CHEMI-SOURCE

REPAINTING THE BUILDING AND REPLACE THE CEE PURLINS, REPAIR THE
LOUVERS OF THE AIR BREATHER AND REPAIR PORTION OF DOOR #3

MATERIALS:

60 GALLONS OF EPOXY PRIMER

30 GALLONS ACRYLIC LACQUER THINNER

20 STEEL BRUSH

150 PCS. CUTTING DISK ‘‘4

71 LENGTH CEE PURLINS 2.0-2x4

5 BOX WELDING ROD 6011

2,000 TEX SCREW 2’’

12 ROUND BARS 16 MM

1 GALLON VULCA SEAL

2 G.I PLAIN SHEET #12

PROCEDURE:

1) REMOVE THE ROOF IN THE MORNING OF WORK AND AFTER WORK, PUT IT BACK
2) REMOVE THE C-PURLINS BY CUTTING THE EAGER AND REPLACE THE C-PURLINS
THE WELDING IT AND PUT ROUND BAR AND WELD
3) REPAIR THE LOUVERS OF THE AIR BREATHER
4) AND REPAINT THE BUILDING INSIDE ALL STEEL
5) REPAIR DOORS (PORTIONS) BY REPLACING THE STEEL PLATE
6) SEALED THE TEXSCREW OF THE ROOF

COST:

LABOR AND MATERIALS PhP 660,720

CARLITO OÑEZ