HARADH GAS INCREMENT PROGRAM

80040 / 10130
CIVIL WORK SUBCONTRACT
OVERALL SCOPE OF WORKS

SCOPE OF WORKS: Works to be quoted include the following activities:

MAIN TASKS:

- Site preparation and fencing


- Excavation and backfillings
- In situ concrete foundations, pits and manholes
- Underground systems
- Paving and roads
- As Built drawings and Quality Dossiers

OPTIONAL TASKS
- Precast concrete foundations, channels and manholes
- Asphalts
- Construction of access roads
- Supply and installation of site fences

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 2


CIVIL WORK SUBCONTRACT
OVERALL SCOPE OF WORKS

SCOPE OF WORKS: Works to be quoted involve the Civil Works for the construction
of:

A) 9 Gas Compression Plants (GCP)


B) 6 Liquid Separation Stations (LSS)
C) 2 Administrative Areas (Operation and Maintenance Areas – O&M-CMX)

General Overviews of GCP (left) and LSS (right) typical arrangement.

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 3


CIVIL WORK SUBCONTRACT
OVERALL SCOPE OF WORKS

SCOPE OF WORKS: Works are to be executed in the following seventeen (17) Locations
Type of Process
Location No. UNIT No. UNIT DESCRIPTION
Unit
1 HWGCP-1 Hawiyah Gas Compression Plant (Unit 510)
2 HDGCP-1 Haradh Gas Compression Plant (Unit 521)
3 HDGCP-2 Haradh Gas Compression Plant (Unit 522)
Gas
4 HDGCP-4 Harah GCP-4 (Unit 523)
Compression
5 Plants GZGCP-1 Ghazak GCP-1 (Unit 526)
6 (GCP’s) WQGCP-1 Waqr GCP-1 (Unit 529)
7 HDGCP-3 Haradh Gas Compression Plant (Unit 522)
8 MDGCP-1 Midrikah Gas Compression Plant (Unit 527)
9 TNGCP-1 Tinat Gas Compression Plant (Unit 528)
10 HWYH LSS Hawiyah Liquid Separation Plant
11 SAHB Sahba LSS (Unit 533)
Liquid
12 MNJR Manjurah LSS (Unit 533)
Separation
13 Stations SHDN Shaden LSS (Unit 533)
14 (LSS’s) ZMLH Zimlah LSS (Unit 533)
15 JUFN-LSS Jufayn Liquid Separation Plant JUFN-LSS
16 Administrative OSB&CMB North Haradh Administrative Area
17 Areas OSB&CME South Haradh Administrative Area

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 4


CIVIL WORK SUBCONTRACT
OVERALL SCOPE OF WORKS

LOCATIONS: The locations are spread over an approx. 150 km x 120 km area.
GPs GCPs LSSs OSB&CMB

So yah LSS

dh
w FN-

ra
HB SS
GC 1

DN S

YN S
LH S
GC 1

QG 1

NJ S
HW P-3

M P-4

HD P-1
TN P-2

Ha
HD P-1

HW P-1

SH -LS

JF -LS
ZM -LS
HD CP-

HD CP-
W CP-

M -LS
SA H-L

Ha /JU
R

h
GC

GC
GP

GC
GC

DG

i
Y

ut
P
HD

GZ
Hd
HDP - 133 236 119 20 138 163 185 77 102 176 42 171 196 204 221 149 66 127
GPs

HdGP 133 - 146 22 127 49 74 95 74 41 50 131 82 107 114 133 23 68 10


GZGCP-1 236 146 - 129 226 148 173 68 172 141 188 229 85 96 77 232 163 167 138
HDGCP-3 119 22 129 - 109 32 57 78 55 25 65 113 65 90 97 115 39 50 12
HWGCP-1 20 127 226 109 - 128 153 175 67 92 170 30 161 186 194 211 144 62 117
HDGCP-4 138 49 148 32 128 - 26 97 74 43 69 131 84 109 116 85 64 69 39
GCPs

MDGCP-1 163 74 173 57 153 26 - 122 99 68 44 156 109 134 141 76 83 94 65


WQGCP-1 185 95 68 78 175 97 122 - 121 90 137 178 30 63 32 181 112 116 87
HDGCP-1 77 74 172 55 67 74 99 121 - 38 117 71 107 132 140 157 90 5 63
HDGCP-2 102 41 141 25 92 43 68 90 38 - 85 95 77 101 109 127 58 33 32
TNGCP-1 176 50 188 65 170 69 44 137 117 85 - 174 124 149 156 120 44 112 53
HWYH-LSS 42 131 229 113 30 131 156 178 71 95 174 - 165 190 197 215 147 66 121
SAHB-LSS 171 82 85 65 161 84 109 30 107 77 124 165 - 49 49 167 98 102 73
MNJR-LSS 196 107 96 90 186 109 134 63 132 101 149 190 49 - 81 192 123 127 98
LSSs

SHDN-LSS 204 114 77 97 194 116 141 32 140 109 156 197 49 81 - 200 131 135 106
ZMLH-LSS 221 133 232 115 211 85 76 181 157 127 120 215 167 192 200 - 159 152 123
JFYN/JUFN-LSS 149 23 163 39 144 64 83 112 90 58 44 147 98 123 131 159 - 85 26
Hawiyah 66 68 167 50 62 69 94 116 5 33 112 66 102 127 135 152 85 - 58
OSB
&

South Haradh 127 10 138 12 117 39 65 87 63 32 53 121 73 98 106 123 26 58 -

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 5


CIVIL WORK SUBCONTRACT
WAY OF QUOTING

LOCATIONS: SUBCONTRACTOR shall price each of the locations as a stand-alone proposal


according to the structure of BOQs provided by CONTRACTOR as each Process Unit could be
awarded to a different SUBCONTRACTOR.

HWGCP-1
HWYH-LSS
OSB&CMB
HDGCP-1
HDGCP-2
MNJR-LSS
HDGCP-3
SAHB-LSS OSB&CMB

WQGCP-1
JUFN-LSS
GZGCP-1
TNGCP-1
SHDN-LSS HDGCP-4
MDGCP-1

ZMLH-LSS

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 6


CIVIL WORK SUBCONTRACT
WAY OF QUOTING

DIRECT UNIT RATES: Unit Rates shall represent only the Direct Cost per
Work Unit, which shall be quoted in Unit Rates sheet of BOQ.
Direct Unit Rate shall be the same for each of the Work Unit independently of the
quantity and the location of each plant.

INDIRECT COST AMOUNT: for each location, related Indirect Costs shall be
quoted as a Lump Sum in dedicated Indirect Cost Sheet of BOQ, where all
considerations of each location shall be taken into account.

DISCOUNTS FOR COMBINATION OF PLANTS: BIDDER is also


requested to provide potential discounts of Direct & Indirect Costs considering a
potential awarding of more than one (1) location. Discounts for aggregated
scopes shall be quoted as requested in Possible Combination of Locations Sheet
of BOQ.

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 7


CIVIL WORK SUBCONTRACT
WAY OF QUOTING

DISCOUNTS FOR COMBINATIONS: SUBCONTRACTOR will find below table in BOQ


which shall fill with the % of discount associated to proposed combinations.
GSCPs LSSs OSBs

NH OSB & CMB


SH OSB & CMB
DIRECT &

HWYH-LSS
HWGCP-1

WQGCP-1

MNJR-LSS
MDGCP-1

SHDN-LSS
ZMLH-LSS
SAHB-LSS

JUFN-LSS
HDGCP-3

HDGCP-4

HDGCP-1
HDGCP-2
GZGCP-1

TNGCP-1
INDIRECT
REMARKS
COST %
DISCOUNT

Scenario 1 x x x x x Pack. 1
Scenario 2 x x x x Pack.1 without Admin Area
Scenario 3 x x x x Pack 1. without LSS
Scenario 4 x x Pack. only LSS & Admin Area
Scenario 5 x x x Pack.1 only GCPs
Scenario 6 x x x x x x x Pack. 2
Scenario 7 x x x Pack.2 only GCPs
Scenario 8 x x x x Pack. without LSS
Scenario 9 x x x x x Pack. 3
Scenario 10 x x x x Pack.3 without Admin Area
Scenario 11 x x x x Pack 3. without LSS
Scenario 12 x x Pack. without LSS & Admin Area
Scenario 13 x x x Pack.3 only GCPs
Scenario 14 x x x x x x North Zone 1
Scenario 15 x x x x North Zone 2
Scenario 16 x x x x x x x x West Zone 1
Scenario 17 x x x x x x x West Zone 2
Scenario 18 x x x x x x South Zone
Scenario 19 x x x x x x East Zone
Scenario 20 x x All Admin. Areas
Scenario 21 TO BE PROPOSED BY BIDDER
Scenario 22 …
SUBCONTRACTOR shall propose other discounts by doing his own
combinations of plants.
HARADH AND HAWIYAH GAS COMPRESSION PROJECT 8
CIVIL WORK SUBCONTRACT
SAMPLE OF ADMINISTRATION AREA

0 Topographical study including benchmarks (by others) NOTE: Feed civil foundations layout for
Administration Area is not available. To
1 Fence (Early Works) be checked when applicable.
NOTE: Fence foundations should be
precast.

1’ Roads (Early Works) (1)

2 Administration and Central


Maintenance Buildings (2)

3 Water and Storage Tanks (2)

4 Auxiliary Buildings,
Shelters, Gasoline
Station, Skids and
Equipment
foundations (2)

5 Parking areas,
remaining
foundations and
underground
system.

(1) Only soil preparation. Asphaltic concrete works will be made later on.
(2) Including underground around these areas.

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 9


CIVIL WORK SUBCONTRACT
SAMPLE OF GCP PLANT

3D Model View

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 10


CIVIL WORK SUBCONTRACT
SAMPLE OF GCP PLANT

0 Topographical study including benchmarks (by others)

1 Fence (Early Works)

1’ Outer road (Early Works) (1)

2 Inner roads (Early Works) (1)

3 Substations and Central Control Room


Including underground
around this area.

3’ Racks, water tanks and


ponds
Including underground
around this area.

3’’ Compressors
foundations
Including
underground
around these
areas.

4 Secondary Rack
Including underground
around this area.

5 Remaining foundations
and underground
system.

(1) Only soil preparation. Asphaltic concrete works will be made later on.

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 11


CIVIL WORK SUBCONTRACT
SAMPLE OF LSS PLANT

3D Model View

HARADH AND HAWIYAH GAS COMPRESSION PROJECT 12


CIVIL WORK SUBCONTRACT
SAMPLE OF LSS PLANT

0 Topographical study including benchmarks (by others)

1 Fence (Early Works)


NOTE: Fence foundations should be
precast.

1’ Outer road and accesses to LSS


(Early Works) (1)

2 Rack and drain holding tank pit


Including underground around this area.

3 RTU building and shelters


Including underground around this area.

4 Skids and equipment foundations


Including underground around these areas.

5 Remaining foundations and underground


system.

(1) Only soil preparation. Asphaltic concrete works will be made later on.