Академический Документы
Профессиональный Документы
Культура Документы
Provisions
Oman Wednesday 23 May 2018
Jonathan Sanderson
Contact: jon.sanderson@qgs.global, www.qgs.global
1
Liquidated Damages and Penalty Provisions
Discussion to outline:
• What are Liquidated Damages (LDs) and what are their benefits and
drawbacks?
• Are LDs a cure at all?
• Typical LDs clauses
• Penalty provisions – Definition
• Common Law position on LDs and Penalties
• LDs General Points under Omani law
• General SA implications
• Discussion Q & A
2
What are Liquidated Damages and what are their benefits and drawbacks?
3
Liquidated Damages - What are they?
• Defined as:
4
Liquidated Damages - Benefits
• Employer’s perspective:
- Stops the need to prove or mitigate the loss of the employer, legally
complex, damages hard to evidence and quantify
- No obligation for the innocent party to mitigate loss
- Gives the employer certainty
• Contractor’s perspective:
• Often used as a threat…. You know what will happen if you don’t
complete…..
6
Are Liquidated Damages a cure at all?
7
Liquidated Damages – A cure?
8
Typical LD clauses
9
Typical LD Clauses
• Structure of clause:
10
Typical LD Clauses
Clause 47 (1)
If the Contractor shall fail to achieve completion of the Works within the time
prescribed by Clause 43 hereof, such extended time as may be allowed under Clause
44 hereof, then the Contractor shall pay to the Employer the sum stated in the
Appendix to the Tender as a penalty for such default for every day or part of a day
which shall elapse between the time prescribed by Clause 43 hereof or the extended
time as the case may be and the date of certified completion of the Works. The
Employer may, without prejudice to any other method of recovery, deduct the
amount of such penalties from any monies in his hands, due or which may become
due to the Contractor. The payment or deduction of such penalties shall not relieve
the Contractor from his obligation to complete the Works, or from any other of his
obligations and liabilities under the Contract.
[Sultanate of Oman, Standard Documents for Building and Civil Engineering Works
Third Edition July 1981]
11
Typical LD Clauses
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion] the
Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay delay damages to
the Employer for this default. These delay damages shall be the sum stated in the
Appendix to Tender which shall be paid for every day which shall elapse between
the relevant Time for Completion and the date stated in the Taking-Over Certificate.
However, the total amount due under this Sub-Clause shall not exceed the maximum
amount of delay damages (if any) stated in the Appendix to Tender.
These delay damages shall be the only damages due from the Contractor for such
default, other than in the event of termination under Sub-Clause 15.2 [Termination
by Employer] prior to completion of the Works, or from any other duties, obligations
or responsibilities which he may have under the Contract.
12
Typical LD Clauses
If Contractor fails to :-
(a) achieve READY FOR START UP of the WORK or any part thereof on or before the
scheduled date for READY FOR START UP (KEY DATES) as provided in PART A of
SECTION III then the CONTRACTOR shall pay or allow to COMPANY those
Liquidated Damages for Delay at the applicable rate set out in PART B of
SECTION III ;
(b) achieve those the PERFORMANCE GUARANTEES listed in PART C of SECTION III
and COMPANY exercises its right to claim Liquidated Damages in respect of such
failure.
then CONTRACTOR shall pay or allow to the COMPANY those Liquidated
Damages set out in PART C of SECTION III
13
Penalty Provisions - Definitions
14
Penalty Provisions - Definitions
• Definition:
15
Common Law position on LDs and Penalties
16
Common Law position on LDs and Penalties
• Pertinent case: Dunlop Pneumatic Tyre Company v New Garage and Motor
Company [1915] A.C. 79
17
Common Law position on LDs and Penalties
• The defendants agreed to pay £5 ‘by way of liquidated damages and not as
a penalty’ for every tyre sold in breach of the agreement
• It was held that the clause was not penal and was a genuine pre estimate of
Dunlop’s potential loss (liquidated damages), therefore the agreement was
enforceable
• Noting that the price undercutting would have damaged the claimants
business, the ability to be precise in the pre-estimation of losses was
impossible
18
Common Law position on LDs and Penalties
c) Where the breach consists of the non-payment of money and the sum to be paid on
breach is greater than the sum which ought to have been paid, the sum is a penalty
d) There is a presumption (but no more) that where a single lump sum is to be paid on
the occurrence of one or more or all of several events, some serious and others not,
is a penalty
e) A sum is not prevented from being liquidated damages by the fact that precise pre-
estimation of the loss is impossible, but in this case it was reasonable in the
circumstances and not therefore a penalty
f) Noting that the above is judged at the date of the agreement and not the breach
19
Common Law position on LDs and Penalties
• The burden rests to prove the damages are invalid by the party arguing that the
damages are ‘extravagant and unconscionable’
• Case of Philips Hong Kong Ltd v A-G of Hong Kong upheld the principle of LDs being
judged at the point of the agreement
• Lord Woolf…..
‘the court has to be careful not to set too stringent a standard and bear in mind that
what the parties have agreed should normally be upheld’ not least because ‘any
other approach will lead to undesirable uncertainty especially in commercial
contracts’
• Principles of Jeancharm Ltd (t/a Beaver International) v Barnet Football Club Ltd
[2003] EWCA 58
• Principles of Jeancharm Ltd (t/a Beaver International) v Barnet Football Club Ltd
[2003] EWCA 58
• Issue of Interest to be paid at five per cent a week (260 per cent per annum) for
late payment of an invoice. Authority found in the Dunlop case
• Held that the sums set out were immodest and far beyond any attempt to estimate
loss, they were therefore invalid as a penalty
21
Common Law position on LDs and Penalties
• In summary:
• LDs will be generally be used as the basis of the damages under common law
subject to the guidance rules
• Courts will resist the reassessment of the pre estimate of the damages (LDs) by
using the ‘Dunlop Principles’
• No need to prove loss but if court rules as a penalty, legal pleadings would need
to be made for Damages at Law in the alternative
22
Common Law position on LDs and Penalties
• In summary:
3. Connect the type of breach with the damages sustained, considering remoteness
and foreseeability
23
Common Law position on LDs and Penalties
• Drafting considerations:
24
Common Law position on LDs and Penalties
Ø Can A sue for its actual losses or does the LDs clause work as a limitation /
exclusion clause ?
25
Common Law position on LDs and Penalties
• No damages available
26
LDs General Points under Omani law
27
LDs General Points under Omani law
• LDs clauses are generally acceptable in GCC jurisdictions and Oman is no different
• However the courts have discretion to adjust the level of compensation agreed
• The Party requesting the adjustment must prove the loss suffered does not
correspond to the amount agreed
• If fixed amount provided for is wholly unrelated to the amount of financial loss
suffered, court could consider this punitive and hence non-recoverable
28
LDs General Points under Omani law
- Article 267
2. In all cases, the court may, upon the application of either of the parties,
amend such agreement to make the compensation equal to the damage, and
any agreement to the contrary shall be null and void.
29
LDs General Points under Omani law
• Burden of proof rests with the party making the application to the court to ‘open
up’ the level of penalties or LD’s
• Consider:
• Contractor risk of seeking to review the damages through the court
could face the fact the damages could increase!
30
LDs General Points under Omani law
• The 3 points previously highlighted in Common Law would equally apply if the
damages were to be assessed by the court:
3. Connect the type of breach with the damages sustained, considering remoteness
and foreseeability
31
SA General Comments
• Usually SA makes EOT award conditional upon the contractor completing the
work within a given timescale
• Issues:
• SA is not actually compensating for the delays already suffered
• LDs being levied for the full period if the Contractor misses the revised
(target) date
32
LDs Examples
33
LDs Examples
• Example 1
• Qatari Law
• At the time of the delay there was an oversupply to the grid and the power
company would not have been able to sell electricity at the planned price
34
LDs Examples
• Example 2
• English law
• Actual damages were much greater than the cap in the LDs clause
35
Liquidated Damages and Penalty Provisions
Any Questions?
36