Вы находитесь на странице: 1из 52

Client code

TECNOMARE S.p.A.
3200 00 FBRV 80101

30124 Venezia, San Marco 3584, +39 041796711


Tecnomare code
20139 Milano, Via Caviglia 11, +39 0255211027
A1390-PRO-T001-001.0

originating division originating office: document codes

NAOC

OPERATED PLANTS

DECOMMISSIONING SPECIFICATION

distribution:

supplementary notes:

0 08/03/2004 Preliminary Issue For Comments 46 Travagnin Perini Perini Peselli


rev. date description pages prepared checked approved authorised
The contents of this document is the property of TECNOMARE S.p.A. and cannot be utilised or divulged without authorisation of the firm.
Eni
E&p Division

DOCUMENT NUMBER
3200 00 FBRV 80101
DISTRIBUTION HOLDS
NAOC, ITEM, AMTE, TEPE

DOCUMENT TITLE

NAOC

OPERATED PLANTS

DECOMMISSIONING SPECIFICATION

ABSTRACT

P0 PRELIMINARY ISSUE FOR COMMENTS Feb 04 46 TM TM TEIC

Prepared Checked Approved


REV DESCRIPTION OF REVISIONS DATE PAGES by: by: by:
Eni S.p.A.
E&P Division

CONTENTS
1. SCOPE OF WORK OUTLINE ...............................................................................................................................................5

2. GENERALITIES ........................................................................................................................................................................7
2.1 DEFINITION OF TERMS AND ABBREVIATIONS.....................................................................................................................8
2.2 SITES CLASSIFICATION AND GENERAL DESCRIPTION ........................................................................................................9
3. PREPARATORY WORKS ................................................................................................................................................... 11

4. DECOMMISSIONING CRITERIA ................................................................................................................................... 15

5. ONSITE ACTIVITIES ........................................................................................................................................................... 17


5.1 GENERALITIES......................................................................................................................................................................18
5.2 PLANT SECURING.................................................................................................................................................................19
5.3 SET UP OF TEMP ORARY UTILITY SYSTEM .....................................................................................................................19
5.4 EQUIPMENT ELECTRICAL AND MECHANICAL ISOLATION ...............................................................................................19
5.5 EQUIPMENT AND LINES DEPRESSURIZATION AND OR DRAINING .................................................................................20
5.6 FLOW LINES AND PIPELINES DRAINING AND FLUSHING..................................................................................................20
5.7 EQUIPMENT AND LINES PURGING AND FLUSHING..................................................................................................21
5.8 CONTROL OF THE ATMOSP HERE INSIDE EACH ITEM OF EQUIPMENT .............................................................................22
5.9 PLANT STATUS BEFORE STARTING DISMANTLING ACTIVITIES ......................................................................................23
5.10 A BOVE GROUND INSTALLATIONS REMOVAL ...................................................................................................................24
5.11 SITE RECLAMATION AND RE -VEGETATION.......................................................................................................................26
5.12 END OF WORKS AND AUTHORITIES APPROVAL:...............................................................................................................26
5.13 HEALT AND SAFETY ENVIRONMENT .................................................................................................................................26
5.14 BATTERY LIMITS..................................................................................................................................................................29
5.15 ORGANIZATION FOR PLANT DISMANTLING......................................................................................................................29
6. TABLES ...................................................................................................................................................................................... 30

7. METHODOLOGIES ............................................................................................................................................................... 31
7.1 DECOMMISSIONING COST DEFINITION ..............................................................................................................................32
7.2 SITES CLASSIFICATION........................................................................................................................................................32
7.3 DECOMMISSIONING COST & TIME EVALUATION............................................................................................................33
7.3.1 Flow stations.............................................................................................................................................................. 33
7.3.2 Process plants............................................................................................................................................................ 37
7.3.3 Booster Station.......................................................................................................................................................... 37
7.3.4 Flow lines................................................................................................................................................................... 37
7.3.5 Pipe lines.................................................................................................................................................................... 39
7.4 LIFTING AND TRANSPORTATION.........................................................................................................................................40
7.5 DISTANCES A SSETS – FINAL DISPOSAL SITES ..................................................................................................................40
8. HYPOTHESIS AND ASSUMPTIONS .............................................................................................................................. 41

9. EXCLUSIONS .......................................................................................................................................................................... 42

10. SUPPORTING TABLES ................................................................................................................................................... 43

APPENDIX A - APPLICABLE NIGERIAN REGULATIONS

APPENDIX B - REFERENCE DOCUMENTS

February 2004 Page 3


Eni S.p.A.
E&P Division

February 2004 Page 4


Eni S.p.A.
E&P Division

1. SCOPE OF WORK OUTLINE


The aim of this job is to give the guidelines how to estimate the relevant costs and times for the
decommissioning of n. 358 oil / condensate / gas production wells and pertinent facilities, located in
some South Eastern States of the Federal Republic of Nigeria.

NAOC operations are relevant to 61 plants concentrated in 4 Oil Mining Leases (OML) or blocks:
OML 60 (Delta, Imo States), OML 61 (Rivers, Delta States), OML 62 (Delta, Bayelsa States), and
OML 63 (Bayelsa, Rivers State). OMLs 60 and 61 are located on land while 62 and 63 are on
swamp area.

The total concession area, in the South Eastern States of the Federal Republic of Nigeria, is
5324 SqKm comprising of 358 SqKm in OML 60, 1499 SqKm in OML 61, 1221 SqKm in OML 62
and 2246 SqKm in OML 63. The below map relevant to “NAOC OPERATED FIELDS” shows all
sites object of this study

The main technical information relevant to the operated sites have been collected in the attached
Site Data Bank and Site Data Sheets that are an integral part of this document.
Times and costs have been estimated on the basis of several assumptions relevant to the
hypothetic decommissioning scenario at the time of abandonment; therefore they are to be deeply
verified during the detailed decommissioning projet when all information relevant to plants
conditions, manpower and working means availability, etc will be well known.

Sites decommissioning and abandonment criteria are defined under the chapter 3 of this
document. Generally they are in accordance with Nigerian local regulation and statutory
requirements as well as with ENI SpA policy for site decommissioning. In particular the aspect
relevant to safety, environmental impact and emission shall be considered and the reference
documents to be applied are the Document No. 1.3.1.61 titled “HSE Technical Guidelines for
Decommissioning Activities”.

February 2004 Page 5


Eni S.p.A.
E&P Division

OKPAI

NAOC OPERATED FIELDS KWALE


BENIKU ODUGRI

AKRI
ASHAKA OML 60
ASEMOKE AGWE

WARRI
ISOKO S. OGBOGENE MBEDE
UMUORU EBOCHA
IRRI OBRIKOM

FORCADOS OML 61 OBIAFU


EBEGORO
OMOKU W

SAMABRI E.
IDU
SAMABRI

BENIBOYE
TAYLOR CR.
OML 62
TUOMO W OSHI
TUOMO MANUSO

EKEDEI

CLOUGH CREEK OML 63


AJAKETON
OGBAINBIRI
AZUZUAMA PORT HARCOURT
EMETTE

PIRIGBENE

OBAMA
TEBIDABA
FIELDS FROM TABLES 2.3 AND 2.4 NIMBE S

DEVELOPED

UNDEVELOPED

Fig.

February 2004 Page 6


Eni S.p.A.
E&P Division

2. GENERALITIES

February 2004 Page 7


Eni S.p.A.
E&P Division

2.1 DEFINITION OF TERMS AND ABBREVIATIONS

Abbreviation Meaning
NAOC Nigerian Agip Oil Company
Nil Not present
N/A Not applicable
PL Pipeline
GL Gas line
TL Test line
DL Delivery line
OML Oil Mining Lease
MSTBD Thousand of Stock tank barrel
MMSCFD Million Standard Cubic Feet per Day
DP Design Pressure
DT Design Temperature
V Volume
TDP Total Different ial Pressure

Decommissioning:

Decommissioning is the process whereby part of facilities, such as a platform or a plant or an


equipment is rendered safe and usually removed when the production of hydrocarbons from the
reservoir becomes unprofitable.

Decommissioning project:

Decommissioning operations are generally similar to those for their installation. Like installation
operations, decommissioning work needs to be carefully engineered and specific procedures
should be followed since, in most cases, the facilities to be removed are approaching the end of
their working life and hence it is necessary to consider all modifications that have taken place over
time.

Decommissioning contractor:

Decommissioning contractor is the contractor selected for facility decommissioning.

Company:

Company is NAOC

February 2004 Page 8


Eni S.p.A.
E&P Division

2.2 SITES CLASSIFICATION AND GENERAL DESCRIPTION

Plants object of this study have been classified as per the below listed categories. Homogeneous
features: like type of prevailing installed equipment, degree of accessibility, etc characterize each
site category.

q Flow stations
q Flow lines and pipelines (including test and delivery lines)
q Well heads
q Process plants

Flow Stations:

A typical flow station is usually equipped with the following installations:

q Three or more stages of separation: high pressure (HP), medium pressure (MP), and low
pressure (LP)
q Very high-pressure separator (HHP)
q A test separator
q Various pumps (number of pumps depends upon the oil production rate)
q A power generator unit
q A firefighting system

In addition to the above listed facilities, each flow station could be equipped with some other
appurtenances typical of each installation (i.e gas compression facilities, hot oil plants, dehydration
unit, etc). Plant data sheets state the main plants’ features on the basis of the available technical
information of each plant.
The produced crude is generally sent via pipeline network to the oil centres, then to terminals
where it is stored; while the produced natural gas is sent (when the flow station is equipped with
gas compression and gas gathering facilities) via gas pipeline network to gas plants, then to gas
pipeline network.

In flow stations not equipped with gas gathering facilities, a portion of the gas produced by the
separation process is used as fuel gas or as instrument gas, while the remaining is flared.

Total number of NAOC operated flow station is 11.

Pipelines:

Each flow station is connected to the nearest oil centre by means of a pipeline. Oil produced in the
flow station is then treated in the relevant oil centre; pipeline network average size is 8”. For the
purpose of this study all pipes have been assumed to be underground.

Flow lines:

Each wellhead is connected to the nearest flowstation by means of a flowline. Flowline average
size is 4”. For the purpose of this study all pipes have been assumed to be aboveground.

Gas lines:

When the flow station is equipped with a gas compression facility the gas produced by the
separation process is sent to the nearest gas plant and then to the pipeline network by means of
gas lines; gas lines average size is 8”. For the purpose of this study all pipes have been assumed
to be underground.

February 2004 Page 9


Eni S.p.A.
E&P Division

Test Lines:

In some cases process considerations have suggested the installation of test lines to allow for
facilities testing; test lines average size is 4”. For the purpose of this study all pipes have been
assumed to be aboveground.

Process Plants:

This category includes the following kinds of installations:

q Gas plants (Total number 2) OB/OB - Kwale/Okpai


q Oil centres (Total number 1) Ebocha
q Booster stations (Total number 1)
q Oil and gas storage terminals (Total number 1) Brass Terminal

February 2004 Page 10


Eni S.p.A.
E&P Division

3. PREPARATORY WORKS

February 2004 Page 11


Eni S.p.A.
E&P Division

Generalities:

Decommissioning project is to be considered as all other projects of the plant’s life; therefore it
shall be deeply engineered, taking also into consideration that the equipment are close to the end
of their life and therefore they are to be carefully handled to avoid injuries to people and to
environment.

The main steps of a typical decommissioning project are the following:

q Preparation and approval of a Preliminary Project Implementation Plan


q Obtaining Authorities approval
q Search and qualification of a contractor to carry out the job:
o Issuing of an Invitation To Tender (including preparation of the necessary
documentation)
o Technical and economical evaluation of the various offers (documentation to be
submitted within the tender)
q Project execution
o Development of the Detailed Project
o Detailed site survey visit and relevant report
o Engineering (preparation of project documentation)
o Onsite activities
o End of works authorities approval

Preliminary project implementation plan (to be at Company care):

A preliminary project implementation plan is the first step of the decommissioning project. It shall
include at least the following activities:

1. Search of all necessary as built revision of engineering documents relevant to the facilities to
be decommissioned
2. Site survey visit to verify that the available documents reflect the actual plant configuration
and to verify the plant general status.
3. Collection of all applicable national and regional regulations
4. Identification of Regional issues in the project areas (labour regulation, security,
communications, etc.)
5. Validation and integration of decommissioning criteria
6. Preliminary identification of requested skills, tools and equipment necessary to carry out the
decommissioning
7. Preliminary estimation of the number of people to be involved in the decommissioning
project, including project management, workers, helpers, etc.
8. Identification of long lead items necessary for the decommissioning project wherefrom start
the qualification and purchasing activity
9. Assessment of a preliminary work schedule based on the available information
10. Assessment of a preliminary project cost based on the available information

Within the completion of this phase, a preliminary project implementation plan is to be issued
including expected cost, time and manpower involvement for plants decommissioning. Project
implementation plan shall be approved by company management.

Authorities approval:

Before a facility can be abandoned and the relevant decommissioning project can start, the
licensees must obtain a written approval from Nigerian Authorities for petroleum. Particularly, an
abandonment plan is to be prepared and all requested documentations submitted in order to get
approval from the Director of Petroleum Resources.

Accordingly to local legal constraints and to contractual undertakings to be verified in each case, it
is therefore recommended to prepare a detailed decommissioning program to be communicated
and/or submitted to the local Authority and/or Joint Venture partners.

February 2004 Page 12


Eni S.p.A.
E&P Division

All requested approval, documents and issues to be solved before abandonment and
decommissioning can start, are better defined under Appendix A “Applicable Nigerian Regulations.

Once authorities’ approval has been obtained the decommissioning project can start.
Invitation to tender:

In order to select a contractor to carry out plants decommissioning, Company shall issue an
invitation to tender, attaching a technical specification collecting at least the following documents:

q Location of facilities to be decommissioned


q Preliminary description of decommissioning works:
o Sites preparation
o Clean up
o Mechanical electro-instrumental and civil demolition
o Disposal of scraps or equipment selling
o Site restoration and land reclamation
q Lay-out and underground drawings of sites to be decommissioned
q Documentation stating the main characteristics of sites to be decommissioned (i.e plant data
sheets including main equipment weights and dimensions, P&ID, etc)
q Preliminary report on existing fillings (water, hydrocarbons, lube oil packing, etc)
q Photographs of the sites object of the decommissioning study
q Description of the boundary conditions (i.e. site’s conditions at the time of hand over to
decommissioning contractor, etc.)
q All information highlighting to decommissioning contractor all possible risks of injuries for
people and environment during the decommissioning execution
q HSE requirements
q Decommissioning criteria

In addition to the above listed documentation, licensee, upon contractor request, has to provide the
contractor with all other information that can help in preparation of the decommissioning project
(i.e. structural calculation reports, installation manuals and documentation, etc.)

Tender documentation:

Contractor shall supply, within his tender, at least the following documentation:

q Preliminary breakdown of activities to be carried out including a preliminary description of the


relevant procedures
q Decommissioning criteria on which the decommissioning project is based on or endorsement
of company criteria
q Preliminary decommissioning project schedule
q Preliminary personnel employment plan for each activity
q Preliminary list of equipments and tools to be used (cranes, scaffolding, special tools, etc.)
q Preliminary plan and characteristics of the areas used for wastes disposal
q Preliminary indication of the final disposal procedure of steel scrap, concrete and plastic
debris, chemicals and liquid hydrocarbons (if any), etc. (Authorized disposal areas)

Contractor shall also, upon customer request, provide any other documents or drawing necessary
to better define the decommissioning process that contractor wish to follow.

Detailed Survey Report:

Once the preliminary project implementation plan has been approved and a contractor selected,
detailed site survey visit shall be paid and relevant reports shall be issued. Each detailed site
survey report shall include at least the following:

1. Number, location and size of the Plants and installations to be decommissioned

February 2004 Page 13


Eni S.p.A.
E&P Division

2. General and photographic description of each Site and relevant installations. Including site
general conditions with particular attention to all aspects related to safety. Report on sewer
system, fire fighting system equipment accessibility means conditions shall be well detailed
3. Buildings description: materials, dimensions, drawings or sketches with approximate size,
description and documentation of the inside fixtures and systems, etc
4. Report on Electrical Equipment (including UPS Battery Systems, MCC panels, etc)
5. Report on visible or invisible existing fillings (water, hydrocarbons, lube oil, packing) as
ascertained by ultrasonic equipment or other reliable detection system. In particular the
volume and the specification (composition, free flowing property, water content, salinity) of
the recoverable hydrocarbons shall be appraised and the viable method for recovery shall be
stated
6. List of equipment and systems that may be re-habilitated for On-Site decontamination
Processes (water strippers, power generators, heaters, steam generators, clarifiers) at a
reasonable cost and effort.
List of equipment that could be refurbished to be re-used and/or sold to the second hand
market
7. Report on the conditions of the launching / receiving pigging stations, that could be used to
pig the line for hydrocarbons displacement and recovery and on conditions of the relevant
lines
8. Report on available oil/water separator and surge capacity for flushing water and / or
hydrocarbon recovery
9. Visible environmental damage and hazards
10. Visible or potential hazardous conditions for Staff and Labour
11. Existing routings and routings obstructions within the Site
12. Access to Site description and constraints for heavy equipment haulage (roads, bridges,
seasonal road disability expectations, right of way claimed by third parties), alternative
routings, evacuation routings, fuel availability on route, advice for dark hours travelling
13. The reference Level 0-0 for the land after Decommissioning completion
14. In site or nearby the Site availability of logistic services (power, service water, potable water,
petrol station, housing, tools and consumable stores, equipment, vehicles and tools rentals)
15. Local labour (skilled, unskilled) availability, wage expectation and transportation to / from
Site
16. Local qualified transportation companies availability, with particular reference to
transportation of chemicals and other pollutant materials
17. Local waste disposal areas availability and suitability for the service, with particular reference
to disposal of chemicals and other pollutant materials
18. Report on local medical assistance centers that can be contacted in case of emergency

Project documentation:

Contractor shall submit a removal manual including all drawings, procedures and documents
necessary to describe the modality to be complied with for plants decommissioning. At least the
following shall be described in the manual:

q General decommissioning procedures (plants facilities and wells shut down sequence. To be
defined in cooperation with client operation group)
q Procedure to ensure plant safeness (i.e. work permit procedure, temporary fencing, walkway
securing, etc)
q Technical specification for plant logistic services and medical assistance during site
decommissioning works
q Procedure for fluid lines cutting
q Procedure for equipment removal
q Diagram for cutting the fluid lines in such a way to reduce, as much as possible, the fluid
spillages (if applicable)
q Procedure for cutting the electric and hydraulic lines (if applicable)
q Diagram for temporary and final lifting including indication of the lifting points and relevant
requested calculations and certifications
q Identification of equipment to be subject to clean up activity and description of precaution to
be taken to avoid spillages and consequent injuries to people and environment

February 2004 Page 14


Eni S.p.A.
E&P Division

q Transportation engineering (if any)


q Disposal plan and final disposal procedure definition
q Land reclamation and site re-vegetation procedure
q Site activities risk assessment study and emergency plan
q Description of plant final configuration

4. DECOMMISSIONING CRIT ERIA

February 2004 Page 15


Eni S.p.A.
E&P Division

This study is based on the following decommissioning criteria:

q All underground piping is to be pigged (where applicable) flushed, plugged and kept in place
q All above ground piping and equipment are to be pigged (where applicable) and flushed;
then they are to be totally removed
q Removal of foundation piles in swamp areas is not considered
q Pollutant materials are to be disposed as per local regulations and statutory laws
requirements
q All areas are to be cleaned; all materials removed and properly disposed, moreover areas
reclamation is to be considered
q All paved areas, roads and equipment foundations are to be totally demolished, removed
and relevant debris properly disposed
q All sites are to be restored as they were before starting the exploration and production
activities (As per ENI HSE policy request)
q Pipelines and flowlines flushing is to be continued up to a water purity of 10 p.p.m. in
volume; a water sample is to be taken every 4 hours of flushing
q Residential areas belonging to process plants are to be kept in place to be handled to local
authorities / communities

February 2004 Page 16


Eni S.p.A.
E&P Division

5. ONSITE ACTIVITIES

February 2004 Page 17


Eni S.p.A.
E&P Division

5.1 GENERALITIES

Once the preparatory works described under the relevant chapter have been completed, the onsite
activities can start. Initially all wells are shut in by operator. From this moment, a rigorous work
permit procedure shall be established and maintained until the plant functional units are fully shut
down, drained and depressurized.

During wells shut in, the operator remains on the plants (with a reduced number of manpower) in
order to run and maintain the limited production and the safety systems. A temporary utility system
shall be set up: provision for an external source of power is to be provided (if necessary), eventual
power generator units powered by produced gas are to be switched (if possible) to be powered by
diesel fuel, external source of gas to maintain the pilot flame of the flare systems and a certain
amount of diesel fuel to power the existing power units, are to be provided, etc. (At the scope gas
lines belonging to the plant can be used as a gas reservoir since they are pressurized).

Particular attention shall be paid, in shutting down the various systems, to the operating aspects of
the process (i.e. in case a hot oil system is present on the plant, the relevant pumps cannot be shut
down until the oil temperature has reached a certain minimum value, surge phenomena for
centrifugal compressor shall be prevented, etc.). In addition, the shut down sequence shall provide
the following system to be maintained in operation as long as possible in order to ensure a safe
and reliable decommissioning process:

q Firefighting
q Domestic and industrial sewer
q Flare and wet blow down
q Cooling water (if any)
q Instrument and plant Air

Once the plant has been shut down, complying with the above-described minimum requirements,
the following activities shall be carried out:

q Plant securing
q Set up of a temporary utility system
q Equipment electrical and mechanical isolation
q Equipment and lines depressurization and or draining (as applicable)
q Flow lines and pipelines draining and flushing
q Equipment and lines purging
q Equipment and lines flushing
q Equipment and lines final gas content verification
q Above ground installations removal
q Site reclamation and re-vegetation

February 2004 Page 18


Eni S.p.A.
E&P Division

5.2 PLANT SECURING

Before any onsite activity can start it is necessary to deeply secure the whole plant from a
structural point of view first and then against the possible fires and explosion induced by hot works
execution.

First of all each structure is to be verified to ensure its safeness: hanged loads are to be secured or
removed, all elevated gangways, stairways and ladders are to be hand railed as necessary.
Moreover all equipment lifting lugs, to be used for lifting, are to be deeply verified and certified for
the purpose. At the moment of the decommissioning project execution, the appointed contractor
will develop a dedicate procedure to be submitted to Company for review and approval.

Once the plant safeness has been established from a structural point o view, the around
atmosphere is to be checked in order to detect gaseous hydrocarbon clouds that could generate
hazard during hot works execution. Eventual clouds of gaseous hydrocarbons are to be recorded
and hot works in the interested area are to be prohibited.

All checks must be certified, decommissioning contractor’s safety and quality manager must
endorse certificates, and certificates are to be submitted for Company review and approval before
any job can be commenced.

5.3 SET UP OF TEMPORARY UTILITY SYSTEM

Once the plant and relevant wellheads have been shut down it is assumed that the living facilities
are out of order. It is therefore decommissioning contractor responsibility either refurbish the
existing facilities or provide temporary living facilities.

At the purpose a preliminary documents describing how contractor intends to deal with this issue is
to be submitted since from tender phase of the project. Such document will be further developed
during the decommissioning design phase, by the way it must be in accordance with applicable
Company specifications and with international regulations ruling and this matters.

5.4 EQUIPMENT ELECTRICAL AND MECHANICAL ISOLATION

Once the safeness has been established all over the plant, the following activities must be
completed:

q Isolation valves of lines connected with the plant are to be closed and locked
q Incoming and outgoing lines are to be blinded at plants’ battery limits
q Wellhead valves are to be closed and the connection with relevant flow line blinded
q Incomer circuit breakers are to be opened and extracted at main switchboard
q Local operation selector switches are to be turned to “Off” position
q Electrical Distribution System upstream feeders/starters are to be opened and extracted
q Electrical motor drawers are to be extracted and local selector switches are to be turned to
“Off” position

Decommissioning contractor cannot operate valves, blinds, switches and or circuit breakers without
a written authorization from safety manager.

February 2004 Page 19


Eni S.p.A.
E&P Division

5.5 EQUIPMENT AND LINES DEPRESSURIZATION AND OR DRAINING

All liquid / gaseous hydrocarbons contained into plant equipment and lines are to be
drained / disposed to the flare. At this scope each functional unit shall be isolated first and then all
drain and vent valves are to be opened in order to allow the hydrocarbons to be drained. Pressure
containing lines and equipment shall be depressurized by opening the vent valve toward the flare
system.

Once lines and equipment have been drained / depressurized they are to be filled with water in
order to displace the remaining hydrocarbons to the closed drain system (for liquid hydrocarbons)
or to the flare system for gaseous ones. During water filling both vent and drain valves must be
kept opened.

During decommissioning detailed study it will be determined whether some lines and or equipment
are to be steam stripped and or purged by Nitrogen before dismantling can take place.

For economic and ecologic reasons it is advisable that the aforesaid activities will be at operator
care. In fact the operator can use the plant facilities and the wet and blow-down systems that, at
the time of plants shut down, are likely operable. Moreover, in this way, the operator can recover as
much oil as possible realizing, in the same time, the maximum profit with the minimum ecologic
impact.

5.6 FLOW LINES AND PIPELINES DRAINING AND FLUSHING

All flow lines and pipelines belonging to the plant to be decommissioned are to be drained, pigged
and flushed before they can be dismantled (for aboveground lines) or abandoned (for underground
lines). For economic and technical reasons it is advisable that these activities will be at operator
care. In fact the operator could use the existing plant facilities that, at the time of plant shut down
are likely operable. Once the plant has been shut down it would be necessary to power up
heavy-duty pumps to carry out the requested activities.

In order to prevent the lines from plugging it is advisable do not use the pig. Pigging can be
performed pumping clean water inside the lines.

Once the line has been drained and pigged, it has to be flushed in order to remove the
hydrocarbon layer adherent to pipe walls. The following minimum equipment are requested to
perform line flushing:

q Well water and relevant pumps


q Fire water tank (or any other plant tank to be used as surge tank)
q Electric driven flushing water pumps
q Oily water separator (corrugated plate interceptor type)

Basically this study and the flushing price/time are based on the assumption that majority of the
above listed equipment are available and operable at site.

The following minimum requirements are to be complied with in performing the lines flushing

q Water speed inside the pipelines is to be in the range of 0.5÷1m/sec


q Demulsifying agent and chemical compounds are to be injected in the water pump suction
lines in order to facilitate the aggregation of oil droplets and the removal of the thin layer of
oil adherent to the piping walls
q Oily water is to be treated in oily water separators before it can be disposed to the ground.
Particular attention should be paid in avoiding ground flooding creating in such way delay to
the subsequent dismantling activity
q Sludge is to be collected and disposed to suitable incinerators

February 2004 Page 20


Eni S.p.A.
E&P Division

The following is to be taken into account in designing the flushing process:

q The total quantity of displacement water is about 110% of the pipeline capacity: this means
8Km/H and 32 Km/H for 4” and 8” piping respectively. Anyhow line flushing shall be
continued up to a water oil content of 10 ppm maximum
q Pressure drop in the pipeline is assumed to be 0.7Kg/m² per Km, therefore the pump total
differential head shall be 0.7Kg/m² times the line length in kilometre
q Pump capacity for a 4” pipe and 8” pipe is in the range of 14÷28m³/h and 56÷112m³/h
respectively
q Final content of oil in the de-oiled water shall be lower than 10 ppm

5.7 EQUIPMENT AND LINES PURGING AND FLUSHING

Any item of equipment or any line containing H2S above 3mg/m³ (=2ppm) or flammable gas above
0.4% by volume has to be purged for reducing the contaminants to the above value before it can
be opened or before hot works can be performed on it; as well as any item of equipment or any line
containing liquid hydrocarbons has to be flushed in order to remove the hydrocarbons. The flushing
is considered satisfactory when a sample of water coming from the flushing show a slight
iridescence. Water can be used for displacing either the gas or the liquid (only if equipment will not
be refurbished). The gas is displaced to the flame, the liquid is drained to close drain or to sewage
system.

For economic and practical reasons it is advisable that operator carries out the flushing. This is
because he can use the plant facilities that, at the time of plant shut down, are likely operable.

The general purging and flushing operational procedure is as follows:

1. Single out the main equipment and associated circuits for rich functional unit
2. Open the isolation valves in the depressurisation lines to flare for each functional unit.
Ensure that all the valves pertaining to the circuits of the unit are opened while the valves at
the battery limit of the same functional unit are closed
3. Make a low level of water in all equipment and drain them in order to drain any traces of
process liquid and sludge. Repeat the operation until water comes out clean
4. Be sure that the water will have a regular down flow to sewage during the lfushing. Fill
completely all equipment with water so that all the gas is displaced to the flare. Close then
the isolation valves in the depressuration line. Open the equipment top vent valve and, one
by one, the valves at the battery limit of the entering and outgoing lines. Flush at first the
main and then the branch lines. Roughly the quantity of water used for the purging and
flushing is two times the capacity of the main equipments of each functional unit. A good
flushing is obtained when water speed into the piping is of 3÷4 mt/sec. The speed of water
increases while the level of liquid and/or the pressure increase
5. Repeat the purging and flushing for all the equipments and associated circuits of the plant.
For the plants the following equipments and associated lines and manifolds are purged and
flushed:
Unit 160 Oil Launching and gas launching Traps
Unit 200 Test separator ? Unit 130 Well Manifold
Unit 200 Production Separator ? Unit 130 Well Manifold ? Unit 100 Flow Lines
Production Separator ? Unit 200 Crude Oil Heater
Production Separator ? Unit 200 Coalescer
Unit 200 Atmospheric stage (Surge Vessel)
Unit 200 Gunbarrel Tank ? Unit 210 Buster Pumps ? Unit 220 Oil Transfer Pumps
Unit 230 Flares
Unit 360 Gas Compressor Suction Coalescer
Gas Compressor Suction Scrubber
Gas Lume Oil Air Cooler
Gas Compressor Discharger K.O. Drum
Unit 410 Heat hers

February 2004 Page 21


Eni S.p.A.
E&P Division

Unit 420 Fuel Gas Scrubber and Filters


Fuel Gas K.O. Drum
Unit 470 Gas Generators
Unit 470 Diesel Generator
6. Pumps are usually flushed with water coming from relevant suction vessel, while dead lines,
filters, API skimmer, metering stations can be flushed by means of a flexible hose
connections. Gas turbo compressors and gas generators have been purged during the
shutdown phase. On the contrary they can be purged with nitrogen or with CO2
extinguishers.
Flares and flare headers are purged with nitrogen when purging of all the plant vessel and
circuits has been completed
7. Once the flushing has been completed plant conditions shall be as follows:
• Drain and vent valves are to be kept opened
• Vessel manholes are to be kept opened so that ventilation is guaranteed
• Oil sewage pits are to be kept covered to avoid gas and cutting scales contamination

5.8 CONTROL OF THE ATMOSPHERE INSIDE EACH ITEM OF EQUIPMENT

Even if all liquid has been drained and all plant equipment have been purged from gaseous
hydrocarbons and toxic compounds, liquid pockets can gather at the lower part of vessels and
circuits while gas pockets can develop caused by liquid hydrocarbons evaporation.

It is therefore contractor responsibility carry out the atmosphere control as well as the liquid
pockets draining and gas pockets venting in order to verify that all items of equipment and circuits
do not contain flammable or toxic fluids and that gaseous hydrocarbons content is below the lower
explosiveness limit.

The presence of liquid inside each item of equipment and associated lines is to be checked by
opening the drain valves. Eventual liquid pockets are to be drained, moreover the atmosphere is to
be analysed by portable H2S detectors and explosimeters. At the purpose sample connections,
vents, drains, and gauge taps can be utilized. Certificates are to be issued, endorsed by safety
manager and submitted to client approval before any dismantling activity can be started. The
results of the checks and analyses are to be recorded in the equipment/line checklist.

February 2004 Page 22


Eni S.p.A.
E&P Division

5.9 PLANT STATUS BEFORE STARTING DISMANTLING ACTIVITIES

Once all activities described within paragraphs from 5.2 to 5.8 have been completed, the
dismantling activity can start. At this stage plant conditions should be as follows:

Process equipment and piping:

q Plant has been shut down and production is cut


q Liquid hydrocarbons, rotating equipment lube oils and chemicals have been recovered
q All piping and equipment have been drained and flushed
q All gas lines and equipment have been depressurized up to flare pressure. Drain and vent
valves have been closed
q Any items of equipment and/or line containing gas have been purged or filled with water in
order to displace the gas trough the flare system
q Isolation valves of lines connected with the plant have been closed and locked. Lines have
been blinded at plant battery limits
q Wellhead valves have been closed and the connection with relevant flow line blinded
(Decommissioning contractor cannot operate valves or remove blinds at plant battery limit)

Electric circuits:

q Incomer circuit breakers have been opened and extracted at main switchboard; local
operation selector switches have been turned to “Off” position
q Electrical Distribution System upstream feeders/starters have been opened and extracted;
local operation selectors switches have been turned to “Off” position
q Electrical motor drawers have been extracted and local selector switches have been turned
to “Off” position

Before plant hand over to removal contractor it is important thoroughly ve rify and freeze the plant
conditions. At the scope the following checklists should be used as plant hand over documents:

EQUIPMENT CHECK LIST

Functional Item Electrical Mechanical Depressurised Drained Purged Flushed Final Gas Safety Ready for
Unit No. Isolation Isolation Content verification Dismantling

LINE CHECK LIST

Final
Functional Line Safety Ready for
Depressurised Drained Purged Flushed Gas
Unit No. verification Dismantling
Content

February 2004 Page 23


Eni S.p.A.
E&P Division

All checks must be carried out or endorsed by Contractor safety manager and witnessed by a
Company representative. Final revision of the above checklists must be agreed among Company
and decommissioning contractor.

5.10 ABOVE GROUND INSTALLATIONS REMOVAL

The dismantling procedure of the various items is to be deeply engineered during the detailed
decommissioning study defining the most suitable, procedure from technical and economical point
of view taking also into account the safety aspect.

For the purpose of this study we have considered that, once removed, the items will be temporary
stored in a lay down area from where they will be loaded on transportation trailers to be disposed to
the final disposal area. This is to avoid to hold the transportation trailers for long periods and to
avoid the presence of transportation trailers in the areas of plant interested to dismantling activities.
Transportation from site to the lay down area will be performed by means of shuttle trucks.

Only the very heavy or unwieldy equipment will be loaded directly in situ to avoid expensive
handling.

Reselling to the second hand market of the removed items has not been considered in this study:
therefore all removed items will be disposed as scraps.

The following minimum requirements have been defined for the purpose of this study:

Dismantling sequence:

Dismantling sequence is to be studied in order to avoid interferences between the various works
and avoid hazards related with such interferences.

In this study the following dismantling sequence has been considered:

1. Piping
2. Tanks: storage, gun-barrel, fire water, etc.
3. Items of equipment at ground levels which have easy accessibility and low, average weight
and overall dimensions (pumps, air compressors, air receivers, K.O. Drums, pig
launchers/receivers, fuel gas scrubber, filters etc.)
4. Heavy weight and high overall dimensions items of equipment: separators, atmospheric
stage surge vessel, gas compressor discharge K.O Drum, gas turbo-compressor, flares,
(platform flooring, handrails, stairways, supports, ladders, insulations are considered part of
the main items and therefore removed at the same time)
5. Cables, MCC, transformers, air conditioners
6. Steel structures, lighting poles, pipe-racks
7. Buildings
8. Foundation concrete

Piping dismantling:

Piping is cut into pieces of 8 meters each maximum in order to avoid special transportation. Piping
pieces are obtained by cutting the pipes by means of cutting torches. Where possible flanged joints
are to be selected in order to minimize cutting operations.

Special precaution must be taken for elevated piping to avoid injuries to dismantling people: piping
shall be suitability secured to cranes before cut it into pieces. A lifting plan is to be prepared and
approved by safety manager.

The time for disconnecting a couple of flanges or for cutting a piece of piping has been assumed to
be 15 minutes being involved two pipe fitters; a piping average diameter of 8” has been assumed.

February 2004 Page 24


Eni S.p.A.
E&P Division

Tank dismantling:

Tanks are dismantled by cutting roof, shell and the bottom plates, into pieces of 2.5x8m. During
dismantling operation use of TIRFOR to brace the tank shell plates has been considered. For the
small tanks TIRFOR use can be replaced by securing the shell plates to the scaffolding structure.

For plates cutting both automatic-cutting machines and cutting torches have been considered. The
average cutting rates have been assumed as follows:

q 20cm/minute for an average thickness of 19mm for automatic cutting machines


q 30 cm/15 min for torches

Equipment dismantling (including steel structures, lighting poles, etc):

Equipment is dismantled reducing them on pieces so small that special transportations are avoided
either for dimensional reasons or for weight limits. Small items of equipment are dismantled in one
piece only.

All items of equipment are properly secured before dismantling activity can be started. Use of
cranes, bracings, scaffoldings and temporary reinforcing welds is to be considered.

Use of equipment lifting lugs, without previous verification and certification, for equipment lifting is
forbidden.

Use of automatic cutting machines is considered for equipment to be reduced in pieces (i.e
separators, columns, etc).

Power and instrument cables:

Above ground power and instrument cables are to be pulled and coiled in wooden drums.
Removed cables will be disposed as scrap. Underground cables will be kept in place.

Buildings and civil structures:

Buildings and civil structures are totally removed by means of excavators provided with hydraulic
hammers and hydraulic clamps. Shovel to collect concrete debris has been considered. Small civil
structures (i.e pump basement) are removed by using portable pneumatic hammers.

Civil residential installations belonging to process plants are kept in place to be handed over to
local authorities and communities. Refurbishment costs of existing structures have not been
considered for the purpose of this study: they will be defined during the detailed decommissioning
study.

February 2004 Page 25


Eni S.p.A.
E&P Division

5.11 SITE RECLAMATION AND RE-VEGETATION

Once the decommissioning process has been completed and all civil structures, roads, paved
areas and mechanical installations have been removed the soil shall be deeply checked in order to
detect eventual hydrocarbon contaminations.

Soil checks must be witnessed by Company representative and must be certified by


decommissioning contractor. Certificates are to be submitted to Company for review and approval
in order to get the permit to proceed with the soil re-vegetation phase.

Eventual contaminations are to be corrected. At the scope a suitable specification is to be prepared


and submitted to Company for review and approval. Decontamination specification is to be in
accordance with international regulations and with Nigerian laws ruling on this matter. The
procedure shall describe all the phases of decontamination project including wastes transportation
and final disposal. Special precautions are to be taken to avoid contamination to expand to
surrounding area. Generally speaking transportation by means of sealed watertight containers
would be preferred. Transportation by dump body truck is allowed only upon company and local
authorities written approval.

5.12 END OF WORKS AND AUTHORITIES APPROVAL

Once mechanical and civil dismantling activities have been completed, decommissioning contractor
shall issue a walk trough request for the dismantled site inspection to be carried out by Company
and authorities.
After site inspection, Company will issue a punch list incorporating also authorities comments.
Removal works can be considered completed only upon punch list items clearance by contractor. A
punch point will be considered cleared once client signature for approval has been collected.

Relevant decommissioning completion certificate shall be issued, signed by Company and returned
to decommissioning contractor as end of works document.

Contractor shall prepare a final quality book collecting all certificates, test reports, test results and
check lists signed by company for approval. Test documentation shall be stored and maintained
available by contractor for at least five years after the issuing of decommissioning completion
certificate.

5.13 HEALT AND SAFETY ENVIRONMENT

During the decommissioning of a site at the end of its working life, clean-up of the facilities (or part
of facilities), the lines connecting the tanks, the tanks themselves, the area around the well, the
lines connecting the well to the facilities, the sewer system etc. plays a fundamental role.
To ensure that the decommissioning activities are carried out in compliance with safety and
environmental protection standards, it is of fundamental importance that thefire- fighting
system and sewer system are the last structures to be dismantled.
The most significant sources of hazard associated with plant dismantling are the following:

q Soil and water contamination by hydrocarbon spillages


q Toxic and flammable gases released from equipment and or lines containing hydrocarbons
q Toxic and flammable liquid hydrocarbons and or chemical released from equipment or lines
q Hanging loads
q Walkways, ladders, gangways and stairways structural stability

All precautions shall be taken to limit, as far as practical, injuries to personnel and environment
pollution due to the above sources of danger. One o more plant safety manager shall be appointed
to deal with the safety issues and a work permit procedure must be established and maintained
during the whole decommissioning process execution.

February 2004 Page 26


Eni S.p.A.
E&P Division

Particularly, at least the following must be complied with:

February 2004 Page 27


Eni S.p.A.
E&P Division

Plant preparation:

Entrance to plant area of people not related with the job shall be prevented with safety fences and
signs to warn of hazards and hanged loads. Safety signs are categorised under the following
headings:

q Mandatory (white on blue)


q Prohibition (red on white)
q Warning (black on yellow)

Use of gloves, helmets and safety glasses shall be prescribed as mandatory together with the use
of safety harness for activities to be carried out on elevated levels.

Moreover plant structural stability is to be verified: all hanged loads are to be fastened or removed
and all elevated platforms, stairways, ladders and gangways are to be hand railed as necessary.

Fire prevention:

To deal with the fire protection issue, the decommissioning sequence should provide the plant
firefighting system to be maintained operable as much as possible. Moreover portable and wheeled
fire extinguishers are to be spread all around the plant and particularly in areas interested by hot
works.
Extinguishers must be located so that they can be easily reached by the pipe fitters that are
working in the area; moreover they must be located on both of the sides of the equipment to be
protected. Type of extinguisher must be selected on case-by -case basis: wheeled extinguishers
are to be used together with portable ones.

Hot works must be subject to work permit procedure: such works cannot be started without
previous verification of the gaseous hydrocarbons content on the environment of the area
interested by hot works. Atmosphere verification must be certified and certificate is to be submitted
to safety manager review and approval before work permit can be obtained.

Lifting activities:

Lifting activities without previous approval by the safety manager of the relevant lifting plan shall be
forbidden.
Lifting plan shall include slings and shackles certificates as well as lifting lugs verification
certificates.
Particularly all equipment’s lifting lugs to be used for equipment lifting are to be verified by an
applicable NDT examination. Type of examination to be applied is to be described in a dedicated
procedure to be agreed with company safety department.

First aid nurse and medical assistance:

At least a male nurse experienced in first aids provided with first aid medical apparatus and
medicines shall be appointed.
Furthermore an agreement with the nearest hospital for an emergency intervention at site of a
doctor with an ambulance shall be stipulated.

February 2004 Page 28


Eni S.p.A.
E&P Division

5.14 BATTERY LIMITS

Decommissioning project should be likely split into three working packages: wellheads, flowlines
and pipelines and flow stations / process plants respectively.

In this case the contractor in charge for process plants and flow stations decommissioning will be
the main contractor. It will be his responsibility to provide accommodation for personnel involved in
wellheads and lines decommissioning as well as provide a lay down area facilities to store
materials removed by the other contractors.

Even if the battery limits will be better defined during the detailed study, as preliminary indication
the following shall be considered:

Main contractor (Process plant / flow station):

q Arrival manifold valves


q Delivery manifold valves
q Incomer circuit breakers (in case of external power supply)

Flow line / pipeline contractor:

q Wellhead wing valves


q Arrival manifold valves

Wellheads contractor:

q Wellhead wing valves

5.15 ORGANIZATION FOR PLANT DISMANTLING

It is strictly necessary that Company monitors the decommissioning contractor activity during the
whole decommissioning project. At the scope Company should foreseen as a minimum, the
following organization (Number of people are referred to a typical flow station, in case of process
plant they are to be increased):

N. 1 Project manager
N. 1 Field engineer
N. 1 Safety engineer
N. 1 Instrument/electrical engineer
N. 1 Mechanical engineer
N. 1 Process engineer
N. 1 Planner and cost controller

February 2004 Page 29


Eni S.p.A.
E&P Division

6. TABLES
The following tables are attached

Plant data base


Plants data sheet
Decommissioning cost table
Decommissioning times table

February 2004 Page 30


Eni S.p.A.
E&P Division

7. METHODOLOGIES

February 2004 Page 31


Eni S.p.A.
E&P Division

7.1 DECOMMISSIONING COST DEFINITION

The following items compose the decommissioning cost:

• Mobilization / demobilization cost (For flowstation)


• Mobilization / demobilization cost (For flowline/pipeline)
• Pipelines flushing unit cost
• Flowlines flushing unit cost
• Flowlines dismantling unit cost
• Wellhead total cost
• Civil structures removal cost
• Steel structures and equipment removal cost
• Land reclamation/re-vegetation cost

7.2 SITES CLASSIFICATION

In order to simplify the demobilization study of NAOC facilities, all sites have been split into four
categories. Homogeneous features like type of prevailing installed equipment, degree of
accessibility, etc characterize each site category.

The following types of installation have been considered on this study:


• Flow stations
• Flow lines and pipelines
• Well heads
• Process plants

Different philosophies have been applied in evaluating the decommissioning costs and times for
each of the above listed type of installation. Main topics of the decommissioning study for each site
category are broken down within the following paragraph.

February 2004 Page 32


Eni S.p.A.
E&P Division

7.3 DECOMMISSIONING COST & TIME EVALUATION

7.3.1 Flow stations

Three sample plants have been studied in detail (Oshi, Idu and Clough Creek). The following
information have been derived:

q IDU flow station total steel and concrete amounts


q IDU flow station decommissioning time
q IDU flow station decommissioning cost
q IDU flow station concrete and steel unit costs

q OSHIE flow station total steel and concrete amounts


q OSHIE flow station decommissioning time
q OSHIE flow station decommissioning cost
q OSHIE flow station concrete and steel unit costs

q CLOUGH CREEK flow station total steel and concrete amounts

The following documents have been produced:

q OSHI FLOW STATION PLANT DETAILED ANALYSIS


q OSHI FLOW STATION DISMANLTING ACTIVITY BAR CHART
q OSHI FLOW STATION DISMANLTING ACTIVITY SUMMARY TABLE

q IDU FLOW STATION PLANT DETAILED ANALYSIS


q IDU FLOW STATION DISMANLTING ACTIVITY BAR CHART
q IDU FLOW STATION DISMANLTING ACTIVITY SUMMARY TABLE

q CLOUGH CREEK FLOW STATION PLANT DETAILED ANALYSIS

Decommissioning costs and times for the remaining flow stations (other than sample plants), have
been derived from the above listed information and documents.

Mobilization/demobilization

Time:
An average mobilization/demobilization period of 15 Days with 11 people involved has been
assumed for all flow stations. Ten days have been considered for mobilization and 5 days for the
demobilization.

Cost:
Mob/demob cost is assumed to be a constant value of 200 K$ for all flow stations.

Civil structures removal cost

Generalities:
A concrete unit cost has been defined as the cost for demolish and dispose one cubic meter of
concrete. Since all flow stations have similar kind of installation, the same concrete unit cost can be
assumed for all of them.

Stated as above the civil structures removal cost can be evaluated on the basis of the equivalent
concrete amount of each installation. Volume of concrete belonging to the sample plants has been
evaluated within the detailed study.

February 2004 Page 33


Eni S.p.A.
E&P Division

Concrete volumes:

Concrete volume belonging to each flow station (other than sample plants) has been assumed to
be related to the number of main equipment installed on the plant. This should be a logic
assumption; in fact a greater number of equipment means a bigger plant extension and likely also a
bigger concrete amount.

The following table and the relevant formula have been derived from sample plants analysis:

PLANT N. OF MAIN EQUIPMENT TOTAL CONCRETE [M3]


OSHIE 21 3.309
IDU 15 1.352
CLOUGH CREEK 15 853

According to the above table, the concrete amount is related to the number of main equipment by
means of the following formula:

Concrete [m3]= 326,167 x N – 3.540

Where N is the number of main equipment (see below list). It shall be noted that the above formula
cannot be applied to the flow stations located in swamp areas (quantity of concrete is lower than
flow station located in land areas); for the above reason a corrective factor of 0.63 will be applied
for swamp area flow station.

For the calculation steel and concrete amounts the following item of equipment have been
considered as “main equipment”.

q Oil / Gas Separators


q Liquid receiver vessels
q Process pumps
q Power generators
q Process gas compressors
q Oil Heaters
q Storage tanks
q Gun barrel
q Metering units
q Oil stabilization units
q Dehydration units
q Flare stacks
q Process gas Scrubber
q Gas Boot

February 2004 Page 34


Eni S.p.A.
E&P Division

Concrete unit cost:

Concrete unit cost has been evaluated on the basis of detailed analysis of IDU and OSHIE flow
station. The following table summarizes the results of sample plants analysis:

PLANT TOTAL CIVIL COST [US $] TOTAL CONCRETE [m3] CONCRETE UNIT COST
[US $/ m3]
OSHIE 1.547.904 3.309 468
IDU 744.615 1.352 550
3
According to the above table, the average concrete unit cost is 510 US $/m . For flow station
located on swamp areas, concrete unit cost has been increased by a factor 1.25 (information by
Contractors operating in local area) to account for a reduced productivity due to environmental
conditions.

Steel structures and mechanical equipment removal cost

Generalities:

A steel unit cost has been defined as the cost for remove and dispose one ton of steel. Since all
flow stations have similar kind of installation, steel unit cost can be assumed to be the same for all
of them.

Stated as above the steel structures and mechanical installations removal cost can be evaluated
on the basis of the equivalent steel amount of each installation. Weight of steel belonging to the
sample plants has been evaluated within the detailed study.

Steel weight:

Steel weight belonging to each flow station (other than sample plants) has been assumed to be
related to the number of main equipment installed on the plant. This should be a logic assumption;
in fact a greater number of equipment means a bigger plant extension and likely also a bigger steel
amount.

The following table and the relevant formula have been derived from sample plants analysis:

PLANT N. OF MAIN EQUIPMENT TOTAL STEEL [Kg]


OSHIE 21 2.828.903
IDU 15 1.033.000
CLOUGH CREEK 15 1.041.000

According to the above table, the steel amount is related to the number of main equipment by
means of the following formula:

STEEL [Tons] = 300xN – 3.456


Where N is the number of main equipment as defined under the paragraph relevant to civil
structure demolition.

February 2004 Page 35


Eni S.p.A.
E&P Division

Steel unit cost:

Steel unit cost has been evaluated on the basis of detailed analysis of IDU and OSHIE flow station.
The following table summarizes the results of sample plants analysis:

PLANT TOTAL MECHANICAL TOTAL STEEL STEEL UNIT COST


COST [US $] [Ton] [US $/ Ton]
OSHIE 1.855.137 2.828.903 666
IDU 944.887 1.033.000 915

According to the above table, the average steel unit cost is 790 US $/Ton. For flow station located
on swamp areas, steel unit cost has been increased by a factor 1.25 (information by Contractors
operating in local area) to account for a reduced productivity and for a greater transportation cost
due to environmental conditions.

Flow station decommissioning time

Since all flow stations have the same kinds of installation, the decommissioning time can be
considered to be a function of the number of main equipment installed on the plant itself.

The following table shows the results of sample plants analysis:

PLANT N. OF MAIN EQUIPMENT TOTAL DISMANTLING TIME [Days]


OSHIE 21 95
IDU 15 87

According to the above table data, the dismantling time is related to the number of main equipment
by means of the following formula:

TIME [Days] = 67 + 1.33xN

Where N is the number of main equipment already defined in the section dedicated to the concrete
and steel amount estimation. For flow station located in swamp areas a corrective factor of 1.25
has been applied to account for a reduced productivity due to environmental conditions.

Land reclamation and re -vegetation

Time:

Times for these activities will be provided by NAOC


Cost:

Costs for these activities will be provided by NAOC and

February 2004 Page 36


Eni S.p.A.
E&P Division

7.3.2 Process plants


Mobilization/demobilization

Time:

An average mobilization/demobilization period of 20 Days has been assumed for all process plants.
Number of involved people depends upon the size of the plant to be decommissioned. Fifteen and
five days have been considered as mobilization and demobilization period respectively.

Cost:

Mob/demob cost is assumed to be a constant value of 200 K$ for all process plants.

Decommissioning costs and times

Decommissioning cost and time for all process plants have been evaluated on a case by case
basis. Detailed plant analysis have been carried out and the following documents have been
produced for all process plants included in the scope of this study:

q PLANT DETAILED ANALYSIS (ITEM LIST, CONCRETE VOLUME AND STEEL WEIGHT
OF MAJOR EQUIPMENT)
q PLANT DISMANTLING ACTIVITY TABLE
q PLANT DISMANLTING ACTIVITY BAR CHARTS
q PLANT DISMANLTING ACTIVITY SUMMARY TABLES

7.3.3 Booster Station


Being documents not available, the booster station decommissioning cost and time have been
evaluated on the basis of the same data stated on the previous revision of this study.

Concrete and steel quantities stated on 2001 revision have been considered still valid, while the unit
costs have been up dated as per 2003 study. Concrete and steel unit costs assumed for the flow
stations have been considered valid for the booster station too.

7.3.4 Flow lines

Mobilization/demobilization

Time:
Mob/demob time for flow lines has been assumed to be 20 days with 4 people involved. This period
accounts for line and equipment preparation for flushing and removal as below detailed:

Preparatory activities:

The following equipment/facilities must be installed/prepared before flushing can be started:

q N. 1 Sludge separator (forecast time 2 days)


q N. 1 Corrugated Plate Interceptor (CPI) (forecast time 6 days)
q N. 1 Surge tank refurbishment, cleaning and connection to the flushing pump (forecast time
4 days)
q N. 1 temporary connection to the plant blow down system (for gas line flushing only and
instead of CPI installation) (Forecast time 2 days)
q N. 1 Surge tank filling with water (forecast time 2 days)
q Obstructions for line accessibility are to be removed

February 2004 Page 37


Eni S.p.A.
E&P Division

Restoring activities:

q Dismantle the temporary facilities (Forecast time 6 days)


q Dispose the recovered oil (vacuum truck and incinerator)
q Dispose the wastewater coming out from CPI (vacuum truck)
q Drain the water from above ground lines (Forecast time 10 hours/ 10 Km of line)
q Dispose the wastewater coming out from line draining (vacuum truck)

It shall be noted that the above estimated times/list of activities are valid under the hypotheses of
availability of the following:

q Electric driven pumps suitable to carry out the line flushing


q Electric power to drive the above mentioned pumps
q Surge tank (Plant fire water storage tank or gun barrel can be used)
q Well water and relevant pumps
q Plant blow down system to burn the gas contained in the gas line

Cost:
Mob / demob price has been assumed to be 100 K$ for flow station. Mob demob price has been
increased by a factor 1.25 for all lines located on swamp areas due to environmental conditions.
The price is valid under the hypothesis that flushing is carried out by operator using plant facilities.

Flushing activities

Time:
Flushing rate has been assumed to be 15 Km/Day (considering 10 hours/day) with 4 people
involved. A fixed period of 20 days has been added to account for the preparatory works.
Time has been increased by a factor 1.25 (information by Contractors operating in local area) for all
assets located on swamp area.

Cost:
Flushing price has been assumed to be 0.4 K$/Km. Price has been further increased by a factor
1.25 (information by Contractors operating in local area) for all lines located on swamp areas due
to environmental conditions.

Dismantling activities

Time:
Removal rate has been assumed to be 1 Km/Day (considering 10 hours/day) with 6 people
involved. For all assets located on swamp area, the rate has been decreased by a factor 1.25
(information by Contractors operating in local area).

Cost:
Removal price has been assumed to be 3.8 K$/Km. Price has been further increased by a factor
1.25 (information by Contractors operating in local area) for all lines located on swamp areas due
to environmental conditions.

February 2004 Page 38


Eni S.p.A.
E&P Division

7.3.5 Pipe lines

Mobilization/demobilization

Time:
Mob/demob time for flow lines has been assumed to be 20 days with 4 people involved. This period
account for line and equipment preparation for flushing and removal as below detailed.

Preparatory activities

The following equipment/facilities must be installed/prepared before flushing/remove can be


started:

q N. 1 Sludge separator (forecast time 2 days)


q N. 1 Corrugated Plate Interceptor (CPI) (forecast time 6 days)
q N. 1 Surge tank refurbishment, cleaning and connection to the flushing pump (forecast time
4 days)
q N. 1 temporary connection to the plant blow down system (for gas line flushing only and
instead of CPI installation) (Forecast time 2 days)
q N. 1 Surge tank filling with water (forecast time 2 days)
q Obstructions for line accessibility are to be removed

Restoring activities

q Dismantle the temporary facilities (Forecast time 6 days)


q Dispose the recovered oil (vacuum truck and incinerator)
q Dispose the wastewater coming out from CPI (vacuum truck)

It shall be noted that the above estimated times/list of activities are valid under the hypotheses of
availability of the following:

q Electric driven pumps suitable to carry out the line flushing


q Electric power to drive the above mentioned pumps
q Surge tank (Plant fire water storage tank could be used)
q Well water and relevant pumps
q Plant blow down system to burn the gas contained in the gas line

Cost:

Mob / demob price has been assumed to be 100 K$ for flow station. Mob demob price has been
increased by a factor 1.25 (information by Contractors operating in local area) for all lines located
on swamp areas due to environmental conditions. The price is valid under the hypothesis that
flushing is carried out by operator using plant facilities.

Flushing activities

Time:

Flushing rate has been assumed to be 15 Km/Day (considering 10 hours/day) with 4 people
involved. A fixed period of 20 days has been added to account for the preparatory works.
Time has been increased by a factor 1.25 (information by Contractors operating in local area) for all
assets located on swamp area.

Cost:

Flushing price has been assumed to be 0.7 K$/Km. Price has been further increased by a factor
1.25 (information by Contractors operating in local area) for all lines located on swamp areas.

Remark: pipeline flushing price has been assumed to be higher than flow line flushing price to
account for the bigger average size of the pipeline if compared with a flow line.

February 2004 Page 39


Eni S.p.A.
E&P Division

7.4 LIFTING AND TRANSPORTATION

In designing the decommissioning and removal procedures, particular attention has been paid in
avoiding special transportations and lifting. Therefore it is assumed that heavy -duty lifting means
are not required. This to avoid use of heavy duty cranes both at the plants to be dismantled and at
the final disposal areas.

Only for tanks dismantling the use of a 50 tons crane is to be considered to allow for lifting of loads
having a considerable eccentricity from the crane base.

Limits for transportation have been assumed to be 2 X 8 meters as maximum allowable dimension
while for lifting a maximum allowable weight of 10 tons has been considered. All piping, equipment
metallic structure, etc have been reduced in pieces so small so that the aforesaid limits are not
exceeded.

Metallic scraps are loaded on trailers of 18 tons average capacity. Number of trucks has been
evaluated dividing the total steel amount by the average truck capacity.

Concrete and wall debris resulting from equipment foundation, buildings, roads and paved areas
demolition are loaded in dump body trucks of 10m³ capacity roughly equivalent to 21tons. Number
of trucks has been evaluated dividing the total concrete amount by the average truck capacity.

A rate of two trips/day (average speed 30 Km/Hr) is assumed for all assets located closer then 50
Km from final disposal areas and of one trip/day for all other assets. Distances assets-final lay
down areas are stated under the next paragraph.

To account for a bigger distance for final disposal area, decommissioning costs for Clough Creek,
Tebidaba and Ogbainbiri has been increased by a factor 1.07.

7.5 DISTANCES ASSETS – FINAL DISPOSAL SITES

Final disposal sites are the following:

q BRASS TERMINAL (For all plants located on swamp areas)


q OBIAFU –OBRIKOM (For all plants located on land areas)

The following table details the distances between each asset and the corresponding final disposal
area:

ASSET LOCATION FINAL DISPOSAL SITE DISTANCE [Km]


AKRI F/S LAND OBIAFU-OBRIKOM 35
KWALE F/S LAND OBIAFU-OBRIKOM 45.5
EBOCHA LAND OBIAFU-OBRIKOM 15
IDU F/S LAND OBIAFU-OBRIKOM 24.5
OSHIE F/S LAND OBIAFU-OBRIKOM 50.7
OBAMA SWAMP BRASS TERMINAL 49
OGBAINBIRI SWAMP BRASS TERMINAL 91
CLOUGH CREEK SWAMP BRASS TERMINAL 119
TEBIDABA SWAMP BRASS TERMINAL 63
BOOSTER STATION SWAMP BRASS TERMINAL 17.5

February 2004 Page 40


Eni S.p.A.
E&P Division

8. HYPOTHESIS AND ASSUMPTIONS

The whole study is based on the following assumptions:

1. Removal of plant facilities will take place a little while later than plant shut down so that cost
for plant refurbishment can be estimated and included in mob/demob price

2. Ten working hours per day with 70% of actual working time and 30 % of idle time has been
considered

3. Seven working days / week has been considered. Holiday periods have not been considered
in evaluating plants decommissioning time

4. Chemicals and other pollutant materials have been collected and properly disposed by
operator. The relevant cost is not included in the scope of this study

5. Operator has performed tanks reclamation and cleaning prior or immediately after plant shut
down. Relevant cost is not included on the scope of this study

6. All removed items will be disposed as scrap. Reselling to the second hand market is not
considered

7. Concrete volumes and equipment weights (for process and sample plants) have been
generally derived from plant documents. When plant documents were not available the
quantities have been estimated by Tecnomare on the basis of characteristics of similar
equipment installed on a different plant

8. Manpower and equipment prices have been supplied by NAOC during site survey

February 2004 Page 41


Eni S.p.A.
E&P Division

9. EXCLUSIONS

The following has not been considered in estimating both decommissioning prices and times

1. Cost and relevant time for refurbishment of installations to be handled to local authorities is

2. Cost for procurement of fixed equipment necessary for site decommissioning (i.e steam
generators, API skimmers, surge tanks)

3. Revenue for selling the used equipment to the second hand market

4. Revenue for selling the steel scrap

5. Back to back shift periods

February 2004 Page 42


Eni S.p.A.
E&P Division

10. SUPPORTING TABLES


The following tables are attached:

q OSHI FLOW STATION PLANT DETAILED ANALYSIS


q OSHI FLOW STATION DISMANTLING ACTIVITY TABLE
q OSHI FLOW STATION DISMANLTING ACTIVITY BAR CHART
q OSHI FLOW STATION DISMANLTING ACTIVITY SUMMARY TABLES
q IDU FLOW STATION PLANT DETAILED ANALYSIS
q IDU FLOW STATION DISMANLTING ACTIVITY BAR CHART
q IDU FLOW STATION DISMANLTING ACTIVITY SUMMARY TABLES
q CLOUGH CREEK FLOW STATION PLANT DETAILED ANALYSIS non c’è
q BRASS TERMINAL DETAILED ANALYSIS
q BRASS TERMINAL DISMANTLING ACTIVITY TABLE
q BRASS TERMINAL DISMANTLING ACTIVITY BAR CHART
q BRASS TERMINAL DISMANTLING ACTIVITY SUMMARY TABLES
q ..................................................................................................................

February 2004 Page 43


Eni S.p.A.
E&P Division

OSHIE FLOW STATION

February 2004 Page 44


Eni S.p.A.
E&P Division

IDU FLOW STATION

February 2004 Page 45


Eni S.p.A.
E&P Division

BRASS MARINE TERMINAL

February 2004 Page 46


Eni S.p.A.
E&P Division

EBOCHA OIL PLANT

February 2004 Page 47


Eni S.p.A.
E&P Division

KWALE-OKPAI GAS PLANT

February 2004 Page 48


Eni S.p.A.
E&P Division

OBIAFU-OBRIKOM GAS PLANT

February 2004 Page 49


NAOC J.V.
OPERATED PLANTS DECOMMISSIONING COSTS
NAOC STUDY 2003
NAOC ABANDONMENT COST OF FACILITIES - AS OF DEC. 2003

F/LINES Flushing Flushing Flushing Flushing


ABOVEGROUND UNDERGROUND F/LINES Mob/Demob Steel unit
ID WELL N° of WELL Total dismantling F/LINES F/LINES P/LINES P/LINES Weight steel Reclamation MOB/DEMOB Steel total Concrete unit Concrete total Plant/FS total TOTAL COST
FIELDS OML AREA LINES LINES dismantling F/line/P/line Concrete (m3) cost
NO N° PLANT FS cost (K$) total cost unit cost total cost unit cost total cost (ton) cost (K$) FS cost (K$) cost (K$) cost (K$/m3) cost (K$) cost (K$) (k$)
[KM] [KM] unit cost (K$) cost (K$) (K$/ton)
(K$) (K$) (K$) (K$) [K$]

1 AGBERI 0 LAND 1 NIL NIL N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
2 AGWE 60 LAND 2 NIL 14 N/A 0 3,8 53 0,4 6 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 59
3 AJAKETON 63 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
4 AKRI 60 LAND 11 1 89 30 0 3,8 338 0,4 36 0,7 21 100 2.844 3.310 0 200 0,79 2.247 0,51 1688 4.135 4.629
5 AKRI WEST 60 LAND 2 NIL 21 N/A 0 3,8 80 0,4 8 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 88
6 ALINSO 0 LAND 1 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
7 ASEMOKE 60 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
8 ASHAKA 60 LAND 1 NIL 7 N/A 0 3,8 27 0,4 3 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 29
9 AZUZUAMA 63 SWAMP 3 NIL 28 35 0 4,8 133 0,5 14 0,875 31 0 0 0 0 0 0,99 0 0,64 0 0 178
10 BENIBOYE 62 SWAMP 11 1 37,7 2 0 4,8 179 0,5 19 0,875 2 125 2.244 1.674 0 200 0,99 2.216 0,64 1067 3.483 3.808
11 BENIBOYE WEST 62 SWAMP 0 NIL 0 0 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
12 BENIBOYE DEEP 62 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
13 BENIKU 60 LAND 2 NIL 21 N/A 0 3,8 80 0,4 8 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 88
14 CLOUGH CREEK 63 SWAMP 9 1 60 52 0 4,8 285 0,5 30 0,875 46 125 1.044 852 0 200 0,99 1.031 0,64 543 1.898 2.260
15 CLOUGH CREEK E 63 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
16 CLOUGH CREEK N 63 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
17 EBEGORO 61 LAND 11 0 84 45,5 0 3,8 319 0,4 34 0,7 32 0 0 0 0 0 0,79 0 0,51 0 0 385
18 EBEGORO DEEP 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
19 EBEGORO S. 61 LAND 2 NIL 7 N/A 0 3,8 27 0,4 3 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 29
21 EKEDEI 63 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
22 EMETTE 63 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
23 IDU 61 LAND 10 1 76 9,2 0 3,8 289 0,4 30 0,7 6 100 1.044 1.353 0 200 0,79 825 0,51 690 1.715 2.140
24 IRRI S 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
25 ISOKO S 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
27 KWALE E 60 LAND 1 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
28 MANUSO 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
29 MANUSO NE 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
30 MBEDE 61 LAND 19 NIL 229 N/A 0 3,8 870 0,4 92 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 962
31 NDONI CREEK 0 LAND 1 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
32 NIMBE S 63 SWAMP 0 0 2,7 N/A 0 4,8 13 0,5 1 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 14
33 OBAMA 63 SWAMP 12 1 78 27 0 4,8 371 0,5 39 0,875 24 125 1.344 1.058 0 200 0,99 1.327 0,64 674 2.201 2.760
34 OBAMA DEEP 63 SWAMP 2 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
37 ODUGRI 60 LAND 2 NIL 32 N/A 0 3,8 122 0,4 13 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 134
38 OGBAINBIRI 63 SWAMP 5 1 24 35 0 4,8 114 0,5 12 0,875 31 125 700 30 0 200 0,99 691 0,64 19 974 1.192
39 OGBOGENE 61 LAND 2 NIL 21 N/A 0 3,8 80 0,4 8 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 88
40 OGBOGENE N 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
41 OGBOGENE W 61 LAND 1 NIL 7 N/A 0 3,8 27 0,4 3 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 29
43 OMOKU E 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
44 OMOKU W 61 LAND 1 NIL 7 N/A 0 3,8 27 0,4 3 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 29
45 OSHI 61 LAND 12 1 80 14 0 3,8 304 0,4 32 0,7 10 100 2.844 3.310 0 200 0,79 2.247 0,51 1688 4.135 4.580
46 PIRIGBENE 63 SWAMP 3 NIL 26,4 20 0 4,8 125 0,5 13 0,875 18 0 0 0 0 0 0,99 0 0,64 0 0 156
47 PIRIGBENE SE 63 SWAMP 1 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
48 SAMABRI 61 LAND 0 NIL 0 18 0 3,8 0 0,4 0 0,7 13 0 0 0 0 0 0,79 0 0,51 0 0 13
49 SAMABRI E 61 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
50 BISENI 40% 0 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
51 TAYLOR CREEK 61 LAND 1 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 0
52 TEBIDABA 63 SWAMP 11 1 84 45 0 4,8 399 0,5 42 0,875 39 125 1.344 1.058 0 200 0,99 1.327 0,64 674 2.355 2.807
53 TUOMO 62 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
54 TUOMO W 62 SWAMP 0 NIL N/A N/A 0 4,8 0 0,5 0 0,875 0 0 0 0 0 0 0,99 0 0,64 0 0 0
55 UMUORU 61 LAND 4 NIL 28 N/A 0 3,8 106 0,4 11 0,7 0 0 0 0 0 0 0,79 0 0,51 0 0 118
Sub Total 144 8 1.064 333 26.458
56 EBOCHA OIL CENTER 61 LAND 18 1 134 135 0 3,8 509 0,4 54 0,7 95 100 2.624 6.963 0 200 N/A N/A N/A N/A 13.732 14.436
57 OB/OB GAS PLANT 61 LAND 0 1 266 295 0 3,8 1.011 0,4 106 0,7 207 100 0 0 0 200 N/A N/A N/A N/A 52.676 53.993
58 KWALE/OKPAI GAS PLANT 60 LAND 18 1 158 17 0 3,8 600 0,4 63 0,7 12 100 0 0 0 200 N/A N/A N/A N/A 38.667 39.380
59 DEL LINE RUMUEKPE 0 LAND 0 NIL N/A 23 0 3,8 0 0,4 0 0,7 16 100 0 0 0 200 N/A N/A N/A N/A N/A 116
60 BOOSTER STATION 0 LAND 0 NIL N/A N/A 0 3,8 0 0,4 0 0,7 0 0 80 50 0 200 2,6 208 0,9 45 453 453
61 BRASS TERMINAL 0 LAND 0 NIL N/A 178 0 3,8 0 0,4 0 0,7 125 100 14.871 50.167 0 200 N/A N/A N/A N/A 29.367 29.591
62 NGL PLANT 0 LAND 0 NIL 0 0 0 3,8 0 0,4 0 0,7 0 0 1.000 700 0 200 2,6 2.600 0,9 630 3.430 3.430
63 NGL GAS PIPELINES 0 LAND 0 NIL 0 195 0 3,8 0 0,4 0 0,7 137 100 0 0 0 0 N/A N/A N/A N/A N/A 237

TOTAL 180 11 1621,8 1.176 0 6.487 683 861 1525 31.983 70.523 0 3.000 14.719 7.718 159.222 168.094

Operated Plants Decommissioning COSTS.xls, DOC N° 723587.01.FGPT.00033 22/11/2004


OPERATED PLANTS DECOMMISSIONING TIMES
NAOC STUDY 2003
Mob/Demob
ABOVEGROUND UNDERGROUND Wells Site Weel head FS Site FS Dismantling Flushing F/Lines TOTAL TIME
ID WELL PLANT / F/lines and
FIELDS OML AREA LINES LINES work time mob/demob work time Mob/Dem F/LINES Time & P/Lines Time [Months]
NO N° FS N° P/lines Time
[KM] [KM] (days) time (days) (days) ob (days) (days) (days) (See Note 1)
(days)

1 AGBERI 0 LAND 1 NIL NIL N/A 0 0 0 0 0 0 0 0,00


2 AGWE 60 LAND 2 NIL 14 N/A 0 0 0 0 14 21 8 1,43
3 AJAKETON 63 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
4 AKRI 60 LAND 11 1 89 30 0 0 94 15 89 28 8 7,81
5 AKRI WEST 60 LAND 2 NIL 21 N/A 0 0 0 0 21 21 8 1,68
6 ALINSO 0 LAND 1 NIL N/A N/A 0 0 0 0 0 0 0 0,00
7 ASEMOKE 60 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
8 ASHAKA 60 LAND 1 NIL 7 N/A 0 0 0 0 7 20 8 1,18
9 AZUZUAMA 63 SWAMP 3 NIL 28 35 0 0 0 0 35 30 8 2,44
10 BENIBOYE 62 SWAMP 11 1 37,7 2 0 0 115 15 47 28 8 7,10
11 BENIBOYE WEST 62 SWAMP 0 NIL 0 0 0 0 0 0 0 0 0 0,00
12 BENIBOYE DEEP 62 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
13 BENIKU 60 LAND 2 NIL 21 N/A 0 0 0 0 21 21 8 1,68
14 CLOUGH CREEK 63 SWAMP 9 1 60 52 0 0 108 15 75 34 8 8,02
15 CLOUGH CREEK E 63 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
16 CLOUGH CREEK N 63 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
17 EBEGORO 61 LAND 11 0 84 45,5 0 0 0 0 84 29 8 4,02
18 EBEGORO DEEP 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
19 EBEGORO S. 61 LAND 2 NIL 7 N/A 0 0 0 0 7 20 8 1,18
21 EKEDEI 63 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
22 EMETTE 63 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
23 IDU 61 LAND 10 1 76 9,2 0 0 87 15 76 26 8 7,04
24 IRRI S 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
25 ISOKO S 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
27 KWALE E 60 LAND 1 NIL N/A N/A 0 0 0 0 0 0 0 0,00
28 MANUSO 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
29 MANUSO NE 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
30 MBEDE 61 LAND 19 NIL 229 N/A 0 0 0 0 229 35 8 9,08
31 NDONI CREEK 0 LAND 1 NIL N/A N/A 0 0 0 0 0 0 0 0,00
32 NIMBE S 63 SWAMP 0 0 2,7 N/A 0 0 0 0 3 25 8 1,22
33 OBAMA 63 SWAMP 12 1 78 27 0 0 110 15 98 34 8 8,80
34 OBAMA DEEP 63 SWAMP 2 NIL N/A N/A 0 0 0 0 0 0 0 0,00

Sheet 1 of 2
OPERATED PLANTS DECOMMISSIONING TIMES
NAOC STUDY 2003
Mob/Demob
ABOVEGROUND UNDERGROUND Wells Site Weel head FS Site FS Dismantling Flushing F/Lines TOTAL TIME
ID WELL PLANT / F/lines and
FIELDS OML AREA LINES LINES work time mob/demob work time Mob/Dem F/LINES Time & P/Lines Time [Months]
NO N° FS N° P/lines Time
[KM] [KM] (days) time (days) (days) ob (days) (days) (days) (See Note 1)
(days)

37 ODUGRI 60 LAND 2 NIL 32 N/A 0 0 0 0 32 22 8 2,07


38 OGBAINBIRI 63 SWAMP 5 1 24 35 0 0 102 15 30 30 8 6,15
39 OGBOGENE 61 LAND 2 NIL 21 N/A 0 0 0 0 21 21 8 1,68
40 OGBOGENE N 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
41 OGBOGENE W 61 LAND 1 NIL 7 N/A 0 0 0 0 7 20 8 1,18
43 OMOKU E 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
44 OMOKU W 61 LAND 1 NIL 7 N/A 0 0 0 0 7 20 8 1,18
45 OSHI 61 LAND 12 1 80 14 0 0 94 15 80 26 8 7,45
46 PIRIGBENE 63 SWAMP 3 NIL 26,4 20 0 0 0 0 33 29 8 2,33
47 PIRIGBENE SE 63 SWAMP 1 NIL N/A N/A 0 0 0 0 0 0 0 0,00
48 SAMABRI 61 LAND 0 NIL 0 18 0 0 0 0 0 21 8 0,97
49 SAMABRI E 61 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
50 BISENI 40% 0 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
51 TAYLOR CREEK 61 LAND 1 NIL N/A N/A 0 0 0 0 0 0 0 0,00
52 TEBIDABA 63 SWAMP 11 1 84 45 0 0 110 15 105 36 8 9,12
53 TUOMO 62 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
54 TUOMO W 62 SWAMP 0 NIL N/A N/A 0 0 0 0 0 0 0 0,00
55 UMUORU 61 LAND 4 NIL 28 N/A 0 0 0 0 28 22 8 1,93
0 0,00
Sub Total 127 8 1.064 333 84,73
56 EBOCHA OIL CENTER 61 LAND 18 1 134 135 0 281 20 134 38 8 15,36
57 OB/OB GAS PLANT 61 LAND 0 1 266 295 0 541 0 266 57 8 29,08
58 KWALE/OKPAI GAS PLANT 60 LAND 18 1 158 17 126 509 0 158 32 8 27,76
59 DEL LINE RUMUEKPE 0 LAND 0 NIL N/A 23 0 0 0 0 22 8 0,98
60 BOOSTER STATION 0 LAND 0 NIL N/A N/A 0 0 0 0 0 0 0,00
61 BRASS TERMINAL 0 LAND 0 NIL N/A 178 0 458 20 0 32 8 16,60
62 NGL PLANT 0 LAND 0 NIL 0 0 0 0 0 0 0 0 0,00
63 NGL GAS PIPELINES 0 LAND 0 NIL 0 195 0 0 0 0 33 8 1,37

TOTAL 163 11 1621,8 1176 126 2399,05 1494 687 192 175,87

NOTE 1 Total decommissioning times have been evaluated adding all partial times, in case activities will be carried out simultaneously, total times are to be reduced as necessary

Sheet 2 of 2

Вам также может понравиться