Action Plan

Task Presumed Due Date Final Due Date Remarks

Deciding on Global July 1st July 1st


Context, Topic,
Goals, and Guiding
Questions

Prior Research August 3rd August 3rd Experiments

Practice on 3d August 31st August 31st Using different


illustration skills functions in the
software, and being
familiar with the
tools within the
software

Research for November 28th December 4th More research than


Criterion A 1st draft expected/Poor time
management

Complete Design November 30th December 4th Poor time


specification management

Hand in Criterion A December 15th December 14th


B first draft

Initial Designs and December 22nd December 22nd


drawings

Final Design December 24th December 24th

Start drawing December 27th December 27th


product using Rhino

Listing and buying January 3rd January 3rd


external parts for
model

Develop wind January 5th January 5th


turbine blades
shape in 3d
software

Complete and print January 14th January 22nd Adjustments are


out 3d model needed for my
product criteria in
order to initiate the
production of my
design
Criterion C/D first January 25th January 25th
draft

Final adjustments to February 2nd February 2nd - There were external


written reports -February 25th March 1st aspects of the
written report that
needs to be fixed
upon further
inspection

Final adjustments to February 2nd - February 2nd - The blades of the


product February 25th February 28th wind turbine had
fallen apart after 2
weeks, so further
reinforcement was
required