Вы находитесь на странице: 1из 24

Name of Project -

Name of Work - 60'x30' 1 Storey R.C.C School (3 Units, 1 Storey)


DETAILS OF MEASUREMENT

Ite Measurement Deductio Contents Unit Totoal of


Particular No.
m L B H ns Each

1 Site Cleaning Work 1 70.00 40.00 - 2800.00 SFT 2800.00

2 Excavation for Foundation


Post Footings 25 3.50 3.50 4.00 1225.00 CFT
Retaining Wall Line 1, 3 & 4 3 39.00 2.50 2.00 585.00 CFT
Retaining Wall Line A, C, E & G 4 19.50 2.50 2.00 390.00 CFT 2200.00

3 Hardcore Filling Work


Post Footings 25 3.50 3.50 0.75 229.69 CFT
Retaining Wall Line 1, 3 & 4 3 39.00 2.50 0.25 73.13 CFT
Retaining Wall Line A, C, E & G 4 19.50 2.50 0.25 48.75 CFT 351.56

4 (1:3:6) Lean Concrete


Post Footings 25 3.50 3.50 0.25 76.56 CFT
Retaining Wall Line 1, 3 & 4 3 39.00 2.50 0.25 73.13 CFT
Retaining Wall Line A, C, E & G 4 19.50 2.50 0.25 48.75 CFT 198.44

5 Brick Work 1st Class in 1:4 Cement Mortor


Retaining Wall Line 1 & 3
1st Step 2 55.50 1.50 0.25 41.63 CFT
2nd Step 2 55.50 1.13 0.25 31.36 CFT
up to plinth 2 55.50 0.75 3.00 249.75 CFT

Retaining Wall Line 4


1st Step 1 55.50 1.50 0.25 20.81 CFT
2nd Step 1 55.50 1.13 0.25 15.68 CFT
up to plinth 1 55.50 0.75 2.67 111.14 CFT

Retaining Wall Line A, C , E & G


Btw: Line 1 & 3, 1st Step 4 22.50 1.50 0.25 33.75 CFT
2nd Step 4 22.50 1.13 0.25 25.43 CFT
up to plinth 4 22.50 0.75 3.00 202.50 CFT
Btw: Line 3 & 4, 1st Step 4 5.25 1.50 0.25 7.88 CFT
2nd Step 4 5.25 1.13 0.25 5.93 CFT
up to plinth 4 5.25 0.75 2.67 42.05 CFT
Stair 6 20.00 1.00 0.63 75.60 CFT 863.50

6 4.5" Thk: Brick Wall in 1:3 Cement Mortor


Wall Line 1 & 3 2 55.50 12.00 1332.00 SFT
Wall Line A, C, E & G 4 22.50 12.00 1080.00 SFT
Wall Line 4 1 37.00 3.25 120.25 SFT
line A & G 2 5.25 3.25 34.13 SFT
2566.38 SFT
Deduction
Windows 13 6.00 5.50 429.00 SFT
Doors 3 4.33 8.50 110.42 SFT
Lintel & Sills(line 1 & 3) 21 9.25 0.25 48.56 SFT
lintel & Sills(line A, C, E & G) 2 4 11.25 0.25 22.50 SFT
RC Frame ( Line C & E) 2 4 11.25 0.25 22.50
Concrete Block over window 9 10 0.67 0.67 40.40 2566.38 SFT
Concrete Block For Verandah 4 10 0.67 0.667 17.88 -691.25 SFT
691.25 1875.12 SFT 1875.12

7 1/2" Thk: Plastering with 1:3 Cement Mortor


Wall 2 1875.12 3750.24 SFT
Lintel, Sill & Handrail 2 93.56 187.13 SFT
Up to Plinth(Main) 1 110.25 3.00 330.75 SFT
up to Plinth (line 3) 1 60.00 0.58 34.80 SFT
up to plinth (Front) 1 53.50 2.67 142.85 SFT
Roof Beam(Main) 1 171.00 1.00 171.00 SFT
Roof Beam(Verandah) 3 72.75 0.75 163.69 SFT
Column(Main) 2 24 0.75 12.00 432.00 SFT
Column(Verandah) 4 7 0.75 10.33 216.93 SFT
sunshade 2 10 7.00 0.38 53.20 SFT 5482.58

8 Earth Filling Work


Main Building 3 19.25 23.25 1.67 2242.29 CFT
Verandah 3 19.25 5.25 1.30 394.14 CFT 2636.43

9 Sand Filling With Watering & Ramming


Main Building 3 19.25 23.25 1.00 1342.69 CFT
Verandah 3 19.25 5.25 1.00 303.19 CFT 1645.88

10 4½" thk; (1:3:6) Concrete Flooring with Water Proof Plastic Sheet
Main Building 3 19.25 23.25 0.38 510.22 CFT
Verandah 3 19.25 5.25 0.38 115.21 CFT 625.43

11 1½" thk; (1:2:4) Concrete Floor Topping


Main Building 3 19.80 24.00 1425.60 SFT
Verandah 1 60.00 5.63 337.80 SFT 1763.40

12 (1:2:4) RC Concrete Work


Footing 25 3.50 3.50 0.75 229.69 CFT
Column (Main Building) 18 0.75 0.75 17.25 174.66 CFT
Column (Verandah) 7 0.75 0.75 14.75 58.08 CFT
Plinth Beam (12"x9")(Line 1 & 3) 2 55.50 0.75 1.00 83.25 CFT
Plinth Beam (9"x9") (line 4) 1 55.50 0.75 0.75 31.22 CFT
Plinth Beam (12"x9")(L A, C, E & G) 4 22.50 0.75 1.00 67.50 CFT
PB (9"x9") (L A, C , E & G) btw L 3 & 4 4 5.25 0.75 0.75 11.81 CFT
Roof Beam (12"x9") (Line 1 & 3) 2 55.50 0.75 1.00 83.25 CFT
Roof Beam (9"x9") (line 4) 1 55.50 0.75 0.75 31.22 CFT
Roof Beam (12"x9")(L A, C, E & G) 4 22.50 0.75 1.00 67.50 CFT
RB (9"x9") (L A, C , E & G) btw L 3 &4 4 5.25 0.75 0.75 11.81 CFT
Lintel,Sill & Handrail(Line 1, 3 &4) 25 9.25 0.42 0.25 24.28 CFT
Lintel, Sill & RC Frame (L A,C,E & G) 4 4 11.25 0.42 0.25 18.90 CFT
Handrail(L A & G btw L 3 & 4) 2 5.25 0.42 0.25 1.10 CFT 894.27

13 Mild Steel Work


(a) Footing ø 16mm ø12mm ø 8mm ø 6mm
ø 16mm @ 6" C/C Both Way 25 14 4.00 1400.00
(b) Column (9"x9") Main
ø 16mm x 6 Nos 18 6 20.63 2227.50
ø 8mm Stirrup @ 6" C/C 18 37 2.50 1676.25
(c) Column (9"x9") Varandah
ø 16mm x 6 Nos 7 6 0.00
ø 8mm Stirrup @ 6" C/C 7 -4 2.50 -70.00
(d) Plinth Beam
Line 1 & 3 (9"x12")
ø 16mm x 3 nos Top Bar 2 3 65.00 390.00
ø 16mm x 3 nos Bottom Bar 2 3 64.67 388.00
ø 8mm Stirrup @ 6" C/C 2 156 3.00 936.00
Line 4 (9"x9)
ø 16mm x 3 nos Top Bar 1 3 65.00 195.00
ø 16mm x 3 nos Bottom Bar 1 3 64.67 194.00
ø 8mm Stirrup @ 6" C/C 1 156 2.50 390.00
Line A, C , E & G (9"x12")
ø 16mm x 3 nos Top Bar 4 3 25.75 309.00
ø 16mm x 3 nos Bottom Bar 4 3 28.75 345.00
ø 8mm Stirrup @ 6" C/C 4 60 3.00 720.00
Line A, C , E & G (9"x9")
ø 16mm x 3 nos Top Bar 4 3 11.17 134.00
ø 16mm x 3 nos Bottom Bar 4 3 7.42 89.00
ø 8mm Stirrup @ 6" C/C 4 11.5 2.50 115.00
(e) Roof Beam
Line 1 & 3 (9"x12")
ø 16mm x 3 nos Top Bar 2 3 65.00 390.00
ø 16mm x 3 nos Bottom Bar 2 3 64.67 388.00
ø 8mm Stirrup @ 6" C/C 2 156 3.00 936.00
Line 4 (9"x9)
ø 16mm x 3 nos Top Bar 1 3 65.00 195.00
ø 16mm x 3 nos Bottom Bar 1 3 64.67 194.00
ø 8mm Stirrup @ 6" C/C 1 156 2.50 390.00
Line A, C , E & G (9"x12")
ø 16mm x 3 nos Top Bar 4 3 25.75 309.00
ø 16mm x 3 nos Bottom Bar 4 3 25.42 305.00
ø 8mm Stirrup @ 6" C/C 4 60 3.00 720.00
Line A, C , E & G (9"x9")
ø 16mm x 3 nos Top Bar 4 3 6.92 83.00
ø 16mm x 3 nos Bottom Bar 4 3 7.42 89.00
ø 8mm Stirrup @ 6" C/C 4 11.5 2.50 115.00
(f) Sills & Lintels (5"x3")
Line A, C , E & G
ø 12mm x 2 nos Lintels 1 16 11.17 178.67
ø 6mm @ 6" c/c 1 192 0.50 96.00
ø 12mm x 2 nos Sills 1 16 11.17 178.67
ø 6mm @ 6" c/c 1 192 0.50 96.00
Line 1 & 3
ø 12mm x 2 nos Lintels 1 24 9.17 220.00
ø 6mm @ 6" c/c 1 240 0.50 120.00
ø 12mm x 2 nos Sills 1 18 9.17 165.00
ø 6mm @ 6" c/c 1 180 0.50 90.00
Line 4 (Handrail)
ø 12mm x 2 nos Handrail (front) 1 8 9.17 73.36
ø 6mm @ 6" c/c 1 80 0.33 26.40
ø 12mm x 2 nos Handrail (sides) 1 4 5.17 20.68
ø 6mm @ 6" c/c 1 22 0.50 11.00
7624.50 836.37 5928.25 439.40 RFT
ø 16mm ø12mm ø 8mm ø 6mm
1.06 0.60 0.26 0.15
8077.84 498.43 1570.18 65.46 Lb 10211.92

14 Formwork
Footing (3.5'x3.5'x9") 25 1 14.00 0.75 262.50 SFT
Main Column (9"x9") 18 1 3.00 18.25 985.50 SFT
Verandah Column (9"x9") 7 1 3.00 15.75 330.75 SFT
Plinth Beam (9"x12") Sides 1 2 156.00 1.00 312.00 SFT
PB (9"x12") Line C & E Sides 2 2 22.50 1.00 90.00 SFT
Plinth Beam (9"x9") Sides 1 2 66.00 0.75 99.00 SFT
PB (9"x9") L C & E Sides 2 2 5.25 0.75 15.75 SFT
Roof Beam (9"x12") Sides & bot; 1 3 156.00 1.00 468.00 SFT
RB (9"x12") L C & E (sides & bot;) 2 3 22.25 1.00 133.50 SFT
Roof Beam (9"x9") sides & bot 1 3 66.00 0.75 148.50 SFT
RB (9"x9") L C & E (Sides & bot;) 2 3 5.25 0.75 23.63 SFT
Lintels for Door (Line 3)
Sides 3 2 9.25 0.25 13.88 SFT
Lintels for Window (Line 1 & 3)
Sides 9 2 9.25 0.25 41.63 SFT
Bottom 9 1 6.00 0.42 22.68 SFT
Sills for Window (line 1 & 3)
Sides 9 2 9.25 0.25 41.63 SFT
Lintel for Window (Line A & G)
Sides 4 2 11.25 0.25 22.50 SFT
Bottom 4 1 6.00 0.25 6.00 SFT
Sills for Window (line A & G)
Sides 4 2 11.25 0.25 22.50 SFT
Lintel & Sill (line C & E)
Sides 4 2 11.25 0.25 22.50 SFT
Handrail (line 4)
Sides 4 2 9.25 0.25 18.50 SFT
Handrail (line A & G)
Sides 2 2 5.25 0.25 5.25 SFT 2823.31

15 Steel Structure Roofing Work


5"x2" U (MS) Tie Beam 5 24.75 123.75 RFT
5"x2" U (MS) TB (Line P) 4 14.67 58.68 RFT
5"x2" U (MS) TB (Line Q) 2 10.38 20.76 RFT 203.19
4"x2" Rafter
Line B & C (Front) 3 1 21.94 65.82 RFT
Line B & C (Back) 3 1 15.48 46.44 RFT
Line A (Front) 2 1 19.79 39.58 RFT
Line A (Back) 2 1 13.33 26.66 RFT
Hip Rafter (Line P) 2 2 21.90 87.60 RFT
Line Q 2 1 15.48 30.96 RFT
H J R (line 3) 2 1 8.75 17.50 RFT
H J R (line 2) 2 1 12.25 24.50 RFT
H J Rafter ( line 1) 2 1 16.02 32.04 RFT
H J Rafter ( line 4) 4 1 2.56 10.24 RFT
H J R (line 5) 4 1 5.79 23.16 RFT
H J R (line 6) 4 1 9.56 38.24 RFT
4" x 2" King Post (RL B & C) 3 1 4.53 13.59 RFT
4" x 2" King Post (RL B & C) 2 1 3.72 7.44 RFT
4"x2" Ridge 1 1 36.00 36.00 RFT 499.77
3"x2" Purlin (GI)
Purlin 1 (Front & Back) 4 1 64.75 259.00 RFT
Purlin 2 2 1 60.75 121.50 RFT
Purlin 3 2 1 56.75 113.50 RFT
Purlin 4 2 1 52.75 105.50 RFT
Purlin 5 2 1 48.75 97.50 RFT
Purlin 6 2 1 44.75 89.50 RFT
Purlin 7 2 1 37.00 74.00 RFT
Purlin 8 (Sides) 2 1 28.75 57.50 RFT
Purlin 9 2 1 24.75 49.50 RFT
Purlin 10 2 1 20.75 41.50 RFT
Purlin 11 2 1 16.75 33.50 RFT
Purlin 12 2 1 12.75 25.50 RFT
Purlin 13 2 1 8.75 17.50 RFT
Purlin 14 2 1 1.00 2.00 RFT
3"x2" GI Ridge Piece 4 2 21.90 175.20 RFT 1262.70
2"x2" Strut (L MS)
Line A 2 18.26 36.52 RFT
Line C 2 18.26 36.52 RFT
Line B 1 29.26 29.26 RFT
Line P 4 23.23 92.92 RFT
Line Q 2 7.68 15.36 RFT
(2"x2" L MS) Purlin Cleat 1 96 0.17 16.32 RFT 226.90

16 4 angle Colour Sheet Roofing (0.4mm thk:)


Roofing Area 1 64.75 34.75 x by slope factor 2423.32 SFT 2423.32

17 Colour Sheet Ridge Covering (0.4mm thk:)


Rigde Cover 1 36.00 36 RFT
Hip cover 4 21.90 87.60 RFT 123.60

18 8"x1" Eave & Verge Board (PKD)


Front & Back 2 64.75 129.50 RFT
Sides (Main) 2 28.75 57.50 RFT
Sides (Verandah) 2 6.46 12.92 RFT 199.92

19 Cement Board Ceiling With C-Channel Frame


Main 3 19.81 24.00 1426.50 SFT
Varandah 1 60.00 5.67 340.20 SFT
Front+Back+Main Soffit 1 187.00 2.00 374.00 SFT
Verandah Soffit 2 6.46 2.00 25.84 SFT 2166.54

20 5"x2" PKD Chowket Work


Door 3 27.33 81.99 RFT 81.99

21 1½" thk; Teak Panelled Door


Door (Double Leaf) 3 4.00 7.00 84.00 SFT 84.00

22 UPVC Window
Window 13 6.00 5.50 429.00 SFT 429.00

23 Providing 3mm thk; Glass Fanlight


Over Door 3 4.00 1.25 15.00 SFT 15.00

24 3 Coats of Plastic Emulsion Paints


Plaster Area 1 Same as Item no. 7 5482.58 SFT
Ceiling Area 1 Same as Item no. 19 2166.54 SFT 7649.12

25 Painting 3 Coats to Wood Work


Eave & Verge Board 1 199.92 0.75 149.94 SFT
Chowket 1 81.99 0.75 61.49 SFT
Door 2 84.00 168.00 SFT 379.43

26 Gutter Work
5"x5" PVC Gutter 1 187.00 187.00 RFT 187.00

27 3"Ø 13.5mm thk; PVC Drain Pipe


Front 2 15.50 31.00 RFT
Back 2 18.00 36.00 RFT 67.00

28 Scaffolding Work
External 1 208.00 16.00 3328.00 SFT 3328.00

29 2000 Gal Water Tank (GI) 2 2.00 No 2.00


30 Apron & Drain
Name of Project -
Name of Work - 60'x30' 1 Storey R.C.C School (3 Units, 1 Storey)
Builder's Estimate

Ite Particular Quantity Unit Rate (Ks) Per Amount (Ks) Remark
m

1 Site Cleaning Work 2800.00 SFT


Labour
Workers 14.00 No 5,000 No 70,000

2 Excavation for Foundation 2200.00 CFT


Labour
Workers 44.00 No 5,000 No 220,000

3 Hardcore Filling Work 351.56 CFT


Material & Labour
Broken Brick 4.39 Sud 25,000 Sud 109,863
Sand 0.88 Sud 85,000 Sud 74,707
Workers 3.52 No 5,000 No 17,578

4 (1:3:6) Lean Concrete 198.44 CFT


Material & Labour
Cement 25.51 Bags 5,700 Bags 145,426
River Shingle 1.91 Sud 90,000 Sud 171,450
Sand 0.95 sud 85,000 sud 80,963
Mason 1.98 No 6,500 No 12,898
Workers 15.88 No 5,000 No 79,375

5 Brick Work 1st Class in 1:4 Cement Mortor 863.50 CFT


Material & Labour
Cement 48.57 Bags 5,700 Bags 276,859
1st Class Bricks 11657.22 Nos 100 Nos 1,165,722
Sand 2.42 sud 85,000 sud 205,512
Mason 34.54 No 6,500 No 224,509
Workers 51.81 No 5,000 No 259,049

6 4.5" Thk: Brick Wall in 1:3 Cement Mortor 1875.12 SFT


Material & Labour
Cement 49.72 Bags 5,700 Bags 283,428
1st Class Bricks 10313.16 Nos 100 Nos 1,031,316
Sand 1.88 sud 85,000 sud 159,385
Mason 37.50 No 6,500 No 243,766
Workers 56.25 No 5,000 No 281,268
X-met 2156.39 RFT 70 RFT 150,947
Concrete Screen Block 130.00 No 450 No 58,500

7 1/2" Thk: Plastering with 1:3 Cement Mortor 5482.58 SFT


Material & Labour
Cement 73.43 Bags 5,700 Bags 418,536
Sand 2.74 sud 85,000 sud 233,010
Mason 54.83 No 6,500 No 356,368
Workers 109.65 No 5,000 No 548,258

8 Earth Filling Work 2636.43 CFT


Material & Labour
Worker 26.36 No 5,000 No 131,822

9 Sand Filling With Watering & Ramming 1645.88 CFT


Material & Labour
Sand 20.57 sud 85,000 sud 1,748,742
Worker 16.46 No 5,000 No 82,294

10 4½" thk; (1:3:6) Concrete Flooring with Water 625.43 CFT


Proof Plastic Sheet
Material & Labour
Cement 63.66 Bags 5,700 Bags 362,863
Stone Ballast 6.00 Sud 90,000 Sud 540,374
Sand 3.00 sud 85,000 sud 255,176
Mason 6.25 No 6,500 No 40,653
Workers 50.03 No 5,000 No 250,173

11 1½" thk; (1:2:4) Concrete Floor Topping 1763.40 SFT


Material & Labour
Cement 40.78 Bags 5,700 Bags 232,438
Stone Ballast 2.03 Sud 90,000 Sud 182,512
Sand 1.01 sud 85,000 sud 86,186
Mason 13.23 No 6,500 No 85,966
Workers 26.45 No 5,000 No 132,255

12 (1:2:4) RC Concrete Work 894.27 CFT


Material & Labour
Cement 165.28 Bags 5,700 Bags 942,096
Stone Ballast 8.23 sud 90,000 sud 740,454
Sand 4.11 sud 85,000 sud 349,659
Mason 17.89 No 6,500 No 116,255
Workers 134.14 No 5,000 No 670,701

13 Mild Steel Work 10211.92 Lb


Material & Labour 4.87 Ton
ø 16mm MS Rod 3.85 Ton 580,000 Ton 2,232,034
ø12mm MS Rod 0.24 Ton 610,000 Ton 144,849
ø 8mm MS Rod 0.75 Ton 610,000 Ton 456,308
ø 6mm MS Rod 0.03 Ton 610,000 Ton 19,025
Binding Wire 27.03 Viss 1,620 Viss 43,785
Steel Fixer 97.30 No 6,500 No 632,453
Workers 97.30 No 5,000 No 486,503

14 Formwork 2823.31 SFT


Material & Labour
Jungle Wood (3 times used) 2.82 Ton 650,000 Ton 1,835,148
5mm Plywood (3 times used) 32.35 Sheet 17,600 Sheet 569,367
Nail 23.53 Viss 2,340 Viss 55,054
Carpenter 112.93 No 6,500 No 734,059
Workers 56.47 No 5,000 No 282,331

15 Steel Structure Roofing Work 2192.56 RFT


Material & Labour
5"x2" U (MS) 213.35 RFT 900 RFT 192,015
4"x2" U(MS) 524.76 RFT 870 RFT 456,540
3"x2" C (GI) 1325.84 RFT 460 RFT 609,884
2"x2" L ( MS) 238.25 RFT 350 RFT 83,386
Steel Fixer 43.85 No 6,500 No 285,033
Worker 32.89 No 5,000 No 164,442
16 4 angle Colour Sheet Roofing (0.4mm thk:) 2423.32 SFT
Material & Labour
7' 4 angle Colour Roofing Sheet 218.10 No 1,080 No 235,546
Roofing Screw 1211.66 No 60 No 72,700
Steel Fixer 36.35 No 6,500 No 236,273
Worker 24.23 No 5,000 No 121,166

17 Colour Sheet Ridge Covering (0.4mm thk:) 123.60 RFT


Material & Labour
Colour Sheet Ridge Cover 138.43 RFT 700 RFT 96,902
Roofing Screw 61.80 No 60 No 3,708
Carpenter 4.12 No 6,500 No 26,753

18 8"x1" Eave & Verge Board (PKD) 199.92 RFT


Material & Labour
8"x1" PKD 0.26 Ton 1,200,000 Ton 307,077
Nail 1.11 Viss 2,340 Viss 2,599
Carpenters 6.00 Nos 6,500 Nos 38,984

19 Cement Board Ceiling With C-Channel Frame 2166.54 SFT


Material & Labour
2'x2' Cement Board 596.64 No 750 No 447,484
3"x2" PKD Joist 0.62 Ton 1,200,000 Ton 745,425
2"x2" PKD Joist 0.78 Ton 1,200,000 Ton 934,320
2"x.5" Teak Beading 0.21 Ton 2,200,000 Ton 469,191
1.5" Wood Screw 152.33 Doz 250 Doz 38,084
Nail 3.53 Viss 2,340 Viss 8,251
Carpenter 59.24 No 6,500 No 385,069

20 5"x2" PKD Chowket Work 81.99 RFT


Material & Labour
5"x2 PKD 0.13 Ton 1,200,000 Ton 157,421
Nail 0.46 Viss 2,340 Viss 1,066
Bracket 18.00 No 1,200 No 21,600
X-met 81.99 RFT 70 RFT 5,739
Carpenter 4.92 No 6,500 No 31,976
21 1½" thk; Teak Panelled Door 84.00 SFT
Material & Labour
5"x2 PKD 0.26 Ton 1,200,000 Ton 306,103
5" Hinge 24.00 No 900 No 21,600
6" Tower Bolt 6.00 No 800 No 4,800
6" Sliding Bolt 3.00 No 800 No 2,400
6" Handle 12.00 No 800 No 9,600
1.5" Wood Screw 30.00 Doz 250 Doz 7,500
Carpenter 4.20 No 6,500 No 27,300

22 UPVC Window 429.00 SFT


Material & Labour
UPVC Window (M & L Lump Sum) 429.00 SFT 3,500 SFT 1,501,500

23 Providing 3mm thk; Glass Fanlight 15.00 SFT


Material & Labour
3mm thk; Glass 22.50 SFT 1,000 SFT 22,500
Teak Beading 0.02 Ton 2,200,000 Ton 49,716
Carpenters 3.28 No 6,500 No 21,288

24 3 Coats of Plastic Emulsion Paints 7649.12 SFT


Material & Labour
Putty 57.65 Gal 5,500 Gal 317,084
Sand Paper 453.28 No 200 No 90,656
Putty Trowel 21.25 No 800 No 16,998
Emusion Paint 76.35 Gal 5,500 Gal 419,922
Roller 21.25 No 700 No 14,873
Painters 77.91 No 6,500 No 506,400
Worker 77.91 No 5,000 No 389,538

25 Painting 3 Coats to Wood Work 379.43 SFT


Material & Labour
Ready Mixed Paint 2.66 Gal 16,000 Gal 42,553
Putty 0.14 Gal 5,500 Gal 780
Painters 4.74 No 6,500 No 30,829
Workers 3.79 No 5,000 No 18,972
26 Gutter Work 187.00 RFT
Material & Labour
5"x5" Gutter 196.35 RFT 1,300 RFT 255,255
Bracket 93.50 No 1,020 No 95,370
Carpenter 2.81 No 6,500 No 18,233
Worker 3.74 No 5,000 No 18,700

27 3"Ø 13.5mm thk; PVC Drain Pipe 67.00 RFT


Material & Labour
PVC Pipe 67.00 RFT 650 RFT 43,550
Offsets & Bends 16.00 No 700 No 11,200
Bracket 33.50 No 150 No 5,025
Plumber 2.01 No 6,500 No 13,065
Worker 2.01 No 5,000 No 10,050

28 Scaffolding Work 3328.00 SFT


Material & Labour
Bamboo 161.78 No 800 No 129,422
Coinyan 11.77 Viss 2,500 Viss 29,424
Wire Nail 4.71 Viss 2,340 Viss 11,016
Worker 17.33 No 5,000 No 86,667

29 2000 Gal Water Tank (GI) 2.00 No


Material & Labour
2000 Gal Water Tank (GI) 2.00 No 95,000 No 190,000
32,238,753

30 Apron & Drain


Cement 466.96
Sand 37.57
Broken Brick 4.39
River Shingle 18.16
1st Class Brick 21970.38
X-met 2238.38
Concrete Screen Block 130.00
16mm MS Rod 3.85
12mm 0.24
8mm 0.75
6mm 0.03
Binding Wire 27.03
Jungle Wood 2.82
5mm Plywood 32.35
Nail 33.33
Roofing Sheet 218.10
Roofing Screw 1273.46
Rigde Cover 138.43
PKD 2.04

Cement Board 596.64


Teak 0.24
1.5" Wood Screw 182.33
Door Bracket 18.00
Name of Project -

Name of Work - 60'x30' 1 Storey R.C.C School (3 Units, 1 Storey)

Abstract of Cost

Ite Quantity Unit Particular Rate (Ks) Per Amount (Ks)


m

1 2,800.00 SFT Site Cleaning Work 25.00 SFT 70,000

2 2,200.00 CFT Excavation for Foundation 100.00 CFT 220,000

3 351.56 CFT Hardcore Filling Work 575.00 CFT 202,148

4 198.44 CFT (1:3:6) Lean Concrete 2,469.86 CFT 490,112

5 863.50 CFT Brick Work 1st Class in 1:4 Cement Mortor 2,468.63 CFT 2,131,652

6 1,875.12 SFT 4.5" Thk: Brick Wall in 1:3 Cement Mortor 1,177.85 SFT 2,208,611

7 5,482.58 SFT 1/2" Thk: Plastering with 1:3 Cement Mortor 283.84 SFT 1,556,171

8 2,636.43 CFT Earth Filling Work 50.00 CFT 131,822

9 1,645.88 CFT Sand Filling With Watering & Ramming 1,112.50 CFT 1,831,036

4½" thk; (1:3:6) Concrete Flooring with Water Proof


10 625.43 CFT 2,317.18 CFT 1,449,239
Plastic Sheet

11 1,763.40 SFT 1½" thk; (1:2:4) Concrete Floor Topping 407.94 SFT 719,357

12 894.27 CFT (1:2:4) RC Concrete Work 3,152.48 CFT 2,819,164

13 1.00 Item Mild Steel Work 4,014,956.37 Item 4,014,956

14 2,823.31 SFT Formwork 1,231.17 SFT 3,475,959

15 1.00 Item Steel Structure Roofing Work 1,791,299.10 Item 1,791,299

16 2,423.32 SFT 4 angle Colour Sheet Roofing (0.4mm thk:) 274.70 SFT 665,685

17 123.60 RFT Colour Sheet Ridge Covering (0.4mm thk:) 1,030.45 RFT 127,364

18 199.92 RFT 8"x1" Eave & Verge Board (PKD) 1,744.00 RFT 348,660

19 2,166.54 SFT Cement Board Ceiling With C-Channel Frame 1,397.54 SFT 3,027,824

20 81.99 RFT 5"x2" PKD Chowket Work 2,656.45 RFT 217,802

21 84.00 SFT 1½" thk; Teak Panelled Door 4,515.51 SFT 379,303

22 429.00 SFT UPVC Window 3,500.00 SFT 1,501,500

23 15.00 SFT Providing 3mm thk; Glass Fanlight 6,233.62 SFT 93,504

24 7,649.12 SFT 3 Coats of Plastic Emulsion Paints 229.50 SFT 1,755,473

25 379.43 SFT Painting 3 Coats to Wood Work 245.46 SFT 93,134


26 187.00 RFT Gutter Work 2,072.50 RFT 387,558

27 67.00 RFT 3"Ø 13.5mm thk; PVC Drain Pipe 1,237.16 RFT 82,890

28 3,328.00 SFT Scaffolding Work 77.08 SFT 256,529

29 2.00 No 2000 Gal Water Tank (GI) 95,000.00 No 190,000

Total Material & Labour Cost 32,238,753


30 Apron & Drain 0.00

0 0.00 0 0 0.00

0 0.00 0 0 0.00

0 0.00 0 0 0.00

0 0.00 0 0 0.00

0 0.00 0 0 0.00

0 0.00 0 0 0.00
Name of Project -
Name of Work - 60'x30' 1 Storey R.C.C School (3 Units, 1 Storey)
Bill of Quantity

Ite Particular Quantity Unit Rate (Ks) Per Amount (Ks)


m

Materials
1 Cement 466.96 Bag 5,700 Bag 2,661,645.48
2 Sand 37.57 Sud 85,000 Sud 3,193,340.49
3 River Shingle 18.16 Sud 90,000 Sud 1,634,789.59
4 Brick 21970.38 No 100 No 2,197,038.12
5 Broken Brick 4.39 Sud 25,000 Sud 109,863.28
6 Concrete Screen Block 130.00 No 450 No 58,500.00
7 X-met 2238.38 RFT 70 RFT 156,686.53
8 Teak 0.24 Ton 2,200,000 Ton 518,907.48
9 Pyinkado 2.04 Ton 1,200,000 Ton 2,450,346.32
10 Jungle Wood 2.82 Ton 650,000 Ton 1,835,148.25
11 5 Plywood 32.35 Sheet 17,600 Sheet 569,366.51
12 Nail 33.33 Viss 2,340 Viss 77,987.04
13 Roofing Screw 1273.46 No 60 No 76,407.52
14 (5"x2") U MS 213.35 RFT 900 RFT 192,014.55
15 (4"x2") U MS 524.76 RFT 870 RFT 456,539.90
16 (3"x2") Lip Channel GI 1325.84 RFT 460 RFT 609,884.10
17 (2"x2") L MS 238.25 RFT 350 RFT 83,385.75
18 16mm ø MS Rod 3.85 Ton 580,000 Ton 2,232,034.49
19 12mm ø MS Rod 0.24 Ton 610,000 Ton 144,848.56
20 8mm ø MS Rod 0.75 Ton 610,000 Ton 456,307.76
21 6mm ø MS Rod 0.03 Ton 610,000 Ton 19,024.53
22 Binding Wire 27.03 Viss 1,620 Viss 43,785.23
23 4 angle Colour Roofing Sheet (0.4mm thk:) 218.10 RFT 1,080 RFT 235,546.44
24 .4mm thk; Colour Plain Ridge Colour 138.43 RFT 700 RFT 96,902.40
25 UPVC Window 429.00 SFT 3,500 SFT 1,501,500.00
26 3mm thk; Glass 22.50 SFT 1,000 SFT 22,500.00
27 Plastic Paint 76.35 Gal 5,500 Gal 419,922.48
28 Readymixed Paint 2.66 Gal 16,000 Gal 42,553.18
29 Putty 57.79 Gal 5,500 Gal 317,864.47
30 Roller 21.25 No 700 No 14,873.29
31 Sand Paper 453.28 No 200 No 90,656.23
32 Putty Trowel 21.25 No 800 No 16,998.04
33 2'x2' Cement Board 596.64 No 750 No 447,483.60
34 6" Tower Bolt 6.00 No 800 No 4,800.00
35 6" Sliding Bolt 3.00 No 800 No 2,400.00
36 5" Hinge 24.00 No 900 No 21,600.00
37 6" Handle 12.00 No 800 No 9,600.00
38 1.5" Wood Screw 182.33 Doz 250 Doz 45,583.71
39 Door Chockwet Bracket 18.00 No 1,200 No 21,600.00
40 5"x5" PVC Gutter 196.35 RFT 1,300 RFT 255,255.00
41 MS Gutter Bracket 93.50 No 1,020 No 95,370.00
42 ø 3" PVC Pipe (13.5) 67.00 RFT 650 RFT 43,550.00
43 Offsets & Bends 16.00 No 700 No 11,200.00
44 Drain Pipe Bracket 33.50 No 150 No 5,025.00
45 Bamboo 161.78 No 800 No 129,422.22
46 Coinyarn 11.77 Viss 2,500 Viss 29,423.87
47 2000 Gal Water Storage Tank (GI) 2.00 No 95,000 No 190,000.00

Total Material Cost 23,849,481.41


Labours
1 Masons 166.22 No 6,500 No 1,080,414.88
2 Carpenters 197.49 No 6,500 No 1,283,662.36
3 Painters 82.65 No 6,500 No 537,228.92
4 Steel Fixers 177.50 No 6,500 No 1,153,759.52
5 Plumbers 2.01 No 6,500 No 13,065.00
6 Workers 864.23 No 5,000 No 4,321,140.45

Total Labour Cost 8,389,271.13

Total Material & Labour 32,238,752.54


Name of Project -
Name of Work - 60'x30' 1 Storey R.C.C School (3 Units, 1 Storey)
Summary

No. Particular Amount (MMK)

Civil Work

1 Total Material Cost 23,849,481.41


2 Total Labour Cost 8,389,271.13

M & E Work

3 Internal Electrical Work 1,500,000.00

Total Cost (Material + Labour + M&E) 33,738,752.54

Grand Total 33,738,752.54

Say 33,730,000.00

Total Cost (Material + Labour + M&E) 33,738,752.54


7% Profit 2,361,712.68
3% Withholding Tax 1,012,162.58
Grand Total 37,112,627.79
Say 37,110,000.00

Вам также может понравиться