Вы находитесь на странице: 1из 9

iesl/pub/guide/01

Rehabilitation of the Revetment along


Galle Marine Drive

T.D.T.Pemasiri and B.Wickramarachchi

Abstract: Galle marine drive is the important highway segment which serves to pass from
Colombo to southern part of the country through Galle. It was constructed in early 1960’s. More than
one kilometer long revetment was also constructed to support the Marin Drive. It was functioned as a
shield to sea waves. However, after construction of the revetment, coastal process got affected and
wide beach was vulnerable to erosion. Successive rehabilitations have been carried out to sustain the
revetment by placing rock boulders, but none of those attempts were succeeded as a long term
solution. It was severely damaged with the hit of Tsunami in 2004 and thereafter it failed to perform to
the requirement. As a part of Tsunami Affected Area Rehabilitation Project (TAARP), rehabilitation
and improvements to the revetment was proposed to enhance its performance, together with other
holistic approaches for the development of the City of Galle.

Keywords: Revetment, Geo-textile, Wave overtopping, Wave transformation

1. Introduction Galle marine drive is a major highway segment


which serves to pass from Colombo to southern
Galle is the capital of Southern Province, part of the country through Galle. There is
situated 116 km away from the City of heavy daily traffic on this drive because this is
Colombo. (Figure 1). Galle, by been a coastal the one and only way to connect west and
city, is highly attracted by both local and south of the country along the coast line. It was
foreign tourists due to its distinct physical and constructed in early 1960’s [7]. Before
social characteristics. Hence improvements for constructing the Marine Drive, the beach
the coastal stretch are extremely important to stretch was rather wide with having
enhance the city’s protection and its scenic approximately 50 meters width. Marine Drive
beauty. was constructed along the seaward land strip,
with reclaiming the beach area. More than one
kilometre long revetment was also constructed
to support the Marin Drive. It was functioned
as a shield to sea waves.

2. Old Revetment Structure

Two Aerial photographs taken in the years of


1956 and 1994 are shown in Figure 2 and Figure
3 respectively. A long and wide beach can be
seen in 1956 inside the bay. Two main
Colombo
developments, Commercial Port and Marine
Drive, can be identified in 1994 image.
Galle However, after construction of the revetment,
coastal process got affected and wide beach was

Eng. T.D.T.Pemasiri, C. Eng., MIE(SL), B.Sc. Eng.


(Moratuwa), M.Sc. (AIT), Engineering Manager, Lanka
Hydraulic Institute

Eng.B.Wickramarachchi, B.Sc. Eng. (Moratuwa), Senior


Figure 1 - Location Map Engineer, Research & Design Division, Coast Conservation
Department

1
vulnerable to erosion. Successive rehabilitations overtopping by placing rock boulders. The size
have been carried out to sustain the revetment of rock boulders initially used for the revetment
by placing rock boulders, but none of those was in the range of 0.25 tons to 0.5 tons.
attempts were successful as a long term However fairly large rock boulders which are
solution. The cross section of old revetment is in the size range of 1.0 tons to 1.5 tons were
shown in Figure 4. being used for the outer layer due to the
continuous reinforcement carried out in recent
past.

Figure 2 - Aerial View of the Beach Stretch in Figure 4 - Old Revetment Section of Galle
1956 (Before the construction of Marine Drive) Marine Drive

Granular filters have been used in this instance The recent strengthening was done in 2005,
with little emphasis in both design and after the Tsunami. So far, placing of rock
construction. Geotextile was not used for boulders has not followed any designed
coastal structures construction industry in its process and it could be said merely a dump.
early stages in Sri Lanka. Instead of that This situation urged for rehabilitation of the
granular filters had been used in layers to revetment in a proper manner.
satisfy the filter criteria [7]. However the
structure is said to be insufficiently constructed 3. Problems with the Existing
mainly without proper filter layers and Condition
inadequate toe protection. The structure slope The revetment is about 1km in length (Figure
is 1:1 which has been too steep. 3). It has been severely affected by Tsunami in
the year 2004 and it is not structurally
performed well. It has been settled at several
places due to scouring, because scour
protection had not been used. Hence the
Marine Drive is also in a danger of collapse and
now it is continuously deteriorating its stability
due to monsoon waves. Moreover, following
problems can also be identified which are
Marine Drive connected with the mal-functioning of the
Commercial damaged revetment;
Port
 There are eight culverts along the Drive
Galle discharging rain and waste water to the
Fortress sea. At present three culverts are
completely blocked by accumulation of
sand. In other five, discharge is
interrupted by pollutants. Out of these
five, one is also seasonally blocked by
Figure 3 - Aerial View of the Beach Stretch in accumulation of sand. During high
1994 (After the construction of Marine Drive
rain, discharge capacity of functioning
and the Revetment)
culverts is insufficient and it results for
inundation of the town.
Revetment was strengthened by Coast
 Sand and sea water overtop the existing
Conservation Department (CCD) time to time
structure during monsoon periods,
as an immediate solution for erosion and
disturbing the traffic flow.

2
 Lack of sufficient space provided for only be maintained between these two factors.
pedestrians and recreational activities. The above wave height range satisfies these
 The existing revetment was not factors and its upper limit, 2.4m is then taken as
properly designed to the required the design significant wave height for the
criteria and the structure is already calculation. The probability distribution data
collapsed at several places due to are given in the Table 1
severe wave attack.
 Fishing site has been developed at one Table 1 - Probability Distribution Data
end of the Drive. Fishermen experience Range of Hs(m) % Occurrence % Exceedance
the problem of narrow beach. 4.4 4.2 0.01 0.00
4.2 4.0 0.01 0.01
Since that it needs urgent and long term 4.0 3.8 0.01 0.02

solution to protect Galle Road and as well as to 3.8 3.6 0.01 0.03

provide facilities to overcome the above 3.6 3.4 0.03 0.06

matters. On these grounds, rehabilitation of the 3.4 3.2 0.00 0.06

revetment along Galle Marine Drive has been 3.2 3.0 0.02 0.08

given the priority. 3.0 2.8 0.07 0.15


2.8 2.6 0.30 0.45

4. Design Considerations
2.6 2.4 0.70 1.15
2.4 2.2 1.44 2.59
2.2 2.0 3.23 5.82
Design of this revetment is based on the 2.0 1.8 7.18 13.00
theories and criteria given in the CIRIA/CUR 1.8 1.6 11.22 24.22
Manual [2] and Coastal Engineering Manual 1.6 1.4 11.79 36.01
[3]. 1.4 1.2 10.43 46.44
1.2 1.0 11.22 57.66
4.1 Wave Climate 1.0 0.8 19.72 77.38
Wave measurements carried out from 1988 to 0.8 0.6 18.64 96.02

1993 and from 1994 to 1995 (Final Reports of 0.6 0.4 3.97 99.99

Galle Wave Measurements prepared for Sri 0.4 0.2 0.01 100.00

Lanka Ports Authority by LHI Limited in the (a) from 1988 to 1993
years of 1993 [4] and 1995 [5]), are used to
determine the design wave parameters. The Range of Hs(m) % Occurrence % Exceedance
Report on the Wave Measurements off-Galle [8] 4.4 4.2 0.00 0.00
also confirms these wave parameters. These 4.2 4.0 0.00 0.00
wave measurements are obtained by means of a 4.0 3.8 0.00 0.00

wave profiling buoy deployed offshore of Galle 3.8 3.6 0.00 0.00

Lighthouse at a depth of 23 meters MSL. 3.6 3.4 0.00 0.00

According to that final report, the analysis of 3.4 3.2 0.00 0.00

wave recordings has clearly indicated that 3.2 3.0 0.00 0.00

mainly a swell wave dominated wave climate 3.0 2.8 0.00 0.00

had prevailed at Galle. Hence for the design, 2.8 2.6 0.00 0.00

only swell wave condition has been considered. 2.6 2.4 0.04 0.04
2.4 2.2 0.44 0.48
2.2 2.0 1.15 1.63
The report had provided two sets of wave
2.0 1.8 3.44 5.07
measurements collected for two different time
1.8 1.6 7.05 12.12
periods. Probability distribution tables of 1.6 1.4 10.27 22.39
significant wave height (Hs) for the above 1.4 1.2 10.01 32.40
periods are also provided. According to the 1.2 1.0 9.83 42.23
both data set it is obvious that a predominant 1.0 0.8 18.42 60.65
probability of occurrence lies between the wave 0.8 0.6 28.16 88.81
heights ranges of 0.4m to 2.2m. Hence it is safer 0.6 0.4 11.15 99.96
to adopt the upper limit of 2.4m-2.2m wave 0.4 0.2 0.04 100.00
height range as the design wave height.
Determining the design wave height is (b) from 1994 to 1995
governed by the two factors of safety and cost
effectiveness. The cost will increase (cost Source of dataset: Final Reports of Galle Wave
effectiveness decrease) while the safety Measurements prepared for Sri Lanka Ports Authority by
increases. Therefore an optimum situation can LHI Limited in the years of 1993 and 1995

3
According to the said report, the significant factors mainly influence the water level
wave heights and corresponding mean wave variations in the sea environment.
periods are concentrated mostly in the
respective ranges of 0.4m – 2.8m and 4.8s. The - Astronomical tide variations
extent of records lies within this band almost - Storm Surge (both positive and
100 percent. This finding, which could be negative effects)
regarded as a general pattern based on all data - Wind and wave set up (shallow water
collected in the seven year period starting from effects)
1988 to 1995. Hence the mean wave period (Tm) - Sea level rise
is taken as 4.8s for the calculation.
The highest astronomical tide with respect to
Wind direction is of great importance in MSL is considered as 0.47m. Having done the
obtaining wave measurements since wind is a adjustments for wind, wave setup and for the
major factor of wave. The predominant wind is storm surge, the design still water level is
along the directions between southwest and finalized to +1.12m MSL. Potential rise in sea
west, during the south west monsoon and level has not been considered as a critical
hence can be considered as 250° N, which criterion in this design calculation.
generates waves compatible with the selected
probability of occurrence. Overtopping
Run-up is calculated to determine the
4.2 Wave Transformation maximum crest level of the structure. Since the
Off shore measured data at 23m depth was proposed structure is extended around 15m
undergone to a wave transformation process to away from the concrete crown wall, 10%
get it transferred to the on shore. Those waves Exeedance level is considered for run-up level
with digitized bathymetry were transformed to calculation, assuming that the estimated
near shore using NSW mathematical model by overtopping will not affect the expected crest
accommodating wave shoaling and refraction. utilisation. The crest level is maintained at
Then the results were justified through a hand +4.0m MSL. Following equations given in the
calculations as per given in the CIRIA/CUR CIRIA/CUR Rock Manual are used for
Manual and the Shore Protection Manual [9]. overtopping calculation;

Orientation of bed contours can be Rm* = (Rc/Hs)√(sm/2π) …………….(1)


approximated to 130° N. Hence the angle of
incident wave will be 30°, when the Qm* = a exp (-bRm*/r) …………….(2)
predominant wave direction is taken as 250° N.
Accordingly, it can be concluded that the waves Qm* = {Q√(s/2π)}/√(gHs3) ……………(3)
break at a depth of 2.9m (≈3.0m)with a breaking
wave height of 2.2m. The Breaker Index is Where
selected as 0.78. Incident wave angle changes Rm* = Dimensionless freeboard
from 30° to 20° while undergoing the Qm* = Dimensionless overtopping discharge
transformation. Summary of wave Q = Estimated overtopping discharge
transformation is given below. r = run-up reduction factor

@ 23m depth On-shore Surprisingly there are very few data available
Hs (m) 2.4 2.2 describing the overtopping. Since that several
assumptions have to be made with respect to
Tm(s) 4.8 4.8
the proposed section.
Direction 250° N
 The run-up coefficient, r depends on
the type of construction. For this
4.3 Hydraulic Parameters
instance, it has been decided to be 0.5-
The main hydraulic parameters such as design
0.6 range which is compatible to
still water level, wave run-up and wave run-
rock/rip-rap with total layer thickness
down, overtopping and scour are considered.
greater than 2Dn50.
Design Still Water Level
 Coefficients ‘a’ and ‘b’ used in equation
For this purpose all the level values are referred
(1), are based on the generalised profile
to the Mean Sea Level (MSL) established by the
for smooth and bermed seawalls
Survey Department of Sri Lanka. The following

4
(Figure 5). However the proposed decided whether the waves are plunging or
structure (Figure 6) comprises of two surging, prior to use the Van Der Meer formula.
berms which are above the MSL. This Combination of several layers of rock in
kind of combination is not covered by different size ranges are used for the structure.
the CIRIA/CUR Rock Manual. Each layer has its own particular function to
Therefore the calculated overtopping perform.
discharge has to be subjected to further
explanation. Van Der Meer formula for deep water condition
is separately used for two different wave
 The estimated overtopping discharge is behaviours, plunging and surging. The
2350 l/s/m which is higher than the transition from plunging to surging waves is
recommended values for revetment determined by ξm and ξmc. ξm < ξmc for
seawalls given in the CIRIA/CUR Rock plunging waves and ξm > ξmc for surging
Manual. Calculation has been carried waves.
out using the coefficients given for the
cases covered by Figure 5. There for the ξm = tan(α)/√s …… (4)
actual overtopping for the proposed ξmc = [6.2P0.31√(tanα)]1/(P+0.5) .…. (5)
structure is assumed to be lower than
that, since its berms are above MSL. Where
α Structure slope, 0.5
s Wave steepness, 2πH/gT2
P Permeability factor, 0.4 (for a structure
having a armour layer and a filter
layer)

From equation (4), ξm = 1.935


From equation (5), ξmc =3.7681 (>ξm) hence
plunging waves prevail

Figure 5 - Generalised profile for smooth and Hs/ΔDn50 = 6.2P0.18 (Sd/√N) 0.2 ξm-0.5 …..(6)
bermed seawalls
Where
The proposed section encounters the risk of
high overtopping. Having this risk in mind, it is Sd Damage level , 2 (the limit equivalent
agreed to do the construction in two phases as a to 'no damage' )
precaution. The first phase will be the proposed N Maximum number of waves, 7500
structure and the second phase will be the (after this number of waves the
addition for controlling overtopping which structure has more or less reached an
only if it will be in a sever level. equilibrium)
∆ Buoyant density of rock, (ρr/ρw)-1
4.4 Structural Parameters
From equation (6), Dn50 = 0.72m. Nominal
Armour Sizes for Cover Layer diameter and the layer thickness comprising
Basic function of the cover layer is to withstand two layers of armour will be then ~1.44m.
and dissipate the energy caused by waves on However in practice, primary armour layer
the structure. The stability of the structure is thickness can be taken as 1.3m due to
mainly governed by the cover layer. The level interlocking of armours in two armour layers.
of withstanding and dissipating energy
depends on the type of material used for the M50 Mass of one armour unit, ρr*(Dn50)3
cover layer. Rip rap and rock armours, concrete
blocks, concrete mattresses, asphalt and Hence the weight of one armour unit is ~1.0t.
gabions are some of the materials used for the Accordingly, 1.0t- 1.5t range can be considered
cover layer. The cover layer should be as the armour for primary layer.
permeable and the permeability should be
greater than that of the filter layer. Under Layer or Filter Layer
Coastal structures normally constructed with
For determination of the armour sizes, Van Der one or more Filter layers. For a good function of
Meer formula is considered. It should be the filter layer, smaller particles should not be

5
washed through the layer and filter stones shape with the greatest principal dimension not
should not be washed through the armour. To exceeding 2½ times the least dimension.
satisfy this criteria, the stone size of the under
layer beneath the cover layer, should be in the There is one major quarry about 2okm away
range of 1/10 to 1/15 of the armour mass. A from the construction site. It supplies boulders.
filter should be more permeable than In addition, there are several quarries which are
underlying material, but less permeable than supplying rock materials suitable for both filter
the revetment cover layer. and core.

Nominal diameter and the mass of filter layer Geotextile


materials are given below; Geotextiles are often used as a separation layer
between fine under-lying materials and a
Dn50F = Dn50A/2 =0.36 m, granular filter layer. This prevents punching of
Hence, M50F =150.00 kg granular material into the sub soil. In order to
ensure effective filter performance, two basic
Nominal diameter and the mass of filter layer criteria must be met by a geotextile, pores
materials are given below; should be small enough to prevent excessive
loss of fines, and the geotextile should be
Dn50C = Dn50F/4 =0.09m permeable enough to prevent build- up of
Hence, M50C =2.34 kg excessive hydraulic pressure within the under
lying material.
Toe Protection
Toe protection for revetment is there for two 4.6 Design Life of the Structure
reasons; to provide support for the revetment Most revetment systems will have been
face and to prevent core material from sliding designed and constructed for a specific design
failure and protect against sour and erosion at life depending on the function of the revetment.
the toe of the structure. The design life will also be selected based on
economic factors such as the cost of
Toe protection can be provided in number of replacement. The elements of the revetment
ways. However the toe must be adequately tied should have adequate durability to last the
into the revetment cover layer to prevent design life of the structure.
washing out of material. Since rock revetments
are generally not susceptible to local scour, 1m
For this particular case, design life of 20 years
thickness is allowed at a depth of 1.5m MSL for
has been selected which gives 30% probability
toe protection.
of exceedance during a return period of 50
years. The graphs given in the BS 6349 Part 7 [1]
Crest Protection
and the Revetment Design Manual [6], give the
The crest is the top part of the revetment. Width
relationship among those parameters. Wave
of the crest is normally determined either by
climate is consequently decided based on that.
construction method (access on the core by
truck or crane) or by functional requirement
(road or crown wall on the top). Function of the 5. Practical Design Aspects and
crest protection is to prevent damage as a result Expected Outcomes
of overtopping. Absence of proper crest
protection leads to instability or deformation of The proposed revetment will be constructed
the structure. over the existing revetment and hence extended
to sea about several meters. It is a berm type
4.5 Construction Material structure with a slope of 1:2 and the crest level
of +3.85m MSL. It backs up the series of pre-
Stone Materials cast concrete wall element which are having the
All materials are obtained from sound gneiss top level of +4.00m MSL. The structure is
quarry stone or rock and have an apparent protected by a toe and further strengthened
specific gravity of not less than 2.6 t/m3 when against settlements by providing a Geotextile.
saturated and surface dry. The stones are All these combination contributes to attenuate
classified into several classes with respect to the the wave overtopping.
layer type. The rock material has be well-
graded quarry stone, rough and angular in Towards the land side, 3m wide walk way has
been provided for pedestrians and it is

6
followed by another turfed area. The existing a situation Coast Conservation Department
road side drain, manholes and the storm water who the client of the project handled the
outlets are redesigned and repaired in such situation very carefully.
away that to compatible with the levels of the

Sea Side

Figure 6 - Proposed Revetment Cross Section

new terrain. Dispersion points of all the storm Construction was started from the Galle
water outlets are extended through the fortress end and continued towards the port
revetment towards the sea. Now the new end. Quarries are available near to the
dispersion points are much beyond than what it construction site and as well as from far away
were in previous hence the outlet blocking will quarries, but the space for stock piles was
not be expected in future. restricted. Since that placing of armours had to
be done at the same time of the armour arrival
The walk way provides pedestrians for passing to the site. This process was highly depended
along and they can spend time leisurely at the on the skilfulness and the efficiency of the
turfed area. They can enjoy themselves with the workers.
incredible panorama around the bay which
surrounded by the Galle historical fortress and The methods adopted were not that modern
the Rumassala nature reserve. With the Gall but the usual way of carrying out the other
Port development, about 800m offshore coastal structures constructions. The existing
breakwater will be constructed to maintain the rock boulders were partly removed in order to
harbour tranquillity. It will further ensure the prepare access path to machines (back hoes). Al
calmness of the bay. In that scene the berm at most all the constructions were carried out in
+2.1m MSL will be expected to improve as a the low tide condition. Toe was laid first on top
marine walk way. In addition, there will be a of the geotextile. Sometimes divers had to be
possibility to develop this bay in such a way assisted in particularly the depth were not
that to allocate more marine activities such as accessible by the machines. Secondary layer of
yacht marinas, boat riding, etc. This possibility quarry stones were then places on top of the
has been considered as provisions for future existing surface of the structure. Levelled
developments in phase two. surface of the secondary layer (+0.8mMSL) was
used as the working platform for the
6. Method of Construction downward primary layer construction. Then
the levelled surface of the primary layer was
Construction of the proposed improvements for used as the working platform for the
the revetment has already commenced in mid construction of the upper part of the primary
2008. Since the area is highly occupied with layer. Likewise the construction was carried out
number of commercial, transport, sport and by two back hoes simultaneously. Figure 7 and
tourist activities, it is extremely difficult to Figure 8 show steps during construction and
handle the construction methods. It restricts the views after construction respectively.
space and complicates the interactions. In such

7
At present the entire structure has been flow for the storm water capacity within the
completed and is being utilised successfully. area. Sand accumulation will be expected at one
Construction was completed during nine end of the structure which could be
months. The construction cost was nearly LKR accommodated for fishing activities in the
75 millions which was provided by ADB as a future. Holistically it can be said that the
loan basis. performance will be enhanced by the proposed
design

Figure 7 - During Construction

Figure 8 - Views after Construction

7. Conclusion Acknowledgement
At present, overtopping is fully controlled by The Galle Marine Drive Rehabilitation was
the proposed berm revetment, hence confirms a implemented by the Tsunami Affected Area
secure and uninterrupted traffic flow along the Rehabilitation Project (TAARP), funded by
Galle Marine Drive. The structure is well Asian Development Bank, where the
supported by introducing a toe and the stability Department of Coast Conservation is the client.
is further confirmed by providing a geotextile.
My gratitude goes to the Project Director-Eng.
The proposed revetment provides more space Nissanka Perera, Chief Engineer-Mr.
for pedestrians and recreational activities. K.D.D.Wijewardhana for giving me this
Drains and culverts are re-designed to new opportunity. I extend my sincere thanks to Mr.
levels and capable of providing an undisturbed B.Wickramarachchi Senior Engineer, Research

8
and Design Division, CCD, for his guidance
and invaluable suggestions for the completion
of this design.

References

1. BS 6349-7 Maritime Structures, Part 7: Guide


to the design and construction of
breakwaters,1991

2. CIRIA/CUR Manual on the use of rock in


coastal and shoreline engineering,1991,
Construction Industry Research and
Information Association, Centre for Civil
Engineering Research and Codes.

3. Coastal Engineering Manual, June 2006, U.S.


Army Corps of Engineers

4. Final Report Galle Wave Measurments,1993,


Lanka Hydraulic Institute Ltd.

5. Final Report Galle Wave Measurments,1995,


Lanka Hydraulic Institute Ltd.

6. Kirsty McConnell, 1998, Revetment systems


against wave attach, A design manual,
Thomas Telford

7. Proceeding Seminar on Filters in Coastal


Structures, CCD-GTZ Coast Conservation
Project, 1989, Colombo, Sri Lanka.

8. Scheffer,H-J., Fernando,K.R.M.D. and


Fittschen,T., 1994, Directional Wave Climate
Study South-West Coast of Sri Lanka, Report
on the Wave Measurements Off Galle.,
Colombo, Sri Lanka.

9. Shore Protection Manual, 1984, Department of


the Army, U.S. Army Corps of Engineers,
Washington.

Bibliographies

1. Karsten Mangor, Shoreline Management


Guidelines, April 2001, DHI Water &
Environment, Denmark.

2. William Kamphuis, J., 2000, Introduction to


Coastal Engineering and Management, World
Scientific Publishing Co. Pvt. Ltd, Singapore.

Вам также может понравиться