FOR
B + G + 5 MIXED USE BUILDING
SUMMERY
SUPPER STRUCTURE
1. CONCRETE WORKS Birr 382,948.56
2. BLOCK WORKS Birr 176,343.04
3. ROOFING Birr 31,490.00
4. ALUMINUM WORKS Birr 3,676,896.20
5. FINISHING WORKS Birr 2,961,803.74
6. GLAZING Birr 250,935.20
7. PAINTING Birr 199,727.74
8.SANITARY INSTALLATION Birr 247,107.78
9.ELECTRICAL INSTALLATION Birr 1,016,985.00
10. LIFT INSTALLATION Birr 1,802,371.52
2 35.587
1 47.29 3 141.87
141.87 m2
1 39.809 3 119.427
119.427 m2
1 39.809 3 119.427
238.854 m2
No Length
plasterin
int &ext
1 2495.52
-1 121.41
-1 367.15
No Length Hight Total Remark No
basment
floor finish
Ceramic
1 19.30 1 19.3 store 1
1 7.50 1 7.5 shope
6 6.50 1 39 shope
1 9.00 1 9 shope
Total sum 74.80 m2
3 139.35
Total sum 139.35 m2
3 171.39
3 243.138 lift shaft
0.6 -4.887 window
1.5 62.1
Total sum 471.74 m2
3 138.222
2.45 25.48 window
2.45 -7.35 window
2.2 -3.96 Door
3 259.182
2.2 -15.84 Door
0.6 -2.4 window
0.6 -3.156 window
390.178 m2
3 213.522
213.522 m2
3 283.74
283.74 m2
3 238.854
238.854 m2
3 238.854
477.708 m2
98.035 1 98.035
196.07 ml
169.576 1 169.576
339.152 ml
Length Hight Total Remark
first
skirting
38.163 1 38.163
147.892 1 147.892
372.11 ml
38.163 1 38.163
147.892 1 147.892
372.11 ml
for 2nd, 4th,5th floor, 1116.33 ml
Length Hight Total Remark
third floor
skirting
65.46 1 65.46
65.46 ml
Remark
stering
ing
basement
ground
first
2nd & 4th
3rd
m2
SUB - STRUCTURE
No of
Drg.No Location Ref No Dia Length No of bar member Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia20
form work
No of
Drg.No Location Ref No Dia Length No of bar member Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia20
0.00
Total Length #REF! 1,165.82 #REF! #REF! 1,065.60 266.40
Unit Wt.(kg/mL) 0.222 0.395 0.62 0.89 1.21 1.58 2.47
Total Weight 0 #REF! 719.31 #REF! #REF! 1,682.58 657.21
No of
Drg.No Location Ref No Dia Length No of bar member Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia20
37.75 37.75 37.75
concrete work
0
3.552
0
Dia24
Dia24
0
3.552
0
No Length Hight Total Remark
all floor
hand rail
No Length Hight
No Length Hight Total Remark all floor
all floor Aluminum cladding
roofing alumimum partition
1 230.1 1 230.1 1 112.33 1
230.1 m2 1 80.62 1
1 90.6 1
No Length Hight Total Remark 1 83.6 1
all floor
for curtain wall
glazing
1 111.2 1 111.2 right elevation
1 71.2 1 71.2 rare elevation
1 173.1 1 173.1 front elevation
355.5 m2
Total Remark
all floor
lintel
5.1 W-1
20.4 W-2
4.3 W-3
17.2 W-4
7.3 W-5
1.46 W-6
8 W-7
7.2 W-8
18.41 W-9
12 W-10
1 W-11
13.2 W-12
115.57 ml
Total Remark
all floor
lintel
24.3 D-1
2 D-2
1.8 D-3
28.1 ml
Total Remark
all floor
Aluminum work
lumimum partition
132.81 ground
163.275 first floor
489.825 2nd,4th&5th
29.25 3rd floor
815.16 m2
Total Remark
all floor
luminum cladding
lumimum partition
112.33 right elevation
80.62 rare elevation
90.6 front elevation
83.6 left elevation
367.15 m2
Item
No. Description Unit Qty. Rate
1. CONCRETE WORKS
Reinforced concrete in C-25, using 360kg
cement/m³ for OPC as per mix design
1.1 instruction , filled into formworks and
vibrated around rod reinforcement. Steel
and formworks measured separately.
a) Elevation Column m³ 3.6855 2500
b) floor beam m³ 6.096 2500
c) 180mm slab m2 82.08 2500
Provide, cut and fix in position sawn zigba
1.2 or steel or the combination of both
formworks to:-
a) Elevation Column m2 49.14 210
b) roof beam m 2
55.88 210
c) 180mm slab m2 82.08 210
fyk = 400mpa, Steel reinforcement
according to drawing. Price includes
1.3
cutting, bending, placing in position and
tying wires.
a) Dia. 8mm. deformed bar. kg 278.633 37.75
b) Dia. 10mm. ditto. kg 1620.168 37.75
c) Dia. 12mm. ditto. kg 0 37.75
c) Dia. 14mm. ditto. kg 100.9757 37.75
d) Dia. 16mm. ditto. kg 1020.192 37.75
3. ROOFING
3.1 Roof cover in G-30 CIS fixed to zigba
purlin with dome headed galvanized nail
and washers. Purlin at c/c 90 cm
measured separetly and roof cover
measured in horizontal projection.
m² 134.00 235.00
TOTAL CARRIED TO SUMMARY ...................................................
4. ALUMINUM WORKS
Doors & Windows are manufactured from
best quality 1.8mm thick wooden color
Aluminum profile, as per the consultant
approval and window door schedule. Unit
price shall include door stopper, 5mm thick
tinted glazing, hinges, best quality ASSA -
ABLOY or equivalent lock with handle, and
all other necessary accessories.
4.1 WINDOW
a) Type -W1 Window size 510 x 200cm pcs 1.00 24480.00
b) Type-W2 Window size 510 x 270cm pcs 4.00 33048.00
c) Type -W3 window size 430 x200cm pcs 1.00 20640.00
d) Type -W4 window size 430x 270cm pcs 12.00 27864.00
e) Type-W5 window size 146x 300cm pcs 5.00 10512.00
f) Type -W6 window size 146x 200cm pcs 1.00 7008.00
g) Type -W7 window size 200x 150cm pcs 4.00 7200.00
h) Type -W8 window size 120x 300cm pcs 6.00 8640.00
i) Type -W9 window size 263x 80cm pcs 7.00 5049.60
j) Type -W10 window size 100x 300cm pcs 12.00 7200.00
k) Type -W11 window size 100x 60cm pcs 1.00 1440.00
l) Type -W12 window size 1320x 80cm pcs 1.00 25344.00
4.2 DOOR
a) Type -D1 Door size 90x 220cm pcs 27.00 4752.00
a) Type -D2 Door size 200x 250cm pcs 1.00 12000.00
a) Type -D3 Door size 180x 220cm pcs 1.00 9504.00
1218.30 650
5.5 Supply and lay Marble tile flooring. The m²
pattern of the tile and the entire work shall
be approved by the engineer. Price shall
include cement mortar (1:3) bed and
grouting. 6.70 1100.00
5.6 Supply and lay 8x80 mm heavy duty ml
ceramic skirting. Price shall include mortar
backing. 972.79 230.00
5.7 supply and fix C-20 lintel. Price shall ml
include formwork and reinforcement.
143.67 360.00
5.8 supply and fix marble trushold for doors ml
28.10 600.00
5.9 Supply and fix marble window cill ml 115.57 600.00
5.1 Granite slab steps thread & riser
bedded in cement mortar 1:3
a) Thread, ml 153.00 600.00
b) Riser, ml 153.00 600.00
c) landing m² 28.38 1100.00
5.11 Marble slab steps thread & riser bedded
in cement mortar 1:3
a) Thread, ml 29.40 700.00
b) Riser, ml 29.40 700.00
5.12 Supply and construct 10cm thick Gypsum m²
board wall partition for Internal walls .
676.59 1400.00
6. GLAZING
6.10
Supply and fix 4 mm thick clear glass.
Price shall include approved quality putty.
m² 271.84 400.00
6.20
Supply and fix 5 mm thick flamed glass for
curtain walls. Price shall include approved
quality putty.
m² 355.50 400.00
TOTAL CARRIED TO SUMMARY ...................................................
7. PAINTING
7.10 Apply three coats of plastic emulsion paint m²
to internal and external walls plastered wall
surface.
2,006.96 40.00
7.20 Ditto but to RC ceiling and soffits of m²
stair case 1,294.77 40.00
7.30 Ditto but to gypsum board m² 1,353.17 50.00
TOTAL CARRIED TO SUMMARY ...................................................
8.SANITARY INSTALLATION
11.1.1 Supply & install Polypropelene, PP-R
Pipes and Fittings, PN 20, for cold and
hot water distribtion to all sanitary
fixures according to the drawing
complete with the necessary pieces
such as tees, bends, unions, etc. The
unit price shall include all necessary
assistance to the installation works
such as supports for horizontal and
vertical pipes, chiseling of walls, slabs,
beams, floors, etc. and closing them
with concrete or cement mortar to
normal condition. The installation shall
be tested at a pressure of 10 kg/scm
at the expense of the contractor.
Diameter 20 mm m.l 102.00 85.00
11.1.2 Supply & fix Gate Valves on PP-R Pipe
lines
complete with PP- union, CP brass head /
hand wheel.
Diameter 20 mm No. 32.00 135.00
11.2.0 Supply and fix the following fixtures
according to detail drawing.All fixtures
which differs from that specified below is
subject to the owner's approval, based on
samples, catalogues and brochures
presented by the contractor....Unit Price
shall include all the necessary fixing
brackets or hooks and all assistance civil
works such as chiseling of walls, floors,
beams etc.
11.2.1 a) Hand wash basins( oval shape double
bowl)
i) Type : RAK
Model :
Approximate size : In the Catalogue
Colour : As per the Architect's
preference
Or Equivalent approved by the engineer No 12.00 4,800.00
11.2.2 Ditto item No 1.1 above but with single No
bowl 6.00 3,200.00
11.2.3 Supply and fix wash down water closets
made of white vitreous china with plastic
seat and cover including low flush cistern
Complete with all necessary accessories..
i) Type : RAK
Approximate size : In the Catalogue
Colour : As per the Architect's
preference
Or Equivalent approved by the engineer No 12.00 3,900.00
11.2.4 Supply and fix toilet paper holder made of No
white vitreous china with necessary
accessories. 12.00 180.00
11.2.5 Supply and fix crystal glass mirrors No
with copper back protection, size 500/400
mm including chrome plated brass mirror
clips with chrome plated screws . Price
shall also include approved quality shelves.
12.00 480.00
1.2.11 Supply and fix stainless steel sink with No
double bowl as where shown on the
drawing. Complete with chrome plated
chain, plug, chrome plated faucet, P-smell
trap and with all necessary accessories.
1.00 4,200.00
1.2.13 Supply and fix floorSize:-
gully 1500 x 600 mm
of approved No
quality, complete with P-smell trap and all
other necessary fittings & accessories. 13.00 690.00
9. ELECTRICAL INSTALLATION
4 Distribution Boards
4.10 Flush mounting distribution Board, MLPP-
B with lockable door and including bus
bars of 25Amp/1Phase, all necessary fixing
and connecting accessories, complete and
consisting:-
3 pc 16A, MCB, 1 Phase
4 pc 10A, MCB, 1 Phase No 1.00 4,500.00
CABLES
5.10 3x35/16+1x16mm sq. m 100.00 750.00
6 Light Points
NOTE
cost estimation,
III. The price of all fittings under this item
to be
EXCLUDED in the contract agreement.
10 PASSENGER LIFT
A 480KG, 6persons Traction Passenger lift,
type OTIS, SCHNDLER, or equivalent, and
subject to the engineers/consultants
approval, custom made for the shaft size
approved by the architect. including all
structural (construction of shear
walls),mechanical and electrical accessories
to be supplied, erected and commissioned
by a nominated sub-contractor, with the
following minimum requirements
Stops:- 7
Operation:-full collective/duplex control
Entrance:-one side
Speed:-1.0m/s
Travel distance:- 21m
Power Supply:-380/221,50HZ
Drive:-VVVF variable voltage and
variable frequency control drive )
Cabin material:-wall,car and landing door
all stainless steel.
Floor cover:-lined with wear resistance
PVC,floor to floor height 3.2m
Lighting:-indirect fluorescent ligting
EMergency light:-battery operated
Car/Landing doors:- automatic telescopic
Power room:- at the top floor
Cabine display:-digital car position and
direction indicators
Over load indicators,light
and buzzer
Wait/Stop push button
Alarm button
Key out of service
Fan switch
Communication:-Interphone/Intercome
Bell push button for
EMergency
Arrival gong
Hand rail:-3sides surface
mirror:-3sides/half
Counter weight:-As per standard
Outer Displays:-Digital number car postion
and direction indicators all floors call panel
up and down
Ventilation:-Natural grill and fan
Guide rail:-Steel profile according to the
standard.
Wire Protection:- According to the
standard.
EMergency device:-Automatic emergency
rescue device when power fails included
wth approved type battery.
Price includes all scaffolding,painting and
other civil works.
Lift machine room provided
Power panel with all controls
Heat resistnt Power cables
Light points
Socket outlets
Shaft light
Provide approved lift shaft lighting with
control switch in machine room, as shown
on the drawing
Pit Socket
Provide one twin socket outlet connected to
16A/1ph /Icu=6KA,branch circuit
supplying no other socket outlet inside the
pit.(EBCS-10,1995 section 21.14.2.4)
To control the lift for upward and
downward movEMet
Counter weight option=Sefty gear on
counter LS 1 1,802,371.52
NOTE:- Regardless of provided
architectural, and associated civil works
shaft design, the cotractor should take, and
verify all the necessary measurement on
site before commencEMent of passanger lift
erection.
TOTAL CARRIED TO SUMMARY ...................................................
Amount
9213.75
15240
205200
10319.4
11734.8
17236.8
10518.39575
61161.34049
0
3811.83192
38512.244225
382,948.56
127,034.40
49,308.64
176,343.04
31,490.00
31,490.00
24,480.00
132,192.00
20,640.00
334,368.00
52,560.00
7,008.00
28,800.00
51,840.00
35,347.20
86,400.00
1,440.00
25,344.00
128,304.00
12,000.00
9,504.00
-
624,155.00
2,037,900.00
64,614.00
3,676,896.20
270,939.06
63,685.04
143,272.80
16,390.35
60,892.83
42,493.50
791,895.00
7,370.00
223,742.16
51,721.20
16,860.00
69,342.00
91,800.00
91,800.00
31,218.00
20,580.00
20,580.00
947,221.80
2,961,803.74
108,735.20
142,200.00
250,935.20
80,278.24
51,790.80
67,658.70
199,727.74
8,670.00
4,320.00
57,600.00
19,200.00
46,800.00
2,160.00
5,760.00
4,200.00
8,970.00
500.00
4,248.00
2,500.00
3,120.00
9,302.40
1,440.00
7,000.00
15,000.00
250.00
630.00
210.00
680.00
680.00
680.00
1,323.00
1,350.00
1,350.00
3,322.00
2,714.63
288.00
3,220.00
3,220.00
350.00
3,359.75
1,890.00
19,200.00
1,600.00
247,107.78
10,000.00
4,500.00
10,000.00
2,500.00
63,000.00
25,000.00
4,500.00
6,000.00
26,000.00
5,000.00
75,000.00
75,000.00
6,250.00
9,500.00
148,000.00
11,475.00
310.00
3,600.00
1,500.00
126,000.00
1,800.00
31,500.00
2,550.00
54,000.00
18,000.00
296,000.00
1,016,985.00
1,802,371.52
1,802,371.52
sanitary