SALINE WATER CONVERSION CORPORATION

STRATEGIC RESERVOIRS AT MAKKAH PHASE II & TAIF


PHASE I

REVISION SHEET
DOC. TITLE: TIE-IN STATION TAIF P&I DIAGRAM

FROM REV: A TO REV: B


DOC. NO: 7 6 - Q P 2 0 - D - 0 0 1
REV. DATE: 13.05.2018
CHANGES TO THE DOCUMENT: Acc. to Engineer’s Comment Sheet EH-AH-D-0101
(10.04.2018)
ENGINEER’S NOTE NO EMM dated 3 - 6 April 2018
CONTRACTOR’S ACTION
1. In order to review such submittal
regarding P&IDs, site layout and pipe Diameters and materials are as per below
schedule (indicating diameters and tender documents
materials) should be approved firstly.  M06 Valves for Water Projects-Rev8
 QC10-H-048 M08 Piping Materials for
Stations-Rev4
 Tie-In Station Existing / New Taif
Strategic Reservoir - P&I Diagram
 New Taif Strategic Reservoir - P&I
Diagram
Size of piping and site layout piping
arrangement is verified within hydraulic
study.
2. All equipment’s (valves & instruments)
typical signal, interlocks and function Noted and revised accordingly.
requirement should be added.

3. The fow meter reducer (1400/950)


and dimension (950mm) are not Noted and revised accordingly.
standard as Mag. Flow meter; it should
be subjected to final design.

4. Dismantling joints installation should


be downstream side for the following Noted and revised accordingly.
units; 76XQ01z251, 252, 254, 255, 258
and 259.
5. Symbol of Control Valve to be used as
per "Legend" given in Contract Noted and revised accordingly.
specifications for uniformity.
6. The Diameter of pipe in station
Noted and revised accordingly.
outlet valve shall be 60”.
OTHER CHANGES (REASONS FOR CHANGES):

none