DOCUMENTATION REVIEW AND PENDING STATUS FOR PACKAG

UNIT 2981
PU 01 DOCUMENT REVIEW STATUS

VESSELS LP VESSELS: DOCUMENTATION COMPLETED


SKID BASE FRAMES & STRUCTURES: ONLY BALANCE IS ONLY MTR'S
STRUCTURES (MATERIAL SUMMARY LIST)

1) CORRECTION COPIES OF LINE INSPECTION SUMMARY LISTS TO BE


REVEIWED & SIGNED FOR CS & SS

PIPING

2) REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS

CORRECTED COPIES OF PAINTING REPORTS SHALL SUBMIT FOR REVIEW


PAINTING & SIGNING

PU 02 DOCUMENT REVIEW STATUS

VESSELS LP VESSELS: DOCUMENTATION COMPLETED


SKID BASE FRAMES & STRUCTURES: ONLY BALANCE IS ONLY MTR'S
STRUCTURES (MATERIAL SUMMARY LIST)
1) CORRECTION COPIES OF LINE INSPECTION SUMMARY LISTS TO BE
REVEIWED & SIGNED FOR CS & SS
PIPING

2) REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS


CORRECTED COPIES OF PAINTING REPORTS SHALL SUBMIT FOR REVIEW
PAINTING & SIGNING

PU 03 DOCUMENT REVIEW STATUS


VESSELS LP VESSELS: DOCUMENTATION COMPLETED
SKID BASE FRAMES & STRUCTURES: ONLY BALANCE IS ONLY MTR'S
STRUCTURES (MATERIAL SUMMARY LIST)
1) CORRECTION COPIES OF LINE INSPECTION SUMMARY LISTS TO BE
REVEIWED & SIGNED FOR CS & SS
PIPING
PIPING

2) REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS


CORRECTED COPIES OF PAINTING REPORTS SHALL SUBMIT FOR REVIEW
PAINTING & SIGNING

PU 03 DOCUMENT REVIEW STATUS


VESSELS LP VESSELS: DOCUMENTATION COMPLETED
SKID BASE FRAMES & STRUCTURES: ONLY BALANCE IS ONLY MTR'S
STRUCTURES (MATERIAL SUMMARY LIST)
1) CORRECTION COPIES OF LINE INSPECTION SUMMARY LISTS TO BE
REVEIWED & SIGNED FOR CS & SS
PIPING

2) REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS


CORRECTED COPIES OF PAINTING REPORTS SHALL SUBMIT FOR REVIEW
PAINTING & SIGNING
D PENDING STATUS FOR PACKAGES

REMARKS

01 FULL DAY REQUIRED TO COMPLETE

02 FULL DAY REQUIRED TO COMPLETE

ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC, DESCON INFOMRED
NOT REVIEW CLIENT ISSUE MATERIALS. SO TCM REVIEW NOT DONE ON
MTC'S. NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)

1/2 DAY REQUIRED TO COMPLETE

REMARKS

01 FULL DAY REQUIRED TO COMPLETE

02 FULL DAY REQUIRED TO COMPLETE

ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC, DESCON INFOMRED
NOT REVIEW CLIENT ISSUE MATERIALS. SO TCM REVIEW NOT DONE ON
MTC'S. NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)

1/2 DAY REQUIRED TO COMPLETE

REMARKS

1/2 DAY REQUIRED TO COMPLETE


ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC, DESCON INFOMRED
NOT REVIEW CLIENT ISSUE MATERIALS. SO TCM REVIEW NOT DONE ON
MTC'S. NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)

REMARKS

1/2 DAY REQUIRED TO COMPLETE

ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC, DESCON INFOMRED
NOT REVIEW CLIENT ISSUE MATERIALS. SO TCM REVIEW NOT DONE ON
MTC'S. NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)
DOCUMENTATION REVIEW AND PENDING STATUS FOR PACKAGES

UNIT 2802

PU 11 DOCUMENT REVIEW STATUS

VESSELS LP VESSELS: DOCUMENTATION COMPLETED

SKID BASE FRAMES & STRUCTURES: ONLY BALANCE IS ONLY MTR'S (MATERIAL
STRUCTURES SUMMARY LIST)

1) FULL SET OF LINE INSPECTION SUMMARY LISTS TO BE REVEIWED & SIGNED


FOR CS & SS
PIPING

2) REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS

CORRECTED COPIES OF PAINTING REPORTS SHALL SUBMIT FOR REVIEW &


PAINTING SIGNING

PU 12 DOCUMENT REVIEW STATUS

VESSELS LP VESSELS: DOCUMENTATION COMPLETED

STRUCTURES SKID BASE FRAMES & STRUCTURES DOCUMENTATION COMPLETED

PIPING

REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS


PAINTING DOCUMENTATION COMPLETED

PU 13 DOCUMENT REVIEW STATUS

VESSELS LP VESSELS: DOCUMENTATION COMPLETED


STRUCTURES SKID BASE FRAMES & STRUCTURES DOCUMENTATION COMPLETED

PIPING

REVIEW OF MILL TEST CERTIFICATES FOR PIPING & FITTINGS


PAINTING DOCUMENTATION COMPLETED
ATUS FOR PACKAGES

REMARKS

01 FULL DAY REQUIRED TO COMPLETE

06 FULL DAY REQUIRED TO COMPLETE (FOR FIRST


REVIEW OF DOCUMENTS)

ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC,


DESCON INFOMRED NOT REVIEW CLIENT ISSUE
MATERIALS. SO TCM REVIEW NOT DONE ON MTC'S.
NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)

1 FULL DAY REQUIRED TO COMPLETE

REMARKS

ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC,


DESCON INFOMRED NOT REVIEW CLIENT ISSUE
MATERIALS. SO TCM REVIEW NOT DONE ON MTC'S.
NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)

REMARKS
ALL PIPING MATERIALS ARE FREE ISSUE FROM SIIRTEC,
DESCON INFOMRED NOT REVIEW CLIENT ISSUE
MATERIALS. SO TCM REVIEW NOT DONE ON MTC'S.
NEARLY ~ 800 MILL TEST CERTIFCATES (~2357 PAGES)