Вы находитесь на странице: 1из 5

STTS WIDEBODY AIRCRAFT FACILITY

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

Document No: P103-STTS-GEC-ASI-MS-ELE-007

REV. DATE DESCRIPTION GENFOCUS ASI/WSP


PREPARED APPROVED

00 27-05-18 Issued for Approval QA/QC PM

DOCUMENT No. REV DATE


Page 1 of7
P103-STTS-GEC-ASI-MS-ELE-007 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

1.0 PURPOSE

1.1 The purpose of this Method Statement is to describe in details the method for installation of Cable
Tray & Trunking

2.0 SCOPE

2.1 The purpose of this Method statement is to define the procedure on installation of cable tray
and Trunking for the arrangements of various Power, Lighting and Control Cables.

3.0 TOOLS AND RESOURCES

3.1 Touch-up material


3.2 Hand tools
3.3 Hand Drilling machine

4.0 RESPONSIBILITIES

4.1 PROJECT MANAGER

4.1.1 Is responsible for ensuring that all works are carried out as per the specifications,
drawing/shop drawings and method statement as per the manufacturer instructions,
coordinated with other works and will plan for the required manpower and tools for all
activities.

4.2 SITE ENGINEER/ SUPERVISOR

4.2.1 Ensure the foreman is aware of cable installation procedures & splicing procedures.
4.2.2 Check periodically that the job is executed safely and following the standards.
4.2.3 Ensure that the installation complies with the approved shop drawings/specifications.
4.2.4 Maintain records of work done and submit the progress report to the authorities concerned.
4.2.5 Follow the ITP procedures and co-ordinate with the QA/QC team for inspections.

DOCUMENT No. REV DATE


Page 2 of7
P103-STTS-GEC-ASI-MS-ELE-007 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

4.3 QA/QC ENGINEER

4.3.1 Carry out the material inspection to ensure that materials received on site are approved
materials.

4.3.2 Monitoring the installation works according to the approved drawings and method statement.

4.3.3 Coordinate with the ENGINEERS and EMPLOYERS REPRESENTATIVE to carry out
inspection/testing of the completed works.

4.3.4 Monitoring the work and ensure all installation or construction work will be carried out in
accordance with specification requirements and good engineering practice.

4.4 HSE OFFICER

4.4.1 Ensure that all installation or construction works will be carried out in accordance with the
ENGINEERS safety manual and EMPLOYERS REPRESENTATIVE standard regulations
and practices.

4.4.2 Ensure that all necessary permits shall be obtained from AUTHORITIES/MAIN
CONTRACTOR/ENGINEER/EMPLOYER REPRESENTATIVE wherever necessary.

4.4.3 Ensure that good housekeeping at work site is implemented.

4.4.4 Ensure that all necessary personnel protective equipment is being provided as per the
requirement of the job.

4.4.5 Ensure that usage of cranes, lifting items and working platforms will be used in accordance
with the ENGINEERS and EMPLOYERS REPRESENTATIVE Safety Manual.

5 PROCEDURE

5.1 Check and verify whether drawings and materials are approved for site execution.

5.2 Approved schedules to verify the site progress with architectural section to properly coordinate
the site execution of schedule.

5.3 Proper coordination with civil architectural works for the erection of tray supports in
trench/wall/ceilings and Mechanical works for the pipeline & other service routings.

DOCUMENT No. REV DATE


Page 3 of7
P103-STTS-GEC-ASI-MS-ELE-007 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

5.4 All Approvals shall be obtained for the installation of tray and supports on the truss/
cladding/floor slab etc. prior to commencement of work

5.5 Submit material inspection request of materials delivered to site.

5.6 Attach delivery receipt of materials and complete description to show the compliance of material
s according to approved technical submittals.

5.7 If materials are not being used immediately, manufacturer’s recommended storage procedure
shall be followed to protect materials from damage.

5.8 Wherever trays are going along the overhead pipes separate supports are used as the tray
supports.

5.9 Wherever pipe racks are not there the overhead tray / Trunking layout is supported by the C
channels fixed in Tie rods anchor fastened to the ceiling or welded to the Flush plate, I beam as
per the approved shop drawing.

5.10 Supports must be located so that splice joints between horizontal runs fall between the support
point and the quarter point of the span.

5.11 The Tray accessories like Bends, Tee, and Cross etc. shall be supported in line with cable bending
radius as per manufacturer recommendation.

5.12 The cable ladder system is used for heavy weight power cables as approved.

5.13 The cables to be laid in each tray are determined and the size of the cable tray required is
determined, accordingly a tray layout is also prepared to be as per specification

5.14 As per the prepared tray schedule, the required number and size of cantilever support is fixed in
the concrete or wall

5.15 The bends and trays are coupled using the coupling plate / Fishplate.

5.16 For connections from higher width to lower width appropriate Right / left hand reducers are used.

5.17 Wherever tray cutting is done, the cut end shall be well grinded to avoid sharp edges and zinc rich
corrosion resistant paint shall be applied with primer.

DOCUMENT No. REV DATE


Page 4 of7
P103-STTS-GEC-ASI-MS-ELE-007 000 27-05-2018
STTS WIDEBODY AIRCRAFT FACILITY
METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY & TRUNKING

5.18 The inside of cable tray system shall present no sharp edges; burrs or projections that can damage
cable insulation.

5.19 Install the cable support system such that it does not interfere with the lift-out feature if lay-in
grating or floor plate panels and so that there is adequate access for the installation of all cable
and wiring.

5.20 Provide rubber or plastic edges protectors to assure that the conductors/cabling will not abrade
directly on any exposed tray edges.

5.21 Secure the cables to the tray with cable ties at intervals

5.22 To prevent damage to cable tray, never pull cable tray from truck trailer by chaining to bottom
rung and dragging out of trailer. Always observe common safety practices when assembling tray
and fittings in the field.

5.23 Personnel should wear safety goggles, dust mask, coveralls, or a shop coat when sawing,
machining, and/or sanding.

5.24 Deliver products in their original packaging with legible manufacturer’s identification.

5.25 Continuous Earthing of Cable Tray / Trunking are done with braided earth strip the ends shall be
earthed at equipotential Bus Bar.

DOCUMENT No. REV DATE


Page 5 of7
P103-STTS-GEC-ASI-MS-ELE-007 000 27-05-2018

Вам также может понравиться