URBAN IMPROVEMENTS & PILGRIM FACILITIES AT MATHURA

UTILISING CSR FUNDS


UTTAR PRADESH BRAJ TIRTH VIKAS PARISHAD

IMPLEMENTATION
(IN Rs. CRORE)
KEY FEATURES

(IN MONTHS)
PROJECT

PERIOD
COST
SNO

1 Solid waste Management -  Door to door waste collection Rs. 95.72 Lac Collection to
Mathura  Waste collection along the per month commence
Parikrama Marg including immediately
 Segregation and compaction operations and Infrastructure to be
of waste capital cost completed in 18
 Transportation to disposal site recovery over 7 months.
 Waste processing Plant years.

2 City Gateway on the Yamuna  The proposal involves Rs 48 crores 18-24 months from
Expressway Interchange installation of two 50 m high including Rs 19.5 date of
bronze sculptures (of Lord Shri crore for each commencement
Krishna or of Shri Krishna and sculpture and
Balram on the interchange and civil/landscape
developing the landscape works
within the loops of the
interchange.
PROPOSED - AERIAL VIEW OF MATHURA INTERCHANGE – YAMUNA EXPRESSWAY
PROPOSED – ROADLEVEL VIEW LOOKING TOWARDS SCULPTURES-FROM 450M DISTANCE
PROPOSED – ROADLEVEL VIEW LOOKING TOWARDS SCULPTURES-FROM 150M DISTANCE
PROPOSED – ROADLEVEL VIEW LOOKING TOWARDS SCULPTURES-FROM 75M DISTANCE
PROPOSED – ROADLEVEL VIEW LOOKING TOWARDS SCULPTURES-FROM BELOW INTERCHANGE