ROBINSONS LAND CORPORATION

Corporate Engineering

Project : PROPOSED REPLACEMENT OF CORRODED CAST IRON WASTE PIPELINES AT RDS


Location : RDS Level 2 , Robinsons Galleria
Project Duration : 30 Working Days

Materials Specification and Bid Breakdown

ITEM DESCRIPTION
QTY UNIT UNIT COST TOTAL COST
I. Materials
A. RDS L2 ( Replacement of Main WP- Kids section)
1 200mmØx3m - Pipe, PVC - Atlanta, Emerald or Approved Equal 20 lengths
2 150mmØx3m - Pipe, PVC - Atlanta, Emerald or Approved Equal 6 lengths
3 200X200mmØ - Wye, PVC 5 pcs
4 200x150mmØ - Wye Reducer, PVC 4 pcs
5 200x100mmØ - Wye Reducer, PVC 22 pcs
6 150x100mmØ - Wye Reducer, PVC 8 pcs
7 200mmØ - Elbow (45°), PVC 7 pcs
8 150mmØ - Elbow (45°), PVC 4 pcs
9 100mmØ - Elbow (45°), PVC 20 pcs
10 200mmØ- Clean Out set, PVC 3 pcs
11 150mmØ- Clean Out set, PVC 2 pcs
12 100x50mmØ - Coupling Reducer 10 pcs
13 200mmØ - No Hub Coupling Assembly w/ Neoprene 8 pcs
14 150mmØ - No Hub Coupling Assembly w/ Neoprene 2 pcs
15 100mmØ - No Hub Coupling Assembly w/ Neoprene 20 pcs
16 50mmØ - No Hub Coupling Assembly w/ Neoprene 10 pcs
17 Plain Round bar 12mmØx20' 9 lengths
18 Flat bar 1"x⅛"x20' 13 lengths
19 Expansion bolt 35 pcs
20 Hexagonal nuts with washer 70 pcs
21 Primer 2 gals
22 Quick Dry Enamel Paint 3 gals
B. RDS L2 ( Replacement of Main WP - Ladies Wear)
1 200mmØx3m - Pipe, PVC - Atlanta, Emerald or Approved Equal 26 lengths
2 150mmØx3m - Pipe, PVC - Atlanta, Emerald or Approved Equal 5 lengths
3 200X200mmØ - Wye, PVC 7 pcs
4 200x150mmØ - Wye Reducer, PVC 4 pcs
5 200x100mmØ - Wye Reducer, PVC 14 pcs
6 150x100mmØ - Wye Reducer, PVC 12 pcs
7 200mmØ - Elbow (45°), PVC 9 pcs
8 150mmØ - Elbow (45°), PVC 8 pcs
9 100mmØ - Elbow (45°), PVC 20 pcs
10 200mmØ- Clean Out set, PVC 4 pcs
11 150mmØ- Clean Out set, PVC 2 pcs
12 100x50mmØ - Coupling Reducer 10 pcs
13 200mmØ - No Hub Coupling Assembly w/ Neoprene 12 pcs
14 150mmØ - No Hub Coupling Assembly w/ Neoprene 3 pcs
15 100mmØ - No Hub Coupling Assembly w/ Neoprene 20 pcs
16 50mmØ - No Hub Coupling Assembly w/ Neoprene 10 pcs
17 Plain Round bar 12mmØx20' 11 lengths
18 Flat bar 1"x⅛"x20' 11 lengths
19 Expansion bolt 40 pcs
20 Hexagonal nuts with washer 80 pcs
21 Primer 2 gals
22 Quick Dry Enamel Paint 4 gals
C. Consumables (epoxy, solvent cement, etc.) 1 lot
TOTAL
II. Labor
1 1 - Leadman 30 days
2 2 - Plumber 30 days
3 2 - Painter 7 days
4 5 - Helper 30 days
TOTAL
III OTHER COST (VAT INCL)
a. Miscellaneous
1 Temporary facilities, tools, equipment and scaffolding 1 lot
2 Testing and commissioning 1 lot
3 Restoration works 1 lot
TOTAL MISCELLANEOUS
b. OVERHEAD/ MARK - UP/ PROFIT 1 lot
c. MOBILIZATION and DEMOBILIZATION 1 lot
d. PERMITS/BONDS/CARI 1 lot
e. SECURITY CHARGES (MALL PARTNER) 1 lot

TOTAL PROJECT COST


Amount in words:

FINAL NEGOTIATED PRICE (VAT incl)

Delivery/Completion 30 Working Days


Warranty 1 Year
Payment Terms
Price Validity
Security Charges (Mall) ₱20,400.00
Remarks
Contractor Name:

Contractor's Representative:

Designation:

Signature:

Date Submitted: