LOOPER WIRE ROPE CHANGING
Page: 2 of 6
1. Introduction:
To pull the accumulator looper car and ensure the tension to the strip.
A. Reference drawings:
1) General Assembly:
1) Looper Winch-L95239
ISSUED BY : APPROVED BY :
ISSUED DATE : 01/06/2011
REF NO: CRM/ESL/4984/W
CTCM REV NO: 00
AMD NO: 00
EFF. DATE : 01.06.2011
LOOPER WIRE ROPE CHANGING
Page: 3 of 6
2 . Description of Facility:
A. Facilities :
Looper winch consist a rope drum on which Wire rope Ø46 is connected through looper car. It is used to provide strip tension and
forward/backward movement of looper car when drum rotates.
B. Equipment details:
QTY
FOR
EQUIPMENT NO SYSTEM CTCM CAPACITY WEIGHT(Kg) LOCATION
Looper Winch
1165 Rope Drum 1 8712 Kg Looper Winch
1165 Wire Rope 240 Mtrs. 1960 KN 2767 Kg Looper Winch
ISSUED BY : APPROVED BY :
ISSUED DATE : 01/06/2011
REF NO: CRM/ESL/4984/W
CTCM REV NO: 00
AMD NO: 00
EFF. DATE : 01.06.2011
LOOPER WIRE ROPE CHANGING
Page: 4 of 6
6. Emergency preparedness:
A. Fire:
a) Inform to fire and safety control room and seek for assistance.
b) Inform the area incharge
c) Inform to CTCM in charge.
d) Inform to operation and maintenance shift in charges.
e) Inform to departmental HOD.
f) Take following actions to control and mitigate the fire:
Seek assistance from fire and safety department and departmental maintenance personnel. .
Evacuate all the personal at surrounding areas other than personal attending FIRE.
Use appropriate fire extinguishers like (CO2 extinguisher) available at site for mitigating the fire.
Use water (Fire water network) to cool the hot areas caused by fire.
Ensure that fire is attended and recorded in log book.
Prepare fire incident report and send it to fire control room for detail investigation to avoid such type of fire in future.
B. Spillage of materials
N/A
7. Safety Equipment and Tools - Required.
A. Safety appliances
a) Helmet.
b) Safety shoes.
c) Hand gloves
a) Fill looper up to maximum % if possible because it reduce wire rope rigging work hence reduces time.
b) Looper tension switched off.
c) Jog looper winch forward to eliminate the rope tension completely. (Tension due to strip weight and rope weight.)
d) Work permit to perform the job. (Do not take winch drive lockout as for removing and fixing rope, winch jog is required.) Take
precaution (E-Stop) for dismounting rope locking clamp on rope drum.
ISSUED BY : APPROVED BY :
ISSUED DATE : 01/06/2011
REF NO: CRM/ESL/4984/W
CTCM REV NO: 00
AMD NO: 00
EFF. DATE : 01.06.2011
LOOPER WIRE ROPE CHANGING
Page: 5 of 6
14. Engineering Change notes - Records to be maintained with proper approvals and formats.
a) All the engineering changes shall be approved on prescribed format from HOD with proper reasons for changes.
b) After changes being made, rewrite the SOPs and revised documents shall be issued to respective control rooms.
17. Documents would be reviewed and authorised person for the change in SOPs.
a) Head of the department / CTCM Mech In charge.
b) SOP Shall be reviewed every 2 years and record shall be maintained.