FASES DE CONTROL MONTO

A01. MOVILIZACION Y DESMOVILIZACION 25000


INDIRECTOS
A02. CONSTRUCCION CAMPAMENTOS 10000
P01. EXCAVACION 16300

P02. RELLENO 19950

P03. CONCRETO 74120


DIRECTOS

P04. ACERO 69000

P05. ENCOFRADO 23800

P06. PAVIMENTOS 57250

295420

1
2
3
4
SEM1 SEM2 SEM3 SEM4 SEM5
HH %Incidencia (HH)

- 50%
1000 70% 30%
252 39% 50% 50%
652 8.9%
400 61% 25.00% 25% 25% 25%
760 760 1 10.4%
36 2% 70% 30%
715 48% 50%
1502 20.5%
36 2% 70%
715 48%
920 50% 50% 50%
1840 25.1%
920 50% 50%
595 50% 50% 50%
1190 16.2%
595 50%
38 3%
1398 19.0%
1360 97%

7342 100.0%

INTEGRANTES

Rojas Paisig Robert Henderson


Cardenas Pariona William
Rojas Diaz James
Vilcherrez Mendieta Raul

xzxzx
SEM6 SEM7 SEM8 SEM9 SEM10 SEM1

50%

20% 30% 30% 20%

50%
30%
50% 50%

50%

50% 50%
30% 40% 30%
50% 50%
PARCIAL (HH) 0
ACUMULADO (HH) 0
% (HH) 0%

planificado
S1 0%
S2 1%
S3 9%
S4 23%
S5 41%
S6 59%
S7 71%
S8 79%
S9 91%
S10 100%
SEM2 SEM3 SEM4 SEM5 SEM6

0 0 126 126
100 100 226 226
100 100 100 100
152
25.2 10.8 0 0
0 0 357.5 357.5
25.2 10.8 382.7
0 0 25.2 10.8
0 0 0 0
460 460 0 0
460 460 460
0 0 460 460
297.5 297.5 0
297.5 297.5
0 0 297.5

100 585.2 994.3 1366.2 1277.8


100 685.2 1679.5 3045.7 4323.5
1% 9% 23% 41% 59%

Curva S
planificado 120%

100%

80%

60%

40%

20%

0%
1 2 3 4 5 6 7
20%

0%
1 2 3 4 5 6 7
SEM7 SEM8 SEM9 SEM10

152 228 228 228 228 152 152


0 0
0 0
368.3 357.5 357.5
0 0
357.5 357.5

460

0
297.5 297.5
297.5
11.4 15.2 11.4
11.4 695.2 691.4
0 680 680
1277.8 883 596.9 847.2 691.4
4323.5 5206.5 5803.4 6650.6 7342
59% 71% 79% 91% 100%

Curva S

6 7 8 9 10
6 7 8 9 10