911.51
13 Pengecatan Tembok Lama dengan Decolite m2 A.4.7.1.11 22,106.18
14 Pengecatan Tembok Lama dengan Mowilex dalam ruangan m2 A.4.7.1.11.1 28,489.88
15 Pengecatan Tembok Lama dengan Mowilex luar ruangan m2 A.4.7.1.11.2 33,545.18
16 Pengecatan Permukaan Baja dg Meni Besi m2 A.4.7.1.16 46,586.25
17 Pengecatan 1 m2 permukaan Besi 3x (SNI) m2 A.4.7.1.22 46,550.89
18 Pengecatan 1 m2 permukaan Trotoir 3x (SNI) m2 A.4.7.1.23 53,444.01

XV HARGA SATUAN PEKERJAAN PEMASANGAN PIPA A.8.4.1


1 Pemasangan 1 m pipa PVC Ø 50 mm (2") m' A.8.4.1.1 49,312.75
2 Pemasangan 1 m pipa PVC Ø 25 mm (1") m' A.8.4.1.1.1 28,788.52
3 Pemasangan 1 m pipa PVC Ø 40 mm (1½") m' A.8.4.1.1.2 41,717.50
4 Pemasangan 1 m pipa PVC Ø 75 mm (3") m' A.8.4.1.2 80,272.88
5 Pemasangan 1 m pipa PVC Ø 90 mm (4") m' A.8.4.1.3 107,420.00
6 Pemasangan 1 m pipa HDPE OD 63 mm m' A.8.4.1.17 61,602.50
7 Pemasangan 1 m pipa HDPE OD 75 mm m' A.8.4.1.17.1 82,978.88
8 Pemasangan 1 m pipa HDPE OD 90 mm m' A.8.4.1.17.2 115,825.00
9 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan) m' A.8.4.1.80 43,227.36
10 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan) m' A.8.4.1.81 61,127.58
11 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan) m' A.8.4.1.82 73,694.08
12 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan) m' A.8.4.1.83 109,388.00
13 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan) m' A.8.4.1.84 165,056.60
14 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan) m' A.8.4.1.85 85,983.83
15 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan) m' A.8.4.1.86 112,094.00
16 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan) m' A.8.4.1.87 149,792.65

XVI HARGA SATUAN PEKERJAAN PENGETESAN PIPA A.8.4.5


1 Pengetesan 1 m pipa Ø 50 mm m' A.8.4.5.1 2,184.48
2 Pengetesan 1 m pipa Ø 75 mm m' A.8.4.5.2 2,225.48
3 Pengetesan 1 m pipa Ø 100 mm m' A.8.4.5.3 2,307.48
4 Pengetesan 1 m pipa Ø 150 mm m' A.8.4.5.4 2,512.48
5 Pengetesan 1 m pipa Ø 200 mm m' A.8.4.5.5 2,778.98
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)

Jepara, Februari 2015

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
ANALISA BIAYA PEKERJAAN
LAPIS PENETRASI MAKADAM (LAPEN) 5 CM KODE
( MENGGUNAKAN BURUH ) K 618

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Semprotkan aspal tack coat 1. Menggunakan tenaga buruh
0,8 liter/m2 2. Harga material ( agregat dan aspal) adalah harga di lokasi proyek
2. Hamparkan agregat pokok 3-5 3. Volume aspal cair untuk tack coat/prime coat 0,8 liter/m2
25 m2/m3 dan padatkan 4. Tebal lapisan penetrasi 5 cm
3. Haparkan split 2-3 45 m2/m3 5. Agregat dikirim ke lokasi oleh leveransir
dan padatkan
4. Semprotkan aspal (2,5 kg/m2)
5. Hamparkan agregat pengunci
split 1-2 90 m2/m3 & padatkan
6. Semprotkan aspal 1,5 kg/m2
dan gilas
7. Taburkan pasir rata-rata 400m2
per m3

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 2.00 3 6.00 200,000.00 1,200,000.00


E Operator terlatih 2.00 3 6.00 175,000.00 1,050,000.00
K Sopir 1.00 3 3.00 40,000.00 120,000.00
E Buruh tak terlatih 66.00 3 198.00 150,000.00 29,700,000.00
R Buruh terlatih ( Tenaga Aspal ) 2.00 3 6.00 150,000.00 900,000.00
J
A

32,970,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Alat bantu 3.10 Set 1,648,500.00 5,110,350.00


A Material batu pecah :
T -Batu pecah 3-5 cm 0.04 56.00 m3 191,900.00 10,746,400.00
E - Batu pecah 2-3 cm 0.02 31.00 m3 215,900.00 6,692,900.00
R - Batu pecah 1-2 cm 0.01 15.50 m3 217,100.00 3,365,050.00
I - Batu ciping 0,5 cm 0.01 7.13 m3 189,400.00 1,350,422.00
A - Abu batu 0.00 3.50 m3 172,700.00 604,450.00
L Aspal 4.48 6,270.00 kg 13,500.00 84,645,000.00
Minyak bakar 0.32 450.00 liter 13,500.00 6,075,000.00

118,589,572.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P Mesin gilas 3 roda 6 - 10 ton 1.00 3 15.00 44,000.00 660,000.00


E Sprayer aspal 200 L 1.00 3 15.00 50,000.00 750,000.00
R Flatbed truck 3,5 T /115 HP 1.00 3 15.00 71,500.00 1,072,500.00
A
L
A
T
A
N

2,482,500.00
TOTAL Rp. 154,042,072.00
Overhead 2.5% 3,851,051.80
TOTAL BIAYA 157,893,123.80

VOLUME/ : 1,400.00 SATUAN: m2 HARGA SATUAN Rp. 112,780.80 Per m2


QUANTITY
ANALISA BIAYA PEKERJAAN
MEMBUAT CAMPURAN, MENGHAMPAR DAN PEMADATAN LATASIR 2 CM KODE
( MENGGUNAKAN BURUH ) K 621.a

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Supplier mengirim material 1. Menggunakan tenaga buruh 400 m2/hari
sampai ke bin spreader 2. Pasir aspal dikirim oleh levelansier ketempat pekerjaan
2. Material dihampar dengan mesin 3. Rata - rata tebal lapisan padat 2 cm
spreader, dipadatkan dengan
mesin gilas roda baja

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 1.00 3 L 061 3.00 200,000.00 600,000.00


E Operator terlatih 1.00 3 L 085 3.00 175,000.00 525,000.00
K Buruh tak terlatih 25.00 3 L 092 75.00 150,000.00 11,250,000.00
E Buruh semi terlatih 10.00 3 L 091 30.00 150,000.00 4,500,000.00
R
J
A

16,875,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M
A Aspal untuk campuran 3.4285 1,371.40 kg M061 13,500.00 18,513,900.00
T Pasir beton 0.0172 6.86 m3 M041 270,300.00 1,854,258.00
E Abu batu (filler) 0.0039 1.57 m3 M027 172,700.00 271,139.00
R Aspal untuk prime coat 0.2514 100.57 kg M061 13,500.00 1,357,695.00
I Minyak bakar 0.5575 223.00 Ltr M065 13,500.00 3,010,500.00
A
L

25,007,492.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P Roller 3 Wheled 8-10 T 51 HP 1.00 1 E 080 5.00 44,000.00 220,000.00


E Aspal Sprayer Towed 350 L 7 HP 1.00 1 E 154 5.00 50,000.00 250,000.00
R
A
L
A
T
A
N

470,000.00
TOTAL Rp. 42,352,492.00
Overhead 2.5% 1,058,812.30
TOTAL BIAYA 43,411,304.30

VOLUME/ : 400.00 SATUAN: m2 HARGA SATUAN Rp. 108,528.26 Per m2


QUANTITY
Mandor 1.19571429 200000 239142.857
Operator terlatih 1.19571429 175000 209250
Sopir 0.59785714 40000 23914.2857
Buruh tak terlatih 39.4585714 150000 5918785.71
Buruh terlatih ( Tenaga Aspal ) 1.20 150,000 179,357
-
Alat bantu 0.62 ### 1,018,420
Material batu pecah : 0.00 - -
-Batu pecah 3-5 cm 11.16 191,900 2,141,604
- Batu pecah 2-3 cm 6.18 215,900 1,333,799
- Batu pecah 1-2 cm 3.09 217,100 670,606
- Batu ciping 0,5 cm 1.42 189,400 269,120
- Abu batu 0.70 172,700 120,458
Aspal 1249.52 13,500 16,868,539
Minyak bakar 89.68 13,500 1,210,661
-
Mesin gilas 3 roda 6 - 10 ton 2.99 44,000 131,529
Sprayer aspal 200 L 2.99 50,000 149,464
Flatbed truck 3,5 T /115 HP 2.99 71,500 213,734
- 30,698,384
Mandor 6.98 200000 1,395,000
Operator terlatih 6.98 175000 1,220,625
Buruh tak terlatih 174.38 150000 26,156,250
Buruh semi terlatih 19.93 150000 2,989,286
-
Aspal untuk campuran 3188.505 13500 43,044,818
Pasir beton 15.9495 270300 4,311,150
Abu batu (filler) 3.65025 172700 630,398
Aspal untuk prime coat 233.82525 13500 3,156,641
Minyak bakar 518.475 13500 6,999,413
0 -
Roller 3 Wheled 8-10 T 51 HP 11.63 44000 511,500
Aspal Sprayer Towed 350 L 7 H 11.63 50000 581,250
###
Mandor 8.17 200,000 1,634,143
Operator terlatih 8.17 175,000 1,429,875
Sopir 0.597857 40,000 23,914
Buruh tak terlatih 213.83 150,000 32,075,036
Buruh terlatih ( Tenaga Aspal ) 1.20 150,000 179,357
Buruh semi terlatih 19.93 150,000 2,989,286
Alat bantu 0.62 ### 1,018,420
-Batu pecah 3-5 cm 11.16 191,900 2,141,604
- Batu pecah 2-3 cm 6.18 215,900 1,333,799
- Batu pecah 1-2 cm 3.09 217,100 670,606
- Batu ciping 0,5 cm 1.42 189,400 269,120
- Abu batu 4.35 172,700 750,856
Aspal 4671.85 13,500 63,069,998
Minyak bakar 608.15 13,500 8,210,073
Pasir beton 15.95 270,300 2,549,605
Mesin gilas 3 roda 6 - 10 ton 1,587,477
mobilisasi 750,000

###

945000
259050

759850
0.4290322581
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMELIHARAAN PRASARANA FISIK
DESA SLAGI KECAMATAN PAKIS AJI KABUPATEN JEPARA
PEKERJAAN : REHABILITASI JALAN ASPAL
LOKASI : RT 01 RW 01
TAHUN ANGGARAN : 2015
VOLUME : 200 x 2,75 = 550 m2

HARGA SATUAN JUMLAH HARGA JUMLAH


NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
A PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan 1 LS 420,000.00 420,000.00
420,000.00
B PEKERJAAN REHAB
I PEKERJAAN PENGASPALAN
1 LAPIS PENETRASI MAKADAM (LAPEN) 5 CM 279 m2 K 618 112,780.80 31,465,843.96
2 MEMBUAT CAMPURAN, MENGHAMPAR DAN PEMADATAN LATASIR 2 CM 930 m2 K 621.a 108,528.26 100,931,282.50
132,397,126.45
-
TOTAL 132,817,126.45
PPN 10 % 13,281,712.65
JUMLAH TOTAL 146,098,839.10
DIBULATKAN 146,090,000.00
TERBILANG
Enam Puluh Tujuh Juta Lima Ratus Ribu Rupiah

Jepara, 2015
MENYETUJUI :
KETUA BPD SLAGI PETINGGI SLAGI

MASTUR SUHARTOYO DAMAM

Konsultan

RETNO KUSUMAWATI, ST
DAFTAR ANALISIS HARGA SATUAN PEKERJAAN
(AHSP)
KABUPATEN JEPARA
TAHUN 2015
SWAKELOLA

HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m


A TENAGA
Pekerja L.01 OH 0.2 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.4 175,000.00 70,000.00
Kepala Tukang L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.02 200,000.00 4,000.00
107,700.00
B BAHAN
Bambu Btg 1.25 13,500.00 16,875.00
Portalnd Semen Kg 2.5 1,410.00 3,525.00
Seng Gelombang 3" - 5" Lbr 1.2 80,000.00 96,000.00
Pasir Beton m3 0.005 270,300.00 1,351.50
Koral Beton m3 0.009 215,900.00 1,943.10
Kayu 5/7X4m Kayu Hutan m3 0.072 2,750,000.00 198,000.00
Paku Biasa 2" - 5" Kg 0.06 12,800.00 768.00
Meni Besi Kg 0.45 29,000.00 13,050.00
331,512.60
C PERALATAN
D Jumlah A + B + C 439,212.60
E Overhead 2.5% 10,980.32
F Harga Satuan Pekerjaan (D+E) 450,192.92
Overhead & Profit
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank
A Tenaga
Pekerja L.01 OH 0.1 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.005 200,000.00 1,000.00
35,350.00
B Bahan
Kayu 5/7x 4m Kayu Hutan m3 0.012 2,750,000.00 33,000.00
Paku Biasa 2" - 5" Kg 0.02 12,800.00 256.00
Kayu Papan 3/20 randu m3 0.007 897,700.00 6,283.90
39,539.90
C PERALATAN
D Jumlah A + B + C 74,889.90
E Overhead 2.5% 1,872.25
F Harga Satuan Pekerjaan (D+E) 76,762.15

3 A.2.2.1.9 Membersihkan Lapangan dan Perataan


A Tenaga
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Pekerja L.01 OH 0.1 150,000.00 15,000.00
Mandor L.04 OH 0.05 200,000.00 10,000.00
25,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C 25,000.00
E Overhead 2.5% 625.00
F Harga Satuan Pekerjaan (D+E) 25,625.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.2.2.1.13 Bongkaran Beton Bertulang


A Tenaga
Pekerja L.01 OH 13.334 150,000.00 2,000,100.00
Mandor L.04 OH 0.666 200,000.00 133,200.00
2,133,300.00
B Bahan
C PERALATAN
D Jumlah A + B + C 2,133,300.00
E Overhead 2.5% 53,332.50
F Harga Satuan Pekerjaan (D+E) 2,186,632.50

5 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah


A Tenaga
Pekerja L.01 OH 6.667 150,000.00 1,000,050.00
Mandor L.04 OH 0.333 200,000.00 66,600.00
1,066,650.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,066,650.00
E Overhead 2.5% 26,666.25
F Harga Satuan Pekerjaan (D+E) 1,093,316.25

6 A.2.2.1.17 Bongkaran 1 m3 Pasangan Batu


A Tenaga
AHSP-SDA Pekerja L.01 OH 1.850 150,000.00 277,500.00
Mandor L.04 OH 0.185 200,000.00 37,000.00
314,500.00
B Bahan
C PERALATAN
D Jumlah A + B + C 314,500.00
E Overhead 2.5% 7,862.50
F Harga Satuan Pekerjaan (D+E) 322,362.50

7 A.2.2.1.18 Pembuatan Steger/Perancah dari Bambu


A Tenaga
AHSP-SDA Pekerja L.01 OH 0.33 150,000.00 49,500.00
Tukang Kayu L.02 OH 0.66 175,000.00 115,500.00
Kepala Tukang L.03 OH 0.066 185,000.00 12,210.00
Mandor L.04 OH 0.0330 200,000.00 6,600.00
183,810.00
B Bahan
Bambu diameter 6 - 8 / 600 cm Btg 1.250 13,500.00 16,875.00
Paku 5 - 7 cm Kg 0.350 12,800.00 4,480.00
21,355.00
C PERALATAN
D Jumlah A + B + C 205,165.00
E Overhead 2.5% 5,129.13
F Harga Satuan Pekerjaan (D+E) 210,294.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
1m2 tebas tebang berupa memotong dan membersihkan lokasi dari tanaman/
8 A.2.2.1.19 tumbuhan diameter < 15cm

A Tenaga
AHSP-SDA Pekerja L.01 OH 0.0750 150,000.00 11,250.00
Mandor L.04 OH 0.0075 200,000.00 1,500.00
12,750.00
B Bahan
Minyak tanah ltr 0.010 13,500.00 135.00
135.00
C PERALATAN
D Jumlah A + B + C 12,885.00
E Overhead 2.5% 322.13
F Harga Satuan Pekerjaan (D+E) 13,207.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m


A TENAGA
Pekerja L.01 OH 0.7500 150,000.00 112,500.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
117,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 117,500.00
E Overhead 2.5% 2,937.50
F Harga Satuan Pekerjaan (D+E) 120,437.50
Overhead & Profit
2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m
A TENAGA
Pekerja L.01 OH 0.9000 150,000.00 135,000.00
Mandor L.04 OH 0.0450 200,000.00 9,000.00
144,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 144,000.00
E Overhead 2.5% 3,600.00
F Harga Satuan Pekerjaan (D+E) 147,600.00

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m


A TENAGA
Pekerja L.01 OH 1.0500 150,000.00 157,500.00
Mandor L.04 OH 0.0670 200,000.00 13,400.00
170,900.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 170,900.00
E Overhead 2.5% 4,272.50
F Harga Satuan Pekerjaan (D+E) 175,172.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m


A TENAGA
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Mandor L.04 OH 0.0320 200,000.00 6,400.00
156,400.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 156,400.00
E Overhead 2.5% 3,910.00
F Harga Satuan Pekerjaan (D+E) 160,310.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m


A TENAGA
Pekerja L.01 OH 1.5000 150,000.00 225,000.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Mandor L.04 OH 0.0600 200,000.00 12,000.00
237,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 237,000.00
E Overhead 2.5% 5,925.00
F Harga Satuan Pekerjaan (D+E) 242,925.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m
A TENAGA
Pekerja L.01 OH 1.2000 150,000.00 180,000.00
Mandor L.04 OH 0.0450 200,000.00 9,000.00
189,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 189,000.00
E Overhead 2.5% 4,725.00
F Harga Satuan Pekerjaan (D+E) 193,725.00

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m


A TENAGA
Pekerja L.01 OH 0.0500 150,000.00 7,500.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
8,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 8,500.00
E Overhead 2.5% 212.50
F Harga Satuan Pekerjaan (D+E) 8,712.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m'


A TENAGA
Pekerja L.01 OH 0.3300 150,000.00 49,500.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
51,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 51,500.00
E Overhead 2.5% 1,287.50
F Harga Satuan Pekerjaan (D+E) 52,787.50

9 A.2.3.1.9 Pengurugan Kembali


Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian
A TENAGA
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
85,000.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 85,000.00
E Overhead 2.5% 2,125.00
F Harga Satuan Pekerjaan (D+E) 29,041.67

10 A.2.3.1.10 Pemadatan Tanah (per 20 cm)


A TENAGA
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
85,000.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 85,000.00
E Overhead 2.5% 2,125.00
F Harga Satuan Pekerjaan (D+E) 87,125.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
11 A.2.3.1.11 Urugan Pasir
A TENAGA
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
47,000.00
B BAHAN
Pasir Urug m3 1.2000 82,000.00 98,400.00
98,400.00
C PERALATAN
D Jumlah A + B + C 145,400.00
E Overhead 2.5% 3,635.00
F Harga Satuan Pekerjaan (D+E) 149,035.00

12 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan


A TENAGA
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
25,500.00
B BAHAN
Ijuk kg 6.0000 23,600.00 141,600.00
141,600.00
C PERALATAN
D Jumlah A + B + C 167,100.00
E Overhead 2.5% 4,177.50
F Harga Satuan Pekerjaan (D+E) 171,277.50

13 A.2.3.1.14 Mengurug Sirtu Padat


A TENAGA
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
42,500.00
B BAHAN
Sirtu m3 1.2000 82,500.00 99,000.00
99,000.00
C PERALATAN
D Jumlah A + B + C 141,500.00
E Overhead 2.5% 3,537.50
F Harga Satuan Pekerjaan (D+E) 145,037.50

14 A.2.3.1.15 Urugan tanah biasa dan dipadatkan


SNI A TENAGA
Pekerja L.01 OH 0.0714 150,000.00 10,710.00
Mandor L.04 OH 0.0178 200,000.00 3,560.00
14,270.00
B BAHAN
Tanah biasa m3 1.2000 41,700.00 50,040.00
50,040.00
C PERALATAN
whell loader jam 0.0178 192,500.00 3,426.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
dump truck jam 0.2289 71,500.00 16,366.35
motor grader jam 0.0061 236,500.00 1,442.65
vibro roller jam 0.0100 30,200.00 302.00
water tangker jam 0.0070 82,500.00 577.50
alat bantu ls 1.0000 1,500.00 1,500.00
23,615.00
D Jumlah A + B + C 87,925.00
E Overhead 2.5% 2,198.13
F Harga Satuan Pekerjaan (D+E) 90,123.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

15 A.2.3.1.16 Urugan tanah padas dan dipadatkan


SNI A PERALATAN
Pekerja L.01 OH 0.0714 150,000.00 10,710.00
Mandor L.04 OH 0.0178 200,000.00 3,560.00
14,270.00
B BAHAN
Tanah padas m3 1.2000 56,500.00 67,800.00
67,800.00
C PERALATAN
whell loader jam 0.0178 192,500.00 3,426.50
dump truck jam 0.2289 71,500.00 16,366.35
motor grader jam 0.0061 236,500.00 1,442.65
vibro roller jam 0.0100 30,200.00 302.00
water tangker jam 0.0070 82,500.00 577.50
alat bantu ls 1.0000 1,500.00 1,500.00
23,615.00
D Jumlah A + B + C 105,685.00
E Overhead 2.5% 2,642.13
F Harga Satuan Pekerjaan (D+E) 108,327.13

16 A.2.3.1.17 Pemasangan trucuk bambu Ø 10 cm panjang 6 m


SNI A PERALATAN
Pekerja L.01 OH 0.1250 150,000.00 18,750.00
Mandor L.04 OH 0.0125 200,000.00 2,500.00
21,250.00
B BAHAN
Bambu btg 1.0000 13,500.00 13,500.00
alat pancang jam 0.1000 9,000.00 900.00
alat bantu jam 0.0165 250.00 4.13
14,404.13
C PERALATAN
D Jumlah A + B + C 35,654.13
E Overhead 2.5% 891.35
F Harga Satuan Pekerjaan (D+E) 36,545.48
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP Lokal
A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 202 1,410.00 284,820.00
Pasir Pasang m3 0.485 142,800.00 69,258.00
525,678.00
C PERALATAN
D Jumlah A + B + C 910,803.00
E Overhead 2.5% 22,770.08
F Harga Satuan Pekerjaan (D+E) 933,573.08

2 A.3.2.1.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP Muntilan


A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 202 1,410.00 284,820.00
Pasir muntilan m3 0.485 270,300.00 131,095.50
587,515.50
C PERALATAN
D Jumlah A + B + C 972,640.50
E Overhead 2.5% 24,316.01
F Harga Satuan Pekerjaan (D+E) 996,956.51
Overhead & Profit
3 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP lokal
A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 163 1,410.00 229,830.00
Pasir Pasang m3 0.52 142,800.00 74,256.00
475,686.00
C PERALATAN
D Jumlah A + B + C 860,811.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 21,520.28
F Harga Satuan Pekerjaan (D+E) 882,331.28
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.3.2.1.2.1 Pemasangan Pondasi Batu Belah 1SP : 4 PP Muntilan
A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 163 1,410.00 229,830.00
Pasir Muntilan m3 0.52 270,300.00 140,556.00
541,986.00
C PERALATAN
D Jumlah A + B + C 927,111.00
E Overhead 2.5% 23,177.78
F Harga Satuan Pekerjaan (D+E) 950,288.78

5 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal


A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 136 1,410.00 191,760.00
Pasir Pasang m3 0.544 142,800.00 77,683.20
441,043.20
C PERALATAN
D Jumlah A + B + C 826,168.20
E Overhead 2.5% 20,654.21
F Harga Satuan Pekerjaan (D+E) 846,822.41

6 A.3.2.1.3.1 Pemasangan Pondasi Batu Belah 1SP : 5 PP muntilan


A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 136 1,410.00 191,760.00
Pasir muntilan m3 0.544 270,300.00 147,043.20
510,403.20
C PERALATAN
D Jumlah A + B + C 895,528.20
E Overhead 2.5% 22,388.21
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 917,916.41
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP lokal
A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 117 1,410.00 164,970.00
Pasir Pasang m3 0.561 142,800.00 80,110.80
416,680.80
C PERALATAN
D Jumlah A + B + C 801,805.80
E Overhead 2.5% 20,045.15
F Harga Satuan Pekerjaan (D+E) 821,850.95

8 A.3.2.1.4.1 Pemasangan Pondasi Batu Belah 1SP : 6 PP muntilan


A TENAGA
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B BAHAN
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 117 1,410.00 164,970.00
Pasir Muntilan m3 0.561 270,300.00 151,638.30
488,208.30
C PERALATAN
D Jumlah A + B + C 873,333.30
E Overhead 2.5% 21,833.33
F Harga Satuan Pekerjaan (D+E) 895,166.63

9 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP lokal


A Tenaga
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B Bahan
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 91 1,410.00 128,310.00
Pasir Pasang m3 0.584 142,800.00 83,395.20
383,305.20
C PERALATAN
D Jumlah A + B + C 768,430.20
E Overhead 2.5% 19,210.76
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 787,640.96
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.3.2.1.5.1 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan
A Tenaga
Pekerja L.01 OH 1.5 150,000.00 225,000.00
Tukang Batu L.02 OH 0.750 175,000.00 131,250.00
Kepala Tukang L.03 OH 0.075 185,000.00 13,875.00
Mandor L.04 OH 0.075 200,000.00 15,000.00
385,125.00
B Bahan
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Portland Sement Kg 91 1,410.00 128,310.00
Pasir muntilan m3 0.584 270,300.00 157,855.20
457,765.20
C PERALATAN
D Jumlah A + B + C 842,890.20
E Overhead 2.5% 21,072.26
F Harga Satuan Pekerjaan (D+E) 863,962.46

11 A.3.2.1.9 Pemasang Batu Kosong/Anstamping


A Tenaga
Pekerja L.01 OH 0.78 150,000.00 117,000.00
Tukang Batu L.02 OH 0.39 175,000.00 68,250.00
Kepala Tukang L.03 OH 0.039 185,000.00 7,215.00
Mandor L.04 OH 0.039 200,000.00 7,800.00
200,265.00
B Bahan
Batu Belah 15/20 m3 1.2 143,000.00 171,600.00
Pasir Urug m3 0.432 82,000.00 35,424.00
207,024.00
C PERALATAN
D Jumlah A + B + C 407,289.00
E Overhead 2.5% 10,182.23
F Harga Satuan Pekerjaan (D+E) 417,471.23

12 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm


A Tenaga
Pekerja L.01 OH 2.40 150,000.00 360,000.00
Tukang Batu L.02 OH 0.8 175,000.00 140,000.00
Kepala Tukang L.03 OH 0.08 185,000.00 14,800.00
Mandor L.04 OH 0.119 200,000.00 23,800.00
538,600.00
B Bahan
Batu Belah 15/20 cm m3 0.45 150,000.00 67,500.00
Portland Semen Kg 194 1,410.00 273,540.00
Pasir Beton m3 0.312 270,300.00 84,333.60
Koral Beton m3 0.468 215,900.00 101,041.20
526,414.80
C PERALATAN
D Jumlah A + B + C 1,065,014.80
E Overhead 2.5% 26,625.37
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,091,640.17
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.3.2.1.12 Pasang Pondasi Rolag Trashraam Bata Merah 1 Pc : 3 Ps


SNI A Tenaga
Pekerja L.01 OH 4.50 150,000.00 675,000.00
Tukang Batu L.02 OH 1.5 175,000.00 262,500.00
Kepala Tukang L.03 OH 0.15 185,000.00 27,750.00
Mandor L.04 OH 0.225 200,000.00 45,000.00
1,010,250.00
B Bahan
bata merah m3 500.00 530.00 265,000.00
semen / PC Kg 156 1,410.00 219,960.00
pasir beton m3 0.330 270,300.00 89,199.00
574,159.00
C PERALATAN
D Jumlah A + B + C 1,584,409.00
E Overhead 2.5% 39,610.23
F Harga Satuan Pekerjaan (D+E) 1,624,019.23

14 A.3.2.1.13 Pasang suling-suling


SDA A Tenaga
Pekerja L.01 OH 0.018 150,000.00 2,700.00
Mandor L.04 OH 0.002 200,000.00 400.00
3,100.00
B Bahan
Pipa PVC 2" m' 0.341 17,000.00 5,797.00
5,797.00
C PERALATAN
D Jumlah A + B + C 8,897.00
E Overhead 2.5% 222.43
F Harga Satuan Pekerjaan (D+E) 9,119.43
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Muntilan m3 0.091 270,300.00 24,597.30
177,456.80
C PERALATAN
D Jumlah A + B + C 312,156.80
E Overhead 2.5% 7,803.92
F Harga Satuan Pekerjaan (D+E) 319,960.72

2 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 270,300.00 25,137.90
168,973.40
C PERALATAN
D Jumlah A + B + C 303,673.40
E Overhead 2.5% 7,591.84
F Harga Satuan Pekerjaan (D+E) 311,265.24

3 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 270,300.00 27,570.60
165,272.60
C PERALATAN
D Jumlah A + B + C 299,972.60
E Overhead 2.5% 7,499.32
F Harga Satuan Pekerjaan (D+E) 307,471.92
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

4 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 270,300.00 32,976.60
165,461.60
C PERALATAN
D Jumlah A + B + C 300,161.60
E Overhead 2.5% 7,504.04
F Harga Satuan Pekerjaan (D+E) 307,665.64

5 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 270,300.00 10,812.00
84,273.70
C PERALATAN
D Jumlah A + B + C 151,623.70
E Overhead 2.5% 3,790.59
F Harga Satuan Pekerjaan (D+E) 155,414.29

6 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Muntilan m3 0.043 270,300.00 11,622.90
81,037.90
C PERALATAN
D Jumlah A + B + C 148,387.90
E Overhead 2.5% 3,709.70
F Harga Satuan Pekerjaan (D+E) 152,097.60
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
7 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 270,300.00 12,163.50
79,012.30
C PERALATAN
D Jumlah A + B + C 146,362.30
E Overhead 2.5% 3,659.06
F Harga Satuan Pekerjaan (D+E) 150,021.36

8 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 270,300.00 13,244.70
78,175.90
C PERALATAN
D Jumlah A + B + C 145,525.90
E Overhead 2.5% 3,638.15
F Harga Satuan Pekerjaan (D+E) 149,164.05

9 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 270,300.00 13,515.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
75,880.00
C PERALATAN
D Jumlah A + B + C 143,230.00
E Overhead 2.5% 3,580.75
F Harga Satuan Pekerjaan (D+E) 146,810.75
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
10 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Terawang / Roster Buah 30 3,300.00 99,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Muntilan m3 0.035 270,300.00 9,460.50
123,970.50
C PERALATAN
D Jumlah A + B + C 191,320.50
E Overhead 2.5% 4,783.01
F Harga Satuan Pekerjaan (D+E) 196,103.51

11 A.4.4.1.2.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Pasang lokal m3 0.091 142,800.00 12,994.80
165,854.30
C PERALATAN
D Jumlah A + B + C 300,554.30
E Overhead 2.5% 7,513.86
F Harga Satuan Pekerjaan (D+E) 308,068.16

12 A.4.4.1.3.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang lokal m3 0.093 142,800.00 13,280.40
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
157,115.90
C PERALATAN
D Jumlah A + B + C 291,815.90
E Overhead 2.5% 7,295.40
F Harga Satuan Pekerjaan (D+E) 299,111.30
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
13 A.4.4.1.4.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang lokal m3 0.102 142,800.00 14,565.60
152,267.60
C PERALATAN
D Jumlah A + B + C 286,967.60
E Overhead 2.5% 7,174.19
F Harga Satuan Pekerjaan (D+E) 294,141.79

14 A.4.4.1.5.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Pasang lokal m3 0.122 142,800.00 17,421.60
149,906.60
C PERALATAN
D Jumlah A + B + C 284,606.60
E Overhead 2.5% 7,115.17
F Harga Satuan Pekerjaan (D+E) 291,721.77

15 A.4.4.1.8.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang lokal m3 0.04 142,800.00 5,712.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
79,173.70
C PERALATAN
D Jumlah A + B + C 146,523.70
E Overhead 2.5% 3,663.09
F Harga Satuan Pekerjaan (D+E) 150,186.79
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
16 A.4.4.1.9.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang lokal m3 0.043 142,800.00 6,140.40
75,555.40
C PERALATAN
D Jumlah A + B + C 142,905.40
E Overhead 2.5% 3,572.64
F Harga Satuan Pekerjaan (D+E) 146,478.04

17 A.4.4.1.10.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Pasang lokal m3 0.045 142,800.00 6,426.00
73,274.80
C PERALATAN
D Jumlah A + B + C 140,624.80
E Overhead 2.5% 3,515.62
F Harga Satuan Pekerjaan (D+E) 144,140.42

18 A.4.4.1.11.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang lokal m3 0.049 142,800.00 6,997.20
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
71,928.40
C PERALATAN
D Jumlah A + B + C 139,278.40
E Overhead 2.5% 3,481.96
F Harga Satuan Pekerjaan (D+E) 142,760.36
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
19 A.4.4.1.12.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang lokal m3 0.05 142,800.00 7,140.00
69,505.00
C PERALATAN
D Jumlah A + B + C 136,855.00
E Overhead 2.5% 3,421.38
F Harga Satuan Pekerjaan (D+E) 140,276.38

20 A.4.4.1.23.1 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Terawang / Roster Buah 30 3,300.00 99,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Pasang lokal m3 0.035 142,800.00 4,998.00
119,508.00
C PERALATAN
D Jumlah A + B + C 186,858.00
E Overhead 2.5% 4,671.45
F Harga Satuan Pekerjaan (D+E) 191,529.45

21 A.4.4.1.2.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Muntilan m3 0.091 270,300.00 24,597.30
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
150,556.80
C PERALATAN
D Jumlah A + B + C 285,256.80
E Overhead 2.5% 7,131.42
F Harga Satuan Pekerjaan (D+E) 292,388.22
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
22 A.4.4.1.3.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 270,300.00 25,137.90
142,073.40
C PERALATAN
D Jumlah A + B + C 276,773.40
E Overhead 2.5% 6,919.34
F Harga Satuan Pekerjaan (D+E) 283,692.74

23 A.4.4.1.4.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 270,300.00 27,570.60
138,372.60
C PERALATAN
D Jumlah A + B + C 273,072.60
E Overhead 2.5% 6,826.82
F Harga Satuan Pekerjaan (D+E) 363,072.60

24 A.4.4.1.5.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 270,300.00 32,976.60
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
138,561.60
C PERALATAN
D Jumlah A + B + C 273,261.60
E Overhead 2.5% 6,831.54
F Harga Satuan Pekerjaan (D+E) 280,093.14
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
25 A.4.4.1.8.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 270,300.00 10,812.00
70,823.70
C PERALATAN
D Jumlah A + B + C 138,173.70
E Overhead 2.5% 3,454.34
F Harga Satuan Pekerjaan (D+E) 141,628.04

26 A.4.4.1.9.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Muntilan m3 0.043 270,300.00 11,622.90
67,587.90
C PERALATAN
D Jumlah A + B + C 134,937.90
E Overhead 2.5% 3,373.45
F Harga Satuan Pekerjaan (D+E) 138,311.35

27 A.4.4.1.10.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 270,300.00 12,163.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
65,562.30
C PERALATAN
D Jumlah A + B + C 132,912.30
E Overhead 2.5% 3,322.81
F Harga Satuan Pekerjaan (D+E) 136,235.11
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

28 A.4.4.1.11.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 270,300.00 13,244.70
64,725.90
C PERALATAN
D Jumlah A + B + C 132,075.90
E Overhead 2.5% 3,301.90
F Harga Satuan Pekerjaan (D+E) 135,377.80

29 A.4.4.1.12.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 270,300.00 13,515.00
62,430.00
C PERALATAN
D Jumlah A + B + C 129,780.00
E Overhead 2.5% 3,244.50
F Harga Satuan Pekerjaan (D+E) 133,024.50

30 A.4.4.1.2.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.091 142,800.00 12,994.80
138,954.30
C PERALATAN
D Jumlah A + B + C 273,654.30
E Overhead 2.5% 6,841.36
F Harga Satuan Pekerjaan (D+E) 280,495.66
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

31 A.4.4.1.3.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang Lokal m3 0.093 142,800.00 13,280.40
130,215.90
C PERALATAN
D Jumlah A + B + C 264,915.90
E Overhead 2.5% 6,622.90
F Harga Satuan Pekerjaan (D+E) 271,538.80

32 A.4.4.1.4.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang Lokal m3 0.102 142,800.00 14,565.60
125,367.60
C PERALATAN
D Jumlah A + B + C 260,067.60
E Overhead 2.5% 6,501.69
F Harga Satuan Pekerjaan (D+E) 350,067.60

33 A.4.4.1.5.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 150,000.00 90,000.00
Tukang Batu L.02 OH 0.2 175,000.00 35,000.00
Kepala Tukang Batu L.03 OH 0.02 185,000.00 3,700.00
Mandor L.04 OH 0.03 200,000.00 6,000.00
134,700.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.122 142,800.00 17,421.60
123,006.60
C PERALATAN
D Jumlah A + B + C 257,706.60
E Overhead 2.5% 6,442.67
F Harga Satuan Pekerjaan (D+E) 264,149.27
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

34 A.4.4.1.8.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang Lokal m3 0.04 142,800.00 5,712.00
65,723.70
C PERALATAN
D Jumlah A + B + C 133,073.70
E Overhead 2.5% 3,326.84
F Harga Satuan Pekerjaan (D+E) 136,400.54

35 A.4.4.1.9.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang Lokal m3 0.043 142,800.00 6,140.40
62,105.40
C PERALATAN
D Jumlah A + B + C 129,455.40
E Overhead 2.5% 3,236.39
F Harga Satuan Pekerjaan (D+E) 132,691.79

36 A.4.4.1.10.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.045 142,800.00 6,426.00
59,824.80
C PERALATAN
D Jumlah A + B + C 127,174.80
E Overhead 2.5% 3,179.37
F Harga Satuan Pekerjaan (D+E) 130,354.17
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

37 A.4.4.1.11.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang Lokal m3 0.049 142,800.00 6,997.20
58,478.40
C PERALATAN
D Jumlah A + B + C 125,828.40
E Overhead 2.5% 3,145.71
F Harga Satuan Pekerjaan (D+E) 128,974.11

38 A.4.4.1.12.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 150,000.00 45,000.00
Tukang Batu L.02 OH 0.1 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.01 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
67,350.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang Lokal m3 0.05 142,800.00 7,140.00
56,055.00
C PERALATAN
D Jumlah A + B + C 123,405.00
E Overhead 2.5% 3,085.13
F Harga Satuan Pekerjaan (D+E) 126,490.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 7.7760 1,410.00 10,964.16
Pasir Muntilan m3 0.0230 270,300.00 6,216.90
17,181.06
C PERALATAN
D Jumlah A + B + C 94,206.06
E Overhead 2.5% 2,355.15
F Harga Satuan Pekerjaan (D+E) 96,561.21

2 A.4.4.2.3.1 Pemasangan Plesteran 1 Pc : 3 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 7.7760 1,410.00 10,964.16
Pasir lokal m3 0.0230 142,800.00 3,284.40
14,248.56
C PERALATAN
D Jumlah A + B + C 91,273.56
E Overhead 2.5% 2,281.84
F Harga Satuan Pekerjaan (D+E) 93,555.40

3 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 6.2400 1,410.00 8,798.40
Pasir Muntilan m3 0.0240 270,300.00 6,487.20
15,285.60
C PERALATAN
D Jumlah A + B + C 92,310.60
E Overhead 2.5% 2,307.77
F Harga Satuan Pekerjaan (D+E) 94,618.37

4 A.4.4.2.4.1 Pemasangan Plesteran 1 Pc : 4 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B Bahan
Portland Semen Kg 6.2400 1,410.00 8,798.40
Pasir lokal m3 0.0240 142,800.00 3,427.20
12,225.60
C PERALATAN
D Jumlah A + B + C 89,250.60
E Overhead 2.5% 2,231.27
F Harga Satuan Pekerjaan (D+E) 91,481.87
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir Muntilan m3 0.0260 270,300.00 7,027.80
14,337.24
C PERALATAN
D Jumlah A + B + C 91,362.24
E Overhead 2.5% 2,284.06
F Harga Satuan Pekerjaan (D+E) 93,646.30

6 A.4.4.2.5.1 Pemasangan Plesteran 1 Pc : 5 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir lokal m3 0.0260 142,800.00 3,712.80
11,022.24
C PERALATAN
D Jumlah A + B + C 88,047.24
E Overhead 2.5% 2,201.18
F Harga Satuan Pekerjaan (D+E) 90,248.42

7 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 4.4160 1,410.00 6,226.56
Pasir Muntilan m3 0.0270 270,300.00 7,298.10
13,524.66
C PERALATAN
D Jumlah A + B + C 90,549.66
E Overhead 2.5% 2,263.74
F Harga Satuan Pekerjaan (D+E) 92,813.40

8 A.4.4.2.6.1 Pemasangan Plesteran 1 Pc : 6 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 4.4160 1,410.00 6,226.56
Pasir lokal m3 0.0270 142,800.00 3,855.60
10,082.16
C PERALATAN
D Jumlah A + B + C 87,107.16
E Overhead 2.5% 2,177.68
F Harga Satuan Pekerjaan (D+E) 89,284.84
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
9 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 3.9360 1,410.00 5,549.76
Pasir Muntilan m3 0.0280 270,300.00 7,568.40
13,118.16
C PERALATAN
D Jumlah A + B + C 90,143.16
E Overhead 2.5% 2,253.58
F Harga Satuan Pekerjaan (D+E) 92,396.74

10 A.4.4.2.7.1 Pemasangan Plesteran 1 Pc : 7 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 3.9360 1,410.00 5,549.76
Pasir lokal m3 0.0280 142,800.00 3,998.40
9,548.16
C PERALATAN
D Jumlah A + B + C 86,573.16
E Overhead 2.5% 2,164.33
F Harga Satuan Pekerjaan (D+E) 88,737.49

11 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Portland Semen Kg 3.4560 1,410.00 4,872.96
Pasir Muntilan m3 0.0290 270,300.00 7,838.70
12,711.66
C PERALATAN
D Jumlah A + B + C 89,736.66
E Overhead 2.5% 2,243.42
F Harga Satuan Pekerjaan (D+E) 91,980.08

12 A.4.4.2.8.1 Pemasangan Plesteran 1 Pc : 8 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 3.4560 1,410.00 4,872.96
Pasir lokal m3 0.0290 142,800.00 4,141.20
9,014.16
C PERALATAN
D Jumlah A + B + C 86,039.16
E Overhead 2.5% 2,150.98
F Harga Satuan Pekerjaan (D+E) 88,190.14
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang batu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir Muntilan m3 0.0260 270,300.00 7,027.80
14,337.24
C PERALATAN
D Jumlah A + B + C 53,042.24
E Overhead 2.5% 1,326.06
F Harga Satuan Pekerjaan (D+E) 54,368.30

14 A.4.4.2.19.1 Pemasangan Berapen 1 Pc : 5Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang batu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir lokal m3 0.0260 142,800.00 3,712.80
11,022.24
C PERALATAN
D Jumlah A + B + C 49,727.24
E Overhead 2.5% 1,243.18
F Harga Satuan Pekerjaan (D+E) 50,970.42

15 A.4.4.2.20 Pemasangan Plesteran Skoning 1 Pc : 2Pp muntilan


A Tenaga
Pekerja L.01 OH 0.0800 150,000.00 12,000.00
Tukang batu L.02 OH 0.4000 175,000.00 70,000.00
Kepala Tukang L.03 OH 0.0400 185,000.00 7,400.00
Mandor L.04 OH 0.0040 200,000.00 800.00
90,200.00
B Bahan
Portland Semen Kg 0.5000 1,410.00 705.00
Pasir Muntilan m3 0.0130 270,300.00 3,513.90
4,218.90
C PERALATAN
D Jumlah A + B + C 94,418.90
E Overhead 2.5% 2,360.47
F Harga Satuan Pekerjaan (D+E) 96,779.37

16 A.4.4.2.20.1 Pemasangan Plesteran Skoning 1 Pc : 2Pp lokal


A Tenaga
Pekerja L.01 OH 0.0800 150,000.00 12,000.00
Tukang batu L.02 OH 0.4000 175,000.00 70,000.00
Kepala Tukang L.03 OH 0.0400 185,000.00 7,400.00
Mandor L.04 OH 0.0040 200,000.00 800.00
90,200.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 0.5000 1,410.00 705.00
Pasir lokal m3 0.0130 142,800.00 1,856.40
2,561.40
C PERALATAN
D Jumlah A + B + C 92,761.40
E Overhead 2.5% 2,319.04
F Harga Satuan Pekerjaan (D+E) 95,080.44
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
17 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
67,350.00
B Bahan
Portland Semen Kg 4.3200 1,410.00 6,091.20
Pasir Muntilan m3 0.0060 270,300.00 1,621.80
7,713.00
C PERALATAN
D Jumlah A + B + C 75,063.00
E Overhead 2.5% 1,876.58
F Harga Satuan Pekerjaan (D+E) 76,939.58

18 A.4.4.2.23.1 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Lokal


A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
67,350.00
B Bahan
Portland Semen Kg 4.3200 1,410.00 6,091.20
Pasir Lokal m3 0.0060 142,800.00 856.80
6,948.00
C PERALATAN
D Jumlah A + B + C 74,298.00
E Overhead 2.5% 1,857.45
F Harga Satuan Pekerjaan (D+E) 76,155.45

19 A.4.4.2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang batu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Portland Semen Kg 3.1080 1,410.00 4,382.28
4,382.28
C PERALATAN
D Jumlah A + B + C 43,087.28
E Overhead 2.5% 1,077.18
F Harga Satuan Pekerjaan (D+E) 44,164.46

20 A.4.4.2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
PP Muntilan m3 0.0120 270,300.00 3,243.60
12,183.00
C PERALATAN
D Jumlah A + B + C 89,208.00
E Overhead 2.5% 2,230.20
F Harga Satuan Pekerjaan (D+E) 91,438.20
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

21 A.4.4.2.26.1 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Lokal
A Tenaga
Pekerja L.01 OH 0.3000 150,000.00 45,000.00
Tukang batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
77,025.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
PP Lokal m3 0.0120 142,800.00 1,713.60
10,653.00
C PERALATAN
D Jumlah A + B + C 87,678.00
E Overhead 2.5% 2,191.95
F Harga Satuan Pekerjaan (D+E) 89,869.95

22 A.4.4.2.27 Pemasangan Acian


A Tenaga
Pekerja L.01 OH 0.2000 150,000.00 30,000.00
Tukang batu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
51,350.00
B Bahan
Portland Semen Kg 3.2500 1,410.00 4,582.50
4,582.50
C PERALATAN
D Jumlah A + B + C 55,932.50
E Overhead 2.5% 1,398.31
F Harga Satuan Pekerjaan (D+E) 57,330.81
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
1 A.4.6.1.1 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu Bengkirai
A Tenaga
Pekerja L.01 OH 7.0000 150,000.00 1,050,000.00
Tukang Kayu L.02 OH 21.0000 175,000.00 3,675,000.00
Kepala Tukang L.03 OH 2.1000 185,000.00 388,500.00
Mandor L.04 OH 0.3500 200,000.00 70,000.00
5,183,500.00
B Bahan B
Kayu Klas I (bengkirai) m3 1.1000 8,648,600.00 9,513,460.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
9,542,260.00
C PERALATAN
D Jumlah A + B + C 14,725,760.00
E Overhead 2.5% 368,144.00
F Harga Satuan Pekerjaan (D+E) 15,093,904.00

2 A.4.6.1.2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu kamfer
A Tenaga
Pekerja L.01 OH 6.0000 150,000.00 900,000.00
Tukang Kayu L.02 OH 18.0000 175,000.00 3,150,000.00
Kepala Tukang L.03 OH 1.8000 185,000.00 333,000.00
Mandor L.04 OH 0.3000 200,000.00 60,000.00
4,443,000.00
B Bahan
Kayu Klas II (kamfer) m3 1.2000 8,116,300.00 9,739,560.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
9,768,360.00
C PERALATAN
D Jumlah A + B + C 14,211,360.00
E Overhead 2.5% 355,284.00
F Harga Satuan Pekerjaan (D+E) 14,566,644.00

3 A.4.6.1.5 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Jati


A Tenaga
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Tukang Kayu L.02 OH 3.0000 175,000.00 525,000.00
Kepala Tukang L.03 OH 0.3000 185,000.00 55,500.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
740,500.00
B Bahan
Kayu jati m3 0.0400 16,875,000.00 675,000.00
Lem Kayu kg 0.0500 12,800.00 640.00
675,640.00
C PERALATAN
D Jumlah A + B + C 1,416,140.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 35,403.50
F Harga Satuan Pekerjaan (D+E) 1,451,543.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.6.1.5.1 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Kamfer
A Tenaga
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Tukang Kayu L.02 OH 3.0000 175,000.00 525,000.00
Kepala Tukang L.03 OH 0.3000 185,000.00 55,500.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
740,500.00
B Bahan
Kayu kamfer m3 0.0400 8,116,300.00 324,652.00
Lem Kayu kg 0.0500 12,800.00 640.00
325,292.00
C PERALATAN
D Jumlah A + B + C 1,065,792.00
E Overhead 2.5% 26,644.80
F Harga Satuan Pekerjaan (D+E) 1,092,436.80

5 A.4.6.1.6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu jati, papan m3 0.0240 16,875,000.00 405,000.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
408,840.00
C PERALATAN
D Jumlah A + B + C 1,001,240.00
E Overhead 2.5% 25,031.00
F Harga Satuan Pekerjaan (D+E) 1,026,271.00

6 A.4.6.1.6.1 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu kamfer m3 0.0240 8,116,300.00 194,791.20
Lem Kayu kg 0.3000 12,800.00 3,840.00
198,631.20
C PERALATAN
D Jumlah A + B + C 791,031.20
E Overhead 2.5% 19,775.78
F Harga Satuan Pekerjaan (D+E) 810,806.98
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.6.1.8 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm)
A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Kayu L.02 OH 2.1000 175,000.00 367,500.00
Kepala Tukang L.03 OH 0.2100 185,000.00 38,850.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
518,350.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 72,200.00 72,200.00
281,891.50
C PERALATAN
D Jumlah A + B + C 800,241.50
E Overhead 2.5% 20,006.04
F Harga Satuan Pekerjaan (D+E) 820,247.54

8 A.4.6.1.9 Pembuatan&Pemasangan 1 m2 Pintu Plywood rangkap, rangka expose kayu klas I atau II
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0256 8,116,300.00 207,777.28
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 72,200.00 72,200.00
286,761.28
C PERALATAN
D Jumlah A + B + C 879,161.28
E Overhead 2.5% 21,979.03
F Harga Satuan Pekerjaan (D+E) 901,140.31

9 A.4.6.1.10 Pembuatan & Pemasangan 1 m2 Jalusi mati Kosen Kayu Klas I atau II
A Tenaga
Pekerja L.01 OH 0.6700 150,000.00 100,500.00
Tukang Kayu L.02 OH 2.0000 175,000.00 350,000.00
Kepala Tukang L.03 OH 0.2000 185,000.00 37,000.00
Mandor L.04 OH 0.3350 200,000.00 67,000.00
554,500.00
B Bahan
Kayu Klas I Bengkirai) m3 0.0600 8,648,600.00 518,916.00
Paku Biasa 1/2" - 1" Kg 0.1500 12,800.00 1,920.00
520,836.00
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 1,075,336.00
E Overhead 2.5% 26,883.40
F Harga Satuan Pekerjaan (D+E) 1,102,219.40
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.4.6.1.11 Pembuatan & Pemasangan 1 m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I
A Tenaga
Pekerja L.01 OH 0.8000 150,000.00 120,000.00
Tukang Kayu L.02 OH 2.4000 175,000.00 420,000.00
Kepala Tukang L.03 OH 0.2400 185,000.00 44,400.00
Mandor L.04 OH 0.0400 200,000.00 8,000.00
592,400.00
B Bahan
Kayu Klas I (Bengkirai) m3 0.0250 8,648,600.00 216,215.00
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 72,200.00 72,200.00
292,639.00
C PERALATAN
D Jumlah A + B + C 885,039.00
E Overhead 2.5% 22,125.98
F Harga Satuan Pekerjaan (D+E) 907,164.98

11 A.4.6.1.12 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II
A Tenaga
Pekerja L.01 OH 0.8500 150,000.00 127,500.00
Tukang Kayu L.02 OH 2.5500 175,000.00 446,250.00
Kepala Tukang L.03 OH 0.2550 185,000.00 47,175.00
Mandor L.04 OH 0.0430 200,000.00 8,600.00
629,525.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.0800 12,800.00 1,024.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 72,200.00 72,200.00
Formika Lbr 0.5000 58,000.00 29,000.00
305,515.50
C PERALATAN
D Jumlah A + B + C 935,040.50
E Overhead 2.5% 23,376.01
F Harga Satuan Pekerjaan (D+E) 958,416.51

12 A.4.6.1.13 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Bengkirai


A Tenaga
Pekerja L.01 OH 4.0000 150,000.00 600,000.00
Tukang Kayu L.02 OH 12.0000 175,000.00 2,100,000.00
Kepala Tukang L.03 OH 1.2000 185,000.00 222,000.00
Mandor L.04 OH 0.2000 200,000.00 40,000.00
2,962,000.00
B Bahan
Kayu Bengkirai m3 1.1000 8,648,600.00 9,513,460.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Paku Biasa 2" - 5" Kg 5.6000 12,800.00 71,680.00
9,888,140.00
C PERALATAN
D Jumlah A + B + C 12,850,140.00
E Overhead 2.5% 321,253.50
F Harga Satuan Pekerjaan (D+E) 13,171,393.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.4.6.1.13.1 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing


A Tenaga
Pekerja L.01 OH 4.0000 150,000.00 600,000.00
Tukang Kayu L.02 OH 12.0000 175,000.00 2,100,000.00
Kepala Tukang L.03 OH 1.2000 185,000.00 222,000.00
Mandor L.04 OH 0.2000 200,000.00 40,000.00
2,962,000.00
B Bahan
Kayu Kruing m3 1.1000 6,582,500.00 7,240,750.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 5.6000 12,800.00 71,680.00
7,615,430.00
C PERALATAN
D Jumlah A + B + C 10,577,430.00
E Overhead 2.5% 264,435.75
F Harga Satuan Pekerjaan (D+E) 10,841,865.75

14 A.4.6.1.15 Pemasangan konstruksi 1 m3 Gording, Kayu bengkirai


A Tenaga
Pekerja L.01 OH 6.7000 150,000.00 1,005,000.00
Tukang Kayu L.02 OH 20.1000 175,000.00 3,517,500.00
Kepala Tukang L.03 OH 2.0100 185,000.00 371,850.00
Mandor L.04 OH 0.3350 200,000.00 67,000.00
4,961,350.00
B Bahan
Kayu Klas I (Bengkirai) m3 1.1000 8,648,600.00 9,513,460.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 3.0000 12,800.00 38,400.00
9,854,860.00
C PERALATAN
D Jumlah A + B + C 14,816,210.00
E Overhead 2.5% 370,405.25
F Harga Satuan Pekerjaan (D+E) 15,186,615.25

15 A.4.6.1.15.1 Pemasangan konstruksi 1 m3 Gording, Kayu Kruing


A Tenaga
Pekerja L.01 OH 6.7000 150,000.00 1,005,000.00
Tukang Kayu L.02 OH 20.1000 175,000.00 3,517,500.00
Kepala Tukang L.03 OH 2.0100 185,000.00 371,850.00
Mandor L.04 OH 0.3350 200,000.00 67,000.00
4,961,350.00
B Bahan
Kayu Klas Kruing m3 1.1000 6,582,500.00 7,240,750.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 3.0000 12,800.00 38,400.00
7,582,150.00
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 12,543,500.00
E Overhead 2.5% 313,587.50
F Harga Satuan Pekerjaan (D+E) 12,857,087.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.4.6.1.16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu Klas II
A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
35,350.00
B Bahan
Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm m3 0.0140 8,648,600.00 121,080.40
Reng (2x3) cm bengkirai m3 0.0036 8,648,600.00 31,134.96
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
155,415.36
C PERALATAN
D Jumlah A + B + C 190,765.36
E Overhead 2.5% 4,769.13
F Harga Satuan Pekerjaan (D+E) 195,534.49

17 A.4.6.1.17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
35,350.00
B Bahan
Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm m3 0.0140 8,648,600.00 121,080.40
Reng (2x3) cm bengkirai m3 0.0072 8,648,600.00 62,269.92
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
186,550.32
C PERALATAN
D Jumlah A + B + C 221,900.32
E Overhead 2.5% 5,547.51
F Harga Satuan Pekerjaan (D+E) 227,447.83

18 A.4.6.1.19 Pemasangan 1 m2 Rangka Langit-langit (50x1,00) m, kayu Klas II atau III


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.3000 175,000.00 52,500.00
Kepala Tukang L.03 OH 0.0300 185,000.00 5,550.00
Mandor L.04 OH 0.0750 200,000.00 15,000.00
95,550.00
B Bahan
Kayu Klas II (Kruing) m3 0.0154 6,582,500.00 101,370.50
Paku Biasa 2" - 5" Kg 0.2000 12,800.00 2,560.00
103,930.50
C PERALATAN
D Jumlah A + B + C 199,480.50
E Overhead 2.5% 4,987.01
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 204,467.51
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

19 A.4.6.1.20 Pemasangan 1 m2 Rangka Langit-langit (60x60) cm, kayu Klas II atau III
A Tenaga
Pekerja L.01 OH 0.2000 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.3000 175,000.00 52,500.00
Kepala Tukang L.03 OH 0.0300 185,000.00 5,550.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
90,050.00
B Bahan
Kayu Klas II (Kruing) m3 0.0163 6,582,500.00 107,294.75
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
110,494.75
C PERALATAN
D Jumlah A + B + C 200,544.75
E Overhead 2.5% 5,013.62
F Harga Satuan Pekerjaan (D+E) 205,558.37

20 A.4.6.1.21 Pemasangan 1 m' Listplank Uk. (3x20)cm Kayu klas I atau II


A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
54,700.00
B Bahan
Kayu klas I Bengkirai) m3 0.0108 8,648,600.00 93,404.88
Paku Biasa 2" - 5" Kg 0.1000 12,800.00 1,280.00
94,684.88
C PERALATAN
D Jumlah A + B + C 149,384.88
E Overhead 2.5% 3,734.62
F Harga Satuan Pekerjaan (D+E) 153,119.50

21 A.4.6.1.22 Pemasangan 1 m' Listplank Uk. (3x30)cm Kayu klas I atau klas II
A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
54,700.00
B Bahan
Kayu klas I Bengkirai) m3 0.0110 8,648,600.00 95,134.60
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
95,774.60
C PERALATAN
D Jumlah A + B + C 150,474.60
E Overhead 2.5% 3,761.87
F Harga Satuan Pekerjaan (D+E) 154,236.47
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

22 A.4.6.1.23 Pemasangan 1 m2 Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.4500 175,000.00 78,750.00
Kepala Tukang L.03 OH 0.0450 185,000.00 8,325.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
111,175.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
186,230.00
C PERALATAN
D Jumlah A + B + C 297,405.00
E Overhead 2.5% 7,435.13
F Harga Satuan Pekerjaan (D+E) 304,840.13

23 A.4.6.1.24 Pemasangan 1 m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.4500 175,000.00 78,750.00
Kepala Tukang L.03 OH 0.0450 185,000.00 8,325.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
111,175.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
Teakwood 120 x 240 cm tebal 4mm Lbr 0.8600 72,200.00 62,092.00
Lem Ltr 0.5600 12,800.00 7,168.00
255,490.00
C PERALATAN
D Jumlah A + B + C 366,665.00
E Overhead 2.5% 9,166.63
F Harga Satuan Pekerjaan (D+E) 375,831.63

24 A.4.6.1.25 Pemasangan 1 m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Kayu L.02 OH 0.6000 175,000.00 105,000.00
Kepala Tukang L.03 OH 0.0600 185,000.00 11,100.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
121,100.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
Plywood 120 x 240 cm tebal 4mm Lbr 0.8600 72,200.00 62,092.00
Lem Ltr 0.5600 12,800.00 7,168.00
255,490.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 376,590.00
E Overhead 2.5% 9,414.75
F Harga Satuan Pekerjaan (D+E) 386,004.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

25 A.4.6.1.26 Pemasangan 1 m2 Dinding Lambriziring dari Papan klas I


A Tenaga
Pekerja L.01 OH 0.6000 150,000.00 90,000.00
Tukang Kayu L.02 OH 1.8000 175,000.00 315,000.00
Kepala Tukang L.03 OH 0.1800 185,000.00 33,300.00
Mandor L.04 OH 0.0300 200,000.00 6,000.00
444,300.00
B Bahan
Kayu klas I (Jati) m3 0.0070 16,875,000.00 118,125.00
Paku Biasa 2" - 5" Kg 0.1000 12,800.00 1,280.00
Paku Sekrup 3,5" Kg 0.1500 13,000.00 1,950.00
121,355.00
C PERALATAN
D Jumlah A + B + C 565,655.00
E Overhead 2.5% 14,141.38
F Harga Satuan Pekerjaan (D+E) 579,796.38

26 A.4.6.1.29 Pasang Kasau & Reng Kayu Bengkirai


A Tenaga
SNI Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
35,350.00
B Bahan
Kayu Bengkirai m3 0.0120 8,648,600.00 103,783.20
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
105,703.20
C PERALATAN
D Jumlah A + B + C 141,053.20
E Overhead 2.5% 3,526.33
F Harga Satuan Pekerjaan (D+E) 144,579.53

27 A.4.6.1.30 Pasang Kasau & Reng Kayu Kruing


A Tenaga
SNI Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
35,350.00
B Bahan
Kayu Kruing m3 0.0120 6,582,500.00 78,990.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
80,910.00
C PERALATAN
D Jumlah A + B + C 116,260.00
E Overhead 2.5% 2,906.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 119,166.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
28 A.4.6.1.31 Pasang Papan sirip
A Tenaga
SNI Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
44,350.00
B Bahan
Kayu Kruing m3 0.0050 6,582,500.00 32,912.50
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
33,552.50
C PERALATAN
D Jumlah A + B + C 77,902.50
E Overhead 2.5% 1,947.56
F Harga Satuan Pekerjaan (D+E) 79,850.06
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 247.000 1,410.00 348,270.00
Pasir Beton Kg 869.000 193.07 167,779.07
Kerikil (maksimum 30 mm) Kg 999.000 159.93 159,766.00
Air ltr 215.000 20.00 4,300.00
680,115.07
C PERALATAN
D Jumlah A + B + C 997,520.07
E Overhead 2.5% 24,938.00
F Harga Satuan Pekerjaan (D+E) 1,022,458.07
Overhead & Profit 12.5%
2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 276.000 1,410.00 389,160.00
Pasir Beton kg 828.000 193.07 159,863.14
Kerikil (maksimum 30 mm) kg 1012.000 159.93 161,845.04
Air ltr 215.000 20.00 4,300.00
715,168.18
C PERALATAN
D Jumlah A + B + C 1,032,573.18
E Overhead 2.5% 25,814.33
F Harga Satuan Pekerjaan (D+E) 1,058,387.51

3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 299.000 1,410.00 421,590.00
Pasir Beton kg 799.000 193.07 154,264.07
Kerikil (maksimum 30 mm) kg 1017.000 159.93 162,644.67
Air ltr 215.000 20.00 4,300.00
742,798.74
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 1,060,203.74
E Overhead 2.5% 26,505.09
F Harga Satuan Pekerjaan (D+E) 1,086,708.83
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A Tenaga
Pekerja L.01 OH 1.200 150,000.00 180,000.00
Tukang Batu L.02 OH 0.200 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.020 185,000.00 3,700.00
Mandor L.04 OH 0.060 200,000.00 12,000.00
230,700.00
B Bahan
Portland Semen Kg 230.000 1,410.00 324,300.00
Pasir Beton Kg 893.000 193.07 172,412.79
Kerikil (maksimum 30 mm) Kg 1027.000 159.93 164,243.93
Air ltr 200.000 20.00 4,000.00
664,956.71
C PERALATAN
D Jumlah A + B + C 895,656.71
E Overhead 2.5% 22,391.42
F Harga Satuan Pekerjaan (D+E) 918,048.13

5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 326.000 1,410.00 459,660.00
Pasir Beton Kg 760.000 193.07 146,734.29
Kerikil (maksimum 30 mm) Kg 1029.000 159.93 164,563.78
Air ltr 215.000 20.00 4,300.00
775,258.06
C PERALATAN
D Jumlah A + B + C 1,092,663.06
E Overhead 2.5% 27,316.58
F Harga Satuan Pekerjaan (D+E) 1,119,979.64

6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 352.000 1,410.00 496,320.00
Pasir Beton Kg 731.000 193.07 141,135.21
Kerikil (maksimum 30 mm) Kg 1031.000 159.93 164,883.63
Air ltr 215.000 20.00 4,300.00
806,638.84
C PERALATAN
D Jumlah A + B + C 1,124,043.84
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 28,101.10
F Harga Satuan Pekerjaan (D+E) 1,152,144.94
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 371.000 1,410.00 523,110.00
Pasir Beton Kg 698.000 193.07 134,763.86
Kerikil (maksimum 30 mm) Kg 1047.000 159.93 167,442.44
Air ltr 215.000 20.00 4,300.00
829,616.30
C PERALATAN
D Jumlah A + B + C 1,147,021.30
E Overhead 2.5% 28,675.53
F Harga Satuan Pekerjaan (D+E) 1,175,696.83

8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 384.000 1,410.00 541,440.00
Pasir Beton Kg 692.000 193.07 133,605.43
Kerikil (maksimum 30 mm) Kg 1039.000 159.93 166,163.04
Air ltr 215.000 20.00 4,300.00
845,508.47
C PERALATAN
D Jumlah A + B + C 1,162,913.47
E Overhead 2.5% 29,072.84
F Harga Satuan Pekerjaan (D+E) 1,191,986.30

9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 406.000 1,410.00 572,460.00
Pasir Beton kg 684.000 193.07 132,060.86
Kerikil (maksimum 30 mm) kg 1026.000 159.93 164,084.00
Air ltr 215.000 20.00 4,300.00
872,904.86
C PERALATAN
D Jumlah A + B + C 1,190,309.86
E Overhead 2.5% 29,757.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,220,067.60
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
Pekerja L.01 OH 1.650 150,000.00 247,500.00
Tukang Batu L.02 OH 0.275 175,000.00 48,125.00
Kepala Tukang L.03 OH 0.028 185,000.00 5,180.00
Mandor L.04 OH 0.083 200,000.00 16,600.00
317,405.00
B Bahan
Portland Semen Kg 413.000 1,410.00 582,330.00
Pasir Beton Kg 681.000 193.07 131,481.64
Kerikil (maksimum 30 mm) Kg 1021.000 159.93 163,284.37
Air ltr 215.000 20.00 4,300.00
881,396.01
C PERALATAN
D Jumlah A + B + C 1,198,801.01
E Overhead 2.5% 29,970.03
F Harga Satuan Pekerjaan (D+E) 1,228,771.04

11 A.4.1.1.17 Pembesian 10 kg dg Besi Polos atau Besi Ulir


A Tenaga
Pekerja L.01 OH 0.070 150,000.00 10,500.00
Tukang Besi L.02 OH 0.070 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.007 185,000.00 1,295.00
Mandor L.04 OH 0.004 200,000.00 800.00
24,845.00
B Bahan
Besi Beton (polos/ulir) Kg 10.500 9,180.00 96,390.00
Kawat Beton Kg 0.150 15,300.00 2,295.00
98,685.00
C PERALATAN
D Jumlah A + B + C 123,530.00
E Overhead 2.5% 3,088.25
F Harga Satuan Pekerjaan (D+E) 126,618.25
Jadi untuk pembesian 1 kg dibagi 10 12,661.83

12 A.4.1.1.19 Jaring Kawat baja/Wire Mesh / 10 kg


A Tenaga
Pekerja L.01 OH 0.025 150,000.00 3,750.00
Tukang Besi L.02 OH 0.025 175,000.00 4,375.00
Kepala Tukang L.03 OH 0.002 185,000.00 370.00
Mandor L.04 OH 0.001 200,000.00 200.00
8,695.00
B Bahan
Jaring Kawat Baja dilas/wiremesh Kg 10.200 17,000.00 173,400.00
Kawat Beton Kg 0.050 15,300.00 765.00
174,165.00
C PERALATAN
D Jumlah A + B + C 182,860.00
E Overhead 2.5% 4,571.50
F Harga Satuan Pekerjaan (D+E) 187,431.50
Jadi untuk pembesian 1 kg dibagi 10 18,743.15
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.1.1.20 Memasang Bekisting untuk Pondasi
A Tenaga
Pekerja L.01 OH 0.520 150,000.00 78,000.00
Tukang Kayu L.02 OH 0.260 175,000.00 45,500.00
Kepala Tukang L.03 OH 0.026 185,000.00 4,810.00
Mandor L.04 OH 0.026 200,000.00 5,200.00
133,510.00
B Bahan
Kayu Klas III (Randu) m3 0.040 897,700.00 35,908.00
Paku Biasa 2" - 5" Kg 0.300 12,800.00 3,840.00
Minyak Bekisting Ltr 0.100 10,000.00 1,000.00
40,748.00
C PERALATAN
D Jumlah A + B + C 174,258.00
E Overhead 2.5% 4,356.45
F Harga Satuan Pekerjaan (D+E) 178,614.45

14 A.4.1.1.21 Memasang Bekisting untuk Sloof


A Tenaga
Pekerja L.01 OH 0.520 150,000.00 78,000.00
Tukang Kayu L.02 OH 0.260 175,000.00 45,500.00
Kepala Tukang L.03 OH 0.026 185,000.00 4,810.00
Mandor L.04 OH 0.026 200,000.00 5,200.00
133,510.00
B Bahan
Kayu Klas III (Randu) m3 0.045 897,700.00 40,396.50
Paku Biasa 2" - 5" Kg 0.300 12,800.00 3,840.00
Minyak Bekisting Ltr 0.100 10,000.00 1,000.00
45,236.50
C PERALATAN
D Jumlah A + B + C 178,746.50
E Overhead 2.5% 4,468.66
F Harga Satuan Pekerjaan (D+E) 183,215.16

15 A.4.1.1.22 Memasang Bekisting untuk Kolom


A Tenaga
Pekerja L.01 OH 0.660 150,000.00 99,000.00
Tukang Kayu L.02 OH 0.330 175,000.00 57,750.00
Kepala Tukang L.03 OH 0.033 185,000.00 6,105.00
Mandor L.04 OH 0.033 200,000.00 6,600.00
169,455.00
B Bahan
Kayu Klas III (Randu) m3 0.040 897,700.00 35,908.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 10,000.00 2,000.00
Balok Kayu m3 0.015 897,700.00 13,465.50
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 2.000 13,500.00 27,000.00
119,193.50
C PERALATAN
D Jumlah A + B + C 288,648.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 7,216.21
F Harga Satuan Pekerjaan (D+E) 295,864.71
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.4.1.1.23 Memasang Bekisting untuk Balok
A Tenaga
Pekerja L.01 OH 0.660 150,000.00 99,000.00
Tukang Kayu L.02 OH 0.330 175,000.00 57,750.00
Kepala Tukang L.03 OH 0.033 185,000.00 6,105.00
Mandor L.04 OH 0.033 200,000.00 6,600.00
169,455.00
B Bahan
Kayu Klas III (Randu) m3 0.040 897,700.00 35,908.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 10,000.00 2,000.00
Balok Kayu m3 0.018 897,700.00 16,158.60
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 2.000 13,500.00 27,000.00
121,886.60
C PERALATAN
D Jumlah A + B + C 291,341.60
E Overhead 2.5% 7,283.54
F Harga Satuan Pekerjaan (D+E) 298,625.14

17 A.4.1.1.24 Memasang Bekisting untuk Lantai


A Tenaga
Pekerja L.01 OH 0.660 150,000.00 99,000.00
Tukang Kayu L.02 OH 0.330 175,000.00 57,750.00
Kepala Tukang L.03 OH 0.033 185,000.00 6,105.00
Mandor L.04 OH 0.033 200,000.00 6,600.00
169,455.00
B Bahan
Kayu Klas III (Randu) m3 0.040 897,700.00 35,908.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 10,000.00 2,000.00
Balok Kayu m3 0.015 897,700.00 13,465.50
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 6.000 13,500.00 81,000.00
173,193.50
C PERALATAN
D Jumlah A + B + C 342,648.50
E Overhead 2.5% 8,566.21
F Harga Satuan Pekerjaan (D+E) 351,214.71

18 A.4.1.1.26 Memasang Bekisting untuk Tangga


A Tenaga
Pekerja L.01 OH 0.660 150,000.00 99,000.00
Tukang Kayu L.02 OH 0.330 175,000.00 57,750.00
Kepala Tukang L.03 OH 0.033 185,000.00 6,105.00
Mandor L.04 OH 0.033 200,000.00 6,600.00
169,455.00
B Bahan
Kayu Klas III (Randu) m3 0.030 897,700.00 26,931.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.150 10,000.00 1,500.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Balok Kayu m3 0.015 897,700.00 13,465.50
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 2.000 13,500.00 27,000.00
109,716.50
C PERALATAN
D Jumlah A + B + C 279,171.50
E Overhead 2.5% 6,979.29
F Harga Satuan Pekerjaan (D+E) 286,150.79
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
19 A.4.1.1.35 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm
A Tenaga
Pekerja L.01 OH 0.180 150,000.00 27,000.00
Tukang batu L.02 OH 0.020 175,000.00 3,500.00
Tukang Kayu L.02 OH 0.020 175,000.00 3,500.00
Tukang Besi L.02 OH 0.020 175,000.00 3,500.00
Kepala Tukang L.03 OH 0.006 185,000.00 1,110.00
Mandor L.04 OH 0.009 200,000.00 1,800.00
40,410.00
B Bahan
Kayu Klas III (Randu) m3 0.002 897,700.00 1,795.40
Paku Biasa 2" - 5" Kg 0.010 12,800.00 128.00
Besi Beton Polos Kg 3.000 9,180.00 27,540.00
Kawat Beton Kg 0.045 15,300.00 688.50
Portland Semen Kg 4.000 1,410.00 5,640.00
Pasir Beton m3 0.006 270,300.00 1,621.80
Kerikil Beton m3 0.009 215,900.00 1,943.10
39,356.80
C PERALATAN
D Jumlah A + B + C 79,766.80
E Overhead 2.5% 1,994.17
F Harga Satuan Pekerjaan (D+E) 81,760.97

20 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm


A Tenaga
Pekerja L.01 OH 0.297 150,000.00 44,550.00
Tukang batu L.02 OH 0.033 175,000.00 5,775.00
Tukang Kayu L.02 OH 0.033 175,000.00 5,775.00
Tukang Besi L.02 OH 0.033 175,000.00 5,775.00
Kepala Tukang L.03 OH 0.010 185,000.00 1,850.00
Mandor L.04 OH 0.015 200,000.00 3,000.00
66,725.00
B Bahan
Kayu Klas III (Randu) m3 0.003 897,700.00 2,693.10
Paku Biasa 2" - 5" Kg 0.020 12,800.00 256.00
Besi Beton Polos Kg 3.600 9,180.00 33,048.00
Kawat Beton Kg 0.050 15,300.00 765.00
Portland Semen Kg 5.500 1,410.00 7,755.00
Pasir Beton m3 0.009 270,300.00 2,432.70
Kerikil Beton m3 0.015 215,900.00 3,238.50
50,188.30
C PERALATAN
D Jumlah A + B + C 116,913.30
E Overhead 2.5% 2,922.83
F Harga Satuan Pekerjaan (D+E) 119,836.13

21 A.4.1.1.37 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm
A Tenaga
Pekerja L.01 OH 0.200 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.500 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.050 185,000.00 9,250.00
Mandor L.04 OH 0.010 200,000.00 2,000.00
128,750.00
B Bahan
kayu randu tebal 2 cm m3 0.022 897,700.00 19,749.40
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
24,869.40
C PERALATAN
D Jumlah A + B + C 153,619.40
E Overhead 2.5% 3,840.49
F Harga Satuan Pekerjaan (D+E) 157,459.89
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0075 185,000.00 1,387.50
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,612.50
B Bahan
Genteng Plentong Buah 25.0000 3,000.00 75,000.00
75,000.00
C PERALATAN
D Jumlah A + B + C 113,612.50
E Overhead 2.5% 2,840.31
F Harga Satuan Pekerjaan (D+E) 116,452.81

Overhead & Profit


2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur
A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Genteng Kodok / Glasur Buah 25.0000 1,200.00 30,000.00
30,000.00
C PERALATAN
D Jumlah A + B + C 68,705.00
E Overhead 2.5% 1,717.63
F Harga Satuan Pekerjaan (D+E) 70,422.63

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
38,705.00
B Bahan
Genteng Plentong Super / Besar Buah 18.0000 6,000.00 108,000.00
108,000.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

C PERALATAN
D Jumlah A + B + C 146,705.00
E Overhead 2.5% 3,667.63
F Harga Satuan Pekerjaan (D+E) 150,372.63
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong


A Tenaga
Pekerja L.01 OH 0.4000 150,000.00 60,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0020 200,000.00 400.00
99,100.00
B Bahan
Genteng Bubung Plentong Buah 5.0000 13,500.00 67,500.00
Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 142,800.00 4,569.60
83,349.60
C PERALATAN
D Jumlah A + B + C 182,449.60
E Overhead 2.5% 4,561.24
F Harga Satuan Pekerjaan (D+E) 187,010.84

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur


A Tenaga
Pekerja L.01 OH 0.4000 150,000.00 60,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0020 200,000.00 400.00
99,100.00
B Bahan
Genteng Bubung Kodok / Glasur Buah 5.0000 5,000.00 25,000.00
Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 142,800.00 4,569.60
40,849.60
C PERALATAN
D Jumlah A + B + C 139,949.60
E Overhead 2.5% 3,498.74
F Harga Satuan Pekerjaan (D+E) 143,448.34

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar


A Tenaga
Pekerja L.01 OH 0.4000 150,000.00 60,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0020 200,000.00 400.00
99,100.00
B Bahan
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

Genteng Bubung Plentong Besar Buah 4.0000 13,500.00 54,000.00


Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 142,800.00 4,569.60
69,849.60
C PERALATAN
D Jumlah A + B + C 168,949.60
E Overhead 2.5% 4,223.74
F Harga Satuan Pekerjaan (D+E) 173,173.34
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

7 A.4.5.2.9 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm


A Tenaga
Pekerja L.01 OH 0.1400 150,000.00 21,000.00
Tukang Kayu L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
37,205.00
B Bahan
Asbes Gelombang Lbr 0.6000 78,000.00 46,800.00
Paku Pancing 60 x 230 Kg 0.1200 25,000.00 3,000.00
49,800.00
C PERALATAN
D Jumlah A + B + C 87,005.00
E Overhead 2.5% 2,175.13
F Harga Satuan Pekerjaan (D+E) 89,180.13

8 A.4.5.2.10 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm


A Tenaga
Pekerja L.01 OH 0.1400 150,000.00 21,000.00
Tukang Kayu L.02 OH 0.0700 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.0070 185,000.00 1,295.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
35,945.00
B Bahan
Asbes Gelombang Lbr 0.6000 72,000.00 43,200.00
Paku Pancing 60 x 230 Kg 0.1200 25,000.00 3,000.00
46,200.00
C PERALATAN
D Jumlah A + B + C 82,145.00
E Overhead 2.5% 2,053.63
F Harga Satuan Pekerjaan (D+E) 84,198.63

9 A.4.5.2.12 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm


A Tenaga
Pekerja L.01 OH 0.1400 150,000.00 21,000.00
Tukang Kayu L.02 OH 0.0700 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.0070 185,000.00 1,295.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
35,945.00
B Bahan
Asbes Gelombang Lbr 0.3500 88,000.00 30,800.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

Paku Pancing 60 x 230 Kg 0.1200 25,000.00 3,000.00


33,800.00
C PERALATAN
D Jumlah A + B + C 69,745.00
E Overhead 2.5% 1,743.63
F Harga Satuan Pekerjaan (D+E) 71,488.63
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

10 A.4.5.2.15 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm


A Tenaga
Pekerja L.01 OH 0.1400 150,000.00 21,000.00
Tukang Kayu L.02 OH 0.0700 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.0070 185,000.00 1,295.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
35,945.00
B Bahan
Asbes Gelombang Lbr 0.5100 62,000.00 31,620.00
Paku Pancing 60 x 230 Kg 0.1200 25,000.00 3,000.00
34,620.00
C PERALATAN
D Jumlah A + B + C 70,565.00
E Overhead 2.5% 1,764.13
F Harga Satuan Pekerjaan (D+E) 72,329.13

11 A.4.5.2.22 Pemasangan 1 m’ bubung stel gelombang 0,92m


A Tenaga
Pekerja L.01 OH 0.0840 150,000.00 12,600.00
Tukang Kayu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0040 200,000.00 800.00
37,680.00
B Bahan
Bubung stel gelombang Lbr 2.4000 30,000.00 72,000.00
Paku skrup 3,5” bj 6.0000 1,600.00 9,600.00
81,600.00
C PERALATAN
D Jumlah A + B + C 119,280.00
E Overhead 2.5% 2,982.00
F Harga Satuan Pekerjaan (D+E) 122,262.00

12 A.4.5.2.30 Pemasangan Atap Genteng Beton


A Tenaga
Pekerja L.01 OH 0.2000 150,000.00 30,000.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0100 200,000.00 2,000.00
51,350.00
B Bahan
Genteng Beton Standrad Lbr 11.0000 6,000.00 66,000.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

Paku Biasa 2" - 5" Kg 0.0300 12,800.00 384.00


66,384.00
C PERALATAN
D Jumlah A + B + C 117,734.00
E Overhead 2.5% 2,943.35
F Harga Satuan Pekerjaan (D+E) 120,677.35
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

13 A.4.5.2.34 Pemasangan Nok Genteng Beton


A Tenaga
Pekerja L.01 OH 0.4000 150,000.00 60,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0200 200,000.00 4,000.00
102,700.00
B Bahan
Nok Genteng Beton Buah 3.5000 13,500.00 47,250.00
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
Portland Semen Kg 10.8000 1,410.00 15,228.00
Pasir Pasang m3 0.0320 142,800.00 4,569.60
Semen Warna Kg 1.0000 11,790.00 11,790.00
79,477.60
C PERALATAN
D Jumlah A + B + C 182,177.60
E Overhead 2.5% 4,554.44
F Harga Satuan Pekerjaan (D+E) 186,732.04

14 A.4.5.2.38 Pemasangan Atap Seng Gelombang


A Tenaga
Pekerja L.01 OH 0.1200 150,000.00 18,000.00
Tukang Kayu L.02 OH 0.0600 175,000.00 10,500.00
Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00
Mandor L.04 OH 0.0060 200,000.00 1,200.00
30,810.00
B Bahan
Seng Gelombang 3" x 6" BJLS 28 Lbr 0.7000 80,000.00 56,000.00
Paku Pancing Kg 0.0200 25,000.00 500.00
56,500.00
C PERALATAN
D Jumlah A + B + C 87,310.00
E Overhead 2.5% 2,182.75
F Harga Satuan Pekerjaan (D+E) 89,492.75

15 A.4.5.2.39 Pemasangan Atap Nok Seng


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Tukang Kayu L.02 OH 0.0700 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.0070 185,000.00 1,295.00
Mandor L.04 OH 0.0060 200,000.00 1,200.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

37,245.00
B Bahan
Seng Plaat 3" x 6" BJLS 28 Lbr 0.3000 80,000.00 24,000.00
Paku Biasa 1/2" - 1" Kg 0.0400 12,800.00 512.00
24,512.00
C PERALATAN
D Jumlah A + B + C 61,757.00
E Overhead 2.5% 1,543.93
F Harga Satuan Pekerjaan (D+E) 63,300.93
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm

A Tenaga
Pekerja L.01 OH 0.030 150,000.00 4,500.00

Tukang Kayu L.02 OH 0.070 175,000.00 12,250.00


Kepala Tukang L.03 OH 0.007 185,000.00 1,295.00

Mandor L.04 OH 0.004 200,000.00 800.00

18,845.00

B Bahan

Plat Asbes Lbr 1.100 25,700.00 28,270.00


Paku Kg 0.010 12,800.00 128.00

28,398.00
C PERALATAN

D Jumlah A + B + C 47,243.00
E Overhead 2.5% 1,181.08

F Harga Satuan Pekerjaan (D+E) 48,424.08

Overhead & Profit (contoh 15%)

2 A.4.5.1.5 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm

A Tenaga
Pekerja L.01 OH 0.100 150,000.00 15,000.00

Tukang Kayu L.02 OH 0.100 175,000.00 17,500.00

Kepala Tukang L.03 OH 0.010 185,000.00 1,850.00

Mandor L.04 OH 0.005 200,000.00 1,000.00


35,350.00

B Bahan
Tripleks (4 mm) Lbr 0.375 55,000.00 20,625.00

Paku Tripleks Kg 0.030 12,800.00 384.00

21,009.00
C PERALATAN

D Jumlah A + B + C 56,359.00

E Overhead 2.5% 1,408.98

F Harga Satuan Pekerjaan (D+E) 57,767.98

3 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm


A Tenaga

Pekerja L.01 OH 0.800 150,000.00 120,000.00

Tukang Kayu L.02 OH 0.800 175,000.00 140,000.00


Kepala Tukang L.03 OH 0.080 185,000.00 14,800.00

Mandor L.04 OH 0.040 200,000.00 8,000.00


282,800.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B Bahan

Kayu Jati,Papan m3 0.015 16,875,000.00 253,125.00


Paku Kg 0.010 12,800.00 128.00

253,253.00
C PERALATAN

D Jumlah A + B + C 536,053.00

E Overhead 2.5% 13,401.33

F Harga Satuan Pekerjaan (D+E) 549,454.33


HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.5.1.7 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm


A Tenaga

Pekerja L.01 OH 0.100 150,000.00 15,000.00


Tukang Kayu L.02 OH 0.050 175,000.00 8,750.00

Kepala Tukang L.03 OH 0.005 185,000.00 925.00

Mandor L.04 OH 0.005 200,000.00 1,000.00

25,675.00

B Bahan
Gypsum Board Lbr 0.364 64,300.00 23,405.20

Paku Sekrup Kg 0.110 13,000.00 1,430.00


24,835.20

C PERALATAN
D Jumlah A + B + C 50,510.20

E Overhead 2.5% 1,262.76

F Harga Satuan Pekerjaan (D+E) 51,772.96

5 A.4.5.1.10 List Langit-Langit Kayu Profil


A Tenaga
Pekerja L.01 OH 0.050 150,000.00 7,500.00
Tukang Kayu L.02 OH 0.050 175,000.00 8,750.00
Kepala Tukang L.03 OH 0.005 185,000.00 925.00
Mandor L.04 OH 0.003 200,000.00 600.00
17,775.00
B Bahan
List Kayu Profil m1 1.050 15,000.00 15,750.00
Paku Kg 0.010 12,800.00 128.00
15,878.00
C PERALATAN
D Jumlah A + B + C 33,653.00
E Overhead 2.5% 841.33
F Harga Satuan Pekerjaan (D+E) 34,494.33
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok
A Tenaga
Pekerja L.01 OH 3.3000 150,000.00 495,000.00
Tukang Batu L.02 OH 1.1000 175,000.00 192,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.1600 200,000.00 32,000.00
721,350.00
B Bahan
Kloset Duduk / Monoblok Buah 1.0000 1,192,800.00 1,192,800.00
Kelengkapan 6% dari harga Kloset 0.0600 1,192,800.00 71,568.00
1,264,368.00
C PERALATAN
D Jumlah A + B + C 1,985,718.00
E Overhead 2.5% 49,642.95
F Harga Satuan Pekerjaan (D+E) 2,035,360.95
Overhead & Profit (contoh 15%)
2 A.5.1.1.2 Memasang Closet Jongkok Porselen
A Tenaga
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Tukang Batu L.02 OH 1.5000 175,000.00 262,500.00
Kepala Tukang L.03 OH 0.1500 185,000.00 27,750.00
Mandor L.04 OH 0.1600 200,000.00 32,000.00
472,250.00
B Bahan
Kloset Jongkok Buah 1.0000 134,700.00 134,700.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 142,800.00 1,428.00
144,588.00
C PERALATAN
D Jumlah A + B + C 616,838.00
E Overhead 2.5% 15,420.95
F Harga Satuan Pekerjaan (D+E) 632,258.95

3 A.5.1.1.4 Memasang Urinoir


A Tenaga
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Tukang Batu L.02 OH 1.0000 175,000.00 175,000.00
Kepala Tukang L.03 OH 0.1000 185,000.00 18,500.00
Mandor L.04 OH 0.0500 200,000.00 10,000.00
353,500.00
B Bahan
Urinoir Buah 1.0000 367,500.00 367,500.00
Perlengkapan 30% Harga Urinoir Ls 0.3000 367,500.00 110,250.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 142,800.00 1,428.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
487,638.00
C PERALATAN
D Jumlah A + B + C 841,138.00
E Overhead 2.5% 21,028.45
F Harga Satuan Pekerjaan (D+E) 862,166.45
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.5.1.1.5 Memasang Wastafel


A Tenaga
Pekerja L.01 OH 1.2000 150,000.00 180,000.00
Tukang Batu L.02 OH 0.1450 175,000.00 25,375.00
Kepala Tukang L.03 OH 0.1500 185,000.00 27,750.00
Mandor L.04 OH 0.0600 200,000.00 12,000.00
245,125.00
B Bahan
Wastafel Buah 1.0000 292,700.00 292,700.00
Perlengkapan 12% Harga Wastafel Ls 0.1200 292,700.00 35,124.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 142,800.00 1,428.00
337,712.00
C PERALATAN
D Jumlah A + B + C 582,837.00
E Overhead 2.5% 14,570.93
F Harga Satuan Pekerjaan (D+E) 597,407.93

5 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3


A Tenaga
Pekerja L.01 OH 3.0000 150,000.00 450,000.00
Tukang Batu L.02 OH 4.5000 175,000.00 787,500.00
Kepala Tukang L.03 OH 0.0500 185,000.00 9,250.00
Mandor L.04 OH 0.9000 200,000.00 180,000.00
1,426,750.00
B Bahan
Bak Fibreglass Buah 1.0000 280,000.00 280,000.00
Perlengkapan 12% Bak Fibreglass Ls 0.1200 280,000.00 33,600.00
313,600.00
C PERALATAN
D Jumlah A + B + C 1,740,350.00
E Overhead 2.5% 43,508.75
F Harga Satuan Pekerjaan (D+E) 1,783,858.75

6 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3


A Tenaga
Pekerja L.01 OH 6.0000 150,000.00 900,000.00
Tukang Batu L.02 OH 3.0000 175,000.00 525,000.00
Kepala Tukang L.03 OH 0.3000 185,000.00 55,500.00
Mandor L.04 OH 0.0300 200,000.00 6,000.00
1,486,500.00
B Bahan
Batu Bata bh 150.00 760.00 114,000.00
Portland Semen Kg 120.00 1,410.00 169,200.00
Pasir Pasang m3 0.3000 142,800.00 42,840.00
Keramik 20 x 20 buah 111.00 2,000.00 222,000.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Semen Nat Kg 6.0000 11,790.00 70,740.00
618,780.00
C PERALATAN
D Jumlah A + B + C 2,105,280.00
E Overhead 2.5% 52,632.00
F Harga Satuan Pekerjaan (D+E) 2,157,912.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell


A Tenaga
Pekerja L.01 OH 0.0300 150,000.00 4,500.00
Tukang Batu L.02 OH 0.3000 175,000.00 52,500.00
Kepala Tukang L.03 OH 0.0300 185,000.00 5,550.00
Mandor L.04 OH 0.0150 200,000.00 3,000.00
65,550.00
B Bahan
Bak Cuci Piring unit 1.0000 176,100.00 176,100.00
Water drain bh 1.0000 60,000.00 60,000.00
236,100.00
C PERALATAN
D Jumlah A + B + C 301,650.00
E Overhead 2.5% 7,541.25
F Harga Satuan Pekerjaan (D+E) 309,191.25

8 A.5.1.1.14 Pemasangan Floor Drain


A Tenaga
Pekerja L.01 OH 0.0100 150,000.00 1,500.00
Tukang Batu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
21,850.00
B Bahan
Floor Drain bh 1.0000 23,100.00 23,100.00
23,100.00
C PERALATAN
D Jumlah A + B + C 44,950.00
E Overhead 2.5% 1,123.75
F Harga Satuan Pekerjaan (D+E) 46,073.75

9 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm


A Tenaga
Pekerja L.01 OH 2.1600 150,000.00 324,000.00
Tukang Batu L.02 OH 0.7200 175,000.00 126,000.00
Kepala Tukang L.03 OH 0.0720 185,000.00 13,320.00
Mandor L.04 OH 0.0110 200,000.00 2,200.00
465,520.00
B Bahan
Batu Bata bh 40.0000 760.00 30,400.00
Semen Portland kg 44.0000 1,410.00 62,040.00
Pasir Pasang m3 0.0700 142,800.00 9,996.00
Pasir Beton m3 0.0600 270,300.00 16,218.00
Kerikil m3 0.0700 215,900.00 15,113.00
Baja Tulangan kg 1.6000 9,180.00 14,688.00
148,455.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 613,975.00
E Overhead 2.5% 15,349.38
F Harga Satuan Pekerjaan (D+E) 629,324.38
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.5.1.1.16 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm


A Tenaga
Pekerja L.01 OH 3.2000 150,000.00 480,000.00
Tukang Batu L.02 OH 1.1500 175,000.00 201,250.00
Kepala Tukang L.03 OH 0.0110 185,000.00 2,035.00
Mandor L.04 OH 0.0160 200,000.00 3,200.00
686,485.00
B Bahan
Batu Bata bh 70.0000 760.00 53,200.00
Semen Portland kg 77.0000 1,410.00 108,570.00
Pasir Pasang m3 0.1300 142,800.00 18,564.00
Pasir Beton m3 0.0900 270,300.00 24,327.00
Kerikil m3 0.0200 215,900.00 4,318.00
Baja Tulangan kg 2.6000 9,180.00 23,868.00
232,847.00
C PERALATAN
D Jumlah A + B + C 919,332.00
E Overhead 2.5% 22,983.30
F Harga Satuan Pekerjaan (D+E) 942,315.30

11 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm


A Tenaga
Pekerja L.01 OH 3.2000 150,000.00 480,000.00
Tukang Batu L.02 OH 1.1500 175,000.00 201,250.00
Kepala Tukang L.03 OH 0.0110 185,000.00 2,035.00
Mandor L.04 OH 0.0160 200,000.00 3,200.00
686,485.00
B Bahan
Batu Bata bh 123.0000 760.00 93,480.00
Semen Portland kg 114.0000 1,410.00 160,740.00
Pasir Pasang m3 0.1840 142,800.00 26,275.20
Pasir Beton m3 0.1200 270,300.00 32,436.00
Kerikil m3 0.0330 215,900.00 7,124.70
Baja Tulangan kg 4.8500 9,180.00 44,523.00
364,578.90
C PERALATAN
D Jumlah A + B + C 1,051,063.90
E Overhead 2.5% 26,276.60
F Harga Satuan Pekerjaan (D+E) 1,077,340.50

12 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½"


A Tenaga
Pekerja L.01 OH 0.0540 150,000.00 8,100.00
Tukang Batu L.02 OH 0.0900 175,000.00 15,750.00
Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00
Mandor L.04 OH 0.0270 200,000.00 5,400.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
30,915.00
B Bahan
Pipa Galvanis Ø ½" m' 1.2000 19,900.00 23,880.00
Perlengkapan 35% x pipa Ls 0.3500 19,900.00 6,965.00
30,845.00
C PERALATAN
D Jumlah A + B + C 61,760.00
E Overhead 2.5% 1,544.00
F Harga Satuan Pekerjaan (D+E) 63,304.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0100 150,000.00 1,500.00
Tukang Batu L.02 OH 0.4000 175,000.00 70,000.00
Kepala Tukang L.03 OH 0.0400 185,000.00 7,400.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
79,900.00
B Bahan
Kran Air bh 1.0000 36,000.00 36,000.00
Sealtape bh 0.0250 2,300.00 57.50
36,057.50
C PERALATAN
D Jumlah A + B + C 115,957.50
E Overhead 2.5% 2,898.94
F Harga Satuan Pekerjaan (D+E) 118,856.44

14 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0540 150,000.00 8,100.00
Tukang Batu L.02 OH 0.0900 175,000.00 15,750.00
Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00
Mandor L.04 OH 0.0270 200,000.00 5,400.00
30,915.00
B Bahan
Pipa Galvanis Ø ¾" m' 1.2000 26,000.00 31,200.00
Perlengkapan 35% x pipa Ls 0.3500 26,000.00 9,100.00
40,300.00
C PERALATAN
D Jumlah A + B + C 71,215.00
E Overhead 2.5% 1,780.38
F Harga Satuan Pekerjaan (D+E) 72,995.38

15 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1"


A Tenaga
Pekerja L.01 OH 0.0540 150,000.00 8,100.00
Tukang Batu L.02 OH 0.0900 175,000.00 15,750.00
Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00
Mandor L.04 OH 0.0270 200,000.00 5,400.00
30,915.00
B Bahan
Pipa Galvanis Ø 1" m' 1.2000 40,000.00 48,000.00
Perlengkapan 35% x pipa Ls 0.3500 40,000.00 14,000.00
62,000.00
C PERALATAN
D Jumlah A + B + C 92,915.00
E Overhead 2.5% 2,322.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 95,237.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ "
A Tenaga
Pekerja L.01 OH 0.1080 150,000.00 16,200.00
Tukang Batu L.02 OH 0.1800 175,000.00 31,500.00
Kepala Tukang L.03 OH 0.0180 185,000.00 3,330.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
52,030.00
B Bahan
Pipa Galvanis Ø 1½" m' 1.2000 60,100.00 72,120.00
Perlengkapan 35% x pipa Ls 0.3500 60,100.00 21,035.00
93,155.00
C PERALATAN
D Jumlah A + B + C 145,185.00
E Overhead 2.5% 3,629.63
F Harga Satuan Pekerjaan (D+E) 148,814.63

17 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3"


A Tenaga
Pekerja L.01 OH 0.1350 150,000.00 20,250.00
Tukang Batu L.02 OH 0.2250 175,000.00 39,375.00
Kepala Tukang L.03 OH 0.0230 185,000.00 4,255.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
65,280.00
B Bahan
Pipa Galvanis Ø 3" m' 1.2000 130,200.00 156,240.00
Perlengkapan 35% x pipa Ls 0.3500 130,200.00 45,570.00
201,810.00
C PERALATAN
D Jumlah A + B + C 267,090.00
E Overhead 2.5% 6,677.25
F Harga Satuan Pekerjaan (D+E) 273,767.25

18 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4"


A Tenaga
Pekerja L.01 OH 0.1350 150,000.00 20,250.00
Tukang Batu L.02 OH 0.2250 175,000.00 39,375.00
Kepala Tukang L.03 OH 0.0230 185,000.00 4,255.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
65,280.00
B Bahan
Pipa Galvanis Ø 4" m' 1.2000 190,300.00 228,360.00
Perlengkapan 35% x pipa Ls 0.3500 190,300.00 66,605.00
294,965.00
C PERALATAN
D Jumlah A + B + C 360,245.00
E Overhead 2.5% 9,006.13
F Harga Satuan Pekerjaan (D+E) 369,251.13
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

19 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½"


A Tenaga
Pekerja L.01 OH 0.0360 150,000.00 5,400.00
Tukang Batu L.02 OH 0.0600 175,000.00 10,500.00
Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00
Mandor L.04 OH 0.0020 200,000.00 400.00
17,410.00
B Bahan
Pipa PVC Ø ½" m' 1.2000 5,100.00 6,120.00
Perlengkapan 35% x pipa Ls 0.3500 5,100.00 1,785.00
7,905.00
C PERALATAN
D Jumlah A + B + C 25,315.00
E Overhead 2.5% 632.88
F Harga Satuan Pekerjaan (D+E) 25,947.88

20 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0360 150,000.00 5,400.00
Tukang Batu L.02 OH 0.0600 175,000.00 10,500.00
Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00
Mandor L.04 OH 0.0020 200,000.00 400.00
17,410.00
B Bahan
Pipa PVC Ø ¾" m' 1.2000 6,600.00 7,920.00
Perlengkapan 35% x pipa Ls 0.3500 6,600.00 2,310.00
10,230.00
C PERALATAN
D Jumlah A + B + C 27,640.00
E Overhead 2.5% 691.00
F Harga Satuan Pekerjaan (D+E) 28,331.00

21 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1"


A Tenaga
Pekerja L.01 OH 0.0360 150,000.00 5,400.00
Tukang Batu L.02 OH 0.0600 175,000.00 10,500.00
Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00
Mandor L.04 OH 0.0020 200,000.00 400.00
17,410.00
B Bahan
Pipa PVC Ø 1" m' 1.2000 8,500.00 10,200.00
Perlengkapan 35% x pipa Ls 0.3500 8,500.00 2,975.00
13,175.00
C PERALATAN
D Jumlah A + B + C 30,585.00
E Overhead 2.5% 764.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 31,349.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
22 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½"
A Tenaga
Pekerja L.01 OH 0.0540 150,000.00 8,100.00
Tukang Batu L.02 OH 0.0900 175,000.00 15,750.00
Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00
Mandor L.04 OH 0.0030 200,000.00 600.00
26,115.00
B Bahan
Pipa PVC Ø 1½" m' 1.2000 10,000.00 12,000.00
Perlengkapan 35% x pipa Ls 0.3500 10,000.00 3,500.00
15,500.00
C PERALATAN
D Jumlah A + B + C 41,615.00
E Overhead 2.5% 1,040.38
F Harga Satuan Pekerjaan (D+E) 42,655.38

23 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2"


A Tenaga
Pekerja L.01 OH 0.0540 150,000.00 8,100.00
Tukang Batu L.02 OH 0.0900 175,000.00 15,750.00
Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00
Mandor L.04 OH 0.0030 200,000.00 600.00
26,115.00
B Bahan
Pipa PVC Ø 2" m' 1.2000 17,000.00 20,400.00
Perlengkapan 35% x pipa Ls 0.3500 17,000.00 5,950.00
26,350.00
C PERALATAN
D Jumlah A + B + C 52,465.00
E Overhead 2.5% 1,311.63
F Harga Satuan Pekerjaan (D+E) 53,776.63

24 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3"


A Tenaga
Pekerja L.01 OH 0.0810 150,000.00 12,150.00
Tukang Batu L.02 OH 0.1350 175,000.00 23,625.00
Kepala Tukang L.03 OH 0.0135 185,000.00 2,497.50
Mandor L.04 OH 0.0040 200,000.00 800.00
39,072.50
B Bahan
Pipa PVC Ø 3" m' 1.2000 32,300.00 38,760.00
Perlengkapan 35% x pipa Ls 0.3500 32,300.00 11,305.00
50,065.00
C PERALATAN
D Jumlah A + B + C 89,137.50
E Overhead 2.5% 2,228.44
F Harga Satuan Pekerjaan (D+E) 91,365.94
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
25 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4"
A Tenaga
Pekerja L.01 OH 0.0810 150,000.00 12,150.00
Tukang Batu L.02 OH 0.1350 175,000.00 23,625.00
Kepala Tukang L.03 OH 0.0135 185,000.00 2,497.50
Mandor L.04 OH 0.0040 200,000.00 800.00
39,072.50
B Bahan
Pipa PVC Ø 4" m' 1.2000 50,800.00 60,960.00
Perlengkapan 35% x pipa Ls 0.3500 50,800.00 17,780.00
78,740.00
C PERALATAN
D Jumlah A + B + C 117,812.50
E Overhead 2.5% 2,945.31
F Harga Satuan Pekerjaan (D+E) 120,757.81

26 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm


A Tenaga
Pekerja L.01 OH 0.0800 150,000.00 12,000.00
Tukang Batu L.02 OH 0.0400 175,000.00 7,000.00
Kepala Tukang L.03 OH 0.0040 185,000.00 740.00
Mandor L.04 OH 0.0040 200,000.00 800.00
20,540.00
B Bahan
pipa tanah bh 1.6000 151,500.00 242,400.00
Semen Portlan kg 35.0000 1,410.00 49,350.00
Pasir Pasang m3 0.0140 142,800.00 1,999.20
Pasir Urug m3 0.0140 82,000.00 1,148.00
294,897.20
C PERALATAN
D Jumlah A + B + C 315,437.20
E Overhead 2.5% 7,885.93
F Harga Satuan Pekerjaan (D+E) 323,323.13

27 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm


A Tenaga
Pekerja L.01 OH 0.0600 150,000.00 9,000.00
Tukang Batu L.02 OH 0.0300 175,000.00 5,250.00
Kepala Tukang L.03 OH 0.0030 185,000.00 555.00
Mandor L.04 OH 0.0030 200,000.00 600.00
15,405.00
B Bahan
pipa tanah bh 1.6000 93,500.00 149,600.00
Semen Portlan kg 6.8000 1,410.00 9,588.00
Pasir Pasang m3 0.0130 142,800.00 1,856.40
Pasir Urug m3 0.0110 82,000.00 902.00
161,946.40
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 177,351.40
E Overhead 2.5% 4,433.79
F Harga Satuan Pekerjaan (D+E) 181,785.19
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
28 A.5.1.1.35 Pemasangan Pipa Beton Ø 20 cm
A Tenaga
Pekerja L.01 OH 0.1400 150,000.00 21,000.00
Tukang Batu L.02 OH 0.0700 175,000.00 12,250.00
Kepala Tukang L.03 OH 0.0070 185,000.00 1,295.00
Mandor L.04 OH 0.0070 200,000.00 1,400.00
35,945.00
B Bahan
pipa beton bh 1.1000 53,000.00 58,300.00
Batu Bata m3 0.0270 570,000.00 15,390.00
Semen Portlan kg 3.9200 1,410.00 5,527.20
Pasir Pasang m3 0.0560 142,800.00 7,996.80
Pasir Urug m3 0.0240 82,000.00 1,968.00
89,182.00
C PERALATAN
D Jumlah A + B + C 125,127.00
E Overhead 2.5% 3,128.18
F Harga Satuan Pekerjaan (D+E) 128,255.18

29 A.5.1.1.36 Pemasangan Pipa Beton Ø 100 cm


A Tenaga
Pekerja L.01 OH 0.3800 150,000.00 57,000.00
Tukang Batu L.02 OH 0.1900 175,000.00 33,250.00
Kepala Tukang L.03 OH 0.0190 185,000.00 3,515.00
Mandor L.04 OH 0.0190 200,000.00 3,800.00
97,565.00
B Bahan
pipa beton bh 1.1000 225,000.00 247,500.00
Batu Bata m3 0.5500 570,000.00 313,500.00
Semen Portlan kg 10.3000 1,410.00 14,523.00
Pasir Pasang m3 0.0610 142,800.00 8,710.80
Pasir Urug m3 0.0690 82,000.00 5,658.00
589,891.80
C PERALATAN
D Jumlah A + B + C 687,456.80
E Overhead 2.5% 17,186.42
F Harga Satuan Pekerjaan (D+E) 704,643.22
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM

1 A.4.2.1.1 Pemasangan Besi Profil

A Tenaga

Pekerja L.01 OH 0.0600 150,000.00 9,000.00

Tukang Besi L.02 OH 0.0600 175,000.00 10,500.00

Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00

Mandor L.04 OH 0.0030 200,000.00 600.00

21,210.00

B Bahan

Besi Profil Kg 1.1500 16,100.00 18,515.00

Meni Besi Kg 0.0600 29,000.00 1,740.00

20,255.00

C PERALATAN

D Jumlah A + B + C 41,465.00

E Overhead 2.5% 1,036.63

F Harga Satuan Pekerjaan (D+E) 42,501.63

Overhead & Profit

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF

A Tenaga

Pekerja L.01 OH 0.0600 150,000.00 9,000.00

Tukang Besi L.02 OH 0.0600 175,000.00 10,500.00

Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00

Mandor L.04 OH 0.0030 200,000.00 600.00

21,210.00

B Bahan

Besi Baja IWF kg 1.1500 16,100.00 18,515.00

18,515.00

C PERALATAN

D Jumlah A + B + C 39,725.00

E Overhead 2.5% 993.13

F Harga Satuan Pekerjaan (D+E) 40,718.13

3 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi

A Tenaga

Pekerja L.01 OH 1.2000 150,000.00 180,000.00

Tukang Besi L.02 OH 1.2000 175,000.00 210,000.00

Kepala Tukang L.03 OH 0.1200 185,000.00 22,200.00

Mandor L.04 OH 0.0060 200,000.00 1,200.00

413,400.00

B Bahan

Pintu Gulung Besi m2 1.0000 350,000.00 350,000.00


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
350,000.00

C PERALATAN

D Jumlah A + B + C 763,400.00

E Overhead 2.5% 19,085.00

F Harga Satuan Pekerjaan (D+E) 782,485.00


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door)

A Tenaga

Pekerja L.01 OH 0.4400 150,000.00 66,000.00

Tukang Besi L.02 OH 0.4400 175,000.00 77,000.00

Kepala Tukang L.03 OH 0.0440 185,000.00 8,140.00

Mandor L.04 OH 0.0220 200,000.00 4,400.00

155,540.00

B Bahan

Pintu Lipat m2 1.0000 434,000.00 434,000.00

434,000.00

C PERALATAN
D Jumlah A + B + C 589,540.00

E Overhead 2.5% 14,738.50

F Harga Satuan Pekerjaan (D+E) 604,278.50

5 A.4.2.1.10 Pemasangan Rolling Door Allumunium

A Tenaga

Pekerja L.01 OH 1.0000 150,000.00 150,000.00

Tukang Besi L.02 OH 1.0000 175,000.00 175,000.00

Kepala Tukang L.03 OH 0.1000 185,000.00 18,500.00

Mandor L.04 OH 0.0500 200,000.00 10,000.00

353,500.00

B Bahan

Rolling Allumunium m2 1.0000 415,000.00 415,000.00

415,000.00

C PERALATAN

D Jumlah A + B + C 768,500.00

E Overhead 2.5% 19,212.50

F Harga Satuan Pekerjaan (D+E) 787,712.50

6 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium

A Tenaga

Pekerja L.01 OH 0.0430 150,000.00 6,450.00

Tukang Besi L.02 OH 0.0430 175,000.00 7,525.00

Kepala Tukang L.03 OH 0.0043 185,000.00 795.50

Mandor L.04 OH 0.0021 200,000.00 420.00

15,190.50

B Bahan

Profil Allumunium m' 1.1000 103,200.00 113,520.00

Skrup Fixer buah 2.0000 1,600.00 3,200.00

Sealant Tube 0.0600 22,500.00 1,350.00


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
118,070.00

C PERALATAN

D Jumlah A + B + C 133,260.50

E Overhead 2.5% 3,331.51

F Harga Satuan Pekerjaan (D+E) 136,592.01


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm

A Tenaga

Pekerja L.01 OH 0.0850 150,000.00 12,750.00

Tukang Besi L.02 OH 0.0850 175,000.00 14,875.00

Kepala Tukang L.03 OH 0.0085 185,000.00 1,572.50

Mandor L.04 OH 0.0042 200,000.00 840.00

30,037.50

B Bahan

Profil Allumunium m' 4.4000 103,200.00 454,080.00

Allumunium Strip m' 14.6000 34,300.00 500,780.00

954,860.00
C PERALATAN

D Jumlah A + B + C 984,897.50

E Overhead 2.5% 24,622.44

F Harga Satuan Pekerjaan (D+E) 1,009,519.94

8 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium

A Tenaga

Pekerja L.01 OH 0.0850 150,000.00 12,750.00

Tukang Besi L.02 OH 0.0850 175,000.00 14,875.00

Kepala Tukang L.03 OH 0.0090 185,000.00 1,665.00

Mandor L.04 OH 0.0050 200,000.00 1,000.00

30,290.00

B Bahan

Pintu Allumunium m' 4.4000 103,200.00 454,080.00

Profil Kaca m' 4.5000 85,000.00 382,500.00

Sealant tube 0.2700 22,500.00 6,075.00

842,655.00

C PERALATAN

D Jumlah A + B + C 872,945.00

E Overhead 2.5% 21,823.63

F Harga Satuan Pekerjaan (D+E) 894,768.63

9 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm

A Tenaga

Pekerja L.01 OH 0.2000 150,000.00 30,000.00

Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00

Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00

Mandor L.04 OH 0.0010 200,000.00 200.00

68,900.00

B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Seng Plaat Lbr 1.0500 31,300.00 32,865.00

Paku Biasa 1 - 2,5 cm Kg 0.0150 12,800.00 192.00

Kayu Papan Klas II atau III m3 0.0190 4,500,000.00 85,500.00

118,557.00

C PERALATAN

D Jumlah A + B + C 187,457.00

E Overhead 2.5% 4,686.43

F Harga Satuan Pekerjaan (D+E) 192,143.43


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm

A Tenaga

Pekerja L.01 OH 0.1500 150,000.00 22,500.00

Tukang Kayu L.02 OH 0.3000 175,000.00 52,500.00

Kepala Tukang L.03 OH 0.0300 185,000.00 5,550.00

Mandor L.04 OH 0.0080 200,000.00 1,600.00

82,150.00

B Bahan

Seng Plaat Lbr 1.0500 31,300.00 32,865.00

Paku Biasa 1 - 2,5 cm Kg 0.0100 12,800.00 128.00

Besi strip Kg 0.5000 20,200.00 10,100.00


43,093.00

C PERALATAN

D Jumlah A + B + C 125,243.00

E Overhead 2.5% 3,131.08

F Harga Satuan Pekerjaan (D+E) 128,374.08

11 A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon

A Tenaga

Pekerja L.01 OH 0.3500 150,000.00 52,500.00

Tukang Kayu L.02 OH 0.3500 175,000.00 61,250.00

Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00

Mandor L.04 OH 0.0180 200,000.00 3,600.00

123,825.00

B Bahan

Rangka metal hollow 40.40.2 mm M1 4.0000 31,300.00 125,200.00

Assesoris (perkuatan, las dll)100% rangka Ls 1.0000 31,300.00 31,300.00

156,500.00

C PERALATAN

D Jumlah A + B + C 280,325.00

E Overhead 2.5% 7,008.13

F Harga Satuan Pekerjaan (D+E) 287,333.13


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa
A Tenaga
Pekerja L.01 OH 0.0100 150,000.00 1,500.00
Tukang Kayu L.02 OH 0.5000 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.0500 185,000.00 9,250.00
Mandor L.04 OH 0.0050 200,000.00 1,000.00
99,250.00
B Bahan
Kunci Tanam Biasa Buah 1.0000 60,800.00 60,800.00
60,800.00
C PERALATAN
D Jumlah A + B + C 160,050.00
E Overhead 2.5% 4,001.25
F Harga Satuan Pekerjaan (D+E) 164,051.25
Overhead & Profit

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi


A Tenaga
Pekerja L.01 OH 0.0050 150,000.00 750.00
Tukang Kayu L.02 OH 0.5000 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.0500 185,000.00 9,250.00
Mandor L.04 OH 0.0025 200,000.00 500.00
98,000.00
B Bahan
Kunci Tanam Kamar Mandi Buah 1.0000 36,600.00 36,600.00
36,600.00
C PERALATAN
D Jumlah A + B + C 134,600.00
E Overhead 2.5% 3,365.00
F Harga Satuan Pekerjaan (D+E) 137,965.00

3 A.4.6.2.4 Pemasangan Kunci Selinder


A Tenaga
Pekerja L.01 OH 0.0050 150,000.00 750.00
Tukang Kayu L.02 OH 0.5000 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.0500 185,000.00 9,250.00
Mandor L.04 OH 0.0025 200,000.00 500.00
98,000.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Kunci Selinder Buah 1.0000 60,800.00 60,800.00
60,800.00
C PERALATAN
D Jumlah A + B + C 158,800.00
E Overhead 2.5% 3,970.00
F Harga Satuan Pekerjaan (D+E) 162,770.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.6.2.5 Pemasangan Engsel Pintu
A Tenaga
Pekerja L.01 OH 0.0150 150,000.00 2,250.00
Tukang Kayu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0008 200,000.00 160.00
31,435.00
B Bahan
Engsel pintu Buah 1.0000 20,500.00 20,500.00
20,500.00
C PERALATAN
D Jumlah A + B + C 51,935.00
E Overhead 2.5% 1,298.38
F Harga Satuan Pekerjaan (D+E) 53,233.38

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu


A Tenaga
Pekerja L.01 OH 0.0100 150,000.00 1,500.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0005 200,000.00 100.00
20,950.00
B Bahan
Engsel Jendela Buah 1.0000 14,100.00 14,100.00
14,100.00
C PERALATAN
D Jumlah A + B + C 35,050.00
E Overhead 2.5% 876.25
F Harga Satuan Pekerjaan (D+E) 35,926.25

6 A.4.6.2.7 Pemasangan Engsel Angin


A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0005 200,000.00 100.00
53,800.00
B Bahan
Engsel Angin Buah 1.0000 19,800.00 19,800.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
19,800.00
C PERALATAN
D Jumlah A + B + C 73,600.00
E Overhead 2.5% 1,840.00
F Harga Satuan Pekerjaan (D+E) 75,440.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.6.2.9 Pemasangan Kait Angin
A Tenaga
Pekerja L.01 OH 0.0150 150,000.00 2,250.00
Tukang Kayu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
32,875.00
B Bahan
Kait Angin Buah 1.0000 5,500.00 5,500.00
5,500.00
C PERALATAN
D Jumlah A + B + C 38,375.00
E Overhead 2.5% 959.38
F Harga Satuan Pekerjaan (D+E) 39,334.38

8 A.4.6.2.10 Pasang Door Closer


A Tenaga
Pekerja L.01 OH 0.0500 150,000.00 7,500.00
Tukang Kayu L.02 OH 0.5000 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.0500 185,000.00 9,250.00
Mandor L.04 OH 0.0025 200,000.00 500.00
104,750.00
B Bahan
Door Closer Buah 1.0000 93,300.00 93,300.00
93,300.00
C PERALATAN
D Jumlah A + B + C 198,050.00
E Overhead 2.5% 4,951.25
F Harga Satuan Pekerjaan (D+E) 203,001.25

9 A.4.6.2.11 Pemasangan Kunci Selot


A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Kayu L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0010 200,000.00 200.00
41,900.00
B Bahan
Kunci Selot Buah 1.0000 8,900.00 8,900.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
8,900.00
C PERALATAN
D Jumlah A + B + C 50,800.00
E Overhead 2.5% 1,270.00
F Harga Satuan Pekerjaan (D+E) 52,070.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.6.2.13 Pemasangan Door Stop
A Tenaga
Pekerja L.01 OH 0.0100 150,000.00 1,500.00
Tukang Kayu L.02 OH 0.1000 175,000.00 17,500.00
Kepala Tukang L.03 OH 0.0100 185,000.00 1,850.00
Mandor L.04 OH 0.0005 200,000.00 100.00
20,950.00
B Bahan
Door Stop Buah 1.0000 35,000.00 35,000.00
35,000.00
C PERALATAN
D Jumlah A + B + C 55,950.00
E Overhead 2.5% 1,398.75
F Harga Satuan Pekerjaan (D+E) 57,348.75

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong


A Tenaga
Pekerja L.01 OH 0.0600 150,000.00 9,000.00
Tukang Kayu L.02 OH 0.6000 175,000.00 105,000.00
Kepala Tukang L.03 OH 0.0600 185,000.00 11,100.00
Mandor L.04 OH 0.0030 200,000.00 600.00
125,700.00
B Bahan
Rel Pintu Dorong Buah 1.0000 183,000.00 183,000.00
183,000.00
C PERALATAN
D Jumlah A + B + C 308,700.00
E Overhead 2.5% 7,717.50
F Harga Satuan Pekerjaan (D+E) 316,417.50

12 A.4.6.2.16 Pemasangan Kaca tebal 3 mm


A Tenaga
Pekerja L.01 OH 0.0150 150,000.00 2,250.00
Tukang Kayu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0008 200,000.00 150.00
31,425.00
B Bahan
Kaca tebal 3mm m2 1.1000 71,200.00 78,320.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
78,320.00
C PERALATAN
D Jumlah A + B + C 109,745.00
E Overhead 2.5% 2,743.63
F Harga Satuan Pekerjaan (D+E) 112,488.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.6.2.17 Pemasangan Kaca tebal 5 mm
A Tenaga
Pekerja L.01 OH 0.0150 150,000.00 2,250.00
Tukang Kayu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0008 200,000.00 150.00
31,425.00
B Bahan
Kaca tebal 5mm m2 1.1000 85,000.00 93,500.00
93,500.00
C PERALATAN
D Jumlah A + B + C 124,925.00
E Overhead 2.5% 3,123.13
F Harga Satuan Pekerjaan (D+E) 128,048.13

14 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm


A Tenaga
Pekerja L.01 OH 0.0150 150,000.00 2,250.00
Tukang Kayu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0008 200,000.00 150.00
31,425.00
B Bahan
Kaca Cermin m2 1.1000 230,000.00 253,000.00
253,000.00
C PERALATAN
D Jumlah A + B + C 284,425.00
E Overhead 2.5% 7,110.63
F Harga Satuan Pekerjaan (D+E) 291,535.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm
A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Abu-abu 30x30 cm Buah 11.8700 2,900.00 34,423.00
Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
54,949.00
C PERALATAN
D Jumlah A + B + C 119,329.00
E Overhead 2.5% 2,983.23
F Harga Satuan Pekerjaan (D+E) 122,312.23

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.2700 150,000.00 40,500.00
Tukang Batu L.02 OH 0.1350 175,000.00 23,625.00
Kepala Tukang L.03 OH 0.0140 185,000.00 2,590.00
Mandor L.04 OH 0.0140 200,000.00 2,800.00
69,515.00
B Bahan
Ubin Abu-abu 20x20 cm Buah 26.5000 1,500.00 39,750.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
60,840.00
C PERALATAN
D Jumlah A + B + C 130,355.00
E Overhead 2.5% 3,258.88
F Harga Satuan Pekerjaan (D+E) 133,613.88

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm


A Tenaga
Pekerja L.01 OH 0.2600 150,000.00 39,000.00
Tukang Batu L.02 OH 0.1300 175,000.00 22,750.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
66,755.00
B Bahan
Ubin Warna 30x30 cm Buah 11.8700 3,000.00 35,610.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Portland Semen Kg 10.0000 1,410.00 14,100.00


Semen warna Kg 1.5000 11,790.00 17,685.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
73,821.00
C PERALATAN
D Jumlah A + B + C 140,576.00
E Overhead 2.5% 3,514.40
F Harga Satuan Pekerjaan (D+E) 144,090.40
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.2700 150,000.00 40,500.00
Tukang Batu L.02 OH 0.1350 175,000.00 23,625.00
Kepala Tukang L.03 OH 0.0140 185,000.00 2,590.00
Mandor L.04 OH 0.0140 200,000.00 2,800.00
69,515.00
B Bahan
Ubin Warna 20x20 cm Buah 26.5000 1,900.00 50,350.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Semen warna Kg 1.6200 11,790.00 19,099.80
Pasir Pasang m3 0.0450 142,800.00 6,426.00
90,539.80
C PERALATAN
D Jumlah A + B + C 160,054.80
E Overhead 2.5% 4,001.37
F Harga Satuan Pekerjaan (D+E) 164,056.17

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm


A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Granito 40x40 cm Buah 6.6300 32,800.00 217,464.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen warna Kg 1.3000 11,790.00 15,327.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
253,035.00
C PERALATAN
D Jumlah A + B + C 317,415.00
E Overhead 2.5% 7,935.38
F Harga Satuan Pekerjaan (D+E) 325,350.38

6 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm warna


A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Batu L.02 OH 0.3500 175,000.00 61,250.00
Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
179,725.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Ubin Keramik 30 x 30 cm warna Buah 11.8700 4,100.00 48,667.00


Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
Semen Warna Kg 1.5000 11,790.00 17,685.00
86,878.00
C PERALATAN
D Jumlah A + B + C 266,603.00
E Overhead 2.5% 6,665.08
F Harga Satuan Pekerjaan (D+E) 273,268.08
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.4.4.3.35.1 Pemasangan Lantai Keramik 30 x 30 cm putih


A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Batu L.02 OH 0.3500 175,000.00 61,250.00
Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
179,725.00
B Bahan
Ubin Keramik 30 x 30 cm putih Buah 11.8700 3,800.00 45,106.00
Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
Semen Warna Kg 1.5000 11,790.00 17,685.00
83,317.00
C PERALATAN
D Jumlah A + B + C 263,042.00
E Overhead 2.5% 6,576.05
F Harga Satuan Pekerjaan (D+E) 269,618.05

8 A.4.4.3.35.2 Pemasangan Lantai Keramik 40 x 40 cm warna

SNI A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Keramik 40 x 40 cm Buah 6.6300 8,300.00 55,029.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 11,790.00 15,327.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
90,600.00
C PERALATAN
D Jumlah A + B + C 154,980.00
E Overhead 2.5% 3,874.50
F Harga Satuan Pekerjaan (D+E) 158,854.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

9 A.4.4.3.35.3 Pemasangan Lantai Keramik 40 x 40 cm putih

SNI A Tenaga
Pekerja L.01 OH 0.2500 150,000.00 37,500.00
Tukang Batu L.02 OH 0.1250 175,000.00 21,875.00
Kepala Tukang L.03 OH 0.0130 185,000.00 2,405.00
Mandor L.04 OH 0.0130 200,000.00 2,600.00
64,380.00
B Bahan
Ubin Keramik 40 x 40 cm putih Buah 6.6300 7,800.00 51,714.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 11,790.00 15,327.00
Pasir Pasang m3 0.0450 142,800.00 6,426.00
87,285.00
C PERALATAN
D Jumlah A + B + C 151,665.00
E Overhead 2.5% 3,791.63
F Harga Satuan Pekerjaan (D+E) 155,456.63

10 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Batu L.02 OH 0.3500 175,000.00 61,250.00
Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
179,725.00
B Bahan
Ubin Keramik 20 x 20 cm Buah 26.5000 2,000.00 53,000.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Semen Warna Kg 1.6200 11,790.00 19,099.80
Pasir Pasang m3 0.0450 142,800.00 6,426.00
93,189.80
C PERALATAN
D Jumlah A + B + C 272,914.80
E Overhead 2.5% 6,822.87
F Harga Satuan Pekerjaan (D+E) 279,737.67

11 A.4.4.3.46 Pemasangan Lantai Parquet Jati


A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Batu L.02 OH 0.3500 175,000.00 61,250.00
Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
179,725.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Parquet Jati m2 1.0500 210,000.00 220,500.00


Lem Vynil Kg 0.6000 35,000.00 21,000.00
241,500.00
C PERALATAN
D Jumlah A + B + C 421,225.00
E Overhead 2.5% 10,530.63
F Harga Satuan Pekerjaan (D+E) 431,755.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

12 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm,


A Tenaga
Pekerja L.01 OH 0.9000 150,000.00 135,000.00
Tukang Batu L.02 OH 0.4500 175,000.00 78,750.00
Kepala Tukang L.03 OH 0.0450 185,000.00 8,325.00
Mandor L.04 OH 0.0450 200,000.00 9,000.00
231,075.00
B Bahan
Keramik Buah 53.0000 1,000.00 53,000.00
Portland Semen Kg 9.3000 1,410.00 13,113.00
Pasir Pasang m3 0.0180 142,800.00 2,570.40
Semen Warna Kg 2.7500 11,790.00 32,422.50
101,105.90
C PERALATAN
D Jumlah A + B + C 332,180.90
E Overhead 2.5% 8,304.52
F Harga Satuan Pekerjaan (D+E) 340,485.42

13 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm,


A Tenaga
Pekerja L.01 OH 0.9000 150,000.00 135,000.00
Tukang Batu L.02 OH 0.4500 175,000.00 78,750.00
Kepala Tukang L.03 OH 0.0450 185,000.00 8,325.00
Mandor L.04 OH 0.0450 200,000.00 9,000.00
231,075.00
B Bahan
Keramik Buah 26.5000 2,000.00 53,000.00
Portland Semen Kg 9.3000 1,410.00 13,113.00
Pasir Pasang m3 0.0180 142,800.00 2,570.40
Semen Warna Kg 1.9400 11,790.00 22,872.60
91,556.00
C PERALATAN
D Jumlah A + B + C 322,631.00
E Overhead 2.5% 8,065.78
F Harga Satuan Pekerjaan (D+E) 330,696.78

14 A.4.4.3.58 Pemasangan Dinding Batu Paras / Batu Tempel Hitam


A Tenaga
Pekerja L.01 OH 0.7000 150,000.00 105,000.00
Tukang Batu L.02 OH 0.3500 175,000.00 61,250.00
Kepala Tukang L.03 OH 0.0350 185,000.00 6,475.00
Mandor L.04 OH 0.0350 200,000.00 7,000.00
179,725.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Batu Paras/batu tempel m2 1.1000 105,000.00 115,500.00


Portland Semen Kg 11.7500 1,410.00 16,567.50
Pasir Pasang m3 0.0350 142,800.00 4,998.00
137,065.50
C PERALATAN
D Jumlah A + B + C 316,790.50
E Overhead 2.5% 7,919.76
F Harga Satuan Pekerjaan (D+E) 324,710.26
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

15 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm


A Tenaga
Pekerja L.01 OH 0.1200 150,000.00 18,000.00
Tukang Batu L.02 OH 0.1200 175,000.00 21,000.00
Kepala Tukang L.03 OH 0.0120 185,000.00 2,220.00
Mandor L.04 OH 0.0060 200,000.00 1,200.00
42,420.00
B Bahan
Papan Kayu Klas II m3 0.0030 6,582,500.00 19,747.50
Paku Sekrup 5 cm kg 0.0500 13,000.00 650.00
20,397.50
C PERALATAN
D Jumlah A + B + C 62,817.50
E Overhead 2.5% 1,570.44
F Harga Satuan Pekerjaan (D+E) 64,387.94

16 A.4.4.3.64 Pasang blok pafing tebal 6 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Tukang Batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
109,025.00
B Bahan
pasir muntilan utk nat m3 0.0050 270,300.00 1,351.50
paving m2 1.0000 55,300.00 55,300.00
56,651.50
C PERALATAN
D Jumlah A + B + C 165,676.50
E Overhead 2.5% 4,141.91
F Harga Satuan Pekerjaan (D+E) 169,818.41

17 A.4.4.3.65 Blok paving tebal 6 cm dengan paving mutu K 225


SNI A Tenaga
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Tukang Batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
109,025.00
B Bahan
pasir muntilan utk nat m3 0.0050 270,300.00 1,351.50
paving m2 1.0000 60,000.00 60,000.00
61,351.50
C PERALATAN
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

D Jumlah A + B + C 170,376.50
E Overhead 2.5% 4,259.41
F Harga Satuan Pekerjaan (D+E) 174,635.91
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

18 A.4.4.3.66 Blok paving tebal 8 cm dengan paving mutu K 300


SNI A Tenaga
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Tukang Batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
109,025.00
B Bahan
pasir muntilan utk nat m3 0.0050 270,300.00 1,351.50
paving m2 1.0000 94,000.00 94,000.00
95,351.50
C PERALATAN
D Jumlah A + B + C 204,376.50
E Overhead 2.5% 5,109.41
F Harga Satuan Pekerjaan (D+E) 209,485.91

19 A.4.4.3.67 Blok paving warna tebal 6 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Tukang Batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
109,025.00
B Bahan
pasir muntilan utk nat m3 0.0050 270,300.00 1,351.50
paving m2 1.0000 51,000.00 51,000.00
52,351.50
C PERALATAN
D Jumlah A + B + C 161,376.50
E Overhead 2.5% 4,034.41
F Harga Satuan Pekerjaan (D+E) 165,410.91

20 A.4.4.3.68 Blok paving warna tebal 8 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 150,000.00 75,000.00
Tukang Batu L.02 OH 0.1500 175,000.00 26,250.00
Kepala Tukang L.03 OH 0.0150 185,000.00 2,775.00
Mandor L.04 OH 0.0250 200,000.00 5,000.00
109,025.00
B Bahan
pasir muntilan utk nat m3 0.0050 270,300.00 1,351.50
paving m2 1.0000 57,500.00 57,500.00
58,851.50
C PERALATAN
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

D Jumlah A + B + C 167,876.50
E Overhead 2.5% 4,196.91
F Harga Satuan Pekerjaan (D+E) 172,073.41
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

21 A.4.4.3.69 pasang saluran U-20 cm


SNI A Tenaga
B Bahan
Buis beton U-20 cm m' 1.0000 46,200.00 46,200.00
Pasang batu bata 1:4 m2 0.8000 303,673.40 242,938.72
Plesteran 1:3 m2 0.5000 94,206.06 47,103.03
Hurugan pasir m3 0.0200 145,400.00 2,908.00
Ongkos pasang Buis U-20 1.0000 4,500.00 4,500.00
343,649.75
C PERALATAN
D Jumlah A + B + C 343,649.75
E Overhead 2.5% 8,591.24
F Harga Satuan Pekerjaan (D+E) 352,240.99

22 A.4.4.3.70 pasang saluran U-30 cm


SNI A Tenaga
B Bahan
Buis beton U-30 cm m' 1.0000 58,700.00 58,700.00
Pasang batu bata 1:4 m2 0.8000 303,673.40 242,938.72
Plesteran 1:3 m2 0.5000 94,206.06 47,103.03
Hurugan pasir m3 0.0200 145,400.00 2,908.00
Ongkos pasang Buis U-30 1.0000 4,500.00 4,500.00
356,149.75
C PERALATAN
D Jumlah A + B + C 356,149.75
E Overhead 2.5% 8,903.74
F Harga Satuan Pekerjaan (D+E) 365,053.49
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Mandor L.04 OH 0.0030 200,000.00 600.00
23,100.00
B Bahan
Soda Api Kg 0.0500 20,000.00 1,000.00
1,000.00
C PERALATAN
D Jumlah A + B + C 24,100.00
E Overhead 2.5% 602.50
F Harga Satuan Pekerjaan (D+E) 24,702.50

2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Mandor L.04 OH 0.0030 200,000.00 600.00
23,100.00
B Bahan
Sabun Kg 0.0500 15,000.00 750.00
750.00
C PERALATAN
D Jumlah A + B + C 23,850.00
E Overhead 2.5% 596.25
F Harga Satuan Pekerjaan (D+E) 24,446.25

3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual


A Tenaga
Pekerja L.01 OH 0.1500 150,000.00 22,500.00
Mandor L.04 OH 0.0080 200,000.00 1,600.00
24,100.00
B Bahan
Sabun Kg 0.0500 15,000.00 750.00
750.00
C PERALATAN
D Jumlah A + B + C 24,850.00
E Overhead 2.5% 621.25
F Harga Satuan Pekerjaan (D+E) 25,471.25
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 150,000.00 10,500.00
Tukang Cat L.02 OH 0.0090 175,000.00 1,575.00
Kepala Tukang L.03 OH 0.0060 185,000.00 1,110.00
Mandor L.04 OH 0.0030 200,000.00 600.00
13,785.00
B Bahan
Cat Menie kg 0.2000 29,000.00 5,800.00
Plamuur kg 0.1500 28,700.00 4,305.00
Cat Dasar kg 0.1700 33,000.00 5,610.00
Cat Penutup kg 0.2600 51,700.00 13,442.00
Kuas bh 0.0100 11,500.00 115.00
Pengencer kg 0.0300 18,000.00 540.00
Amplas lbr 0.2000 13,100.00 2,620.00
32,432.00
C PERALATAN
D Jumlah A + B + C 46,217.00
E Overhead 2.5% 1,155.43
F Harga Satuan Pekerjaan (D+E) 47,372.43

5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 150,000.00 10,500.00
Tukang Cat L.02 OH 0.1050 175,000.00 18,375.00
Kepala Tukang L.03 OH 0.0040 185,000.00 740.00
Mandor L.04 OH 0.0030 200,000.00 600.00
30,215.00
B Bahan
Cat Menie kg 0.2000 29,000.00 5,800.00
Plamuur kg 0.1500 28,700.00 4,305.00
Cat Dasar kg 0.1700 33,000.00 5,610.00
Cat Penutup kg 0.3500 51,700.00 18,095.00
Kuas bh 0.0100 11,500.00 115.00
Pengencer kg 0.0300 18,000.00 540.00
Amplas lbr 0.2000 13,100.00 2,620.00
37,085.00
C PERALATAN
D Jumlah A + B + C 67,300.00
E Overhead 2.5% 1,682.50
F Harga Satuan Pekerjaan (D+E) 68,982.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil


A Tenaga
Pekerja L.01 OH 0.0400 150,000.00 6,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0630 185,000.00 11,655.00
Mandor L.04 OH 0.0030 200,000.00 600.00
29,280.00
B Bahan
Teak Oil Ltr 0.3600 42,000.00 15,120.00
15,120.00
C PERALATAN
D Jumlah A + B + C 44,400.00
E Overhead 2.5% 1,110.00
F Harga Satuan Pekerjaan (D+E) 45,510.00

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur


A Tenaga
Pekerja L.01 OH 0.0400 150,000.00 6,000.00
Tukang Cat L.02 OH 0.0600 175,000.00 10,500.00
Kepala Tukang L.03 OH 0.0160 185,000.00 2,960.00
Mandor L.04 OH 0.0030 200,000.00 600.00
20,060.00
B Bahan
Politur Ltr 0.1500 20,000.00 3,000.00
Spiritus Ltr 0.3720 11,600.00 4,315.20
Ampelas Lbr 2.0000 13,100.00 26,200.00
33,515.20
C PERALATAN
D Jumlah A + B + C 53,575.20
E Overhead 2.5% 1,339.38
F Harga Satuan Pekerjaan (D+E) 54,914.58

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter


A Tenaga
Pekerja L.01 OH 0.1000 150,000.00 15,000.00
Mandor L.04 OH 0.0060 200,000.00 1,200.00
16,200.00
B Bahan
Residu atau Ter Ltr 0.3500 3,400.00 1,190.00
1,190.00
C PERALATAN
D Jumlah A + B + C 17,390.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 434.75
F Harga Satuan Pekerjaan (D+E) 17,824.75
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis
A Tenaga
Pekerja L.01 OH 0.1600 150,000.00 24,000.00
Tukang Cat L.02 OH 0.1600 175,000.00 28,000.00
Kepala Tukang L.03 OH 0.0160 185,000.00 2,960.00
Mandor L.04 OH 0.0030 200,000.00 600.00
55,560.00
B Bahan
Vernis Ltr 0.1500 40,000.00 6,000.00
Dempul Ltr 0.0500 28,700.00 1,435.00
Ampelas Lbr 0.1000 13,100.00 1,310.00
8,745.00
C PERALATAN
D Jumlah A + B + C 64,305.00
E Overhead 2.5% 1,607.63
F Harga Satuan Pekerjaan (D+E) 65,912.63

10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Decolite
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 18,000.00 4,680.00
10,930.00
C PERALATAN
D Jumlah A + B + C 26,720.50
E Overhead 2.5% 668.01
F Harga Satuan Pekerjaan (D+E) 27,388.51

11 A.4.7.1.10.1 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 52,600.00 13,676.00
19,926.00
C PERALATAN
D Jumlah A + B + C 35,716.50
E Overhead 2.5% 892.91
F Harga Satuan Pekerjaan (D+E) 36,609.41
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
12 A.4.7.1.10.2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.0630 175,000.00 11,025.00
Kepala Tukang L.03 OH 0.0063 185,000.00 1,165.50
Mandor L.04 OH 0.0030 200,000.00 600.00
15,790.50
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 45,000.00 4,500.00
Cat Penutup 2 kali Kg 0.2600 80,000.00 20,800.00
27,050.00
C PERALATAN
D Jumlah A + B + C 42,840.50
E Overhead 2.5% 1,071.01
F Harga Satuan Pekerjaan (D+E) 43,911.51

13 A.4.7.1.11 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Decolite


A Tenaga
Pekerja L.01 OH 0.0280 150,000.00 4,200.00
Tukang Cat L.02 OH 0.0420 175,000.00 7,350.00
Kepala Tukang L.03 OH 0.0042 185,000.00 777.00
Mandor L.04 OH 0.0030 200,000.00 600.00
12,927.00
B Bahan
Cat Dasar Kg 0.1200 45,000.00 5,400.00
Cat Penutup 2 kali Kg 0.1800 18,000.00 3,240.00
8,640.00
C PERALATAN
D Jumlah A + B + C 21,567.00
E Overhead 2.5% 539.18
F Harga Satuan Pekerjaan (D+E) 22,106.18

14 A.4.7.1.11.1 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0280 150,000.00 4,200.00
Tukang Cat L.02 OH 0.0420 175,000.00 7,350.00
Kepala Tukang L.03 OH 0.0042 185,000.00 777.00
Mandor L.04 OH 0.0030 200,000.00 600.00
12,927.00
B Bahan
Cat Dasar Kg 0.1200 45,000.00 5,400.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Cat Penutup 2 kali Kg 0.1800 52,600.00 9,468.00
14,868.00
C PERALATAN
D Jumlah A + B + C 27,795.00
E Overhead 2.5% 694.88
F Harga Satuan Pekerjaan (D+E) 28,489.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
15 A.4.7.1.11.2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0280 150,000.00 4,200.00
Tukang Cat L.02 OH 0.0420 175,000.00 7,350.00
Kepala Tukang L.03 OH 0.0042 185,000.00 777.00
Mandor L.04 OH 0.0030 200,000.00 600.00
12,927.00
B Bahan
Cat Dasar Kg 0.1200 45,000.00 5,400.00
Cat Penutup 2 kali Kg 0.1800 80,000.00 14,400.00
19,800.00
C PERALATAN
D Jumlah A + B + C 32,727.00
E Overhead 2.5% 818.18
F Harga Satuan Pekerjaan (D+E) 33,545.18

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi


A Tenaga
Pekerja L.01 OH 0.0200 150,000.00 3,000.00
Tukang Cat L.02 OH 0.2000 175,000.00 35,000.00
Kepala Tukang L.03 OH 0.0200 185,000.00 3,700.00
Mandor L.04 OH 0.0025 200,000.00 500.00
42,200.00
B Bahan
Meni Besi Kg 0.1000 29,000.00 2,900.00
Perekat / Lem Kg 0.0100 35,000.00 350.00
3,250.00
C PERALATAN
D Jumlah A + B + C 45,450.00
E Overhead 2.5% 1,136.25
F Harga Satuan Pekerjaan (D+E) 46,586.25

17 A.4.7.1.22 Pengecatan 1 m2 permukaan Besi 3x


SNI A Tenaga
Pekerja L.01 OH 0.0500 150,000.00 7,500.00
Tukang Cat L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0075 185,000.00 1,387.50
Mandor L.04 OH 0.0025 200,000.00 500.00
22,512.50
B Bahan
Cat Kg 0.2600 57,600.00 14,976.00
Pengencer L 0.1740 18,000.00 3,132.00
Meni Kg 0.0750 29,000.00 2,175.00
Amplas Bh 0.2000 13,100.00 2,620.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
22,903.00
C PERALATAN
D Jumlah A + B + C 45,415.50
E Overhead 2.5% 1,135.39
F Harga Satuan Pekerjaan (D+E) 46,550.89
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
18 A.4.7.1.23 Pengecatan 1 m2 permukaan Trotoir 3x
SNI A Tenaga
Pekerja L.01 OH 0.0500 150,000.00 7,500.00
Tukang Cat L.02 OH 0.0750 175,000.00 13,125.00
Kepala Tukang L.03 OH 0.0075 185,000.00 1,387.50
Mandor L.04 OH 0.0025 200,000.00 500.00
22,512.50
B Bahan
Cat Kg 0.2600 57,600.00 14,976.00
Pengencer L 0.1740 18,000.00 3,132.00
Amplas Bh 0.2000 57,600.00 11,520.00
29,628.00
C PERALATAN
D Jumlah A + B + C 52,140.50
E Overhead 2.5% 1,303.51
F Harga Satuan Pekerjaan (D+E) 53,444.01
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
XV A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
1 A.8.4.1.1 Pemasangan 1 m pipa PVC Ø 50 mm (2")
A TENAGA
Pekerja L.01 OH 0.081 185,000.00 14,985.00
Tukang pipa L.02 OH 0.041 175,000.00 7,175.00
Mandor L.04 OH 0.008 200,000.00 1,600.00
23,760.00
B BAHAN
Pipa PVC Ø 50 mm m 1.000 24,350.00 24,350.00
24,350.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 48,110.00
E Overhead 2.5% 1,202.75
F Harga Satuan Pekerjaan (D+E) 49,312.75

2 A.8.4.1.1.1 Pemasangan 1 m pipa PVC Ø 25 mm (1")


A TENAGA
Pekerja L.01 OH 0.067 185,000.00 12,384.30
Tukang pipa L.02 OH 0.034 175,000.00 5,929.75
Mandor L.04 OH 0.007 200,000.00 1,322.31
19,636.36
B BAHAN
Pipa PVC Ø 25 mm m 1.000 8,450.00 8,450.00
8,450.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 28,086.36
E Overhead 2.5% 702.16
F Harga Satuan Pekerjaan (D+E) 28,788.52

3 A.8.4.1.1.2 Pemasangan 1 m pipa PVC Ø 40 mm (1½")


A TENAGA
Pekerja L.01 OH 0.074 185,000.00 13,622.73
Tukang pipa L.02 OH 0.037 175,000.00 6,522.73
Mandor L.04 OH 0.007 200,000.00 1,454.55
21,600.00
B BAHAN
Pipa PVC Ø 40 mm m 1.000 19,100.00 19,100.00
19,100.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 40,700.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead 2.5% 1,017.50
F Harga Satuan Pekerjaan (D+E) 41,717.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.8.4.1.2 Pemasangan 1 m pipa PVC Ø 75 mm (3")
A TENAGA
Pekerja L.01 OH 0.094 185,000.00 17,390.00
Tukang pipa L.02 OH 0.047 175,000.00 8,225.00
Mandor L.04 OH 0.009 200,000.00 1,800.00
27,415.00
B BAHAN
Pipa PVC Ø 75 mm m 1.000 50,900.00 50,900.00
50,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.009 -
-
D Jumlah A + B + C 78,315.00
E Overhead 2.5% 1,957.88
F Harga Satuan Pekerjaan (D+E) 80,272.88

5 A.8.4.1.3 Pemasangan 1 m pipa PVC Ø 90 mm (4")


A TENAGA
Pekerja L.01 OH 0.105 185,000.00 19,425.00
Tukang pipa L.02 OH 0.053 175,000.00 9,275.00
Mandor L.04 OH 0.011 200,000.00 2,200.00
30,900.00
B BAHAN
Pipa PVC Ø 90 mm m 1.000 73,900.00 73,900.00
73,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.009 -
-
D Jumlah A + B + C 104,800.00
E Overhead 2.5% 2,620.00
F Harga Satuan Pekerjaan (D+E) 107,420.00

6 A.8.4.1.17 Pemasangan 1 m pipa HDPE OD 63 mm


A TENAGA
Pekerja L.01 OH 0.035 185,000.00 6,475.00
Tukang pipa L.02 OH 0.017 175,000.00 2,975.00
Mandor L.04 OH 0.003 200,000.00 600.00
10,050.00
B BAHAN
Pipa HDPE OD 63 mm m 1.000 50,050.00 50,050.00
50,050.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 60,100.00
E Overhead 2.5% 1,502.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 61,602.50
Overhead & Profit
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.8.4.1.17.1 Pemasangan 1 m pipa HDPE OD 75 mm
A TENAGA
Pekerja L.01 OH 0.039 185,000.00 7,122.50
Tukang pipa L.02 OH 0.019 175,000.00 3,272.50
Mandor L.04 OH 0.003 200,000.00 660.00
11,055.00
B BAHAN
Pipa HDPE OD 75 mm m 1.000 69,900.00 69,900.00
69,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 80,955.00
E Overhead 2.5% 2,023.88
F Harga Satuan Pekerjaan (D+E) 82,978.88

8 A.8.4.1.17.2 Pemasangan 1 m pipa HDPE OD 90 mm


A TENAGA
Pekerja L.01 OH 0.040 185,000.00 7,400.00
Tukang pipa L.02 OH 0.020 175,000.00 3,500.00
Mandor L.04 OH 0.004 200,000.00 800.00
11,700.00
B BAHAN
Pipa HDPE OD 90 mm m 1.000 101,300.00 101,300.00
101,300.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 113,000.00
E Overhead 2.5% 2,825.00
F Harga Satuan Pekerjaan (D+E) 115,825.00

9 A.8.4.1.80 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan)
Galian tanah keras m3 0.075 160,310.00 12,023.25
Urugan tanah kembali m3 0.065 29,041.67 1,887.71
Buangan sisa galian m3 0.010 52,787.50 527.88
Pemasangan Pipa 1.000 28,788.52 28,788.52
Harga Satuan Pekerjaan 43,227.36

10 A.8.4.1.81 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan)
Galian tanah keras m3 0.100 160,310.00 16,031.00
Urugan tanah kembali m3 0.080 29,041.67 2,323.33
Buangan sisa galian m3 0.020 52,787.50 1,055.75
Pemasangan Pipa 1.000 41,717.50 41,717.50
Harga Satuan Pekerjaan 61,127.58

11 A.8.4.1.82 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 160,310.00 20,038.75
Urugan tanah kembali m3 0.095 29,041.67 2,758.96
Buangan sisa galian m3 0.030 52,787.50 1,583.63
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Pemasangan Pipa 1.000 49,312.75 49,312.75
Harga Satuan Pekerjaan 73,694.08

12 A.8.4.1.83 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 160,310.00 24,046.50
Urugan tanah kembali m3 0.120 29,041.67 3,485.00
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 80,272.88 80,272.88
Harga Satuan Pekerjaan 109,388.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.8.4.1.84 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan)
Galian tanah keras m3 0.300 160,310.00 48,093.00
Urugan tanah kembali m3 0.265 29,041.67 7,696.04
Buangan sisa galian m3 0.035 52,787.50 1,847.56
Pemasangan Pipa 1.000 107,420.00 107,420.00
Harga Satuan Pekerjaan 165,056.60

14 A.8.4.1.85 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 160,310.00 20,038.75
Urugan tanah kembali m3 0.095 29,041.67 2,758.96
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 61,602.50 61,602.50
Harga Satuan Pekerjaan 85,983.83

15 A.8.4.1.86 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 160,310.00 24,046.50
Urugan tanah kembali m3 0.120 29,041.67 3,485.00
Buangan sisa galian m3 0.030 52,787.50 1,583.63
Pemasangan Pipa 1.000 82,978.88 82,978.88
Harga Satuan Pekerjaan 112,094.00

16 A.8.4.1.87 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan)
Galian tanah keras m3 0.175 160,310.00 28,054.25
Urugan tanah kembali m3 0.140 29,041.67 4,065.83
Buangan sisa galian m3 0.035 52,787.50 1,847.56
Pemasangan Pipa 1.000 115,825.00 115,825.00
Harga Satuan Pekerjaan 149,792.65

XVI A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA

1 A.8.4.5.1 Pengetesan 1 m pipa Ø 50 mm


A TENAGA
Pekerja L.01 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0008 200,000.00 160.00
1,640.00
B BAHAN
Air test (air bersih) m3 0.002 20,000.00 40.00
Bahan bakar liter 0.060 6,400.00 384.00
Oli liter 0.002 33,600.00 67.20
491.20
C PERALATAN
D Jumlah A + B + C 2,131.20
E Overhead 2.5% 53.28
F Harga Satuan Pekerjaan (D+E) 2,184.48

2 A.8.4.5.2 Pengetesan 1 m pipa Ø 75 mm


A TENAGA
Pekerja L.01 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0008 200,000.00 160.00
1,640.00
B BAHAN
Air test (air bersih) m3 0.004 20,000.00 80.00
Bahan bakar liter 0.060 6,400.00 384.00
Oli liter 0.002 33,600.00 67.20
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
531.20
C PERALATAN
D Jumlah A + B + C 2,171.20
E Overhead 2.5% 54.28
F Harga Satuan Pekerjaan (D+E) 2,225.48
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
3 A.8.4.5.3 Pengetesan 1 m pipa Ø 100 mm
A TENAGA
Pekerja L.01 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0008 200,000.00 160.00
1,640.00
B BAHAN
Air test (air bersih) m3 0.008 20,000.00 160.00
Bahan bakar liter 0.060 6,400.00 384.00
Oli liter 0.002 33,600.00 67.20
611.20
C PERALATAN
D Jumlah A + B + C 2,251.20
E Overhead 2.5% 56.28
F Harga Satuan Pekerjaan (D+E) 2,307.48

4 A.8.4.5.4 Pengetesan 1 m pipa Ø 150 mm


A TENAGA
Pekerja L.01 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0008 200,000.00 160.00
1,640.00
B BAHAN
Air test (air bersih) m3 0.018 20,000.00 360.00
Bahan bakar liter 0.060 6,400.00 384.00
Oli liter 0.002 33,600.00 67.20
811.20
C PERALATAN
D Jumlah A + B + C 2,451.20
E Overhead 2.5% 61.28
F Harga Satuan Pekerjaan (D+E) 2,512.48

5 A.8.4.5.5 Pengetesan 1 m pipa Ø 200 mm


A TENAGA
Pekerja L.01 OH 0.0080 185,000.00 1,480.00
Mandor L.04 OH 0.0008 200,000.00 160.00
1,640.00
B BAHAN
Air test (air bersih) m3 0.031 20,000.00 620.00
Bahan bakar liter 0.060 6,400.00 384.00
Oli liter 0.002 33,600.00 67.20
1,071.20
C PERALATAN
D Jumlah A + B + C 2,711.20
E Overhead 2.5% 67.78
F Harga Satuan Pekerjaan (D+E) 2,778.98
PEKERJAAN : PEMBUATAN SUMUR PRODUKSI

An.1 Jenis pekerjaan : Mobilisasi/demobilisasi driling rig & peralatan pemboran

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3
Crew pengeboran Hari 4.00 x 1.00 50,000.00 200,000.00
4
Pengemudi Hari 2.00 x 2.00 40,000.00 160,000.00
II. PERALATAN
1 Sewa kendaraan Hari 2.00 x 2.00 250,000.00 1,000,000.00
angkut ( truk )

JUMLAH 1,485,000.00

An.2 Jenis pekerjaan :Pemboran pilot hole diameter 6", 0 -- 50 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 70.00 x 1.00 6,400.00 448,000.00
2 Olie mesin Ltr 5.00 x 1.00 33,600.00 168,000.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 400,000.00 400,000.00

JUMLAH 2,063,200.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 206,320.00
Overhead 2.5% 5,158.00
211,478.00
An.3 Jenis pekerjaan :Pemboran pilot hole diameter 6", 50 -- 100 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 6,400.00 480,000.00
2 Olie mesin Ltr 5.00 x 1.00 33,600.00 168,000.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 50.00 x 1.00 11,400.00 570,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,184,200.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 218,420.00
Overhead 2.5% 5,460.50
223,880.50

An.4 Jenis pekerjaan :Pemboran pilot hole diameter 6", 100 -- 150 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 85.00 x 1.00 6,400.00 544,000.00
2 Olie mesin Ltr 6.00 x 1.00 33,600.00 201,600.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 60.00 x 1.00 11,400.00 684,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,428,900.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 242,890.00
Overhead 2.5% 6,072.25
248,962.25
An.5 Jenis pekerjaan : Pekerjaan reaming, 0 -- 65 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 60.00 x 1.00 6,400.00 384,000.00
2 Olie mesin Ltr 4.00 x 1.00 33,600.00 134,400.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 1,940,600.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 194,060.00
Overhead 2.5% 4,851.50
198,911.50

An.6 Jenis pekerjaan : Pekerjaan reaming ,65 -- 130 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 6,400.00 480,000.00
2 Olie mesin Ltr 6.00 x 1.00 33,600.00 201,600.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 55.00 x 1.00 11,400.00 627,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,307,900.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 230,790.00
Overhead 2.5% 5,769.75
236,559.75
An.7 Jenis pekerjaan : Electric logging

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
4
Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
II. PERALATAN
1 Recorder paper Unit 1.00 x 1.00 20,000.00 20,000.00
2 Alat tulis Unit 1.00 x 1.00 15,000.00 15,000.00
III. PERALATAN
Mesin peralatan logging Unit 1.00 x 1.00 700,000.00 700,000.00
Tranportasi peralatan logging Unit 1.00 x 1.00 150,000.00 150,000.00

JUMLAH 1,170,000.00
1 HARI RATA-RATA 50 M' ----> JADI PER METER 23,400.00
Overhead 2.5% 585.00
23,985.00

An.8 Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 8"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 6,400.00 768,000.00
2 Olie mesin Ltr 3.00 x 1.00 33,600.00 100,800.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
Pipa jambang diameter 8" Mtr 60.00 x 578,400.00 34,704,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 36,587,000.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 609,783.33
Overhead 2.5% 15,244.58
625,027.92
DIBULATKAN 625,000.00
An.9 Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 6"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 6" Mtr 30.00 x 310,000.00 9,300,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 10,503,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 350,115.33
Overhead 2.5% 8,752.88
358,868.22
DIBULATKAN 358,000.00

An.10 Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 6"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 6 : Mtr 30.00 x 1,719,900.00 51,597,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 52,800,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,760,015.33
Overhead 2.5% 44,000.38
1,804,015.72
DIBULATKAN 1,804,000.00
An.8' Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 6" (GIP)

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 6,400.00 768,000.00
2 Olie mesin Ltr 3.00 x 1.00 33,600.00 100,800.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
5 Pipa jambang diameter 6" Mtr 60.00 x 323,200.00 19,392,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 21,275,000.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 354,583.33
Overhead 2.5% 8,864.58
363,447.92
DIBULATKAN 363,000.00

An.9' Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 4" (GIP)

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 4" Mtr 30.00 x 283,500.00 8,505,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 9,708,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 323,615.33
Overhead 2.5% 8,090.38
331,705.72
DIBULATKAN 331,000.00
An.10' Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 4"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 6,400.00 256,000.00
2 Olie mesin Ltr 1.00 x 33,600.00 33,600.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 4" : Mtr 30.00 x 1,181,300.00 35,439,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 36,642,460.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,221,415.33
Overhead 2.5% 30,535.38
1,251,950.72
DIBULATKAN 1,251,000.00
ANALISA BIAYA PEKERJAAN
LAPIS PENETRASI MAKADAM (LAPEN) 5 CM KODE
( MENGGUNAKAN BURUH ) K 618

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Semprotkan aspal tack coat 1. Menggunakan tenaga buruh
0,8 liter/m2 2. Harga material ( agregat dan aspal) adalah harga di lokasi proyek
2. Hamparkan agregat pokok 3-5 3. Volume aspal cair untuk tack coat/prime coat 0,8 liter/m2
25 m2/m3 dan padatkan 4. Tebal lapisan penetrasi 5 cm
3. Haparkan split 2-3 45 m2/m3 5. Agregat dikirim ke lokasi oleh leveransir
dan padatkan
4. Semprotkan aspal (2,5 kg/m2)
5. Hamparkan agregat pengunci
split 1-2 90 m2/m3 & padatkan
6. Semprotkan aspal 1,5 kg/m2
dan gilas
7. Taburkan pasir rata-rata 400m2
per m3

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 0.004 2.00 3 6.00 200,000.00 1,200,000.00


E Operator terlatih 0.004 2.00 3 6.00 175,000.00 1,050,000.00
K Sopir 0.002 1.00 3 3.00 40,000.00 120,000.00
E Buruh tak terlatih 0.141 66.00 3 198.00 150,000.00 29,700,000.00
R Buruh terlatih ( Tenaga Aspal ) 0.004 2.00 3 6.00 150,000.00 900,000.00
J
A

32,970,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Alat bantu 3.10 Set 1,648,500.00 5,110,350.00


A Material batu pecah :
T -Batu pecah 3-5 cm 0.0400 56.00 m3 191,900.00 10,746,400.00
E - Batu pecah 2-3 cm 0.0221 31.00 m3 215,900.00 6,692,900.00
R - Batu pecah 1-2 cm 0.0111 15.50 m3 217,100.00 3,365,050.00
I - Batu ciping 0,5 cm 0.0051 7.13 m3 189,400.00 1,350,422.00
A - Abu batu 0.0025 3.50 m3 172,700.00 604,450.00
L Aspal 4.4786 6,270.00 kg 13,500.00 84,645,000.00
Minyak bakar 0.3214 450.00 liter 13,500.00 6,075,000.00

118,589,572.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P Mesin gilas 3 roda 6 - 10 ton 1.00 3 15.00 44,000.00 660,000.00


E Sprayer aspal 200 L 1.00 3 15.00 50,000.00 750,000.00
R Flatbed truck 3,5 T /115 HP 1.00 3 15.00 71,500.00 1,072,500.00
A
L
A
T
A
N

2,482,500.00
TOTAL Rp. 154,042,072.00
Overhead 2.5% 3,851,051.80
TOTAL BIAYA 157,893,123.80

VOLUME/ : 1,400.00 SATUAN: m2 HARGA SATUAN Rp. 112,780.80 Per m2


QUANTITY
ANALISA BIAYA PEKERJAAN
MEMBUAT CAMPURAN, MENGHAMPAR DAN PEMADATAN LATASIR 2 CM KODE
( MENGGUNAKAN BURUH ) K 621.a

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Supplier mengirim material 1. Menggunakan tenaga buruh 400 m2/hari
sampai ke bin spreader 2. Pasir aspal dikirim oleh levelansier ketempat pekerjaan
2. Material dihampar dengan mesin 3. Rata - rata tebal lapisan padat 2 cm
spreader, dipadatkan dengan
mesin gilas roda baja

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 0.0075 1.00 3 L 061 3.00 200,000.00 600,000.00


E Operator terlatih 0.0075 1.00 3 L 085 3.00 175,000.00 525,000.00
K Buruh tak terlatih 0.19 25.00 3 L 092 75.00 150,000.00 11,250,000.00
E Buruh semi terlatih 0.08 10.00 3 L 091 30.00 150,000.00 4,500,000.00
R
J
A

16,875,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M
A Aspal untuk campuran 3.4285 1,371.40 kg M061 13,500.00 18,513,900.00
T Pasir beton 0.01715 6.86 m3 M041 270,300.00 1,854,258.00
E Abu batu (filler) 0.003925 1.57 m3 M027 172,700.00 271,139.00
R Aspal untuk prime coat 0.251425 100.57 kg M061 13,500.00 1,357,695.00
I Minyak bakar 0.5575 223.00 Ltr M065 13,500.00 3,010,500.00
A
L

25,007,492.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P Roller 3 Wheled 8-10 T 51 HP 1.00 1 E 080 5.00 44,000.00 220,000.00


E Aspal Sprayer Towed 350 L 7 HP 1.00 1 E 154 5.00 50,000.00 250,000.00
R
A
L
A
T
A
N

470,000.00
TOTAL Rp. 42,352,492.00
Overhead 2.5% 1,058,812.30
TOTAL BIAYA 43,411,304.30

VOLUME/ : 400.00 SATUAN: m2 HARGA SATUAN Rp. 108,528.26 Per m2


QUANTITY
ANALISA BIAYA PEKERJAAN
KONSTRUKSI LAPIS PONDASI BAWAH (LPB) KLAS C SIRTU KODE
( MENGGUNAKAN BURUH ) K 515

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Kerikil ditimbun sepanjang jalan 1. Menggunakan tenaga manusia setempat
oleh leveransir 2. Kerikil ditimbuan disepanjang jalan oleh leveransir
2. Menghampar agregat dengan 3. Kerikil dg ukuran lebih yang tersingkir saat penghamparan dg orang dihitung 6 %
tenaga manusia 4. Dihampar dalam 2 lapis & dipadatkan tebal 10 cm padat
3. Pemadatan dalam 2 lapis dg 5. Penggunaan alat bantu 1 bulan-orang
truk air dan mesin gilas 6. Hasil kerja menghampar & memadatkan 600 m2/hari ( 4 m x 150 m)
4. Perapihan dengan tangan 7. Kerikil kali tanpa disaring dikirim leveransir samapi tempat pekerjaan

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 3.00 1 L 061 3.00 200,000.00 600,000.00


E Operator terlatih 1.00 1 L 081 1.00 175,000.00 175,000.00
K Sopir 1.00 1 L 091 1.00 40,000.00 40,000.00
E Buruh tak terlatih 60.00 1 L 101 60.00 150,000.00 9,000,000.00
R
J
A

9,815,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Alat bantu 2.50 Set M 170 490,750.00 1,226,875.00


A Sirtu 75.00 m3 M 029 82,500.00 6,187,500.00
T
E
R
I
A
L

7,414,375.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P
E Mesin gilas 3 roda 6 Ton 1.00 1 E 080 5.00 44,000.00 220,000.00
R Truck tangki air 68 HP 1.00 1 E 182 5.00 82,500.00 412,500.00
A
L
A
T
A
N

632,500.00
TOTAL Rp. 17,861,875.00
Overhead 2.5% 446,546.88
TOTAL BIAYA 18,308,421.88

VOLUME/ : 60.00 SATUAN: m3 HARGA SATUAN Rp. 305,140.36 Per m3


QUANTITY
ANALISA BIAYA PEKERJAAN
KONSTRUKSI LAPIS PONDASI ATAS (LPA) KLAS A KODE
( MENGGUNAKAN ALAT ) K 520

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Agregat ditempatkan sepanjang 1. Menggunakan peralatan berat
oleh leveransir 2. Material dikirim dan ditimbun oleh leveransir
2. Menghampar agregat dengan 3. Penghamparan & pemadatan sampai tebal 10 cm
grader 4. Menggunakan : 135 m3 batu pecah, mesin dg binder 24 m3 atau 140 m3 kerikil
3. Pemadatan dilakukan dengan pecah mesin dengan binder 15 m3
mesin gilas getar disertai dg 5. Tambahkan binder untuk mengisi rongga
truk air 6. Dicampur dan dipadatkan 1200 m2 per-hari

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 1.00 1 L 061 1.00 200,000.00 200,000.00


E Operator terlatih 2.00 1 L 081 2.00 175,000.00 350,000.00
K Sopir 1.00 1 L 091 1.00 40,000.00 40,000.00
E Buruh tak terlatih 4.00 1 L 101 4.00 150,000.00 600,000.00
R
J
A

1,190,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Pasir hurug 72.00 m3 M 040 82,000.00 5,904,000.00


A Batu pecah 3 - 5 cm 45.00 m3 M 023 191,900.00 8,635,500.00
T Batu pecah 2 - 3 cm 23.00 m3 M 024 215,900.00 4,965,700.00
E Batu pecah 1 - 2 cm 13.00 m3 M 025 217,100.00 2,822,300.00
R Batu pecah 0,5 - 1 cm 27.00 m3 M 026 189,400.00 5,113,800.00
I Alat bantu 1.00 Set M 170 59,500.00 59,500.00
A
L

27,500,800.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P Grader 110 HP 1.00 1 E 010 5.00 236,500.00 1,182,500.00


E Mesin gilas getar 1 ton 1.00 1 E 087 5.00 30,200.00 151,000.00
R Truck tangki air 68 HP 1.00 1 E 182 4.00 82,500.00 330,000.00
A
L
A
T
A
N

1,663,500.00
TOTAL Rp. 30,354,300.00
Overhead 2.5% 758,857.50
TOTAL BIAYA 31,113,157.50

VOLUME/ : 150.00 SATUAN: m3 HARGA SATUAN Rp. 207,421.05 Per m3


QUANTITY
ANALISA BIAYA PEKERJAAN
KONSTRUKSI LAPIS PONDASI ATAS (LPA) KLAS A KODE
( MENGGUNAKAN BURUH ) K 521

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Agregat ditempatkan sepanjang 1. Menggunakan tenaga manusia
oleh leveransir 2. Material dikirim dan ditimbun oleh leveransir
2. Menghampar agregat dengan 3. Buruh menghampar batu pecah diatas ( kurang lebih 15 cm)
Tenaga manusia 4. Menggunakan : 135 m3 batu pecah, mesin dg binder 24 m3 atau 140 m3 kerikil
3. Pemadatan dilakukan dengan pecah mesin dengan binder 15 m3
mesin gilas roda baja disertai dg 5. Tambahkan binder untuk mengisi rongga
tangki air 6. Dipadatkan sampai 10 cm padat
7. Hasil kerja menghampar dan memadatkan 600 m2/hari

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 1.00 1 L 061 1.00 200,000.00 200,000.00


E Operator terlatih 1.00 2 L 085 2.00 175,000.00 350,000.00
K Sopir 1.00 2 L 087 2.00 40,000.00 80,000.00
E Buruh tak terlatih 66.00 2 L 092 66.00 150,000.00 9,900,000.00
R
J
A

10,530,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Pasir hurug 29.00 m3 M 023 82,000.00 2,378,000.00


A Alat bantu 2.00 Set 526,500.00 1,053,000.00
T Kerikil pecah tersaring:
E Batu pecah 3 - 5 cm 18.00 m3 M 004 191,900.00 3,454,200.00
R Batu pecah 2 - 3 cm 9.00 m3 M 005 215,900.00 1,943,100.00
I Batu pecah 1 - 2 cm 6.00 m3 M 006 217,100.00 1,302,600.00
A Batu pecah 0,5 - 1 cm 10.00 m3 M 007 189,400.00 1,894,000.00
L

12,024,900.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P
E Mesin gilas 3 roda 6 T 1.00 1 E 080 5.00 44,000.00 220,000.00
R Truck tangki air 68 HP 1.00 1 E 182 4.00 82,500.00 330,000.00
A
L
A
T
A
N

550,000.00
TOTAL Rp. 23,104,900.00
Overhead 2.5% 577,622.50
TOTAL BIAYA 23,682,522.50

VOLUME/ : 60.00 SATUAN: m3 HARGA SATUAN Rp. 394,708.71 Per m3


QUANTITY
ANALISA BIAYA PEKERJAAN
KONSTRUKSI LAPIS PONDASI BAWAH (LPB) TELFORD KODE
( MENGGUNAKAN BURUH ) K 516

PROPINSI : KODE KABUPATEN : KODE: DISIAPKAN OLEH : TANGGAL:


JAWA TENGAH 33 JEPARA 20 CIPTAKARYA Jepara, Februari 2015

URAIAN : ANGGAPAN / ASUMSI :


1. Material disiapkan dilokasi pe- 1. Menggunakan tenaga manusia 400 m2 perhari
kerjaan 2. Kerikil ditimbuan disepanjang jalan oleh leveransir
2. Menghampar pasir tebal 5 cm 3. Batu sudah dipecah
3. Batu pecah berukuran besar 4. Tanah dasar sudah disiapkan
10-15 cm disusun berdiri 5. Dipadatkan sampai tebal 20 cm
4. Batu pecah yang lebih kecil
mengisi rongga diatasnya se-
hungga rata & dipadatkan dg
mesin gilas

PEKERJA Jumlah Hari Kode Jumlah Upah Biaya Sub Total


Orang Hari-Org (Rp./Org/Hari) (Rp.) (Rp.)

P Mandor 3.00 1 L 061 3.00 200,000.00 600,000.00


E Operator terlatih 1.00 1 L 081 1.00 175,000.00 175,000.00
K Buruh tak terlatih 99.00 1 L 101 99.00 150,000.00 14,850,000.00
E
R
J
A

15,625,000.00
MATERIAL Jumlah Volume Kode Harga Satuan Biaya Sub Total
Satuan (Rp.) (Rp.) (Rp.)

M Alat bantu 4.00 Set M 170 781,250.00 3,125,000.00


A Batu belah 15 - 20 cm 50.00 m3 M 020 143,000.00 7,150,000.00
T Batu pecah 5 - 7 cm 20.00 m3 M 022 191,900.00 3,838,000.00
E Pasir hurug 30.00 m3 M 040 82,000.00 2,460,000.00
R
I
A
L

16,573,000.00
PERALATAN Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)

P
E Mesin gilas 3 roda 6 Ton 1.00 1 E 080 5.00 44,000.00 220,000.00
R
A
L
A
T
A
N

220,000.00
TOTAL Rp. 32,418,000.00
Overhead 2.5% 810,450.00
TOTAL BIAYA 33,228,450.00

VOLUME/ : 80.00 SATUAN: m3 HARGA SATUAN Rp. 415,355.63 Per m3


QUANTITY
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN DRAINASE
LOKASI : RW. 03 DAN RW. 04
TAHUN ANGGARAN : 2015
VOLUME : …………………

HARGA SATUAN JUMLAH HARGA JUMLAH


NO URAIAN PEKERJAAN KOEFISIEN VOLUME
Rp Rp Rp
A Menggali Tanah Biasa sedalam 1 m 232.54 m3
1 TENAGA
- Pekerja 0.7500 174.405 HOK 60,000 10,464,300
- Mandor 0.0250 5.8135 HOK 80,000 465,080
10,929,380
Overhead ( 2.5% ) 0.0250 273,235
Harga Satuan Pekerjaan 11,202,615

B Urugan Pasir 16.61 m3


1 TENAGA
Pekerja 0.3000 4.983 HOK 60,000 298,980
Mandor 0.0100 0.1661 HOK 80,000 13,288
312,268
2 BAHAN
Pasir Urug 1.2000 19.932 m3 82,000 1,634,424
1,634,424
Jumlah 1 + 2 1,946,692
Overhead ( 2.5% ) 0.0250 48,667
Harga Satuan Pekerjaan 1,995,359

C Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal 123.82 m3


1 TENAGA
Pekerja 1.5000 185.73 HOK 60,000 11,143,800
Tukang Batu 0.7500 92.87 HOK 75,000 6,964,875
Kepala Tukang 0.0750 9.29 HOK 80,000 742,920
Mandor 0.0750 9.29 HOK 80,000 742,920
19,594,515
2 BAHAN
Batu Belah 15/20 1.2 148.58 m3 143,000 21,247,512
Portland Sement 136 16839.52 Kg 1,410 23,743,723
Pasir Pasang 0.544 67.36 m3 142,800 9,618,734
54,609,969
Jumlah 1 + 2 74,204,484
Overhead ( 2.5% ) 0.0250 1,855,112
Harga Satuan Pekerjaan 76,059,596

D Pemasangan Plesteran 1 Pc : 5 Pp muntilan Tebal 15 mm 694.60 m2


1 Tenaga
Pekerja 0.3000 208.38 HOK 60,000 12,502,800
Tukang batu 0.1500 104.19 HOK 75,000 7,814,250
Kepala Tukang 0.0150 10.42 HOK 80,000 833,520
Mandor 0.0150 10.42 HOK 80,000 833,520
21,984,090.00
2 Bahan
Portland Semen 5.1840 3600.81 Kg 1,410 5,077,137
Pasir Muntilan 0.0260 18.06 m3 270,300 4,881,510
9,958,646.90
Jumlah 1 + 2 31,942,736.90
Overhead ( 2.5% ) 0.0250 798,568.42
Harga Satuan Pekerjaan 32,741,305.33

TOTAL 121,998,875.25
PPn dan PPh (11.5 %) 14,029,870.65
JUMLAH TOTAL 136,028,745.91
DIBULATKAN 136,020,000.00

TERBILANG

Err:511

Jepara, 25 April 2015


PANITIA PEMBANGUNAN
RT. 01 RW. 03
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN KOEFISIEN VOLUME
Rp Rp Rp

Ketua Sekretaris

ASYHADI, S.Ag ACHMAD MUNIF


Mengetahui
Ketua RT. 02 RW. 02

MUSTA'IN
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN DRAINASE
LOKASI : RW. 03 DAN RW. 04
TAHUN ANGGARAN : 2015
VOLUME : …………………

HARGA SATUAN JUMLAH HARGA JUMLAH


NO URAIAN PEKERJAAN KOEFISIEN VOLUME
Rp Rp Rp
A Pemasangan Lantai Keramik 40 x 40 cm putih 49 m2
1 Tenaga
Pekerja 0.2500 12.25 HOK 60,000 735,000
Tukang Batu 0.1250 6.125 HOK 75,000 459,375
Kepala Tukang 0.0130 0.637 HOK 80,000 50,960
Mandor 0.0130 0.637 HOK 80,000 50,960
Harga Satuan Pekerjaan 1,296,295

B Bahan 49.00 m2
Ubin Keramik 40 x 40 cm putih 6.6300 324.87 Buah 7,800 2,533,986
Portland Semen 9.8000 480.2 Kg 1,410 677,082
Semen Warna 1.3000 63.7 Kg 11,790 751,023
Pasir Pasang 0.0450 2.205 m3 142,800 314,874

Harga Satuan Pekerjaan 4,276,965

C Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal 123.82 m3


1 TENAGA
Pekerja 1.5000 185.73 HOK 60,000 11,143,800
Tukang Batu 0.7500 92.87 HOK 75,000 6,964,875
Kepala Tukang 0.0750 9.29 HOK 80,000 742,920
Mandor 0.0750 9.29 HOK 80,000 742,920
19,594,515
2 BAHAN
Batu Belah 15/20 1.2 148.58 m3 143,000 21,247,512
Portland Sement 136 16839.52 Kg 1,410 23,743,723
Pasir Pasang 0.544 67.36 m3 142,800 9,618,734
54,609,969
Jumlah 1 + 2 74,204,484
Overhead ( 2.5% ) 0.0250 1,855,112
Harga Satuan Pekerjaan 76,059,596

D Pemasangan Plesteran 1 Pc : 5 Pp muntilan Tebal 15 mm 694.60 m2


1 Tenaga
Pekerja 0.3000 208.38 HOK 60,000 12,502,800
Tukang batu 0.1500 104.19 HOK 75,000 7,814,250
Kepala Tukang 0.0150 10.42 HOK 80,000 833,520
Mandor 0.0150 10.42 HOK 80,000 833,520
21,984,090.00
2 Bahan
Portland Semen 5.1840 3600.81 Kg 1,410 5,077,137
Pasir Muntilan 0.0260 18.06 m3 270,300 4,881,510
9,958,646.90
Jumlah 1 + 2 31,942,736.90
Overhead ( 2.5% ) 0.0250 798,568.42
Harga Satuan Pekerjaan 32,741,305.33

TOTAL 114,374,161.45
PPn dan PPh (11.5 %) 13,153,028.57
JUMLAH TOTAL 127,527,190.02
DIBULATKAN 127,520,000.00

TERBILANG

Err:511

Jepara, 25 April 2015


PANITIA PEMBANGUNAN
RT. 01 RW. 03
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN KOEFISIEN VOLUME
Rp Rp Rp

Ketua Sekretaris

ASYHADI, S.Ag ACHMAD MUNIF


Mengetahui
Ketua RT. 02 RW. 02

MUSTA'IN

Вам также может понравиться