Field Direction / Clarification Notice

PROJECT:____________________________ DATE:_________

CONTRACTOR:_______________________________________

ATTENDEES:_________________________________________
__________________________________________
__________________________________________

QUESTION/PROBLEM:_________________________________
______________________________________________________
______________________________________________________
______________________________________________________

ANSWER/DIRECTION:_________________________________
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________

ACTION BY CONTRACTOR:

____Provide a cost proposal BEFORE proceeding with work.


____Proceed with work at a cost not to exceed $_____________,
and_______ days time extension.
____Information only, no change in cost or time.

SIGNED:_______________________, Elon University.