QUALITY CONTROL PROGRAM

: Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road


Name of Project
Limits : k1549+430 Location: Veruela, Agusan del Sur
Appropriation/Contract Amount:P 1,954,012.06 Source of Funds:

Test to be Performed
ITEM DESCRIPTION UNIT QTY. NO. OF TEST (Minimum)
A. FACILITIES FOR THE ENGINEERS
A.1.1(3) Construction of Combined Field Office ls 1.00 P.E. Cert-1
A.1 Low Cost Field Office/Quarters/Viewdeck
B. Other General Requirements
B.4(1) Construction Survey & Staking kms. 0.04 P.E. Cert-1
B.5 Project Bilboard each 4.00 P.E. Cert-1
B.7 Occupational Safety and Health Program month 1.77 P.E. Cert-1
B.8 Traffic Management month 1.77 P.E. Cert-1
B.9 Mobilization / Demobilization ls 1.00 P.E. Cert-1
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction lm 6.00 P.E. Cert. - 1
103(1)a Structure Excavation cu.m. 111.13 P.E. Cert. - 1
104(2)a Embankment from Borrow(Common Soil) cu.m. 150.33 GPC-1, D-6
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course cu.m. 61.60 GPC-1, CBR-1, D-3
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 kgs. 10,236.35 Q-1/size/10,000kg
405(1)a3 Structural Concrete Class A cu.m. 103.31 CCS-2 sets
a. Cement bags 981.35 *
b. Fine Aggregates cu.m 51.65 **
c. Coarse Aggregates cu.m 103.31 ***
d. Water P.E. Cert. - 1
407(8) Lean Concrete cu.m. 6.73 CCS-1 set
a. Cement bags 63.94 *
b. Fine Aggregates cu.m 3.37 **
c. Coarse Aggregates cu.m 6.73 ***
d. Water P.E. Cert. - 1

Summary: for items 405(1)a3 & 407(8)


a. Cement * bags 1,045.29 Q-1
b. Fine Aggregates ** cu.m. 55.02 Q-1, G-1
c. Coarse Aggregates *** cu.m. 110.04 Q-1,G-2
G-7
COMPUTATION BREAKDOWN AND APPORTIONMENT OF QUALITY CONTROL COST:
1. Q.C Const.(Direct Cost Sub-Total 1,954,012.06 0.5000% Q.C Chart--------- P 9,770.06
2. Breakdown of Test Per Regional Memos Apportionment (For Adm.Projects
dated Dec. 12,1973 & July 17, 1974 For Dist./City Project
a.) Serv./Fld. Test - (65%) (B-1)-- P 6,350.54 Lab.(66%) (P-L) - - - - - - P
b.) Q. Test - (15%) (B-1) - - - - - - P 1,465.51 Reg.l Lab. - - - - - - -- - - - P
c.) Misc. & Other - (20%) - - - -- P 1,954.01 (34%) (B-1A) - - - - - - - - - P
d.) TOTAL COST - - - - - - - - - - - P 9,770.06 TOTAL - - - - - - - - - - - - - P

PREPARED BY: CHECKED BY:

JIMMY F. CABURNAY JR. HANNIBAL M. SALCEDO


ME-1 , Accred # 4493 ENGINEER II/ME-1, Accred. # D1-00986
MRS BUILDERS Quality Assurance Engineer

RECOMMENDING APPROVAL: NOTED BY:

LEODEGARIO M. MAZO MANUEL C. NARIO


Engineer III Engineer III
Chief, Quality Assurance Section Chief, Construction Section
APPROVED :

MARCELINO M. OPERARIO
District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
April 8, 2018
Date

CERTIFICATE OF QUALITY CONTROL ASSURANCE

Project : Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

k1549+430

Contractor: MRS BUILDERS & SUPPLY

We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 2-7, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :

Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.

A. FACILITIES FOR THE ENGINEERS

A.1.1(3) Construction of Combined Field Office 1.00 ls ls ls 0.00%


###
A.1 Low Cost Field Office/Quarters/Viewdeck ###
B. Other General Requirements
B.4(1) Construction Survey & Staking 0.04 kms. kms. kms. 0.00%
B.5 Project Bilboard 4.00 each each each 0.00%
B.7 Occupational Safety and Health Program 1.77 month month month 0.00%
B.8 TTraffic Management 1.77 month month month 0.00%
B.9 Mobilization / Demobilization 1.00 ls ls ls 0.00%
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction 6.00 lm lm lm 0.00%
103(1)a Structure Excavation 111.13 cu.m. cu.m. cu.m.
104(2)a Embankment from Borrow(Common Soil) 150.33 cu.m. cu.m. cu.m. 0.00%
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course 61.60 cu.m. cu.m. cu.m. 0.00%
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 10,236.35 kgs. kgs. kgs. 0.00%
405(1)a3 Structural Concrete Class A 103.31 cu.m. cu.m. cu.m. 0.00%
407(8) Lean Concrete 6.73 cu.m. cu.m. cu.m. 0.00%
Note:
Project on-going…

HANNIBAL M. SALCEDO VENDEY M. GALDIANO


(Project Quality Control Engineer) Project Engineer I

Note: To be submitted every quarter of the month


1st report 1 - 7
2nd report 8 - 15

3rd report 16 - 22

4th report 23-30/31


Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
April 8, 2018
Date

CERTIFICATE OF QUALITY CONTROL ASSURANCE

Project : Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

k1549+430

Contractor: MRS BUILDERS & SUPPLY

We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 2-7, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :

Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.

A. FACILITIES FOR THE ENGINEERS

A.1.1(3) Construction of Combined Field Office 1.00 ls ls ls 0.00%


###
A.1 Low Cost Field Office/Quarters/Viewdeck ###
B. Other General Requirements
B.4(1) Construction Survey & Staking 0.04 kms. kms. kms. 0.00%
B.5 Project Bilboard 4.00 each each each 0.00%
B.7 Occupational Safety and Health Program 1.77 month month month 0.00%
B.8 TTraffic Management 1.77 month month month 0.00%
B.9 Mobilization / Demobilization 1.00 ls ls ls 0.00%
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction 6.00 lm lm lm 0.00%
103(1)a Structure Excavation 111.13 cu.m. cu.m. cu.m.
104(2)a Embankment from Borrow(Common Soil) 150.33 cu.m. cu.m. cu.m. 0.00%
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course 61.60 cu.m. cu.m. cu.m. 0.00%
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 10,236.35 kgs. kgs. kgs. 0.00%
405(1)a3 Structural Concrete Class A 103.31 cu.m. cu.m. cu.m. 0.00%
407(8) Lean Concrete 6.73 cu.m. cu.m. cu.m. 0.00%
Note:
Project on-going…

HANNIBAL M. SALCEDO VENDEY M. GALDIANO


(Project Quality Control Engineer) Project Engineer I

Note: To be submitted every quarter of the month


1st report 1 - 7
2nd report 8 - 15

3rd report 16 - 22

4th report 23-30/31


Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
April 8, 2018
Date

CERTIFICATE OF QUALITY CONTROL ASSURANCE

Project : Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

k1549+430

Contractor: MRS BUILDERS & SUPPLY

We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 2-7, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :

Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.

A. FACILITIES FOR THE ENGINEERS

A.1.1(3) Construction of Combined Field Office 1.00 ls ls ls 0.00%


###
A.1 Low Cost Field Office/Quarters/Viewdeck ###
B. Other General Requirements
B.4(1) Construction Survey & Staking 0.04 kms. kms. kms. 0.00%
B.5 Project Bilboard 4.00 each each each 0.00%
B.7 Occupational Safety and Health Program 1.77 month month month 0.00%
B.8 TTraffic Management 1.77 month month month 0.00%
B.9 Mobilization / Demobilization 1.00 ls ls ls 0.00%
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction 6.00 lm lm lm 0.00%
103(1)a Structure Excavation 111.13 cu.m. cu.m. cu.m.
104(2)a Embankment from Borrow(Common Soil) 150.33 cu.m. cu.m. cu.m. 0.00%
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course 61.60 cu.m. cu.m. cu.m. 0.00%
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 10,236.35 kgs. kgs. kgs. 0.00%
405(1)a3 Structural Concrete Class A 103.31 cu.m. cu.m. cu.m. 0.00%
407(8) Lean Concrete 6.73 cu.m. cu.m. cu.m. 0.00%
Note:
Project on-going…

HANNIBAL M. SALCEDO VENDEY M. GALDIANO


(Project Quality Control Engineer) Project Engineer I

Note: To be submitted every quarter of the month


1st report 1 - 7
2nd report 8 - 15

3rd report 16 - 22

4th report 23-30/31


Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
April 8, 2018
Date

CERTIFICATE OF QUALITY CONTROL ASSURANCE

Project : Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

k1549+430

Contractor: MRS BUILDERS & SUPPLY

We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 2-7, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :

Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.

A. FACILITIES FOR THE ENGINEERS

A.1.1(3) Construction of Combined Field Office 1.00 ls ls ls 0.00%


###
A.1 Low Cost Field Office/Quarters/Viewdeck ###
B. Other General Requirements
B.4(1) Construction Survey & Staking 0.04 kms. kms. kms. 0.00%
B.5 Project Bilboard 4.00 each each each 0.00%
B.7 Occupational Safety and Health Program 1.77 month month month 0.00%
B.8 TTraffic Management 1.77 month month month 0.00%
B.9 Mobilization / Demobilization 1.00 ls ls ls 0.00%
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction 6.00 lm lm lm 0.00%
103(1)a Structure Excavation 111.13 cu.m. cu.m. cu.m.
104(2)a Embankment from Borrow(Common Soil) 150.33 cu.m. cu.m. cu.m. 0.00%
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course 61.60 cu.m. cu.m. cu.m. 0.00%
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 10,236.35 kgs. kgs. kgs. 0.00%
405(1)a3 Structural Concrete Class A 103.31 cu.m. cu.m. cu.m. 0.00%
407(8) Lean Concrete 6.73 cu.m. cu.m. cu.m. 0.00%
Note:
Project on-going…

HANNIBAL M. SALCEDO VENDEY M. GALDIANO


(Project Quality Control Engineer) Project Engineer I

Note: To be submitted every quarter of the month


1st report 1 - 7
2nd report 8 - 15

3rd report 16 - 22

4th report 23-30/31


MONTHLY MATERIALS QUALITY CONTROL PROGRESS REPORT

April 2018
Month Year

Project: Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

Veruela, Agusan del Sur k1549+430

P 1,954,012.06 MRS BUILDERS & SUPPLY


Contract Amount and Sources of Funds Contractor

VENDEY M. GALDIANO
(Project Engineer,Gov't)

Quality Control Activity

a. Similar ( Number and kind sent to Control / Regional Office lab. )

b. Test done in regional or Project laboratory ( kind & item No. )


c. Inspection

Quality Control Works Accomplished

0.00% 0.00%
(Current Month) Total to Date

Quality Control personnel in project ( Name & Designation )

PREPARED BY:

ARVIN D. AYOSO
Materials Engineer - 1
DATREBIL CONSTRUCTION & SUPPLY

SUBMITTED BY:

LEODEGARIO M. MAZO
Engineer III
Chief, Quality Assurance Section
0.00%
STATUS OF TEST
Date: May 2, 201

Project: Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road


Location: Veruela, Agusan del Sur
Our records indicate that the status of test in the above project for April 1 - 30, 2018
is as follows.
Actual Medium Number Test
Estimated No. of Test on Balance
Item Materials Quantities Required File
A. FACILITIES FOR THE ENGINEERS
A.1.1(3) Construction of Combined Field Office 1.00 ls P.E. Cert-1 0 1
A.1 Low Cost Field Office/Quarters/Viewdeck
B. Other General Requirements
B.4(1) Construction Survey & Staking 0.04 kms. P.E. Cert-1 0 1
B.5 Project Bilboard 4.00 each P.E. Cert-1 0 1
B.7 Occupational Safety and Health Program 1.77 month P.E. Cert-1 0 1
B.8 Traffic Management 1.77 month P.E. Cert-1 0 1
B.9 Mobilization / Demobilization 1.00 ls P.E. Cert-1 0 1
C. Earthworks
101(4)b Removal of Actual Structures/Obstruction 6.00 lm P.E. Cert. - 1 0 1
103(1)a Structure Excavation 111.13 cu.m. P.E. Cert. - 1 0 1
104(2)a Embankment from Borrow(Common Soil) 150.33 cu.m. GPC-1 0 1
D-6 0 6
D. SUBBASE & BASE COURSE
200(1) Aggregates Subbase Course 61.60 cu.m. GPC-1 0 1
CBR-1 0 1
D-3 0 3
B. Bank & Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 10,236.35 kgs. Q-1/size/10,000kg 0 1
405(1)a3 Structural Concrete Class A 103.31 cu.m. CCS-2 sets 0 2
a. Cement 981.35 bags *
b. Fine Aggregates 51.65 cu.m **
c. Coarse Aggregates 103.31 cu.m ***
d. Water P.E. Cert. - 1 0 1
407(8) Lean Concrete 6.73 cu.m. CCS-1 set 0 1
a. Cement 63.94 bags *
b. Fine Aggregates 3.37 cu.m **
c. Coarse Aggregates 6.73 cu.m ***
d. Water P.E. Cert. - 1 0 1

Summary: for items 405(1)a3 & 407(8)


a. Cement * 1,045.29 bags Q-1 0 1
b. Fine Aggregates ** 55.02 cu.m. Q-1 0 1
G-1 0 1
c. Coarse Aggregates *** 110.04 cu.m. Q-1 0 1
G-2 0 2

PHYSICAL ACCOMPLISHMENT 0.00%


\
PREPARED BY: NOTED:

ARVIN D. AYOSO VENDEY M. GALDIANO


ME-1/ Accred #2251 Engineer II
DATREBIL CONSTRUCTION Project Engineer I
LEGEND
M- Mechanical or Sieve Analysis P- Plastic and Liquid Limits Test
C- Compaction of Test D- Field Density Test
Q- Quality Test SF- Shrinkage Factor Test
FT- Free Test IR- Inspection Report
-One test of every layer of 20 cu.m. distance between test holes not to exceed 150 linear meters.
-One set by Cylinder samples for every dry pouring but not exceed 75 cu.m
-One set by beam samples for every dry pouring but not exceed 75 cu.m.
Date: May 2, 2018

April 1 - 30, 2018

Work
Accom.

0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%

0.00%
0.00%

0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%

M. GALDIANO
gineer II
Engineer I

astic and Liquid Limits Test


Shrinkage Factor Test
nspection Report
SUMMARY REPORTS OF FIELD TESTS

Project :

Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road For the period: April 1 - 30, 2018
Location : Veruela, Agusan del Sur

Quality Original Source Kind of Spec's SAMPLED TESTED Remarks/


Laboratory Kind of Materials
Represented of Materials Test Item By Date By Date Recommendation

Note:

Project on-going…

PREPARED BY: CERTIFIED CORRECT: ATTESTED BY:

ARVIN D. AYOSO HANNIBAL M. SALCEDO VENDEY M. GALDIANO


ME-1/ Accred #2251 Engineer II/ME-1, D1-00826 Engineer II
DATREBIL CONSTRUCTION Quality Assurance Section Project Engineer I
MONITORING OF QUALITY ASSURANCE (QA) IMPLEMENTATION BY THE
DISTRICT ENGINEERING & CITY OFFICES IN DPWH INFRASTRUCTURE PROJECTS

Name of Project : Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

Contractor : MRS BUILDERS & SUPPLY Veruela, Agusan del


Implementing Office : DPWH 2nd District Engineering Office , San Francisco, ADS Project Cost : P
Project Duration : a.) Date Started :
b.) Project Date of Completion :
c.) Calendar Days :

CONCERN REMARKS
* Accreditation of PE/PI A
VENDEY M. GALDIANO PE I
Accreditation No.
* Accreditation of Contractors'/Consultants'
ME B
ARVIN D. AYOSO ME-I
Project on going…
Acreditation No.
* Limits of Assignment of PE/ME C

PE - Project being implemented do not exceed ₱ 20 M


in cost.

* Current or latest sanction(s) Imposed on


DPWH PE/PI/ME or Contractor's/ME

None

* Approval of BRS on Special Items of Works


(SPL) D

None

* Accreditation of Private Testing Laboratory


and Batching Plants E
* The minimum testing requirement were perfo
Compliance to Minimum Testing Requirements F contractor.

A. D.O. No. 73, s.1998


B. D.O. No. 184, s.1999
C. D.O. No. 42 s.2006, D.O. No. 41,s. 2007 and D.O. 55 s.2012
D. D.O. No. 43, s.2006
E. D.O. No. 253, s.2003 and D.O No. 26, s.1989
F. DPWH Secretary's Memorandum dated 25 January 1989
BRS FORM QA-1
LITY ASSURANCE (QA) IMPLEMENTATION BY THE
CITY OFFICES IN DPWH INFRASTRUCTURE PROJECTS

ance of Bank Protection along Asuncion-Laak-Veruela Road

Veruela, Agusan del Sur


46,350,100.31

REMARKS

Project on going…
The minimum testing requirement were performed by the
contractor.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur

April 30, 2018


Date

CERTIFICATION
Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

Name of Project :

Location : Veruela, Agusan del Sur

Contractor : MRS BUILDERS & SUPPLY

I hereby certify that Item 1714(1) which represents the Gabions of the above named projec
a total quantity of Twenty (20) cubic meter was done in accordance to the approved plans &
specifications.

VENDEY M. GALDIAN
Project Engineer I

R.13.11.6/qas/ads II/fconolIIIfiles
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur

April 30, 2018


Date

CERTIFICATION
Repair/Maintenance of Bank Protection along Asuncion-Laak-Veruela Road

Name of Project :

Location : Veruela, Agusan del Sur

Contractor : MRS BUILDERS & SUPPLY

I hereby certify that Item 1713(2) which represents the Mattresses of the above named pro
with a total quantity of One-Hundred Ninety five (195) cubic meter was done in accordance to the
approved plans & specifications.

VENDEY M. GALDIAN
Project Engineer I

R.13.11.6/qas/ads II/fconolIIIfiles
Republic of the Philippines
NT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
TRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur

April 30, 2018


Date

IFICATION
ank Protection along Asuncion-Laak-Veruela Road

1) which represents the Gabions of the above named project with


er was done in accordance to the approved plans &

VENDEY M. GALDIANO
Project Engineer I
Republic of the Philippines
NT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
TRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur

April 30, 2018


Date

IFICATION
ank Protection along Asuncion-Laak-Veruela Road

2) which represents the Mattresses of the above named project


ety five (195) cubic meter was done in accordance to the

VENDEY M. GALDIANO
Project Engineer I