Project : TOLEDO UNITY PARK AND GOVERNMENT CENTER

Owner : GOVERNMENT OF TOLEDO CITY CEBU


Location : BRGY. POBLACION TOLEDO CITY CEBU
Subject : BAR CHART / PROGRAM OF WORKS
Date :

UNITY PARK A
Contract Percentage
SCOPE OF WORK
Amount Weight Month1 Month2 Month3 Month4 Month5 Month6 Month7 Month8
wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3

1 GENERAL REQUIREMENTS 10,685,694.80 2.00

2 SITE WORKS / EARTH WORKS 17,493,875.27 3.27

3 STRUCTURAL/CONCRETE WORKS 321,865,170.92 60.09

4 MASONRY WORKS 12,585,487.30 2.35

5 METAL WORKS 3,901,611.53 0.73

6 THERMAL / MOISTURE PROTECTION 3,954,748.70 0.74

7 FINISHES 80,285,118.48 14.99

8 PLUMBING AND SANITARY WORKS 21,994,644.00 4.11

9 FIRE PROTECTION 13,551,959.77 2.53

10 MECHANICAL WORKS 21,487,593.66 4.01

11 ELECTRICAL WORKS 27,796,121.99 5.19

12 AUXILLIARY WORKS 3,885,916.68 0.73

13 SITE DEVELOPMENT 11,108,160.00 5.19

TOTAL 535,602,026.42 105.92


AND COMMUNITY CENTER- Project Construction Program of Works
Duration
Month9 Month10 Month11 Month12 Month13 Month14 Month15 Month16 Month17 Month18
wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4 wk1 wk2 wk3 wk4