Вы находитесь на странице: 1из 5

Akhtar Ansari

From: Shahid <shahid.aa@metalfabme.com>


Sent: Thursday, June 14, 2018 2:06 PM
To: rafeek@metalfabme.com
Cc: Tabrez; 'Riaz | Metal FAB'; 'VINEETH'; dhanesh.pd@metalfabme.com; 'Anish Madhavan'; Salahuddin; akhtar.a@metalfabme.com; Liagath;
Harsiddhkumar; Janshar; robert.a@metalfabme.com; Chesvin; Aravind; Arun
Subject: Pending Document list & Submission Dates

Dear Sir, 
 
Please find the pending document list and its forecast submission dates below for your kind review. 
 
Pending Document List 
 
MFJO709 ‐ Flare Gas Recovery Unit (Zeeco) 
 
Engineering: 
 
 Revised Isometric Drawing (Code B) – Awaiting confirmation on tie rod material 
 
QC Documents: 
 
 Revised Welding Documents (Heat Exchanger) – Under Testing  
 Revised Positive Material Identification (Optical Emission Spectrometer Test) – Proposed date of Submission is 20th June 2018 
 
MFJO723 – Thermal Oxidizer (Aereon) 
 
 Revised Packing Procedure  
                                                       
MFJO727 ‐ BAPCO Flare Stack (John Zink) 
 
 Revised Trail Assembly Procedure 
 Revised Galvanizing Procedure – Proposed date of Submission is 18th June 2018  
 

1
MFJO728A ‐ ADCO CIS (UMG) 
 
 Strainer Datasheet  
 Motor Datasheet  
 
MFJO734 ‐ Flare Package ‐ Technip (John Zink) 
 
 Revised Galvanizing Procedure (Galva Coat)  
 Revised Painting procedure (Awaiting Technip Comments)  
 Revised Trail Assembly Procedure (Code 2) 
 
MFJO735 ‐ Odorant Package (Milton Roy) 
 
 Revised Hydro Test Procedure – Proposed date of Submission is 18th June 2018 
 Instruments Datasheets  
 FAT Procedure 
 
MFJO748 ‐ Air Receiver (Atlascopco)  
 
 Transportation Drawing – Awaiting Comments / Approval on GA 
 
MFJO750 – Trail Gas Incinerator Stack (Spetco)  
 
Engineering  
 
 Revised Stack General Arrangement drawing – Awaiting FE analysis from Vendor 
 Revised Stack Mechanical Design Calculation – Awaiting FE analysis from Vendor 
 
QC Documents 
 
 Revised Galvanizing Procedure – Proposed date of Submission is 20th June 2018 
 Painting Procedure – Proposed date of Submission is 20th June 2018 
 
MFJO755 ‐ Pressure Vessels (Eversendai) 
 
Engineering: 
 
2
 Revised Vessel GA Drawing (95 Ltr) – Proposed date of Submission is 20th June 2018 
 Revised Mechanical Design Calculation (95 Ltr)  – Proposed date of Submission is 20th June 2018 
 Revised Vessel GA Drawing (2400 Ltr) – Proposed date of Submission is 20th June 2018 
 
QC Documents: 
 
 Revised Hydro Test Procedure – Proposed date of Submission is 20th June 2018 
 
MFJO758 – Foam Concentrate Storage Tank (Consilium) 
 
Engineering: 
 
 Revised Foam ‐ Tank GA Drawing  – Proposed date of Submission is 18th June 2018 
 Revised Foam Tank ‐  Mechanical Design Calculation – Proposed date of Submission is 18th June 2018 
 Revised Foam tank ‐ Lifting Lug Calculation – Proposed date of Submission is 18th June 2018 
 Revised Foam tank ‐ Lifting Loading Data – Proposed date of Submission is 18th June 2018 
 
QC Documents: 
 
 Revised Welding Documents – Proposed date of Submission is 18th June 2018 
    
MFJO760 ‐ PDO Compressor Skid (Atlascopco) 
 
 Cable, Cable Tray and Cable Gland  Datasheet  
 Ball Valve Datasheet 
 
MFJO762 ‐ Rania Compressor Skid (Atlascopco) 
 
Engineering 
 
 Revised Dry air receiver drawing (25 m3) – Awaiting TQ Response from Client   
 Revised Wet air receiver drawing (50 m3) – Awaiting TQ Response from Client   
 Revised Dry air receiver Mechanical Design Calculation (25 m3) – Awaiting TQ Response from Client   
 Revised Wet air receiver Mechanical Design Calculation (50 m3) – Awaiting TQ Response from Client   
 Revised Skid General Arrangement Drawing – Awaiting TQ Response from Client  
 Revised Piping & Instrumentation Diagram – Awaiting TQ Response from Client  
 Revised Wiring Diagram 
3
 Name Plate Drawing  
 Load Test Procedure  
 Structural GA Drawing   
 
QC Documents 
 
 Revised Hydro Test Procedure –  Proposed date of Submission is 20th June 2018 
 Painting Procedure – Proposed date of Submission is 20th June 2018 
 
MFJO769 – Air Receivers (Emerson) (On hold) 
 
Engineering 
 
 Vessel GA Drawing  
 Mechanical Design Calculation  
 
QC Documents  
 
 Inspection & Test Plan 
 Welding Documents 
 Radiographic Test Procedure 
 Painting Procedure 
 Hydro Test Procedure 
 
MFJO770 – KIPC VRU (John Zink) 
 
 Cable Tray Datasheet  
 
MFJO772 – Incinerator Air Duct (John Zink) 
 
 Welding Documents – Proposed date of Submission is 20th June 2018 
 Painting Procedure – Proposed date of Submission is 20th June 2018 
 
MFJO773 ‐ RANIA Flare system (John Zink) 
 
Engineering: 
 
4
 Stack GA drawing – Proposed date of Submission is 14th June 2018 
 Mechanical Design Calculation for Stack – Proposed date of Submission is 14th June 2018 
 Structural GA Drawing – Proposed date of Submission is 14th June 2018 
 Utility Piping Drawing – Proposed date of Submission is 18th June 2018  
 
QC Documents  
 
 Painting Procedure – Proposed date of Submission is 21st June 
 
Regards, 
 
SHAHID A.A    