CLIENT PMC SUPERVISION CONSULTANT CONTRACTOR

YAS SOUTH DEVELOPMENT

Method Statement for Construction of Street Lighting Pole Pile


SUBJECT/TITLE : ORIGINATOR : HYDER
Foundation
DOCUMENT REF. NO : YSD-P01-0205-SL-HIL-MT-000005 REVISION NO. : Rev.02

Sl. Comments Response


No.
General
1 Please provide details of the pressure tremie hose as highlighted in Page 7 of 1.Concrete pouring shall be done in concrete
CLIENT PMC SUPERVISION CONSULTANT CONTRACTOR

YAS SOUTH DEVELOPMENT

Sl. Comments Response


No.
the MS Bucket attached with none pressure tremie
pipe
2 Please provide the reinforcement details of Stage 1 and Stage 2 together with 2. As Attached Approved Shop Drawing
the pile cut-off construction joint level.
3 The submitted schedule of works is incomplete as it only provides the duration. 3.The schedule shall be followed as per
Please provide the approximate dates and ensure that it matches with the revised baseline program submitted by
CLIENT PMC SUPERVISION CONSULTANT CONTRACTOR

YAS SOUTH DEVELOPMENT

Sl. Comments Response


No.
revised Baseline program submitted by Hilalco. HILALCO
4 In risk assessment - for the activity Mobilization; control measures for adverse Incorporated
Weather, manual lifting, and electrocution is not provided. Check the relevancy
of the identified risk and if it is applicable for the said activity, then provide the
adequate control measures.
5 For the activity- concreting using a concrete pump, proper set up of the Incorporated
CLIENT PMC SUPERVISION CONSULTANT CONTRACTOR

YAS SOUTH DEVELOPMENT

Sl. Comments Response


No.
concrete pump must be ensured to prevent possible overturning and
associated risks.
6 This Method Statement is explicitly applicable only for Stage 1 Pile foundation Incorporated
of the street light poles. An independent method statement must be issued for
the 2nd stage construction including but not limited to shuttering, formwork,
conduits, anchor bolts, anchor plates, etc.
CLIENT PMC SUPERVISION CONSULTANT CONTRACTOR

YAS SOUTH DEVELOPMENT

Sl. Comments Response


No.
7 The pile installation record must be properly documented, in accordance with Noted
the Specifications Requirements.