a) Settling Zone
W2 = W1 – 2 x (d1/2) x Z 8.60 m
L2 = L1 – 2 x (d1/2) x Z 13.60 m
At base level :
WB = W1 – 2 x Z (Y1 / 2 + y2)
= 6.2 m Try WB = 3 m
LB = L1 - 2 x Z x (Y1 /2 + Y2 )
= 11.2 m Try LB = 5 m
i) assume riser pipe flow is orifice flow through the top of the pipe only.
ii) riser pipe head is 300mm,i.e. the height between the top of the pipe and the spillway crest
level
a) Detemination of Q10
b) Detemination of Qriser
Try
Csp = 1.48 Table 2.7
B = 0.30 m
Hp1.5 = 0.30 m