DURACION DE ACTIVIDADES MO

OBRA : “CONSTRUCCIÓN DE LOCAL PARA EL COMEDOR ESTUDIANTIL ACCHA-PARURO-CUSCO”

UBICACION : CUSCO - PARURO


ENTIDAD : MUNICIPALIDAD DISTRITAL DE ACCHA
PRESUPUESTO DE OBRA: S/. 510,457.24
FECHA PPTO
FECHA DE INICIO DE OBRA 11/1/2014
FECHA DE CONCLUSION DE OBRA 3/30/2015

PRECEDENCI UNID. DE UNID. DE DURACION


N° CODIGO DESCRIPCION SIMBOLO METRADO REND. DURACION
A MEDIDA MEDIDA REDONDEADA

01 OBRAS PROVISIONALES
1 01.01 Cartel de Identificacion de Obra A - 1.00 und 1.00 1.00 1.00
2 01.02 Cerco provisional con arpillera B D 46.20 m 25.00 m/DIA 1.90 2.00
02 TRABAJOS PRELIMINARES
3 02.01 Demolición de Construcción Existente C A 181.41 m2 10.00 m2/dia 18.20 19.00
4 02.02 Eliminación de Material Excedente D C 306.49 m3 250.00 m3/dia 1.30 2.00
03 MOVIMIENTO DE TIERRAS -
5 03.01 Trazo , Nivelación del Terreno y Apisonado E B 181.41 m2 45.00 m2/dia 4.10 5.00
03.02 Excavaciones -
6 03.02.01 Excavacion de Zanjas F E 193.88 m3 3.00 64.70 65.00
03.02.04 Relleno y compactado con material de 72.31 m3 2.90
7 L 25.00 3.00
prestamo con equipo I m3/dia
8 03.02.05 Eliminación de Material Exedente II I 229.25 m3 5.00 m3/dia 45.90 46.00
04 OBRAS DE CONCRETO SIMPLE -
04.01 Solado -
9 04.01.01 Solado para Vigas de conexion J F 5.04 m2 70.00 m2/dia 0.10 1.00
10 04.01.02 Solado para Zapatas K F 106.00 m2 70.00 m2/dia 1.60 2.00
04.02 Cimientos -
11 04.02.01 Concreto en Cimientos Corridos (1:10+30% L U, P 25.70 m3 12.00 m3/dia 2.20 3.00
04.03 P.G.)
Sobrecimientos -
12 04.03.01 Concreto 1:8+25% P.M. para Sobrecimientos M N 4.76 m3 10.00 m3/dia 0.50 1.00
13 04.03.02 Encofrado (Sobrecimientos) N L 43.78 m2 10.00 m2/dia 4.40 5.00
14 04.03.03 Desencofrado (Sobrecimientos) O M 10.95 m2 10.00 m2/dia 1.10 2.00
05 OBRAS DE CONCRETO ARMADO -
05.01 Vigas de Conexion -
15 05.01.01 Concreto f'c= 210 Kg/cm2, Viga Cimentación P R 3.23 m3 12.00 m3/dia 0.30 1.00
Armado de Acero Corrugado f'y= 4200
16 05.01.02 Q CA 5,104.47 kg 120.00 42.60 43.00
Kg/cm2 (Viga Cimentación - Muro Reforzado)
17 05.01.03 Colocado de Acero Corrugado f'y= 4200 R J,Q 1,276.12 kg 120.00 10.70 11.00
05.02 Kg/cm2
Zapatas(Viga Cimentación- Muro Reforzado) -
05.02.01 Armado de Acero Corrugado f'y= 4200
18 S Q 938.40 kg 120.00 kg/dia 7.90 8.00
Kg/cm2 (Zapatas)
05.02.02 Colocado de Acero Corrugado f'y= 4200
19 T K, S 234.60 kg 120.00 2.00 2.00
Kg/cm2 (Zapatas)
20 05.02.03 Concreto f'c= 210 Kg/cm2, Zapatas U T 70.75 m3 12.00 m3/dia 5.90 6.00
05.03 Muro Reforzado -
21 05.03.01 Encofrado (Muros Reforzado) X P 47.04 m2 10.00 m2/dia 4.80 5.00
22 05.03.02 Desencofrado (Muros Reforzado) Y Z 11.76 m2 10.00 1.20 2.00
23 05.03.03 Concreto f'c= 210 Kg/cm2 (Muros Reforzado) Z X 7.35 m3 9.00 m3/dia 0.90 1.00
05.04 Columnas -
05.04.01 Armado de Acero Corrugado f'y= 4200
24 AA S 1,650.40 kg 120.00 kg/dia 13.80 14.00
Kg/cm2 (Columnas)
05.04.02 Colocado de Acero Corrugado f'y= 4200
25 AB AA, O 412.60 120.00 3.50 4.00
Kg/cm2 (Columnas)
26 05.04.03 Encofrado (Columnas) AC AB 86.50 m2 9.00 m2/dia 9.70 10.00
27 05.04.04 Desencofrado (Columnas) AD AE 21.62 9.00 2.50 3.00
28 05.04.05 Concreto f'c= 210 Kg/cm2 (Columnas) AE AC 10.22 m3 9.00 m3/dia 1.20 2.00
05.05 Vigas - Losa Aligerada -
05.05.01 Armado de Acero Corrugado f'y= 4200
29 AF AA 2,967.10 kg 120.00 m3/dia 24.80 25.00
Kg/cm2 (Vigas - Losa Aligerada)
Armado de Acero Corrugado f'y= 4200
2,042.40 120.00 kg/dia 17.10 18.00
Kg/cm2 (Vigas)
Armado de Acero Corrugado f'y= 4200
924.70 120.00 kg/dia 7.80 8.00
Kg/cm2 (Losa Aligerada)
05.05.02 Colocado de Acero Corrugado f'y= 4200
30 AG AH, AF 741.78 kg 120.00 6.20 7.00
Kg/cm2 (Vigas - Losa Aligerada)
31 05.05.03 Encofrado (Vigas - Losa Aligerada) AH AD 251.30 m2 9.00 m2/dia 28.00 28.00
32 05.05.04 Desencofrado (Vigas - Losa Aligerada) AI CL 62.82 m2 9.00 m2/dia 7.00 7.00
33 05.05.05 Concreto f'c= 210 Kg/cm2 (Vigas - Losa AJ BW 39.83 m3 9.50 m2/dia 4.20 5.00
05.07 Aligerada)
Escalera -
05.07.01 Armado de Acero Corrugado f'y= 4200
34 AP FM 600.80 kg 120.00 kg/dia 5.10 6.00
Kg/cm2 (Escalera)
05.07.02 Colocado de Acero Corrugado f'y= 4200
35 AQ AP, AR 150.20 120.00 1.30 2.00
Kg/cm2 (Escalera)
36 05.07.03 Encofrado (Escalera) AR AI 21.86 m2 7.00 m2/dia 3.20 4.00
37 05.07.04 Desencofrado (Escalera) AS AT 5.47 7.00 0.80 1.00
38 05.07.05 Concreto f'c= 210 Kg/cm2 (Escalera) AT AQ 8.33 m3 10.00 m3/dia 0.90 1.00
06 MUROS Y TABIQUES DE ALBAÑILERIA -
39 06.01 Muro de Bloqueta de 0.15x0.20x0.40 m AU AV 111.09 m2 7.50 m2/dia 14.90 15.00
40 06.02 Muro de Bloqueta de 0.20x0.20x0.40 m AV AI 172.79 m2 7.50 m2/dia 23.10 24.00
07 REVOQUES ENLUCIDOS Y MOLDURAS -
41 07.01 Tarrajeo Rayado Primario AW BB 30.08 m2 8.00 m2/dia 3.80 4.00
42 07.02 Tarrajeo en Muros Interiores y Exteriores C:A AX AW 483.35 m2 8.00 m2/dia 60.50 61.00
43 07.03 Tarrajeo de Columnas Inc. Aristas C:A AY AX 60.69 m2 8.00 m2/dia 7.60 8.00
44 07.04 Tarrajeo de Vigas Inc. Aristas C:A AZ AU 38.22 m2 8.00 m2/dia 4.80 5.00
45 07.05 Vestidura de Derrames BA AY 14.76 m2 8.00 m2/dia 1.90 2.00
08 CIELORRASOS -
46 08.01 Cielo Raso con Yeso BB AZ 194.71 m2 8.00 m2/dia 24.40 25.00
09 PISOS Y PAVIMENTOS -
47 09.01 Falso Piso Concreto E= 4" BC BA 205.12 m2 60.00 m2/dia 3.50 4.00
48 09.02 Contrapisos BD BC 205.12 m2 85.00 m2/dia 2.50 3.00
49 09.03 Piso de Cerámico Nacional (0.30x0.30 de BE BD 205.12 m2 8.00 m2/dia 25.70 26.00
50 09.04 Color)
Vereda de Circulación E= 4" BF BE 20.11 m2 30.00 m2/dia 0.70 1.00
10 CONTRAZOCALOS -
51 10.01 Contrazocalo de madera BG BF 150.18 m 20.00 m/dia 7.60 8.00
11 ZOCALOS -
52 11.01 Zocalo de Mayólica 0.20x0.20 Nacional BH BG 30.08 m2 6.00 m2/dia 5.10 6.00
12 REVESTIMIENTOS DE GRADAS Y -
53 12.01 ESCALERAS
Piso de Cerámico Nacional (0.30x0.30 de BI AS 34.97 m2 8.00 m2/dia 4.40 5.00
13 Color)
CARPINTERIA DE MADERA -
54 13.01 Puerta de Tablero Rebajado BJ BH 24.17 m2 2.00 m2/dia 12.10 13.00
14 CARPINTERIA METALICA -
55 14.01 Baranda Metálica Tub. Galv. Ø 1 1/2" BK BI 79.92 m 8.00 m/dia 10.00 10.00
15 CERRAJERIA -
56 15.01 Bisagra y Chapa de Seguridad BL BJ 40.00 Jgo 7.50 m2/dia 5.40 6.00
16 VIDRIOS Y CRISTALES -
57 16.01 Vidrios Templado 6mm. BM BP, BN 220.00 P2 45.00 p2/dia 4.90 5.00
17 PINTURA -
58 17.01 Pintura en muros, columnas, vigas y BN BA 563.78 m2 33.50 m2/dia 16.90 17.00
17.02 derrames
Pintura en Cielo Rasos con Mezcla (Interiores
59 BO BB 194.71 m2 33.00 m2/dia 6.00 6.00
y Exteriores)
60 17.03 Pintura en Puertas BP BJ 48.31 m2 25.00 m2/dia 2.00 2.00
18 APARATOS Y ACCESORIOS SANITARIOS -
61 18.01 Aparatos y Accesorios Sanitarios BQ BH 6.00 Pza 2.50 m2/dia 2.40 3.00
19 INSTALACIONES SANITARIAS -
62 19.01 Instalaciones Sanitarias BR AG 33.40 Glb 5.30 m2/dia 6.40 7.00
63 19.02 Tubería PVC SAL Ø 4" BS AV 15.00 m 7.00 m/dia 2.20 3.00
20 INSTALACIONES DE AGUA FRIA Y
-
CONTRAINCENDIO
64 20.01 Accesorios de Agua, tuberia y salida de agua BT BR 16.30 Glb 5.17 m2/dia 3.20 4.00
65 20.02 fria
Tubería PVC SAP Ø 3/4" BU BS 14.20 m 7.00 m/dia 2.10 3.00
21 INSTALACIONES ELECTRICAS -
66 21.01 Instalaciones Electricas BV BU 44.00 Pza 13.00 m2/dia 3.40 4.00
21.02 Salidas para centros de Luz, Tomacorrientes
67 BW BT 57.00 Glb 5.50 m2/dia 10.40 11.00
e interruptores
68 21.03 Fluorescente y spot Light BX BV 21.00 Und 6.00 m2/dia 3.50 4.00
22 EQUIPAMIENTO -
69 22.01 Equipamiento e Implementacion de Modulos BZ EZ 1.00 Und 1.00 und/dia 1.00 1.00
23 TRANSPORTE -
70 23.01 Transporte de materiales a obra CA B 119,447.37 Kg 88.00 kg/dia 1,357.40 1,358.00
SEGUNDO NIVEL
01 OBRAS PROVISIONALES
71 01.01 Cerco provisional con arpillera CB AJ, DJ 46.20 m 25.00 und/dia 1.90 2.00
02 OBRAS DE CONCRETO ARMADO -
02.01 Columnas -
Armado de Acero Corrugado f'y= 4200
72 02.01.01 CC DT 840.00 Kg 120.00 kg/dia 7.00 7.00
Kg/cm2 (Columnas)
Colocado de Acero Corrugado f'y= 4200
73 02.01.02 CD CB, CC 210.00 Kg 120.00 1.80 2.00
Kg/cm2 (Columnas)
74 02.01.03 Encofrado (Columnas) CE CD 48.70 m2 9.00 m2/dia 5.50 6.00
75 02.01.04 Desencofrado (Columnas) CF CG 12.18 m2 9.00 1.40 2.00
76 02.01.05 Concreto f'c= 210 Kg/cm2 (Columnas) CG CE 5.77 m3 9.00 m3/dia 0.70 1.00
02.02 Vigas - Losa Aligerada -
Armado de Acero Corrugado f'y= 4200
77 02.02.01 CH CC 2,235.50 Kg 120.00 kg/dia 18.70 19.00
Kg/cm2 (Vigas - Losa Aligerada)
Colocado de Acero Corrugado f'y= 4200
78 02.02.02 CI CJ 558.87 Kg 120.00 kg/dia 4.70 5.00
Kg/cm2 (Vigas - Losa Aligerada)
79 02.02.03 Encofrado (Vigas - Losa Aligerada) CJ CH, CF 188.98 m2 9.00 kg/dia 21.00 21.00
80 02.02.04 Desencofrado (Vigas - Losa Aligerada) CK EF 47.25 m2 9.00 kg/dia 5.30 6.00
81 02.02.05 Concreto f'c= 210 Kg/cm2 (Vigas - Losa CL FI 28.75 m2 9.50 kg/dia 3.10 4.00
02.04 Aligerada)
Escalera -
02.04.01 Armado de Acero Corrugado f'y= 4200 3.37
82 EA 120.00 4.00
Kg/cm2 (Escalera) CR 404.00 Kg kg/dia
Colocado de Acero Corrugado f'y= 4200
83 02.04.02 CS CR, CT 101.00 Kg 120.00 0.84 1.00
Kg/cm2 (Escalera)
84 02.04.03 Encofrado (Escalera) CT CK 15.95 m2 7.00 m2/dia 2.28 3.00
85 02.04.04 Desencofrado (Escalera) CU CV 3.99 m2 7.00 0.57 1.00
86 02.04.05 Concreto f'c= 210 Kg/cm2 (Escalera) CV CS 5.15 m3 10.00 m3/dia 0.52 1.00
03 MUROS Y TABIQUES DE ALBAÑILERIA -
87 03.01 Muro de Bloqueta de 0.15x0.20x0.40 m CW CX 110.32 m2 7.50 m2/dia 14.71 15.00
88 03.02 Muro de Bloqueta de 0.20x0.20x0.40 m CX CU 123.69 m2 7.50 m2/dia 16.49 17.00
04 REVOQUES ENLUCIDOS Y MOLDURAS -
89 04.01 Tarrajeo en muros Y Columnas CY DB 350.67 m2 8.00 kg/dia 43.90 44.00
90 04.02 Tarrajeo de Vigas Inc. Aristas C:A CZ CW 41.30 m2 8.00 m2/dia 5.16 6.00
91 04.03 Vestidura de Derrames DA CY 10.14 m2 8.00 m2/dia 1.27 2.00
05 CIELORRASOS -
92 05.01 Cielo Raso con Yeso DB CZ 147.48 m2 8.00 m2/dia 18.44 19.00
06 PISOS Y PAVIMENTOS -
93 06.01 Falso Piso Concreto E= 4" DC DA 165.39 m2 60.00 m2/dia 2.76 3.00
94 06.02 Contrapisos DD DC 165.39 m2 85.00 m2/dia 1.95 2.00
95 06.03 Piso de Cerámico Nacional (0.30x0.30 de DE DD 165.39 m2 8.00 m2/dia 20.67 21.00
96 06.04 Color)
Vereda de Circulación E= 4" DF DE 40.20 m2 30.00 m2/dia 1.34 2.00
07 CONTRAZOCALOS -
97 07.01 Contrazocalo de madera DG DF 145.96 m 20.00 m/dia 7.30 8.00
08 REVESTIMIENTOS DE GRADAS Y -
ESCALERAS
98 08.01 Piso de Cerámico Nacional (0.30x0.30 de DH CU 31.58 m2 8.00 m2/dia 3.95 4.00
09 Color)
CARPINTERIA DE MADERA -
99 09.01 Puerta de Tablero Rebajado DI DG 17.99 m2 2.00 m2/dia 9.00 9.00
10 CARPINTERIA METALICA -
100 10.01 Baranda Metálica Tub. Galv. Ø 1 1/2" DJ DH 6.00 m 8.00 m/dia 0.75 1.00
11 CERRAJERIA -
101 11.01 Bisagra y Chapa de Seguridad DK DI 28.00 Pza 7.60 kg/dia 3.70 4.00
12 VIDRIOS Y CRISTALES -
102 12.01 Vidrios Templado 6mm. DL DO, DM 934.13 Pza 45.00 pza /dia 20.76 21.00
13 PINTURA -
Pintura en Muros Interiores y Exteriores +
103 13.01 DM DA 583.20 m2 33.00 m2/dia 17.67 18.00
Columnas y Vigas
Pintura en Cielo Rasos con Mezcla (Interiores
104 13.02 DN DB 147.48 m2 33.00 m2/dia 4.47 5.00
y Exteriores)
105 13.03 Pintura en Puertas DO DI 35.98 m2 25.00 m2/dia 1.44 2.00
14 INSTALACIONES ELECTRICAS -
106 14.01 Instalaciones Electricas DP DM , DN 41.00 Pza 13.37 m2/dia 3.07 4.00
Salidas para centros de Luz, Tomacorrientes
107 14.02 DQ CI 46.00 Pto 4.50 m2/dia 10.22 11.00
e interruptores
Fluorescente Recto 2x40 w Incluye Equipo y
108 14.03 DR DP 14.00 Und 5.00 und/dia 2.80 3.00
Pantalla
15 TRANSPORTE -
109 15.01 Transporte de materiales a obra DT CB 54,116.30 Kg 88.00 kg/dia 614.96 615.00
TERCER NIVEL
01 OBRAS PROVISIONALES
110 01.01 Cerco provisional con arpillera DU CL 46.20 m 25.00 m/dia 1.85 2.00
02 OBRAS DE CONCRETO ARMADO -
02.01 Columnas -
Armado de Acero Corrugado f'y= 4200
111 02.01.01 DV 630.75 Kg 120.00 kg/dia 5.26 6.00
Kg/cm2 (Columnas)
Colocado de Acero Corrugado f'y= 4200
112 02.01.02 DW DV, DU 210.25 Kg 120.00 1.75 2.00
Kg/cm2 (Columnas)
113 02.01.03 Encofrado (Columnas) DX DW 39.25 m2 9.00 m2/dia 4.36 5.00
114 02.01.04 Desencofrado (Columnas) DY DZ 13.08 m2 9.00 1.45 2.00
115 02.01.05 Concreto f'c= 210 Kg/cm2 (Columnas) DZ DX 4.91 m3 9.00 m3/dia 0.55 1.00
02.02 Vigas - Losa Aligerada -
Armado de Acero Corrugado f'y= 4200
02.02.01 EA DV 1,023.90 Kg 120.00 kg/dia 8.60 9.00
Kg/cm2 (Vigas - Losa Aligerada)
Colocado de Acero Corrugado f'y= 4200
02.02.02 EB EA, EC 341.30 Kg 120.00 kg/dia 2.90 3.00
Kg/cm2 (Vigas - Losa Aligerada)
02.02.03 Encofrado (Vigas - Losa Aligerada) EC DY 68.97 Kg 8.50 kg/dia 8.20 9.00
02.02.04 Desencofrado (Vigas - Losa Aligerada) ED DB 22.99 Kg 8.60 kg/dia 2.70 3.00
Concreto f'c= 210 Kg/cm2 (Vigas - Losa
02.02.05 EF FJ 12.27 Kg 9.00 kg/dia 1.40 2.00
Aligerada)
03 ESTRUCTURAS DE MADERA Y -
126 03.01 COBERTURAS
Tijeral de Madera EL ED 428.85 Pza 28.02 m2/dia 15.31 16.00
127 03.02 Cobertura con Planchas de teja andina EM EL 176.25 m2 45.00 m2/dia 3.92 4.00
04 MUROS Y TABIQUES DE ALBAÑILERIA -
128 04.01 Muro de Bloqueta de 0.15x0.20x0.40 m EN EO 86.20 m2 7.50 m2/dia 11.49 12.00
129 04.02 Muro de Bloqueta de 0.20x0.20x0.40 m EO ED 132.41 m2 7.50 m2/dia 17.65 18.00
05 REVOQUES ENLUCIDOS Y MOLDURAS -
130 05.01 Tarrajeo Rayado Primario EP EN 33.60 m2 8.00 m2/dia 4.20 5.00
131 05.02 Tarrajeo en muros, Columnas EQ ET 328.14 m2 8.00 kg/dia 41.10 42.00
132 05.03 Tarrajeo de Vigas Inc. Aristas C:A ER EP 26.86 m2 8.00 m2/dia 3.36 4.00
133 05.04 Vestidura de Derrames ES EQ 59.88 m2 8.00 m2/dia 7.49 8.00
06 CIELORRASOS -
134 06.01 Cielo Raso con Yeso /Enchaclado con Pintoc ET ER 180.69 m2 8.00 m2/dia 22.59 23.00
07 PISOS Y PAVIMENTOS -
135 07.01 Contrapisos EU ES 185.26 m2 85.00 m2/dia 2.18 3.00
136 07.02 Piso de Cerámico Nacional (0.30x0.30 de EV EU 185.26 m2 8.00 m2/dia 23.16 24.00
08 Color)
CONTRAZOCALOS -
137 08.01 Contrazocalo de madera EW EV 98.29 m 20.00 m/dia 4.91 5.00
09 ZOCALOS -
138 09.01 Zocalo de Mayólica 0.20x0.20 Nacional EX EW 33.60 m2 6.00 m2/dia 5.60 6.00
10 CARPINTERIA DE MADERA -
139 10.01 Puerta de Tablero Rebajado EY EX 13.98 m2 2.00 m2/dia 6.99 7.00
11 CERRAJERIA -
140 11.01 Bisagra y Chapa de Seguridad EZ EY 28.00 Jgo 7.58 kg/dia 3.70 4.00
12 VIDRIOS Y CRISTALES -
141 12.01 Vidrios Templado 6mm. FA FB 307.48 p2 45.00 p2/dia 6.83 7.00
13 PINTURA -
142 13.01 Pintura en muros, columnas, vigas y FB ES 363.97 m2 33.50 kg/dia 10.90 11.00
13.02 derrames
Pintura en Cielo Rasos con Mezcla (Interiores 0.85
143 ET 33.00 1.00
y Exteriores) FC 27.96 m2 m2/dia
14 APARATOS Y ACCESORIOS SANITARIOS -
144 14.01 Aparatos Sanitarios FD EX 7.00 Pza 3.75 kg/dia 1.90 2.00
15 INSTALACIONES SANITARIAS -
145 15.01 Instalaciones Sanitarias FE FF 36.80 Glb 5.50 kg/dia 6.70 7.00
16 INSTALACIONES DE AGUA FRIA Y CONTRAINCENDIO -
146 16.01 Accesorios de Agua, tuberia y salida de agua f FF EB 29.50 Glb 6.00 kg/dia 5.00 5.00
17 SISTEMA DE AGUA DE LLUVIA -
147 17.01 Canaleta de Plancha Galvanizada FG EM 20.10 M 20.00 m/dia 1.01 2.00
18 INSTALACIONES ELECTRICAS -
148 18.01 Instalaciones Electricas FH FB 44.00 Pza 14.17 kg/dia 3.20 4.00
149 18.02 Tomacorriente de Piso FI DQ 3.00 Pto 15.00 pto/dia 0.20 1.00
150 18.03 Salidas para centros de Luz, Tomacorrientes e FJ FE 56.00 Pza 4.60 m2/dia 12.17 13.00
151 18.04 Fluorescente y spot Light FK FH 19.00 Jgo 5.00 kg/dia 3.80 4.00
19 TRANSPORTE -
152 19.01 Transporte de materiales a obra FM CM 37,610.38 Kg 88.00 kg/dia 427.39 428.00
CRONOGRAMA VALORIZADO DE
PROYECTO

###
###
PRESUPUESTO DE O#REF!
FECHA DE INICIO D #REF!
### #REF!
Plazo de Ejecucion #REF!
1 2 3 4 5 6

MES
dias L M M J V S
Item Partidas
fecha

1.00

2.00

3.00

4.00

5.00

6.00
6.00

7.00

8.00

9.00

###

###

###

###

###

###

COSTO DIERECTO
GASTOS GENERALES 80%
UTILIDADES (7%)
SUB TOTAL
IGV (18%)
VALOR REFERENCIAL
SUPERVISION Y LIQUIDACION
EXPEDIENTE TECNICO
TOTAL DE PRESUPUESTO
DO DE AVANCE DE OBRA

7 8 9 10 11 12 13 14 15 16 17 18 19 20

D L M M J V S D L M M J V S
21 22 23 24 25 26 27 28 29 30 31 32 33 34

D L M M J V S D L M M J V S
35 36 37 38 39 40 41 42 43 44 45 46 47 48

D L M M J V S D L M M J V S
49 50 51 52 53 54 55 56 57 58 59 60 61 62

D L M M J V S D L M M J V S
63 64 65 66 67 68 69 70 71 72 73 74 75 76

D L M M J V S D L M M J V S
77 78 79 80 81 82 83 84

D L M M J V S D
CRONOGRAMA VALORIZADO DE AVANCE DE OB
PROYECTO ###
#REF! ###
#REF! ###
PRESUPUESTO DE OBRA: #REF!
FECHA DE INICIO DE OBRA #REF!
#REF! #REF!
Plazo de Ejecucion en (DC) #REF!
1 2 3
SALDO POR
Item Partidas
EJECUTAR 3 4 5

01 OBRAS PROVISIONALES 465.23


1.01 Cerco provisional con arpillera 465.23

02 OBRAS DE CONCRETO ARMADO 24,235.95


02.01 Columnas 8,410.83
02.01.01 Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Columnas) 4,238.64

02.01.02 Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Columnas) 1,412.88

02.01.03 Encofrado (Columnas) 771.21


02.01.03 Encofrado (Columnas) 771.21

02.01.04 Desencofrado (Columnas) 257.07

02.01.05 Concreto f'c= 210 Kg/cm2 (Columnas) 1,731.02

02.02 Vigas - Losa Aligerada 15,825.12


Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas - Losa
02.02.01 6,880.61
Aligerada)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas - Losa
02.02.02 2,293.54
Aligerada)

02.02.03 Encofrado (Vigas - Losa Aligerada) 1,755.51

02.02.04 Desencofrado (Vigas - Losa Aligerada) 585.17

02.02.05 Concreto f'c= 210 Kg/cm2 (Vigas - Losa Aligerada) 4,310.30

03 ESTRUCTURAS DE MADERA Y COBERTURAS 32,965.34


3.01 Tijeral de Madera 18,377.12

3.02 Cobertura con Planchas de teja andina 14,588.21

04 MUROS Y TABIQUES DE ALBAÑILERIA 6,124.07


4.01 Muro de Bloqueta de 0.15x0.20x0.40 m 2,289.47

4.02 Muro de Bloqueta de 0.20x0.20x0.40 m 3,834.59


4.02 Muro de Bloqueta de 0.20x0.20x0.40 m 3,834.59

05 REVOQUES ENLUCIDOS Y MOLDURAS 6,198.71


5.01 Tarrajeo Rayado Primario 471.07

5.02 Tarrajeo en muros, Columnas 4,502.08

5.03 Tarrajeo de Vigas Inc. Aristas C:A 377.65

5.04 Vestidura de Derrames 847.90

06 CIELORRASOS 9,045.34
6.01 Cielo Raso con Yeso /Enchaclado con Pintoc 9,045.34

07 PISOS Y PAVIMENTOS 12,065.98


7.01 Contrapisos 2,223.12

7.02 Piso de Cerámico Nacional (0.30x0.30 de Color) 9,842.86

08 CONTRAZOCALOS 561.24
8.01 Contrazocalo de madera 561.24

09 ZOCALOS 1,359.12
9.01 Zocalo de Mayólica 0.20x0.20 Nacional 1,359.12

10 CARPINTERIA DE MADERA 1,553.88


10.01 Puerta de Tablero Rebajado 1,553.88
10.01 Puerta de Tablero Rebajado 1,553.88

11 CERRAJERIA 958.86
11.01 Bisagra y Chapa de Seguridad 958.86

12 VIDRIOS Y CRISTALES 9,501.13


12.01 Vidrios Templado 6mm. 9,501.13

13 PINTURA 2,003.99
13.01 Pintura en muros, columnas, vigas y derrames 1,861.68

13.02 Pintura en Cielo Rasos con Mezcla (Interiores y Exteriores) 142.32

14 APARATOS Y ACCESORIOS SANITARIOS 902.10


14.01 Aparatos Sanitarios 902.10

15 INSTALACIONES SANITARIAS 563.64


15.01 Instalaciones Sanitarias 563.64

16 INSTALACIONES DE AGUA FRIA Y CONTRAINCENDIO 998.89


16.01 Accesorios de Agua, tuberia y salida de agua fria 998.89

17 SISTEMA DE AGUA DE LLUVIA 212.26


17.01 Canaleta de Plancha Galvanizada 212.26

18 INSTALACIONES ELECTRICAS 2,439.53


18.01 Instalaciones Electricas 371.71
18.01 Instalaciones Electricas 371.71

18.02 Tomacorriente de Piso 16.68

18.03 Salidas para centros de Luz, Tomacorrientes e interruptores 686.00

18.04 Fluorescente y spot Light 1,365.14

19 TRANSPORTE 3,761.04
19.01 Transporte de materiales a obra 3,761.04

TOTAL COSTO DIRECTO S/. 115,916.28 S/. 0


PORCENTAJE PROGRAMADO SEMANAL 0.00
PORCENTAJE PROGRAMADO MENSUAL
PROGRAMADO MENSUAL

LEYENDA:
PROGRAMADO
DE OBRA

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

NOVIEMBRE-2014 DI
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00%
S/. 0.00 S/. 0.00 S/. 0.00

RUTA CRITICA:
PROGRAMADO:
36 37 38 39 40 41

DICIEMBRE-2014
14 15 16 17 18 19 20 21

TERCER NIVEL
S/. 0.00 S/. 0.00
0.00% 0.00%
0.00%
S/. 0.00
42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72

014 ENERO-2014
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

TERCER NIVEL
x
100.00%
S/. 465.23

x x x x x
40.00% 60.00%
S/. 1,695.46 S/. 2,543.18
x
100.00%
S/. 1,412.88
x x x
66.67% 33.3
S/. 514.14 S/. 25
x
100.0
S/. 25
x
100.0
S/. 1,7

x x x
100.00%
S/. 6,880.61

x
80.0
S/. 1,4
x
100.00%
S/. 16.68

x
100.00%
S/. 3,761.04

S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,456.49 S/. 9,440.47 S/. 2,392.26 S/. 3,6
0.00% 0.00% 0.00% 4.71% 8.14% 2.06% 3.15
0.00% 4.71% 11.29%
S/. 0.00 S/. 5,456.49 S/. 13,090.04
73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104

FEBRERO-2014
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6
33.33%
S/. 257.07

100.00%
S/. 257.07

100.00%
S/. 1,731.02

x x
100.00%
S/. 2,293.54
x x x x
80.00% 20.00%
S/. 1,404.41 S/. 351.10
x
100.00%
S/. 585.17
x x x
100.00%
S/. 4,310.30

x x x x x
60.00% 40.00%
S/. 11,026.27 S/. 7,350.85
x x
100.00%
S/. 14,588.21

x x
100.00%
S/. 2,289.47
x x x x
75.00% 25.00%
S/. 2,875.95 S/. 958.65

x
100.00%
S/. 471.07

x
100.00%
S/. 377.65
x
50.00%
S/. 423.95

x
33.33%
S/. 3,015.11
x
100.00%
S/. 563.64

x
100.00%
S/. 998.89

x
100.00%
S/. 212.26
x x
50.00% 50.00%
S/. 343.00 S/. 343.00

S/. 3,649.57 S/. 4,550.16 S/. 4,653.30 S/. 0.00 S/. 14,487.39 S/. 29,687.23
3.15% 3.93% 4.01% 0.00% 12.50% 25.61%
7.94% 12.50% 32
S/. 9,203.46 S/. 14,487.39 S/. 3
105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125

MARZO-2014
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
40.00%
S/. 7,350.85

100.00%
S/. 14,588.21

100.00%
S/. 2,289.47
25.00%
S/. 958.65

100.00%
S/. 471.07
x x x x x x
33.33% 66.67%
S/. 1,500.69 S/. 3,001.39

100.00%
S/. 377.65
x
50.00% 50.00%
S/. 423.95 S/. 423.95

x x x x x
33.33% 66.67%
S/. 3,015.11 S/. 6,030.23

x
100.00%
S/. 2,223.12
x x x
100.00%
S/. 9,842.86

x
100.00%
S/. 561.24

x
100.00%
S/. 1,359.12

x x x
66.67% 33.33%
S/. 1,035.92 S/. 517.96

x
100.00%
S/. 958.86

x x
50.00% 50.00%
S/. 4,750.57 S/. 4,750.57

x x x x x x
16.67% 83.33%
S/. 310.28 S/. 1,551.40
x
100.00%
S/. 142.32

x
100.00%
S/. 902.10

100.00%
S/. 212.26

x
100.00%
S/. 371.71

x x
100.00%
S/. 1,365.14

/. 29,687.23 S/. 7,673.24 S/. 5,958.74 S/. 20,374.91 S/. 7,592.53


25.61% 6.62% 5.14% 17.58% 6.55%
32.23% 24.13%
S/. 37,360.46 S/. 27,967.44
CALENDARIO DE AVANCE DE OBRA VALORIZ

OBRA : “CONSTRUCCIÓN DE LOCAL PARA EL COMEDOR ESTUDIANTIL ACCHA

UBICACION : CUSCO - PARURO


ENTIDAD : MUNICIPALIDAD DISTRITAL DE ACCHA Plazo de Ejecucion
PRESUPUESTO DE OBRA: S/. 510,457.24
FECHA PPTO
FECHA DE INICIO DE OBRA 11/1/2014
FECHA DE CONCLUSION DE OBRA3/30/2015

VIII. ) GRÁFICOS REPRESENTATIVOS DE EJECUCIÓN

AVANCE FISICO PROGRAMADO


"OCTUBRE - 2014"

PROGRAMADO
ITEM PERIODO (S/.) PORCENTAJE
MENSUAL ACUMULADO MENSUAL ACUMULADO
1 noviembre-14 #REF! #REF! #REF! #REF!
2 diciembre-14 #REF! #REF! #REF! #REF!
3 enero-15 #REF! #REF! #REF! #REF!

4 febrero-15 #REF! #REF! #REF! #REF!


5 marzo-15 #REF! #REF! #REF! #REF!

AVANCE FÍSICO ACUMULADO


(PROGRAMADO)
100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
novi embre-14 di ci embre-14 enero-15 febrero-15

Col umn G
30.00%

20.00%

10.00%

0.00%
novi embre-14 di ci embre-14 enero-15 febrero-15

Col umn G

, ,,

AVANCE FÍSICO MENSUAL


(PROGRAMADO)
100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
novi embre-14 di ci embre-14 enero-15 febrero-15

Col umn F
AVANCE FISICO MENSUAL
(PROGRAMADO)
1000.00%

900.00%

800.00%

700.00%

600.00%

500.00%

400.00%

300.00%

200.00%

100.00%

0.00%
noviembre-14 diciembre-14 enero-15 febrero-15

AVANCE FINANCIERO PROGRAMADO


"OCTUBRE - 2014"

PROGRAMADO
ITEM PERIODO (S/.) PORCENTAJE
MENSUAL ACUMULADO MENSUAL ACUMULADO
1 noviembre-14 #REF! #REF! #REF! #REF!
2 diciembre-14 #REF! #REF! #REF! #REF!
3 enero-15 #REF! #REF! #REF! #REF!
4 febrero-15 #REF! #REF! #REF! #REF!
5 marzo-15 #REF! #REF! #REF! #REF!

AVANCE FINANCIERO ACUMULAD


(PROGRAMADO)
600,000.0

Column E
mi l es de nuevos sol es

0.0
n ov i e m b re - 1 4 d i c i e m b re - 1 4 e n e ro - 1 5 fe b re ro - 1 5 m
mi l es de nuevos s
0.0
n ov i e m b re - 1 4 d i c i e m b re - 1 4 e n e ro - 1 5 fe b re ro - 1 5 m

mes

AVANCE FINANCIERO MENSUAL


(PROGRAMADO)
200,000.00

0.00
noviembre-14 diciembre-14 enero-15 febrero-15 m
E OBRA VALORIZADO

EDOR ESTUDIANTIL ACCHA-PARURO-CUSCO”

Plazo de Ejecucion en (DC) 150 Dias

ATIVOS DE EJECUCIÓN

CO PROGRAMADO
UBRE - 2014"

ACUMULADO
MADO)

5 febrero-15 marzo-15
5 febrero-15 marzo-15

O MENSUAL
MADO)

5 febrero-15 marzo-15
NSUAL
O)

5 febrero-15 marzo-15

UBRE - 2014"

NCIERO ACUMULADO
GRAMADO)

fe b re ro - 1 5 m a r zo - 1 5
fe b re ro - 1 5 m a r zo - 1 5

NSUAL

febrero-15 marzo-15
NUMERO DE HORAS HOMBRE POR MES
CARGO UNID. P.U. NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO CANTIDAD HH SUB TOTAL
OPERARIO HH S/. 3.75 1,236.00 1,744.00 1,776.00 2,580.00 3,288.00 10,624.00 S/. 39,840.00
OFICIAL HH S/. 3.13 1,868.00 1,318.00 1,256.00 1,488.00 1,873.60 7,803.60 S/. 24,386.25
PEON HH S/. 2.25 2,724.00 3,106.00 1,556.00 1,808.00 2,126.00 11,320.00 S/. 25,470.00
29,747.60 S/. 89,696.25

COSTO DE HORAS HOMBRE MENSUAL


CARGO UNID. P.U. NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO SUB TOTAL
OPERARIO HH S/. 3.75 4,635.00 6,540.00 6,660.00 9,675.00 12,330.00 S/. 39,840.00
OFICIAL HH S/. 3.13 5,837.50 4,118.75 3,925.00 4,650.00 5,855.00 S/. 24,386.25
PEON HH S/. 2.25 6,129.00 6,988.50 3,501.00 4,068.00 4,783.50 S/. 25,470.00
TOTAL COSTO POR MES 16,601.50 17,647.25 14,086.00 18,393.00 22,968.50 S/. 89,696.25

NUMERO DE PERSONAL OBRERO MENSUAL


CARGO UNID. NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO SUB TOTAL TOTAL HH
OPERARIO DIA 5.00 7.00 8.00 10.00 14.00 44.00 10,630.40
OFICIAL DIA 7.00 6.00 6.00 6.00 7.00 32.00 7,731.20
PEON DIA 11.00 13.00 6.00 8.00 9.00 47.00 11,355.20
TOTAL COSTO POR MES 23.00 26.00 20.00 24.00 30.00 123.00 29,716.80
CRONOGRAMA

OBRA : “CONSTRUCCIÓN DE LOCAL PARA EL COMEDOR ESTUDIANTIL ACCHA-PARURO-

UBICACION : CUSCO - PARURO


ENTIDAD : MUNICIPALIDAD DISTRITAL DE ACCHA
PRESUPUESTO DE OBRA: S/. 510,457.24
FECHA PPTO
FECHA DE INICIO DE OBRA 11/1/2014
FECHA DE CONCLUSION DE OBRA 3/30/2015

4200 Kg/cm2 G-

4200 Kg/cm2 G-
Corrugado f'y=

Corrugado f'y=

Alambre Negro
PVC SAP 3/4"
ADAPTADOR
UNID

Acero
Acero

N°16
60

60
PRECEDEN . DE
N° CODIGO DESCRIPCION SIMBOLO METRADO
CIA MEDI
DA

kg kg und kg
01 OBRAS PROVISIONALES
1 01.01 Cartel de Identificacion de Obra A - 1.00 und
2 01.02 Cerco provisional con arpillera B D 46.20 m 0.05
02 TRABAJOS PRELIMINARES
3 02.01 Demolición de Construcción Existente C A 181.41 m2
4 02.02 Eliminación de Material Excedente D C 306.49 m3
03 MOVIMIENTO DE TIERRAS
5 03.01 Trazo , Nivelación del Terreno y Apisonado E B 181.41 m2
03.02 Excavaciones
6 03.02.01 Excavacion de Zanjas F E 193.88 m3 0 0 0
Excavación de Zanjas para Cimientos 25.70 m3
Excavacion de Zanjas para Vigas de Cimentación 7.36 m3
Excavación de Zanjas para Zapatas 160.82 m3
04 OBRAS DE CONCRETO SIMPLE
04.01 Solado
9 04.01.01 Solado para Vigas de conexion J F 5.04 m2
10 04.01.02 Solado para Zapatas K F 106.00 m2
04.02 Cimientos
11 04.02.01 Concreto en Cimientos Corridos (1:10+30% P.G.) L U, P 25.70 m3
05 OBRAS DE CONCRETO ARMADO
05.01 Vigas de Conexion
15 05.01.01 Concreto f'c= 210 Kg/cm2, Viga Cimentación P R 3.23 m3
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Viga
16 05.01.02 Q CA 5,104.47 kg
Cimentación - Muro Reforzado) 1.712 8,738.86 0 0.104
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Viga 4,418.40 kg 1.07 0.065
Cimentación)
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Muros 686.07 kg 1.07 0.065
17 05.01.03 Reforzado)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Viga R J,Q 1,276.12 kg 0.428 546.18 0 0.026
Cimentación- Muro Corrugado
Colocado de Acero Reforzado)f'y= 4200 Kg/cm2 (Viga 1,104.60
Cimentación)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Muros 171.52
05.02 Reforzado)
Zapatas
18 05.02.01 Armado de Acero Corrugado f'y= 4200 Kg/cm2 S Q 938.40 kg 0.856 803.27 0.052
19 05.02.02 (Zapatas)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 T K, S 234.60 kg 0.214 50.20 0.013
20 05.02.03 (Zapatas)
Concreto f'c= 210 Kg/cm2, Zapatas U T 70.75 m3
05.03 Muro Reforzado
21 05.03.01 Encofrado (Muros Reforzado) X P 47.04 m2
22 05.03.02 Desencofrado (Muros Reforzado) Y Z 11.76 m2
23 05.03.03 Concreto f'c= 210 Kg/cm2 (Muros Reforzado) Z X 7.35 m3
05.04 Columnas
24 05.04.01 Armado de Acero Corrugado f'y= 4200 Kg/cm2 AA S 1,650.40 kg 0.856 753.46 0.042
70 23.01 (Columnas)
Transporte de materiales a obra CA B ### Kg
SUMATORIA TOTAL 10891.9719813 0 0.417
COSTO S/. 5.2
TOTAL 56638.2543029 0 0
TOTAL COSTO DE MATERIALES S/. 102,290.00
Alambre Negro

kg
N°16

2.31
Alambre Negro

kg
N°8

0
ANTIL ACCHA-PARURO-CUSCO”

Alambre Negro

kg
N°8

Arena Fina

m3

0
Cartel de
identifcacion
de obra

glb
c/panafex
inc/instalacion

0
1
Cartel de
identifcacion
de obra
glb

c/panafex
inc/instalacion
1.00

Cemento
Portland Tipo I
bls

(42.5 Kg)

0
Cemento
Portland Tipo I
bls

(42.5 Kg)

Clavos para
kg

Madera C/C 2"


0

Clavos para
kg

Madera C/C 2"


0.05 2.31

Clavos para
kg

Madera C/C 3"


0

Clavos para
kg

Madera C/C 3"


CRONOGRAMA DE ADQUISICION DE MATERIALES - MES NOVIEMBRE

Clavos para
kg

Madera C/C 5"


0

Hoja de Sierra
und

Hoja de Sierra
und

Hormigón
m3

0
Plazo de Ejecucion e
0.095
0.275 29.15 0.095

2.95 75.82 0.88

9.73 31.43 1.05

530.87 0 0 0 0 0 0 0 0.0096 49.00 0


0.006
0.006
33.18 0 0 0 0 0 0 0 0.0024 3.06 0

48.80 0.0048 4.50


0.0012 0.28
9.73 688.40 1.05

0.208 9.78 0.104 4.89216


0.052 0.61 0.026 0.31
9.73 71.52 1.05

36.97 0.0048 4.23

652.119916 0.26 10.39584 0 1 1 32.415 896.3059 0.05 2.31 0.13 5.19792 0 0.0348 61.0764784 4.22
4.3 4.3 350 25.5 4.3 4.3 5
2804.115639 0 44.702112 0 0 350 0 22855.8 0 9.933 0 22.351056 0 0 305.382392 0
Hormigón

m3
Inodoro Tanque

pza
Bajo

0
Listones de zo de Ejecucion en (DC)
2"x2"x10'

pza
(Madera
Corriente)

0.6

0
Listones de
2"x2"x10'

pza
(Madera
Corriente)

27.72
Madera

p2
Corriente

0
Madera
p2 Corriente

Piedra Mediana
m3

de 6"

Pisón de
150 Dias

pza

Conccreto

0.51
Regla de
Madera
p2

3.63 Corriente

Transporte de
materiales a
kg

obra
m

Yute
48.51
0.48 0.56
10.07 11.87

22.62 14.14

3.39

0 0 0

0 0 0

74.29

3.864 181.76
0.966 11.36
7.72

119,447.37
118.5613 0 0.6 27.72 4.83 193.1227 14.135 0.508 16.06468 119447.37 48.51
50 4 1.5 50 25 1.5 0.1 5
5928.065 0 0 110.88 0 289.6841 706.75 12.7 24.09702 11944.737 242.55
CRO

: “CONSTRUCCIÓN DE LOCAL PARA EL COMEDOR ESTUDIANTIL ACCHA-PARURO-


OBRA
CUSCO”
UBICACION
ENTIDAD
PRESUPUESTO DE OBRA: ###
FECHA PPTO
FECHA DE INICIO DE OBRA
FECHA DE CONCLUSION DE OBRA

Alambre Negro N°8


f'y= 4200 Kg/cm2
Acero Corrugado

Alambre Negro

Arena Gruesa
Arena Fina
METRADO

N°16
UNID

G-60
. DE
N° CODIGO DESCRIPCION
MEDI
DA

kg kg kg m3 m3
05.07 Escalera
34 05.07.01 Armado de Acero Corrugado f'y= 4200 Kg/cm2 600.80 kg 514.28 31.24
35 (Escalera)de Acero Corrugado f'y= 4200 Kg/cm2
05.07.02 Colocado 150.20 32.14 1.95
36 05.07.03 (Escalera)
Encofrado (Escalera) 21.86 m2 1.40 0.87
37 05.07.04 Desencofrado (Escalera) 5.47 0.09 0.05
38 05.07.05 Concreto f'c= 210 Kg/cm2 (Escalera) 8.33 m3
06 MUROS Y TABIQUES DE ALBAÑILERIA
40 06.02 Muro de Bloqueta de 0.20x0.20x0.40 m 172.79 m2 3.63
07 REVOQUES ENLUCIDOS Y MOLDURAS
44 07.04 Tarrajeo de Vigas Inc. Aristas C:A 38.22 m2 0.88
08 CIELORRASOS
46 08.01 Cielo Raso con Yeso 194.71 m2
12 REVESTIMIENTOS DE GRADAS Y ESCALERAS
53 12.01 Piso de Cerámico Nacional (0.30x0.30 de Color) 34.97 m2 1.12
14 CARPINTERIA METALICA
55 14.01 Baranda Metálica Tub. Galv. Ø 1 1/2" 79.92 m
63 19.02 Tubería PVC SAL Ø 4" 15.00 m
65 20.02 Tubería PVC SAP Ø 3/4" 14.20 m
21 INSTALACIONES ELECTRICAS
66 21.01 Instalaciones Electricas 44.00 Pza
Tablero de Distribución 12"x12" 1.00 Pza
Interuptor Thermomágnetico de 20A 3.00 Und
Tomacorriente doble 24.00 Pto
Interuptor Simple 15.00 Pza
Interuptor Triple 1.00 Pza
68 21.03 Fluorescente y spot Light 21.00 Und
Fluorescente Recto 2x40 w Incluye Equipo y Pantalla 10.00 Und
Spot Light 11.00 Jgo
01 OBRAS PROVISIONALES
71 01.01 Cerco provisional con arpillera 46.20 m 2.31
Colocado de Acero Corrugado f'y= 4200 Kg/cm2
73 02.01.02 210.00 Kg 44.94 13.65
(Columnas)
74 02.01.03 Encofrado (Columnas) 48.70 m2 11.68896
75 02.01.04 Desencofrado (Columnas) 12.18 m2 0.73056
76 02.01.05 Concreto f'c= 210 Kg/cm2 (Columnas) 5.77 m3
02.02.00 Vigas - Losa Aligerada
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas -
78 02.02.01 1,659.50 Kg 710.264288 53.93362
Losa Aligerada)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas) 216.20 Kg
Colocado de Acero Corrugado f'y= 4200 Kg/cm2 (Losa 198.67 Kg
79 02.02.03 Aligerada)
Encofrado (Vigas - Losa Aligerada) 188.98 m2 151.1872 31.749312
Encofrado (Vigas) 69.18 m2
Encofrado (losa aligerada) 119.81 m2
81 02.02.05 Concreto f'c= 210 Kg/cm2 (Vigas - Losa Aligerada) 28.75 m2
Concreto f'c= 210 Kg/cm2 (Vigas) 12.97 m3
Concreto f'c= 210 Kg/cm2 (Losa aligerada) 15.78 m3
02.04 Escalera
82 02.04.01 Armado de Acero Corrugado f'y= 4200 Kg/cm2 404.00 Kg 172.912 10.9888
(Escalera)
Salidas para centros de Luz, Tomacorrientes e
107 14.02 46.00 Pto
interruptores
Salida para Centros de Luz 9.00 Pto
Salida para Interuptores 9.00 Pto
Salida para Tomacorrientes 28.00 Pto
01 OBRAS PROVISIONALES
110 01.01 Cerco provisional con arpillera 46.20 m 2.31
02 OBRAS DE CONCRETO ARMADO
02.01 Columnas
Armado de Acero Corrugado f'y= 4200 Kg/cm2
111 02.01.01 630.75 Kg 539.92 32.80
(Columnas)
Colocado de Acero Corrugado f'y= 4200 Kg/cm2
112 02.01.02 210.25 Kg 44.99 2.73
(Columnas)
113 02.01.03 Encofrado (Columnas) 39.25 m2 9.42
114 02.01.04 Desencofrado (Columnas) 13.08 m2 0.78
115 02.01.05 Concreto f'c= 210 Kg/cm2 (Columnas) 4.91 m3
02.02 Vigas - Losa Aligerada
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas -
02.02.01 1,023.90 Kg 1752.9168 106.4856
Losa Aligerada)
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Vigas) 850.50 Kg
Armado de Acero Corrugado f'y= 4200 Kg/cm2 (Losa
173.40 Kg
Aligerada)
02.02.03 Encofrado (Vigas - Losa Aligerada) 68.97 Kg 4.96584 10.428264
Encofrado (Vigas) 46.40 m2
Encofrado (losa aligerada) 22.58 m2
149 18.02 Tomacorriente de Piso 3.00 Pto
19 TRANSPORTE 3,761.04
152 19.01 Transporte de materiales a obra 37,610.38 Kg
SUMATORIA TOTAL 3963.563388 264.857062 65.730666 1.9981 3.62859
COSTO S/. 5.2 4.3 4.3 50 50
TOTAL 20610.52962 1138.885367 282.641864 99.905 181.4295
Baranda Metálica

m
Tub. Galv. Ø 1 1/2"

Bloque Hueco de A-PARURO-


Concreto de

und
0.30x0.15x0.15 m.

Bloqueta de

und
0.20x0.20x0.40

2,073.48
Caja Galvanizada
para Tablero

pza
12"x12"

Caja Octogonal de

und
Plástico 4"x4"x2"

Caja Rectangualr
de Plástico
und 4"x2"x2"

Cemento Portland
bls

Tipo I (42.5 Kg)

9.34
6.12
20.22
81.05 Clavos para
kg

Madera C/C 2"

Clavos para
kg

Madera C/C 3"


0.11

3.80138
1.74912

3.822

Fluorescente
Recto 2x40 w
und

Incluye Equipo y
Pantalla
Plazo de Ejecucion en (DC)

Fragua
kg

5.94
CRONOGRAMA DE ADQUISICION DE MATERIALES - MES ENERO

Hoja de Sierra
und

0.18
2.88
150 Dias

Hormigón
m3

8.75

Interruptor Simple
pza

de Bakelita

Interruptor
Termomagnético
und

de 20A
83.92

1.00
3.00

15.00

10.00

2.31

6.623744
0.413984
56.1421 6.0585

4.978488

1606.364 52.91552

559.475 60.375

1.212
9
9
28

2.31

3.03
0.25
5.34
0.44
47.77 5.16

9.82944

215.39331 17.38044

83.916 1821.75731 2073.48 1 18 28 780.11092 4.62 92.597973 10 5.9449 22.363908 80.3355 15 3


41.67 1.5 1.5 45 2 2 25.5 4.3 4.3 68 6 5 50 3.5 25
3496.77972 2732.635965 3110.22 45 36 56 19892.82846 19.866 398.1712839 680 35.6694 111.81954 4016.775 52.5 75
Interruptor Triple
Bipolar de

pza
Bakelita

Listones de
2"x2"x10' (Madera

pza
Corriente)

Madera Corriente

p2

22.17
100.22
100.40
6.27
Mayólica Nacional

m2
(0.30x0.30)

36.72
Pegamento para

gln
PVC

Petroleo Diessel

gln
N° 2

Regla de Madera
p2

Corriente

0.70
3.50
1.91
Spot Light
jgo

Tomacorriente
pza

Doble

Transporte de
kg

materiales a obra

Tubería PVC SAL Ø


m

4"

YEE PVC SAL DE


pza

4" X 4"

Yeso
sac

68.15
m

Yute
0.08 15.75
0.07 14.91

24.00

1.00

11.00

27.72 48.51

251.31264 0.97408
0.3044

1268.08264 7.55936
27.72 48.51

162.01 0.98
13.50

588.948624 3.10365

3.00

37,610.38

1 55.44 2512.91898 36.7185 0.146 12.9226775 6.11518 11 27 37610.38 30.66 0 68.1485 97.02
5 4 1.5 33 100 10 1.5 22 3.5 0.1 8 8 7.5 5
5 221.76 3769.37847 1211.7105 14.6 129.226775 9.17277 242 94.5 3761.038 245.28 0 511.11375 485.1
CRONOGRAMA DE INVERSION MAQUINARIAS Y/O EQUIPOS
Noviembre
Partida Metrado Cantidad Und. Descripcion Total
D 306.49 1 hm Volquete de 10 m3 306.49
J 5.04 0.1143 hm Mezcladora de concreto de 9-11 p3 0.58
K 106.00 0.1143 hm Mezcladora de concreto de 9-11 p3 12.12
P 3.23 0.6667 hm Mezcladora de concreto de 9-11 p3 2.15
P 3.23 0.6667 hm Vibrador de concreto 4HP 2.15
U 70.75 0.6667 hm Mezcladora de concreto de 9-11 p3 47.17
U 70.75 0.6667 hm Vibrador de concreto 4HP 47.17
L 25.70 0.6667 hm Mezcladora de concreto de 9-11 p3 17.13
Z 7.35 0.8889 hm Mezcladora de concreto de 9-11 p3 6.53
Z 7.35 0.8889 hm Vibrador de concreto 4HP 6.53

PU Total Horas Descripcion PARCIAL


128.00 306.49 Volquete de 10 m3 S/. 39,230.72
6.25 85.68 Mezcladora de concreto de 9-11 p3 S/. 535.51
3.75 55.86 Vibrador de concreto 4HP S/. 209.46
Total S/. 39,975.69

Diciembre
Partida Metrado Cantidad Und. Descripcion Total
I 72.31 0.64 hm Compactador vibratorio tipo plancha 46.28
M 4.76 0.8 hm Mezcladora de concreto de 9-11 p3 3.81
AE 10.22 0.8889 hm Mezcladora de concreto de 9-11 p3 9.08
AE 10.22 0.8889 hm Vibrador de concreto 4HP 9.08

PU Total Descripcion PARCIAL


Horas
46.28
6.25 Compactador vibratorio tipo plancha S/. 289.24
6.25 12.89 Mezcladora de concreto de 9-11 p3 S/. 80.58
3.75 9.08 Vibrador de concreto 4HP S/. 34.07
Total S/. 403.89

Enero

Partida Metrado Cantidad Und. Descripcion Total

CG 5.77 0.8889 hm Mezcladora de concreto de 9-11 p3 5.128953


CG 5.77 0.8889 hm Vibrador de concreto 4HP 5.128953
DQ 46.00 0.0625 pza Winche para cableado 2.875
CL 28.75 1.6889 hm Mezcladora de concreto de 9-11 p3 48.555875
CL 28.75 1.6889 hm Vibrador de concreto 4HP 48.555875
DZ 4.91 0.8889 hm Mezcladora de concreto de 9-11 p3 4.364499
DZ 4.91 0.8889 hm Vibrador de concreto 4HP 4.364499
AT 8.33 0.8 hm Mezcladora de concreto de 9-11 p3 6.664

AT 8.33 0.8 hm Vibrador de concreto 4HP 6.664


Total
PU Descripcion PARCIAL
Horas
12.00 2.88 Winche para cableado S/. 34.50
6.25 64.71 Mezcladora de concreto de 9-11 p3 S/. 404.46

3.75 64.71 Vibrador de concreto 4HP S/. 242.67

Total S/. 681.63

Febrero

Partida Metrado Cantidad Und. Descripcion Total

FJ 56.00 0.0625 pza Winche para cableado 3.50

EF 12.27 1.6889 hm Mezcladora de concreto de 9-11 p3 20.72


EF 12.27 1.6889 hm Vibrador de concreto 4HP 20.72
BO 194.71 0.0303 pza Espatula 5.90
CV 5.15 0.8 hm Mezcladora de concreto de 9-11 p3 4.12
CV 5.15 0.8 hm Vibrador de concreto 4HP 4.12
DN 147.48 0.0303 pza Espatula 4.47

BC 205.12 0.1333 hm Mezcladora de concreto de 9-11 p3 27.34

Total
PU Descripcion PARCIAL
Horas
12.00 3.50 Winche para cableado S/. 42.00

10.00 10.37 Espatula S/. 103.68

6.25 52.19 Mezcladora de concreto de 9-11 p3 S/. 326.16

3.75 24.84 Vibrador de concreto 4HP S/. 93.16


Total S/. 565.00

Marzo
Partida Metrado Cantidad Und. Descripcion Total
BD 205.12 0.0941 hm Mezcladora de concreto de 9-11 p3 19.30
DC 165.39 0.1333 hm Mezcladora de concreto de 9-11 p3 22.05
DD 165.39 0.0941 hm Mezcladora de concreto de 9-11 p3 15.56
DM 583.20 0.0303 pza Espatula 17.67
BF 20.11 0.2667 hm Mezcladora de concreto de 9-11 p3 5.36
FC 27.96 0.0303 pza Espatula 0.85
DF 40.20 0.2667 hm Mezcladora de concreto de 9-11 p3 10.72
EU 185.26 0.0941 hm Mezcladora de concreto de 9-11 p3 17.43
FB 363.97 0.0303 pza Espatula 11.03
Total
PU Descripcion PARCIAL
Horas
10.00 29.55 Espatula S/. 295.46
6.25 90.43 Mezcladora de concreto de 9-11 p3 S/. 565.18
Total S/. 860.65