Tabla 19 Flujo de Caja Proyecto Sin uso de Relleno cementado

0 1 2 3 4 5 6
Toneladas tratadas (ton) 200000 600000 720000 720000 720000 90800
Producción de Cu (tmf) 3220 9660 11592 11592 11592 1461.88
Recuperación Metalúrgica 92% 92% 92% 92% 92% 92%
Precio Cu (US$/ton) $5,070.58 $5,070.58 $5,070.58 $5,070.58 $5,070.58 $5,070.58
Costo Operacional (US$/ton) $29.40 $29.40 $29.40 $29.40 $29.40 $29.40
Ingreso por Ventas $15,021,086 $45,063,259 $54,075,910 $54,075,910 $54,075,910 $6,819,573
Costos Variables ($5,680,000) ($17,040,000) ($20,448,000) ($20,448,000) ($20,448,000) ($2,578,720)
Depreciación Legal ($1,825,911) ($1,825,911) ($1,825,911) ($1,825,911) ($1,825,911) ($1,825,911)
Ganancias de Capital ($448,440)
Perdidas Ejercicios Anteriores
U. A. I. $7,515,175 $26,197,347 $31,801,999 $31,801,999 $31,801,999 $1,966,502
Impuesto (20%) ($1,503,035) ($5,239,469) ($6,360,400) ($6,360,400) ($6,360,400) ($393,300)
U. D. I. $6,012,140 $20,957,878 $25,441,599 $25,441,599 $25,441,599 $1,573,202
Ganancias de Capital $448,440
Depreciación Legal $1,825,911 $1,825,911 $1,825,911 $1,825,911 $1,825,911 $1,825,911
Perdidas Ejercicios Anteriores
FLUJO CAJA OPERACIONAL $7,838,051 $22,783,789 $27,267,510 $27,267,510 $27,267,510 $3,847,553
Inversión Fija ($49,778,328)
Valor Residual de la Inversión $4,035,960
Capital de Trabajo ($2,840,000)
Recuperación Capital de Trabajo $2,840,000
FLUJO DE CAPITALES ($52,618,328) $0 $0 $0 $0 $0 $6,875,960
FLUJO DE CAJA ($52,618,328) $7,838,051 $22,783,789 $27,267,510 $27,267,510 $27,267,510 $10,723,513
𝑉𝐴𝑁 (8%) 𝑑𝑒𝑙 𝑝𝑟𝑜𝑦𝑒𝑐𝑡𝑜 = 41.176.258 [𝑈𝑆$]