Weekly Progress Report

Project Name: Hlaine Tet Hotel Project Location: Kyaike Wine


Project Code: 6YG 039 00 Report Date : 2018.1.25 Thursday Report No. WPR-082
Proj Start Date 2016-6-22 Contract Period Calendar Day Period From
Estimate Completion Date Remain Period Calendar Day 2018.1.19 2018.1.25
Work Force Machine & Equipments onsite

Sr No Description 1 2 3 4 5 6 7 Total Sr No Description 1 2 3 4 5 6 7 Total

1 PM 1 Tank (4'x4'x4') 1 1 1 1 1 1 1 7
2 PE 1 1 1 1 1 1 1 7 2 165KVA Generator 1 1 1 1 1 1 1 7
3 SSE 3 Empty Drum 10 10 10 10 10 10 10 70
4 SE 1 1 - 1 1 1 1 6 4 High Speed Cutter(14") 1 1 1 1 1 1 1 7
5 QA/QC 5 7" Concrete Gun 1 1 1 1 1 1 1 7
6 QS 6 Air Blower 1 1 1 1 1 1 1 7
7 Admin 1 1 1 1 1 1 1 7 7 Submersible Pump 1 1 1 1 1 1 1 7
8 Safety
9 Site Store 1 1 1 1 1 1 1 7
10 Supervisor
11 M&E 1 1 1 1 1 1 1 7
12 Surveyer
13 Geotech
14 Mason - 12 7 10 10 10 10 59
15 Carpenter 2 2 - 5 2 2 2 15
16 Smith 2 2 - 2 2 2 2 12
Wateproof
17 - - - 2 - 5 3 10
workers
18 Welder 2 3 3 - 2 3 3 16
Alu; Curtain
19 32 33 34 31 33 31 33 227
Installer
Roofing
20
worker
Painter(Exter
21 4 3 - 5 5 10 8 35
&Stair)
22 Worker 16 17 9 16 19 18 18 113

Total 63 77 57 76 78 86 84 521 Total 16 16 16 16 16 16 16 112


Progress Detail
Description Previous This Wk Ccmmulative Description Previous This Wk Ccmmulative
Foundation % % % 4th Floor
Main Building 100 0 100 Brick Work 100 0 100
Plastering Work 99 0 99
Sub-structure Topping Work (Not include Bath & W/C) 85 0 85
Main Building 100 0 100
5th Floor
Super Structure Brick Work 99 1 100
Main Building Work 100 0 100 Plastering Work 99 0 99
Concrete Work ( Stairs 1 & 2) 100 0 100

Architectural work 6th Floor


Ground Floor Brick Work 100 0 100
Brick Work 99 0 99 Plastering Work 99 0 99
Plastering Work 91 2 93 Topping Work 85 5 90

Mezzanine Floor 7th Floor


Brick Work 97 0 97 Brick Work 100 0 100
Plastering Work 90 5 95 Plastering Work 99 0 99
Topping Work 85 5 90
1st Floor
Brick Work 100 0 100 Penthouse Floor
Plastering Work 99 0 99 Brick Work 95 2 97
Topping Work 85 0 85 Plastering Work 80 10 90

FO-PM-04 REV-01 Page: 1/2


2nd Floor
Brick Work 100 0 100 Lower Roof
Plastering Work 99 0 99 Brick Work 80 10 90
Plastering Work 40 40 80
3rd Floor
Brick Work 100 0 100
Plastering Work 99 0 99
Topping Work (Not include Bath & W/C) 85 0 85 Total Overall Progress 95.16%

This Week Activities


Trades Of Work Location Remark
1 Brick Laying Work & Concrete Casting for Glass Wall Penthouse
2 Plastering Work Liftpit Areas(External corner ) & Penthouse & Lower Roof
3 Additional Handrail Installation at Front Stair Level-1 to Lower Roof Start Date-21.12.2017
4 Rebar Production & Installation for Stiffner Columns,Beams & Septic Tank Ground Floor, Lower Roof & Penthouse
5 Topping Casting in Bath & W/C & Front Stair Leve-7 to Level-5
6 Aluminium Curtain Panels, Flexy Board,Terracotta Panel & Glass Installation GF to Lower Roof Start Date-9.9.2017
7 Water Proofing Work in Bath & W/C Level-4 & 3 Start Date-26.12.2017
8 External Putty Work Level-1 to Penthouse Start Date-12.12.2017
9 Excavation Work for Septic Tank Ground Floor Start Date-12.1.2018
Plan For Next Week
Trades Of Work Location Remark
1 Excavation Work for Septic Tank Ground Floor
3 Plastering Work between Door Frame Level-6 to Level-2
4 Steel Frame Installation for ACOD & Main Entrance Ground Floor & Mezzanine Floor
5 Rebar Production & Installation for Septic Tank GF to Lower Roof
6 Topping Work for Front Stair & Remaining Rooms (Bath & W/C, M&E ) Leve-1 to Lower Roof
7 Aluminium Curtain Panels, Flexy Board, Louver Wall & Glass Installation GF to Lower Roof
8 Water Proofing Work in Bath & W/C Level-4,3
9 External Putty Work Level-1 to Penthouse
SI/VO/NCR
Status Status
No. of SI Issue for previous No of VO previous NCR previous
No. of SI Issue for this week No of VO this week NCR this week
Total SI up to this week No of VO up to this wk NCR up to this wk
Project Manager Project Engineer Prepare By: Site Engineer Sign
Name Sign Nyo Aung Sign Ohm Mar Htay
PROGRESS PHOTOS Preriod From: 2018.1.19 To: 2018.1.25

Photo 1 Photo 2
`

Concrete Casting for Glass Wall at Penthouse Floor Glass Installation

Topping Casting at Front Stair Excavation Work for Bio Tank

FO-PM-04 REV-01 Page: 2/2