Академический Документы
Профессиональный Документы
Культура Документы
• Support an excavation
• Provide access
Temporary Works – Legal bits
Copies of the British Standard for TW’s and the CDM Regulations are available for
viewing within CIMS under ‘Legislation/HSE Info’.
Temporary Works – Examples
• Underpinning • Hoists
• Cofferdams • Propping
• Formwork • Hoarding/Fencing
5. TWC completes Design/RAMS Brief (Form A) for each item on the TW Register.
7. Design/RAMS Certificate (Form B) is issued back to the TWC by the allotted time
(detailed in TW Register and on Form A Section 9) with the relevant information
ie drawings, specs, requirements, detailed hazards/risks or; for a CAT 0 – the
RAMS.
8. The details and documents detailed and supplied are reviewed by the TWC and
Section 6 on Form B is then completed when accepted. Any queries are to be
sent to the issuer noted on Section 5 of Form B.
9. Completed Forms A and B with a blank Form C (Permit to Proceed), and a copy
of the TW Register, can now be issued to site with all associated
documents/drawings etc.
10. Form C - Permit to Proceed is issued by the TWC or TWS on site as required with
the agreed safe method, design or process followed accordingly.
Temporary Works Procedure
Important Notes:
• Only until Forms A to B have been fully completed and all required
documents/drawings are received can a Form C Permit to Proceed be issued.
• No deviation from the agreed work or method is allowed and any design/scope
changes are to be referred back to the appropriate designer or issuer of RAMS and
Forms A-C completed again accordingly.
• Other site working documents such as Scaffold Inspections, Excavation Permits and
Inspections shall also be utilised in conjunction with any relevant temporary works.
• Form C Permit to Proceed may be issued on a daily basis or for the duration of that
works. It is dependent on the design or scope of works or requirements noted in Form
C under Section 3.0 Particular Requirements (as determined from information
provided on Form B Design/RAMS Certificate.
• Review and inspection of the works are to be carried out as specified within Form C as
deemed from information provided in Form B.
Temporary Works Responsibilities
• Designers
Under the CDM Regulations 2015 all designers are responsible for considering
Temporary Works and designing out risk where possible. Where this is not possible risks
should be reduced and residual risks highlighted for consideration during the tender
stage. Residual risks should also be raised to the site team to be appropriately managed
where appropriate.
• Estimator/Bid Manager
The Estimator, or person(s) responsible for reviewing, calculating and preparing tender
submissions, is responsible for identifying temporary works and the appropriate
construction methods and resources required and conveying this information to relevant
persons.
Temporary Works Responsibilities
• Quantity Surveyors
QS’s must ensure that any identified Temporary Works that are the responsibility of
Chalcroft have suitable costs, provisions and resources allocated to address the works.
• Contracts/Project/Build Managers
All Contracts Managers, Project Managers and Build Managers are responsible for all
Temporary Works and ensuring competency of duty holders. They are required to
appoint a Temporary Works Co-ordinator in writing and if required, a Temporary Works
Supervisor.
Temporary Works Responsibilities
• Temporary Works Co-ordinator (TWC)
The TWC shall be a Site Manager or Site Supervisor (or in certain occasions the Contracts/Build/Project
Managers for small works or short duration works) who is:
Cont’ over:
Temporary Works Responsibilities
• Temporary Works Co-ordinator (TWC)
- The design is checked and any queries are referred back to the designer
- Changes and corrections are designed, verified and carried out as required
- Inspections are done at critical stages during construction and before loading
- The strength of the permanent works is adequate to permit removal of the TW
- Formal permits to load/dismantle are issued on the appropriate forms
- Any temporary works designs match the design brief and residual risks are entered into the register
The TWS should be a General or trades Foreman, Engineer or Site Supervisor who:
Cont’ over:
Temporary Works Responsibilities
• Temporary Works Supervisor (TWS)
- Safety
This classification is on a basis of risk and assigns it with the level of design required.
The table on the following page is based on BS 5975:2008 and is broken down into four
categories 0-3:
The level of input into design, design checking, construction methods and controls is
relevant to the level of risk.
TW’s Categories of Design Checks
Category Scope Comment Independence of Checker
• HSE/LA Prosecution
Further information and guidance:
This presentation only provides some information on managing temporary works. Please
refer to the policy and procedure within CIMS or contact a member of the EHS
Department.