Академический Документы
Профессиональный Документы
Культура Документы
1
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
3
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
4
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
5
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
Overall Assessment
The Project is considered successful, based on a review of its relevance, efficacy,
efficiency, and sustainability, and impact on institutional development. Appendix 15
6
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
Lessons Learned
The Project was successful in many aspects, except for significant delays with various
causes. An important lesson from the Project concerns that of the availability of counterpart
funding. At appraisal, WAPDA was to finance approximately 43% of the total project cost.
However, due to the declining performance of WAPDA and the impossibility of increasing
tariffs, the level of funds available declined. The foreign development partners increase
their disbursements in June 1997, to assist in covering WAPDA’s shortage of funds. Th
continued until June 1999. Due to WAPDA’s not being able to generate its share of the
finances, project implementation suffered. In the future, the availability of counterpart
funds needs to be guaranteed more fully, and ADB assistance to the power sector in the
country should take this into account.
A key lesson of the Project relates to environmental and social impacts. The environmental
aspects are mainly positive, in that they obviate the need for a comparably sized (thermal)
generation plant and thereby reduce the damaging atmospheric impacts of such plants.
However, as demonstrated in the Project, reducing the potential social impacts to
manageable levels is also possible, through rigorous evaluation of alternatives and public
consultation and awareness building. In this context, the selection of the final power
channel alignment (and the conscious decision to avoid existing villages and settlements,
even at somewhat higher costs) and locations of the barrage and powerhouse deserve to be
highlighted. These decisions substantially reduced the scale of the resettlement and
relocation under the Project without adversely affecting its economic and financial viability
ADB should have been more involved with the environmental and resettlement aspects.
Although the World Bank was responsible for the environmental and resettlement aspects
of the Project, ADB could have taken a more active role, as was noted in discussions with
a World Bank mission. ADB had a total of seven different project officers throughout the
Project’s duration, and this was detrimental to overall project coordination. Furthermore,
coordination among financers could have been more efficient, if a mechanism was
7
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018
Recommendations
a. Financial Control
WAPDA has not always submitted audited project accounts and corporate financial
statements on time, as required by the loan covenants. The PCR Mission had difficulty
determining how much WAPDA spent each year on each project component. Significant
improvements in WAPDA’s financial record keeping must be made, and financial accounts
need to be submitted promptly, in accordance with the covenants.
b. Future Monitoring
The generation and transmission distribution facilities that have been added under the
Project are critical to reliable power supply in the country, and maintaining these facilities
is essential. The PCR Mission recommended that the facilities should be operated and
maintained properly, to keep them in good working condition and ensure the long-term
success of the Project. ADB should keep in close contact with WAPDA through ongoing
loans, to ensure than maintenance is being undertaken correctly.
Covenants
WAPDA has had difficulty complying with some of the financial loan covenants, such as
maintaining a minimum 40% self-financing ratio and a minimum 1.5 times DSR. Both
ratios have been improving, but ADB should continue to monitor and review WAPDA’s
financial viability. The Borrower and WAPDA need to make further efforts to fulfill the
major loan covenants, including those related to the financial and operational performance
of WAPDA, such as system losses, so that WAPDA’s operations and commercial and
financial performance can be elevated. This will eventually improve the country’s
capability to tap domestic and international capital markets for additional financial
resources, which can be used increase the power supply.
Further Action or Follow-Up
8
HYDRAULICS AND IRRIGATION ENGINEERING 05/23/2018