- During request list for all material / equipment
installation to HO of Hyosung
- Make BQ for Lighting for PH & Installation for
WLS - Make BQ for additional material - During recapitulation material on site ( WLS, PA/PAGING ) - Review for method work for installation lighting at 1st Floor of Power House and Installation water level system
- Cordination with Subcon for Public Lighting
Access Road than make appointment on July 06,2018. Plan of work ( July 2 Status 1st
- Complete all method statement &
submitted to HEC submit to HEC
- Check Material for Installation
on Progress FA/PA/CCTV/etc at Switchyard & Power House
- Check Additional Material for
on Progress Installation Support at Switchyard & Power House - Review Drawing for Installation at a wait response from Mr. Mangesh Power House & Switchyard
- follow up replacement material of
a wait response from HO of Hyosung interlock key from CG
- Purpose for Cable Schdule Plan
on Progress ( SWYD & PH ) Follow up to supplier
on Progress
on Progress
Confirmed to Meeting & discuss on July
06,2018 Plan of work ( July 2018 ) / Weekly Plan
2nd 3rd
- Complete all method statement - Complete all method statement &
& submit to HEC submit to HEC
- Check Material for Installation - Execution work for all material of
FA/PA/CCTV/etc at Switchyard & Installation FA/PA/CCTV already on site Power House
- Check Additional Material for - Prepare for Inspection partially for
Installation Support at Switchyard equipment & installation on switchyard & Power House area - Purpose for Installation of - Purpose for Installation of Lighting Panel at Building Control Building Control & Switchyard
- Review Drawing for Installation - Purpose for Installation of Panel at