JONES NICHOLSON PTY LTD

CONSULTING ENGINEERS

Structural Design Brief

For

New Advertising Signage Structures


Eastern Creek and Dean Park

November 5, 2010
Our Ref: 20101074

SYDNEY ABN 51 003 316 032 WOLLONGONG - Tel: 02 4228 0570


PO Box 477, SUTHERLAND NSW 1499 PICTON - Tel: 02 4677 0441
Suite 45, 40-44 Belmont Street, Sutherland NSW 2232 SINGLETON - Tel: 0438 122 111
Tel: 02 9521 3088 Fax: 02 9521 3066 GOULBURN - Tel: 02 4822 8177
Email: mail@jonesnicholson.com.au www.jonesnicholson.com.au GOLD COAST - Tel: 07 5593 1844
Project: Billboard Structures Structural Design Brief
Ref: 20101074

TABLE OF CONTENTS

1.0 PROJECT OVERVIEW AND SCOPE OF WORKS ........................................................ 3


1.1 INTRODUCTION...................................................................................................... 3
1.2 PROJECT DESCRIPTION........................................................................................... 3
1.3 GENERAL SCOPE OF WORKS ................................................................................. 3
1.4 PROJECT DETAILS ................................................................................................. 4
2.0 STRUCTURAL DESIGN .............................................................................................. 4
2.1 DESIGN STANDARDS ............................................................................................. 4
2.2 DESIGN LIFE.......................................................................................................... 4
2.3 DURABILITY .......................................................................................................... 4
2.4 DESIGN LOADING .................................................................................................. 4
2.5 FATIGUE ................................................................................................................ 5
2.6 DESIGN FOR MAINTENANCE AND DISMANTLING ................................................... 5
3.0 DOCUMENTATION .................................................................................................... 6
3.1 STRUCTURAL DESIGN DRAWINGS .......................................................................... 6
3.2 STRUCTURAL QUALITY CONTROL .......................................................................... 6
3.3 AS BUILT DRAWINGS ............................................................................................ 6

Date: November 2010 Jones Nicholson


Issue: 2 2 of 6
Project: Billboard Structures Structural Design Brief
Ref: 20101074

1.0 PROJECT OVERVIEW AND SCOPE OF WORKS

1.1 INTRODUCTION

This specification outlines the scope of structural design for the new billboard structures and
defines the required standards for the project.

1.2 PROJECT DESCRIPTION

The project is the design and construction of two “Spectacular” Billboards to be constructed
adjacent to the M7 motorway. Details of the proposed billboards is are shown on the attached
drawings by OPUS.
Drawings Numbers SY T-12286.00 01
SY T-12286.00 02

1.3 GENERAL SCOPE OF WORKS

The works required for this project and as detailed on the drawings and specified within this
document comprise of the following.

Structural design and construction of


• Foundations for billboard structures based on the parameters in the geotechnical report
provided by the client,
• Monopole and support frames for billboard,
• Billboard surface sheeting to receive advertising – Maxi rib cladding with angle cover
trims,
• The structure is to be designed for tensioned vinyl signs which rely on a tensionable sail
track system.
• Access maintenance gantries at two levels including handrails.
o The bottom gantry is positioned level with the bottom of the sign and is required to
be offset 300mm clear from the back of the sign to allow had and tool access to the
bottom edge of the sign.
o The floor level of the upper gantry is to be positioned between handrail and chest
height below the top of the sign.
• The monopole is to be accessed by portable ladder. The design is to include ladder hooks
at a height to be determined by the contractor in accordance with his risk assessment.
Climbing pegs or an access ladder complete with ladsafe fall arrest cable is required from
the ladder hooks to the upper gantry level.
• A permanent ladder is required on the back face at each end of each sign (4 in total per
site). These ladders are to provide access to the edge of the sign between the lower and
upper gantries.
• A swinging davit and winch to get tools and materials up to the gantries. The winch is
required to have a minimum capacity of 100kg.
• Cantilevered arms to support lighting. Position of arms to be determined by lighting
designer to achieve appropriate lighting levels without casting shadows on the signage.
The outreach arms are to be hinged or similar to allow maintenance of lights from the
upper gantry.
• A 2m2 concrete pad is required at the base of the monopole to provide a firm platform for
supporting the portable ladder. The concrete pad is to be positioned so that ladders can
be hung from the ladder hooks and inclined at the correct grade in accordance with
relevant standards and workcover requirements.
• An all weather gravel access road for occasional use by maintenance crews. The road is
to be suitable for use by light commercial vehicles (vans, utilities and 4WD’s).
• Services trenches associated with the billboard.
• Co-ordination of the structural works with other aspects of the project including but not
limited to lighting, electrical conduits, landscaping etc.
• Production of design documentation for review by the project manager.
• Certification of the structural design and construction.

Date: November 2010 Jones Nicholson


Issue: 2 3 of 6
Project: Billboard Structures Structural Design Brief
Ref: 20101074

• Certification and test certificates where relevant for ladsafe cables and other height safety
systems.
• Production of as built drawings at the end of the project.

The contractor is to allow for attendance at the following design meetings


1. Pre-design meeting which will provide a forum to clarify design and operational matters.
This meeting will be attended by the Principal, the Principal’s Authorised Person and the
Licensee for the structures.
2. 50% design review meeting.
3. 1 other design meeting as required.

The contractor should allow for attendance by both structural and electrical design representatives.

1.4 PROJECT DETAILS

The project details are as follows:

Client Western Sydney Parklands Trust


Project Manager Complete Urban Solutions
Site 1 M7 Motorway, near Symonds Rd, Dean Park
Site 2 M7 Motorway, near Church St., Eastern Creek

The contractor shall, prior to submitting the tender for the project, complete a site visit of the site
to fully understand the scope of works and all conditions and restrictions of the site and the
installation.

2.0 STRUCTURAL DESIGN

2.1 DESIGN STANDARDS

The structural design shall be completed in accordance with the current version of the following
relevant Standards

• The Building Code of Australia,


• AS/NZS 1170 parts 0 to 4 – Structural Design Actions
• AS 4100 Steel Structures
• AS 3600 Concrete Structures
• AS/NZS 1554.1 Welding of steel structures
• AS/NZS 2312 Guide to the protection of structural steel.

Design of all ladders, handrails, gantries, fall arrest systems and height access provisions are to
comply with relevant Australian standards and Workcover requirements.

2.2 DESIGN LIFE

The design life of the structure to be 50 years.

2.3 DURABILITY

The structural steel is to be protected from the environment using a paint system designed to
achieve a maintenance free period of at least 15 years. The structural details are to be developed to
avoid ponding or water traps which could lead to increased corrosion risk -refer to AS/NZS 2312.

Where dissimilar metals are used the designer is to ensure that there is no increased corrosion risk.
If necessary, the method of isolating the metals is to be detailed on the structural drawings.

2.4 DESIGN LOADING

Date: November 2010 Jones Nicholson


Issue: 2 4 of 6
Project: Billboard Structures Structural Design Brief
Ref: 20101074

The structure is to be designed for the following loading:


• Imposed Loading in accordance with AS/NZS 1170.1
• Wind loading in accordance with AS/NZS 1170.2. The designer is to visit site to assess
the terrain category, topographic multiplier and all other relevant conditions so that the
appropriate wind loading can be calculated.
• Earthquake loading in accordance with AS/NZS 1170.4

2.5 FATIGUE

The design of the steel structure and in particular the welds shall take into account the anticipated
loading cycles and comply with Section 11 of AS4100. The minimum load cycles for fatigue
design shall be taken as:
• Site wind speed for fatigue loading = 16m/s
• No. Of cycles = 100,000 cycles per year.

2.6 DESIGN FOR MAINTENANCE AND DISMANTLING

The design of the structure shall allow for:


• maintenance and painting of all surfaces,
• access to all parts of the structure to allow for inspection and maintenance,
• dismantling of the structure

Date: November 2010 Jones Nicholson


Issue: 2 5 of 6
Project: Billboard Structures Structural Design Brief
Ref: 20101074

3.0 DOCUMENTATION

3.1 STRUCTURAL DESIGN DRAWINGS

The contractor shall provide design drawings for review by the project manager prior to
fabrication of any structural members. The drawings must detail:

• Design loadings – Imposed load, wind load, earthquake load etc.,


• Allowable bearing pressure used for foundation design,
• All other design assumptions and criteria,
• Size and layout of all structural members,
• Reinforcement details for foundations,
• Structural connections including bolt and weld sizes.
• Details of the proposed paint system.

3.2 STRUCTURAL QUALITY CONTROL

The contractors engineer is to carry out regular workshop and site inspections to confirm that
the construction complies with the design drawings. As a minimum the contractors engineer is
to inspect and provide certification for the following:

• Inspection of the excavation for the foundations


• Inspection of the foundation reinforcement cage and hold down bolts prior to pouring
concrete.
• Inspection of the steel framing at the workshop prior to delivery to site. Inspection to
include confirmation of weld size and quality.
• Final inspection of erected framework on site prior to handover.
• Certification of the design and the completed structure.

3.3 AS BUILT DRAWINGS

As built drawings shall be completed at the end of the project and shall specifically include
the following as a minimum:

• Be submitted in both AutoCAD and PDF versions,


• Be of the same size as the design documents,
• Have the contractors details, client name, project name and address on the title block,
• All components of the installation that have changed during the installation shall be
modified on the drawings. This shall include all additions, relocations, deletions and
substitutes,

Date: November 2010 Jones Nicholson


Issue: 2 6 of 6