Академический Документы
Профессиональный Документы
Культура Документы
2
Field Architecture
Field Architecture Overview – Facilities
Facilities
Processing facility in the field that separates and processes the fluid from the reservoir(s).
May be manned or unmanned; minor processing through to full production and storage.
Production may be exported to shore by pipeline or offloaded in shipments.
Facilities can be fixed structures or moored structures and even disconnectable.
ELECTRO-
HYDRAULIC PRODUCTION /
FIXED UMBILICALS WATER
PLATFORM INJECTTION WELLS
TIE-BACK PIPELINES
SSIV WATER
INJECTION
5
Field Architecture Overview – Floater
TURRET
WATER
INJECTION MOORINGS
WELLS
RISERS
FLOWLINES
PRODUCTION
WELLS
GAS
INJECTION
WELLS
6
Field Architecture Overview – Video
7
Field Architecture Overview – NWS Examples
11
Installation Vessels
12
Installation Vessels
SSCV (Semi Submersible Construction Vessel) DCV (Deepwater Construction Vessel)
Pipelay (J-lay, deepwater) / Heavy Lift Pipelay (Deepwater reel-lay with liftable
1000Te – 7000Te Crane cartridge reels) / Heavy Lift
Anchors / DP 1000Te – 4000Te Crane
Hs < 4m Dynamic Positioning
Hs < 3m
13
Installation Vessels
14
Installation Vessels – MIV Video
15
Installation Vessels
16
Installation Vessels
AHT (Anchor Handling Tug) / Supply vessel
Mooring Installation and tows
100Te – 500Te winches / A-frame optional (removable) / Limited crane
Stern roller / tow pins / Karm Forks / Chain Lockers / Gypsies
Small - moderate deck area
Reduced accommodation and facilities
Hs< 3m
17
Installation Vessels
18
Installation Vessels
19
Installation Vessels
20
Installation Vessels
21
Installation Vessels - Positioning
Dynamic Positioning
Computer controlled thrusters
Global or Local Reference
22
Installation Vessels – Positioning Reference
DGPS (Differential Global Positioning System)
0.02 – 3m at surface
Inbuilt as part of the vessel DP
Accessible by separate subsea construction survey system
23
Installation Vessels – Acoustic Positioning
Subsea Acoustic Positioning
Systems used to position equipment during installation.
Additional equipment mobilised onto the installation vessel but
tied into the GPS as well as hull mounted transceiver.
24
Installation Vessels – Auxiliary Positioning
Taut Wire
Clump weight is lowered to the seabed
The length and angle of the wire is measured to
determine the vessel position
Fanbeam
Laser position reference system
Reflects signal off a prism installed on a fixed structure
Radar . Artemis
Radar based system with a transmitter installed on a
fixed structure and receiver installed on the vessel.
25
Installation Vessels – Crane Capacity & Lifting
Stated crane capacity is typically the maximum capacity for the
optimal radius for an inshore lift.
Capacity influenced by:
Crane configuration
Number of wire falls (parts)
Crane radius and position
On deck or subsea / amount of wire paid out
Lift weights influenced by:
Weather / Vessel motions
Subsea hydrodynamic affects on the structure
Combined crane / structure considerations:
Crane heave compensation
Passive heave compensation
26
Installation Vessels – Crane Capacity & Lifting
27
Installation Vessels – Selection
Vessel Selection Considerations (just to name a few)
Environmental response / Workability
Deck space and capacity
Crane capacity and reach
Station keeping capability / redundancy
Stability and manoeuvrability
Auxiliary power
Equipment maintenance regime
Accommodation
Transit speed
Shallow water capability
Berthing draft
Day rate and availability
28
Working Underwater - Diving
DSV
1 Bar
0m
SEA LEVEL
2 Bar
-10m
3 Bar
-20m 20M
4 Bar
AIR DIVING
-30m SATURATION DIVING
Breathing Mix: Air (Oxygen/Nitrogen)
5 Bar
Diving Basket/Bell Typically - 18 msw to -200msw
-40m
Breathing Mix: HeO2 (Helium/Oxygen)
6 Bar Sealed System & Diving Bell
-50m
NITROX DIVING
7 Bar
-60m Breathing Mix: Raised O2 %
8 Bar (Nitrogen/Oxygen)
-70m Diving Basket/Bell
BELL
9 Bar
-80m
DIVER
SEA BED
DIVE CONTROL
CONTAINER
(D.C.C.)
WET
TWINLOCK DECOMPRESSION
CHAMBER UMBILICAL
DIVE
PANEL SURFACE
AIR
DIVE STANDBY
PANEL
DIVER
AIR TUGGER
WINCH
OXYGEN HP AIR
O2 QUAD QUADS
AIR WET BELL
LAUNCH/RECOVERY
‘A’ FRAME
AIR WET
BELL
CLUMP
WEIGHT
DIVING BELL
LIVING CHAMBERS
DIVE CONTROL
MOONPOOL
39
Installation of Structures – Foundations
40
Installation of Structures – Foundations
41
Installation of Structures – Foundations
Installation - Drilled and Grouted Piles
Typically 12” to 84” , 10m to >50m , 15t to >150t
Surface Drilling rig required
Direct Circulation – <36”
Reverse Circulation – >24”
Upend / Insert / Grout
DSV vs MIV vs DLB vs JUR
42
Installation of Structures – Foundations
Installation - Suction Anchors
Typically 4m to 9m diameter, 5m to
>20m , 35t to >150t
Sub-Surface Pump Skid Required
Direct mount skid
ROV skid
Overboard / Landout / Penetration
AHT vs DSV vs MIV vs DLB vs JUR
43
Installation of Structures – Suction Pile Video
44
Installation of Structures – Foundations
Installation –
Gravity Anchors
Skirted Deadweight vs
Berm Grillage
Single part vs Ballasted
Overboard / Landout /
Ballast
AHT vs DSV vs MIV vs
DLB vs JUR
45
Installation of Structures – Foundations
Installation Design Factors
Soil Stratigraphy / Seabed Topography
Deployment Loads (overboard, splash zone, at depth, recovery)
Environmental Criteria / Workability
Overall Dimensions
Twist / rotation
Landout tolerances
Landout forces / speed
Final position tolerances (level, verticality, spatial)
Diver / ROV Access
Connection Systems
Interfaces
46
Installation of Structures – Manifold / SSIV
47
Installation of Structures – Weld head protection
48
Installation of Structures – PLET / PLEM
49
Installation of Pipelines
Installation of Pipelines – Overview
Flexible Pipe (Flowline, Riser)
Production / Gas Lift / Gas Injection / Water Injection
Short length, e.g. < 20 km
Small or medium diameter, e.g. 2” to 20”
Specialist product delivered on reels
Bespoke design, materials and layers
Rigid Pipeline (Flowline, SCR, Export)
Flowline - Production / Gas Lift / Gas Injection / Water Injection
Medium to long lengths > 20km
Up to large diameters > 20”
Various pipe types (SML, HFW, DSAW etc) from pipe mills in 12m joints
Various coatings (CWC, corrosion, GSPU / GSPP insulation)
Special types (PIP)
Umbilicals
51
Installation of Pipelines – Flexible Pipe
Installation of Pipelines – Flexible Type
Pipeline Types – Flexible - Composite structure
Rough Bore
Smooth Bore
53
Installation of Pipelines – Flexible Layers
Pressure Vault
External Pressure / Internal
Pressure / Crushing
Teta
Zeta
Carcass
External Pressure /
Armour Wires Crushing
Axial Tensile and
Compressive Loads
54
Installation of Pipelines – Flexible Layers
Pressure Sheath
External Sheath
55
Installation of Pipelines – Flexible Properties
Carcass at max
and min pitch
56
Installation of Pipelines – IPB & Umbilical
Umbilical Integrated Production
Bundle
57
Installation of Pipelines – Flexible Risers
SHAPES:
“S” Shapes – Incorporates a midwater arch
CONFIGURATIONS:
“Steep” Configuration – Incorporates and riser base
or bottom stiffener
58
Installation of Pipelines – Flexible Risers
Flexible Riser – Free hanging
Top stiffener
59
Installation of Pipelines – Flexible Risers
Flexible Riser – Steep S
Bottom stiffener
60
Installation of Pipelines – Flexible Risers
Flexible Riser – Steep Wave
Top stiffener
• Good for congested seabed
developments
• Limited to single lines.
• Very good dynamic response.
Bottom stiffener
Buoyancy modules
61
Installation of Pipelines – Flexible Risers
Flexible Riser – Lazy S
Top stiffener
Tether
Clump weight
62
Installation of Pipelines – Flexible Risers
Flexible Riser – Lazy Wave
Top stiffener
63
Installation of Pipelines – Flexible Risers
Flexible Riser – Pliant Wave ™
Top stiffener
• Developed as an hybrid
between lazy wave and steep Buoyancy
wave. modules
• Retains advantages of lazy wave
and dynamic behaviour of
steep wave.
Tether(s) Clamp
Clump weight
64
Installation of Pipelines – Flexible Risers
Free Standing Hybrid Riser
Flexible
Jumper
Buoyancy
Tank
Rigid riser
• Good for deepwater applications.
• Shorter flexible riser makes this
more cost effective for deep water.
Bottom
Assembly &
Riser Base
65
Installation of Pipelines – Flexible Supply & URB
Installation
Reels typically 8.6m dia & 200Te reel
Can be up to 14m dia and 400Te
Reels are driven by Under Rollers or Hub
Drives
Lay over an Overboarding Wheel /
Overboarding Chute
66
Installation of Pipelines – Flexible Reel Hub Drive
Installation - Hub Drive
Technip TR System
260-450 Te product
Overboarding Wheel /
Overboarding Chute
67
Installation of Pipelines – Tensioners & Chutes
Installation - Horizontal Tensioner
Bi-cat ~ 10 Te
Tri-cat ~ 30 Te
Quad-cat ~ 60 Te
Overboarding Wheel /
Overboarding Chute
68
Installation of Pipelines – Flexible Lay System
Installation – Purpose built lay system with overboarding chute and tensioner
69
Installation of Pipelines – Flexible VLS / Carousel
Installation - Vertical Lay
System
Fed by Reels or Carousel
Single or dual quad-track; 125
or 270+ Te line tension
70
Installation of Pipelines – Flexible VLS / Carousel
Deployment of the Flexible
CSO Constructor with VLS
Vertical Lay / VLS:
Vertical quad tensioners installed
over moonpool
Suitable for deep water / high
tension
Up to 135 Te for single VLS
Up to 270 Te tension holding
capacity for double VLS
Modular system can be mounted on
different vessel
Typical lay speed 900m/hour
Installation of Pipelines – Flexible
Installation Considerations
Route Alignment
Environmental Criteria / Workability
Tie In Approaches
Minimum Bend Radius
“Grip” on product vs crushing
Transportation – Reels or Carousel
Damage to external coatings
Stability on Seabed
Connection System
Diver / Diverless
API / ANSI / Vendor hub
Vertical / Horizontal
72
Installation of Pipelines – Rigid Pipe
Installation of Pipelines – Rigid
74
Installation of Pipelines – Rigid Pipe in Pipe
75
Installation of Pipelines – Rigid Pipe Fabrication
Pipeline Fabrication
Pipe supplied in 40’ / 12m length (joints) from the pipe mill
Pipe coating applied at coating plant
Coated joints must be connected together
Welding / Inspection
Local field joint coating
May be pre-connected into double, triple or quad lengths in preparation for
installation
76
Installation of Pipelines – Rigid Pipe
Pipeline Installation Techniques
S-lay Shallow water to deepwater but limited by tensioner / vessel
thrust for large dia pipe
J-lay Not for shallow water and typically for deep water / large dia
77
Installation of Pipelines – S Lay
79
Installation of Pipelines – S Lay
Work Station
Welding
Inspection
Field Joint Coating
80
Installation of Pipelines – S Lay
81
Installation of Pipelines – S Lay Video
82
Installation of Pipelines – J Lay
84
Installation of Pipelines – J Lay
85
Installation of Pipelines – J Lay
Workstation
(Welding, NDT & FJC)
86
Installation of Pipelines – Reel Lay
88
Installation of Pipelines – Technip Spoolbases
Orkanger
Evanton
Mobile
Luanda
Installation of Pipelines – Pipe Delivery to Base
90
Installation of Pipelines – Pipe Joint Handling
91
Installation of Pipelines – Line Up for Stalking
92
Installation of Pipelines – Root and Hotpass
93
Installation of Pipelines – Fill / Weld Completion
94
Installation of Pipelines – NDE
95
Installation of Pipelines – NDE Acceptance
96
Installation of Pipelines – Cleaning
97
Installation of Pipelines – Field Joint Coating
98
Installation of Pipelines – Pipe Stalks Racked
99
Installation of Pipelines – Reeling onto Vessel
Dual Spooling
100
Installation of Pipelines – Reel Lay
102
Installation of Pipelines – PLETS
PLET must be designed for vessel and lay aystem
Size
Weight
Dimensions
PLR?
Installation of Pipelines – Deep Energy
Carrier Pipe
105
Installation of Pipelines – Bundle Preparation
Bottom-tow Bundle
PLET
Bundle
Possible inline
structure
106
Installation of Pipelines – Bundle Tow
Bottom-tow Bundle
Gulf of Mexico Installation
Manifold or PLET
107
Installation of Pipelines – Bundle Tow
Controlled Depth Tow Method Bundle
North sea installation
108
Installation of Pipelines – Bundle Tow
CDTM Bundle
109
Installation of Pipelines – Pipeline Stabilisation
Trenching
Concrete Mattress
Rock Dumping
Rock Bolting
110
Installation of Pipelines – Considerations
Rigid Pipeline Installation Considerations
Route Alignment Buckle detection
Pipe Size and Properties Line Tension
Environmental Criteria / Workability Material Specification & Welding Criticality
Initiation / Tie Ins / Dry & Wet Recovery Fatigue
In Line Structure Interaction Horizontal Catenary Load
Hog Bend Stress / Sag Bend Stress Temporary and Permanent Stability
111
Installation of Pipelines – Tie-Ins
Installation of Pipelines – Tie-Ins
Umbilical jumpers
Flowlines
Multi-bore
Rigid spools Separate cores
Flying Leads
Flexible jumpers
Electrical jumpers
113
Installation of Pipelines – Rigid Spools
114
Installation of Pipelines – 6” Spool Installation
115
Installation of Pipelines – 36” Spool Installation
116
Installation of Pipelines – E-Spool Installation
117
Installation of Pipelines – Flexible Jumpers
First End
118
Installation of Pipelines – Flexible Jumpers
Second End
119
Installation of Pipelines – FMC ROVCON Video
120
Installation of Pipelines – Flying Leads
Hydraulic / Electrical
Basket deployed to seabed
ROV or Diver fly to place
121
Installation of Pipelines – Flying Leads
122
Installation of Pipelines – Tie-Ins
Installation considerations
Approach Alignment
Sequencing
Connection system
ROV/Diver access
Metrology and fabrication (rigid)
Environmental Criteria / Workability
Initiation / Laydown
Over-length management (flexibles)
Mechanical alignment
Stabilisation
Flooding and hydrotesting
123
Installation of Mooring Systems
Mooring Components
Installation Equipment / Vessels
Methods
124
Installation of Mooring Systems - Components
Anchors / Piles
Anchors
Several variations on the same
basic principal
Driven Piles
Hammered into seabed using
specialist subsea hammer
Suction Piles
Suction applied to pull pile into the
seabed (often used in soft muddy
seabed conditions)
Anchors / Piles
128
Installation of Mooring Systems – Suction Piles
129
Installation of Mooring Systems – Preload
Mooring Preload
Generally specified by Client
Can sometimes be challenged / influenced early in the design phase
Has a major impact on vessel / methodology selection
Required to:
Prove anchor / pile holding capacity
Pull chain through mud to establish ‘inverse’ catenary for piles
130
Installation of Mooring Systems – Preload
131
Installation of Mooring Systems – Lines
Mooring Lines
Chain
Simple, hard to damage
Studlink vs studless
Torque neutral
132
Installation of Mooring Systems – Lines
Connecting Links
Shackles
H-Links
Used for long term
chain to chain
connections
Kenter Links
Not long term
(fatigue) rated so
usually used only
during installation
Pear Links
Used where a
change in size is
required e.g. to a
different size of
chain
133 Introduction to Mooring Systems and Installation
Installation of Mooring Systems – Lines
Dynamic or static
Corrosion
Strength
Wear
134 Introduction to Mooring Systems and Installation
Installation of Mooring Systems – Hookup
Flappers
One way locking movement used to pull chain in from the
surface
Triplates
Can be used to connect two lines together and then
deploy the connection
Ballgrabs
Self engaging – the harder you pull the stronger they grip
Equipment
Large Winch
Chain Gypsy
Chain lockers
Stern Roller
136
Installation of Mooring Systems – AHT’s
Gypsies
Mounted on the ends of the winch drum
138
Installation of Mooring Systems – Installation
139
Installation of Mooring Systems – Installation
Beware of Uplift at
the Anchor
140
Installation of Mooring Systems – Installation
141
Installation of Mooring Systems – Installation
Wire from Riser Column transferred to Deep Orient and connected to chain
142
Installation of Mooring Systems – Installation
143
Subsea Installation – Conclusions
Installation can drive the overall design and execution philosophy
Interface knowledge transfer is critical to success
144
Transfer Between Two Floating Platforms Video
145
Thank you
www.technip.com
Presentation Improvements
148
Pipelines - Rigid
Seamless - <16”
149
Pipelines – Rigid
150
Installation of Pipelines – Rigid Pipe Fabrication
Welding
Number of different techniques to suit
Material
Speed
Cost and availability of welders and equipment
Mechanised or manual processes available
Shielded Metal Arc Welding (SMAW) - Manual
“Stick” welding
Gas Metal Arc Welding (GMAW) – Semi Automatic
“MIG” welding
Gas Tungsten Arc Welding (GTAW) – Semi Automatic
“TIG” welding
151
Manual GTAW (TIG)
152
Mechanised GMAW (MIG)
153
Diver hot tapping works – West Delta
project Egypt
154
Diver hot tapping works – West Delta
project Egypt
155