Time Line for Implementing Bio-Incubator Project

2012 2013 2014 2015


Task Name Duration Start Finish
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8

Submit Proposal to BIRAC-DBT 90 days 03.03.12 15.06.12


Site Selection 22 days 06.07.12 31.07.12
Building plan design 60 days 01.08.12 09.10.12
Statutary Clearances 120 days 10.10.12 26.02.13
Building Construction 300 days 12.04.13 27.03.14
Market/Advertise 10 days 08.05.14 18.05.14
Dev Operating plan 60 days 27.02.14 07.05.14
Aquire Equipment and Furniture 90 days 26.04.14 08.08.14
Management Team in place 15 days 08.05.14 24.05.15
Admission Committee Established] 15 days 09.08.14 26.08.14
Recuittenants 45 days 27.08.14 17.10.14
Develop Training Program 60 days 27.08.14 04.10.14
Investment fund formation 92 days 27.08.14 11.12.14
Accept Application 5 days 05.11.14 10.11.14
Due dilligence 30 days 12.12.14 15.01.15
First round of Investments 45 days 16.01.15 09.03.15
Make working Capita; Fund Loan 30 days 10.03.15 13.04.15
Raise working capital Funds 30 days 14.04.15 18.05.15
Admit tenant Bt companies 10 days 19.05.15 29.05.15
Business Skill Assess 5 days 30.05.15 04.06.15
Deliver Business Skill Training 15 days 05.06.15 22.06.15
Manager Traing/audit/Follow-up 15 days 23.06.15 09.07.15