Академический Документы
Профессиональный Документы
Культура Документы
03
SITE ANALYSIS - SITE INVESTIGATION- SITE PREPARATION- SETTING OUT
Prepared By Saurav Shrestha
3. EXCAVATION
EXCAVATION
Any man-made cut or cavity or trench or
depression in on earths surface formed by
earths removal
In simple words , excavation means digging.
TRENCHES
A narrow excavation in relation to its length
made below the ground surface.
Depth of trench is greater than its width but
not wider than 15feet.
3. EXCAVATION
DEEP EXCAVATION
If trench side is deep enough , it requires external support (side support)
Depth above 1.5m
DE-WATERING
Process of removing water or lowering the water table within construction
site to provide dry working platform.
Normally, dewatering process is done by pumping or evaporation.
Usually done prior to excavation for footings or to lower the water table that
might be causing problems during excavation.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
Suitable when excavation are deep and quanitity of sub-soil water to be handled is large.
In this system, sumps also known as wells, are constructed along the sides of the
trenches. Side drains are constructed along the bottom of the trenches by giving suitable
slope so that water getting access to these drain is led to the sumps. The water thus
collected is continuously pumped out by means of centrifugal pumps. The sumps may be 1m x
1m x 1m in size and side drains 200mm diameter semicircular. Sizes of sumps and drains
actually depend upon the area they are incharge of and intensity of seepage from subsoil.
Center to center spacing of sumps along the centre line of the trenches may vary from
40 to 60m.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
3. By cement grouting .
Used for stopping leakages from rocks or soft soils.
Stopping leakage from rocks : if soft patches are noticed in rocks, holes are drilled whose
depth, direction and inclination are varied depending upon the kind of the rock. Thereafter
the cement grout is prepared by adding sufficient water to the cement and holes are
filled with grout under pressure. The process of grouting is continued till no grout is coming
through the hole. No holes should be left unfilled.
Stopping leakage from soft soils : In this case, the process of formation of channels of
least resistance is undertaken before grouting. For this purpose, two pipes are driven at
small distance, and water is forced through one of the pipes until water appears in the
second pipe. Thus, number of channels of least resistance are formed in soil. Now, cement
grout is continued till grout appears in another pipe. The grout thus forced in the soil
around the trenches and thus, water proofing layer is formed and water leakage into the
trenches is prevented.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
3. By cement grouting .
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
4. Freezing Process
In this process area under excavation is frozen and the soil is converted into wall of frozen
of earth.
First, 100 to 150mm diameter steel pipes closed from bottom are driven into the ground
at an interval of 1-1.5m surrounding the area to be excavated. 25 to 50 mm diameter
small pipes (open-ended or perforated pipe)are inserted into the large pipe and
connected to a common pipe linked with refrigeration plant.
Secondly, the cold water or other liquid is circulated through circuit at -23 degree
Celsius to -30 degree. The cold liquid coming through small pipes goes up through large
pipes. If proper control is maintained in this process a wall of considerable thickness can
be developed and excavation of the enclosed area can be done without much difficulty.
Applicable only in case of water bearing sand, gravel or silt soil.
Very expensive process and stability of frozen soil is unreliable for longer times.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
4. Freezing Process
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
In this method, the soil around the area to be excavated is solidified using solutions of
chemical compounds like silicate of soda and calcium chloride.
First the pipes like well points are driven into the ground surrounding the area to be
excavated. One of above mentioned chemicals are forced into these pipes. After reaching the
desired depth , pipes are withdrawn and second chemical is forced through the pipe. As a
consequence, both chemical reacts chemically and solidifies the soil.
This process is very expensive and should not be used in ordinary conditions.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
7. Electro-osmosis
In case of very fine soil, it becomes difficult to be drained because such soils have very poor
permeability . These soils tend to hold the water by capillary action.
When direct current is passed through the two electrodes driven in the saturated soil , water
contained in the soil is repelled by positive electrode (i.e anode) and is attracted by
negative electrode (i.e cathode) .
When cathode electrodes are put into well points and anode electrodes at mid-distance
between two well points and direct current passed through them, the flow of ground water
towards cathodes i.e well points is increased, from where it is pumped out and rainage of the
area is achieved .
Very expensive process as it involves use of very expensive equipments.
3.2. Excavation in Water Logged areas
MEASURES ADOPTED FOR DEWATERING TRENCHES
7. Electro-osmosis
3.3. Protective systems in excavation
1 Shoring Support system for trench faces that
prevents soil movement, underground
utilities and foundation .
Types : Timber, Hydraulic, Pneumatic and
Screw jack systems.
2 Shielding Support system that includes trench box
to protect workers from cave-in or any
other accident.
pressure
4 Screw & Includes struts of a screw jack
jacks system that has to adjusted
system manually
Screw and Jacks system
3.4. TIMBERING IN TRENCHES
TIMBERING
Process of arranging timber planks in trenches to provide temporary
support to the collapsible sides of the trench
Polling Vertical
board sheeting
Strut
Wale
Runner
Soil to be
excavate
d
8 First and Box > to treat minor accidents and injuries on site.
9 Fencing and Lighting > to prevent any person falling in the trench and lights to avoid accidents.
IMPORTANT REFERENCES
BUILDING CONSTRUCTION BY R. CHUDLEY
PAGE 251-256