Вы находитесь на странице: 1из 9

G.R. No.

152303 During the pendency of these cases, on September 1, 1980, MCI


ceded to the Development Bank of the Philippines (DBP) some of
UNIVERSITY PHYSICIANS SERVICES, INCORPORATED,
the leased buildings, including certain facilities, furniture, fixtures
Petitioner, v. MARIAN CLINICS, INC. and DR. LOURDES MABANTA, and equipment found therein, in full settlement of MCIs debt to
Respondents. DBP. The Deed of Cession of Properties in Payment of Debt (Dacion
en Pago) contained an annex (Annex A) which listed the properties
What happens when personal properties inside leased premises ceded to DBP.[8] Upon the execution of the dacion en pago, UPSI
are stipulated as included in the contract of lease? Does a paid P60,000 of the monthly rental to DBP as the new owner of the
judgment on a suit for unlawful detainer ejecting the lessees from properties subject of the dacion en pago.
the subject property carry with it the return of these personal
properties as well? Finally, the trickier part which is the crux of this On April 21, 1983, the RTC of Manila affirmed the City Court
petition: what if some of these personal properties are lost, Decision dismissing MCIs unlawful detainer case. This case was
destroyed or sold by the lessor? May the ejected lessees still be appealed to the Intermediate Appellate Court[9] (IAC), where it was
ordered to pay for their value? docketed as CA-G.R. SP No. 00994.

This is a Petition for Review under Rule 45[1] of the Rules of Court On February 24, 1984, while the RTC Decision in the unlawful
assailing the October 18, 2001 Decision[2] of the Court of Appeals detainer case was under review with the IAC, UPSI bought from
in CA-G.R. CV No. 34971, which in turn affirmed the Order[3] in DBP the leased properties ceded to the latter by MCI under
Execution dated November 5, 1990 of the Regional Trial Court the dacion en pago.[10]
(RTC) of Manila.
On February 28, 1985, the IAC rendered its Decision[11] reversing
The factual and procedural antecedents of this case are as follows: the rulings of the lower courts. According to the IAC, the absence
of the certificates of occupancy for two of the leased buildings,
On May 31, 1973, Marian Clinics, Inc. (MCI) and University being a matter between the owner of the building and the city
Physicians Services, Incorporated (UPSI) entered into a Lease government, did not impair the peaceful and adequate enjoyment
Agreement whereby the former leased to the latter the Marian by UPSI of the premises.[12] The IAC further held that the alleged
General Hospital (MGH) and four schools for a period of ten (10) defective electrical installations on the premises leased is no
years, from June 1, 1973 to May 31, 1983. The land, buildings, justification for the refusal to pay rentals, as, under Article 1663 of
facilities, fixtures and equipment appurtenant thereto, including the Civil Code, the lessee may have said installations properly
the Soledad Building, were included in the lease, for which a reinstalled at the expense of the lessor.[13] The dispositive portion
monthly rental of P70,000 was agreed upon. of the IAC Decision reads:
On October 7, 1975, UPSI filed a complaint for specific Upon all the foregoing considerations, the decision of respondent
performance against MCI, alleging that (1) MCI failed to deliver court, under review, is hereby REVERSED. [UPSI] is hereby ordered
Certificates of Occupancy on certain buildings, and (2) there were to pay to [MCI and Dr. Mabanta] the agreed rental of
some defective electrical installations that caused the issuance of a PhP70,000.00 a month from November 1975 to May 31, 1983,
Condemned Installation Notice by the Office of the City Electrician deducting therefrom the amount already withdrawn by [MCI and
of the City of Manila. UPSI prayed for the delivery of the Dr. Mabanta] from the rentals deposited with respondent court in
Certificates of Occupancy of the buildings leased, for the Civil Case No. 99934; crediting to [UPSI] the amount of
correction of the defects in the electrical installations thereon, and PhP60,000.00 monthly from September 24, 1980 to May 31, 1983,
damages. The complaint was docketed as Civil Case No. 99934 in said amount having been paid the DBP for the properties ceded by
the Court of First Instance[4] (CFI) of Manila, Branch 34. [MCI and Dr. Mabanta] in the dacion en pago; and to pay interests
on the amounts still due, at the legal rate, from the time that said
On October 30, 1975, UPSI sent a letter to MCI, informing it of the
amounts became due until they are fully paid.
filing of the complaint and the suspension of payment of the
monthly rentals until the resolution of the case. On November 7, [UPSIs] motion for reconsideration of the resolution of the Court
1975, MCI sent a demand letter to UPSI for the payment of the dated October 1, 1984 is hereby GRANTED and the issue of
rent.[5] compensation for the continued occupancy of the remaining
leased premises as well as the renewal of the lease and the return
On December 18, 1975, MCI and Dr. Lourdes F. Mabanta (Dr.
of the hospital equipment, fixtures, and supplies prayed for, are
Mabanta) filed a Complaint for Unlawful Detainer against UPSI
hereby left to the decision in Civil Case No. 83-21275 in the
with the then City Court of Manila (now the Metropolitan Trial
Regional Trial Court in Manila. Costs against [UPSI].[14]
Court of Manila [MeTC]). The Complaint[6] was docketed as Civil
Case No. 006665-CV. Both MCI and UPSI filed Motions for Reconsideration of the above
Decision. MCI assailed the IACs failure to include in its order the
In the meantime, UPSI filed with the CFI a Motion availing of its
ejectment of UPSI from the premises and the return of the
right to suspend payment of rentals under Article 1658[7] of the
same. UPSI, however, insists that there was no violation of the
Civil Code. In an Order dated January 29, 1976, the CFI ordered
lease agreement, raising the same arguments it presented before
that all payments shall be made to said court pending the
the February 28, 1985 Decision.
resolution of the case.
On July 18, 1985, the IAC issued a Resolution[15] granting MCIs
On August 10, 1980, the City Court rendered its Decision in Civil
Motion for Reconsideration and denying that of UPSI. Noting the
Case No. 006665-CV, dismissing the unlawful detainer case on the
finding that UPSI violated the lease agreement by failing to pay the
finding that (1) UPSIs suspension of rental payments was justified;
stipulated rentals, the IAC ruled that MCI may now require UPSI to
and (2) there was no ground to cause the rescission of the lease
vacate the leased premises. As regards UPSIs Motion, the IAC held
and warrant the ejectment of UPSI. MCI and Dr. Mabanta appealed
that the issues concerning the alleged defective electrical
to the RTC of Manila, where the case was raffled to Branch 35 and
installations and failure to deliver certificates of occupancy had
was docketed as Civil Case No. 135396.
already been sufficiently passed upon. The IAC thus amended the
dispositive portion of the February 28, 1985 Decision to read as
follows:
C. WHETHER OR NOT THE ORDER IN EXECUTION DATED
NOVEMBER 5, 1990 OF THE REGIONAL TRIAL COURT CHANGED
Upon all the foregoing considerations, the decision of respondent
THE ORIGINAL CAUSE OF ACTION OF PRIVATE RESPONDENT FROM
court, under review, is hereby REVERSED. [UPSI] is hereby ordered
UNLAWFUL DETAINER TO RECOVERY OF PERSONAL PROPERTIES
to pay to the [MCI and Dr. Mabanta] the agreed rentals
AND/OR REPLEVIN THUS VIOLATING PETITIONERS RIGHT TO DUE
of P70,000.00 a month from November 1975 to May 31, 1983,
PROCESS;
deducting therefrom the amount already withdrawn by [MCI and
Dr. Mabanta] from the rentals deposited with respondent court in D. WHETHER OR NOT ARTICLE 1667 OF THE NEW CIVIL CODE IS
Civil Case No. 99934; crediting to [UPSI] the amount of P60,000.00 SQUARELY APPLICABLE TO THE CASE AT BENCH; AND
monthly from September 24, 1980 to May 31, 1983, said amount
E. WHETHER OR NOT THE OBLIGATION OF THE PETITIONER UNDER
having been paid the DBP for the properties ceded by [MCI and Dr.
THE ORDER IN EXECUTION DATED NOVEMBER 5, 1990 FOR THE
Mabanta] in the dacion en pago; and to pay interests on the
REPLACEMENT/RETURN AND/OR PAYMENT OF SUBJECT FIXTURES
amounts still due, at the legal rate, from the time that said
HAS BEEN RENDERED MOOT AND ACADEMIC FOR IT WAS
amounts became due until they are fully paid, and [UPSI] or
EXTINGUISHED FIRST BY DACION EN PAGO DATED SEPTEMBER 1,
anyone occupying the premises under it, is hereby ordered to
1980 EXECUTED BY PRIVATE RESPONDENT WITH THE DBP AND
vacate the leased properties including the fixtures, supplies and
SECOND BY THE DEED OF CONDITIONAL SALE EXECUTED BY THE
equipment, listed in Exhibit A (other than the property ceded to
DBP IN FAVOR OF PETITIONER UPSI AND THIRD BY WAY OF
the Development Bank of the Philippines in the dacion en pago),
PAYMENT IN FULL SATISFACTION OF THE JUDGMENT CREDIT IN
more particularly, what is now occupied by Juanchitos Restaurant
CIVIL CASE NO. 52978.[18]
and the passageway of the premises still owned by [MCI and Dr.
Mabanta]. UPSI explains that the judgment sought to be executed enjoined it
to do only the following:
[UPSIs] motion for reconsideration of the resolution of this court
dated October 1, 1984 is hereby granted, and said resolution is 1. to pay the back rentals with interest less the rentals
hereby set aside.[16] consigned in court and the subject of the dacion en pago; and
The aforementioned Resolution was appealed to this Court, where 2. to vacate the Juanchitos Restaurant and passageway as
the petition was docketed as G.R. No. 71579. This Court dismissed well as the fixtures appurtenant to the subject leased premises,
the same. Thus, the IAC judgment attained finality. excluding those ceded in the dacion en pago.
During execution, the RTC of Manila, Branch 33, acting on MCIs UPSI points out that the Order in Execution dated November 5,
Motion for the Delivery of Leased Facilities/Equipment/Supplies 1990 of the RTC affirmed by the Court of Appeals varied the
and/or the Payment of their Value if Defendant cannot Deliver judgment sought to be executed as it instead mandated the
Them, issued an Order dated November 5, 1990, the dispositive following:
portion of which reads:

Accordingly, Defendant University Physician Services, Inc. is hereby


directed to replace the equipment, facilities, supplies, etc. as 1. to replace and/or pay the value of the equipment,
reflected in the inventories. Annexes A to A-8 and B to B-8. If the facilities, supplies, etc., as reflected in Annexes A to A-8 and B to B-
same could not be substituted or replaced within the period of 8; and
thirty days from receipt of this order, said defendant has to pay
2. to return and deliver and/or pay the value of the leased
the value in the amount of P450,932.50 and P387,212.05 indicated
facilities, equipment, supplies, etc., listed in the Summary of
in the aforesaid annexes. Defendant is likewise directed to return
Inventory with Annex A.
and deliver the leased facilities, equipments, supplies, etc., listed in
the Summary of Inventory with Annex A or pay the plaintiff their The Court of Appeals ruled that the judgment sought to be
value in the amount of P5,534,818.50 within the period of two executed reveals the intent of the court to have all of the leased
months from receipt of this order.[17] properties returned upon the execution of the judgment. Indeed,
the original Writ of Execution issued on April 10, 1987 included
On November 29, 1990, UPSI appealed the above Order to the
these personal properties. As some of the leased properties were
Court of Appeals, claiming that said Order varies the term of the
not returned, causing only a partial execution of the judgment, the
IAC judgment, arguing that said judgment did not order the
November 5, 1990 Order was necessitated. Said Order, according
replacement of the leased properties lost or deteriorated and/or
to the appellate court, did not vary the terms of the judgment but
to pay their value if replacement cannot be made. UPSI further
merely implemented the IACs Decision. The Court of Appeals
claims that the Court erred in giving MCI the discretion to
added that a contrary ruling would result in unjust enrichment on
determine the circumstances when replacement or payment of
the part of UPSI.[19]
value shall be made. The appeal was docketed as CA-G.R. CV No.
34971. UPSI counters that the remedy of MCI is to file an action for
recovery of personal properties or collection of the value thereof,
On October 18, 2001, the Court of Appeals rendered the assailed
as these actions have totally different and distinct cause of actions
Decision affirming the November 5, 1990 RTC Order. Thus, this
from that of ejectment.[20] UPSI points out that the only issue to be
Petition, in which UPSI submits the following issues for the
resolved in an unlawful detainer case is possession de facto, i.e.,
resolution of this Court:
who between the party litigants has a better right of possession,
A. WHETHER OR NOT THE ORDER IN EXECUTION DATED and therefore an order to replace or pay the value of a leased
NOVEMBER 5, 1990 OF THE REGIONAL TRIAL COURT, BR. 33, NCJR, property has no place in such action. UPSI argues that it was
MANILA IS NULL AND VOID FOR IT TOTALLY CHANGED THE FINAL precisely because the cause of action of MCI was ejectment that
JUDGMENT SOUGHT TO BE EXECUTED; the IAC merely directed UPSI to vacate the leased premises and
not to replace or pay the value of the appurtenances of the leased
B. WHETHER OR NOT THE REGIONAL TRIAL COURT, BR. 33, NCJR, properties if allegedly lost or destroyed.
MANILA, HAS JURISDICTION IN ISSUING THE ORDER IN EXECUTION
DATED NOVEMBER 5, 1990;
It is settled that a writ of execution must conform substantially to
every essential particular of the judgment promulgated. Execution
(d) Shall keep the LEASED ASSETS in good and decent condition
not in harmony with the judgment is bereft of validity. It must
and maintain the same at its own expense. Maintenance shall
conform, more particularly, to that ordained or decreed in the
include, but shall not be limited to, keeping all equipment in good
dispositive portion of the decision.[21]
running condition, x x x and painting and repairing the buildings as
Did the writ of execution conform substantially to the essentials of may be necessary to keep them in decent and usable condition. x x
the promulgated judgment? x.

The Court rules in the affirmative. xxxx

To begin with, it cannot be disputed that the subject matter of the (h) Shall surrender quickly and peacefully unto the LESSORS all the
lease agreement between the parties included real and personal LEASED ASSETS, x x x upon termination of this Agreement.
properties. The pertinent portion of the lease contract provides:
xxx
WHEREAS, MARIAN is the owner and operator of that enterprise,
8. In addition, the LESSEE agrees that:
consisting of a hospital and 4 schools (nursing, medical X-ray
technology, midwifery and medical secretarial science) operating (e) All pillows, linen, sheets, mattresses, rubber sheets, x x x and
at 918 United Nations Avenue, Manila, under the names and style such other similar breakable, losable or deteriorating items as may
of MARIAN GENERAL HOSPITAL, MARIAN SCHOOL OF NURSING, be included in Annex A hereto attached, shall upon termination of
MARIAN SCHOOL OF MIDWIFERY, and MARIAN SCHOOL OF this Agreement, be replaced by the LESSEE in the same quantity as
MEDICAL SECRETARIAL SCIENCE (the last 4 being known turned over herewith by the LESSORS. All medical equipment also,
collectively as MARIAN SCHOOLS), together with the land, if deteriorated upon termination hereof, shall be replaced in the
buildings, facilities, furnitures (sic), fixtures and equipment same quantity and quality in which they were received by the
appurtenant thereto, a inventory of which is hereto attached as LESSEE, ordinary wear and tear excepted.[23] (Emphasis supplied.)
Annex A;
Under the principle of the parties freedom of contract, the
WHEREAS, MARIAN is the owner of that lot located at 918 United contracting parties may establish such stipulations, clauses, terms
Nations Avenue, Manila, covered by and described in Transfer and conditions as they may deem convenient, provided they are
Certificate of Title No. 105778 of the Register of Deeds of Manila, not contrary to law, morals, good customs, public order, or public
together with that building existing thereon known as the policy.[24] Obligations arising from contracts have the force of law
SOLEDAD BUILDING, and other constructions and improvements between the parties.[25] The provisions in the lease contract that:
thereon, which are also used by the hospital and schools, a list of
which is hereto attached as Annex B; (1) All pillows, linen, sheets, mattresses, rubber sheets, x x x and
such other similar breakable, losable or deteriorating items x x x
xxxx shall upon termination of this Agreement, be replaced by the
LESSEE in the same quantity as turned over herewith by the
NOW, THEREFORE, for and in consideration of the above premises
LESSORS; and
and the terms and conditions hereinafter enumerated, the
LESSORS agree to deliver unto the LESSEE, by way of lease, with (2) All medical equipment also, if deteriorated upon termination
right to possess, use, run and operate, that certain hospital and hereof, shall be replaced in the same quantity and quality in which
schools above-described, together with the lands, buildings, they were received by the LESSEE. x x x.[26]
facilities, furnitures (sic), fixtures and equipment listed in Annexes
A and B hereto attached (all of which hospital, schools and assets clearly show the parties binding covenant that, upon the
as enumerated are collectively referred to herein as the LEASED termination of the lease, certain types of movable properties
ASSETS x x x.[22] (Emphasis supplied.) subject of the lease will not simply be returned but replaced in the
same quantity and/or quality in case of loss or deterioration.
As discussed in the Decision of the Court of Appeals, the basis for
the obligation of UPSI to return, and in certain circumstance, The IACs final and executory July 18, 1985 Resolution, ordering
replace or pay the value of the above-mentioned appurtenances in UPSI to vacate the leased properties, including the fixtures,
the leased properties is both law and contract. supplies and equipment was in effect a judicial termination of the
lease. Upon the termination of the contract, UPSIs duty to return
Article 1665 of the Civil Code provides that [t]he lessee shall return and/or replace the leased properties arose. The return and/or
the thing leased, upon the termination of the lease, just as he replacement of the leased properties being a necessary
received it, save what has been lost or impaired by the lapse of consequence of the termination of the lease, the November 5,
time, or by ordinary wear and tear, or from an inevitable 1990 Order of the execution court did not vary the IAC judgment
cause. Article 1667 likewise states that [t]he lessee is responsible which ordered the restitution of the leased assets.
for the deterioration or loss of the thing leased, unless he proves
that it took place without his fault. In other words, by law, a lessee UPSI further argues that Article 1667 of the Civil Code is not
is obliged to return the thing(s) leased and be responsible for any applicable considering that the inventories of the leased properties
deterioration or loss of the properties, except for those that were which it was obligated to return was not yet established. UPSI also
not his fault. asserts that the order for the replacement of the subject fixtures
had been rendered moot as it had already been extinguished by
However, it is significant to note that the parties saw fit to go a the dacion en pago dated September 1, 1980 with the DBP, by the
step further and stipulate the following: deed of conditional sale executed by the DBP in favor of UPSI, and
by UPSIs payment in full of the judgment in Civil Case No. 529778,
4. During the term of this contract, the operation of the hospital
a complaint for compensation and damages filed by MCI against
and schools shall be deemed exclusively the enterprise and
UPSI.
business of the LESSEE, and, therefore, the LESSEE:

xxxx
As regards Article 1667 of the Civil Code, we hold that the [G.R. No. 147465. January 30, 2002]
applicability thereof, or of the provision of the lease contract
METROPOLITAN MANILA DEVELOPMENT AUTHORITY, petitioner,
holding UPSI liable in case of loss or deterioration of the subject
vs. JANCOM ENVIRONMENTAL CORPORATION and JANCOM
properties, are not dependent on the presence, at the moment, of
INTERNATIONAL DEVELOPMENT PROJECTS PTY. LIMITED OF
inventories. The execution court may conduct hearings to
AUSTRALIA, respondents.
determine the existence of such an inventory and, if found that
such is unavailable, further hearings may be conducted to DECISION
reconstruct the same and determine the value of the properties
that should be returned or replaced, if necessary. MELO, J.:

On UPSIs argument that the order for the replacement of the Before the Court is a petition for review on certiorari under Rule 45
subject properties had been rendered moot by dacion en pago, by of the Rules of Civil Procedure filed by petitioner Metropolitan
a deed of conditional sale, and by payment in full satisfaction of Manila Development Authority (MMDA), seeking to reverse and
the judgment credit in Civil Case No. 529778, we rule that the set aside the November 13, 2000 decision of the Court of Appeals
same may also be and are best threshed out in hearings to be declaring valid and perfected the waste management contract
conducted by the execution court. Indeed, there is a need for the entered into by the Republic of the Philippines, represented by the
execution court to (1) identify the mass of properties actually Secretary of National Resources and the Executive Committee to
leased to UPSI; (2) identify and exclude the properties transferred oversee the build-operate-transfer implementation of solid waste
to DBP under the dacion en pago and to UPSI under the management projects, and JANCOM Environmental Corporation.
conditional deed of sale; and (3) identify and exclude properties
The pertinent facts are as follows:
which UPSI already returned, replaced or paid the value of in Civil
Case No. 529778. UPSI can be made responsible for only the In 1994, then President Fidel V. Ramos issued Presidential
remaining leased assets which have not been previously returned Memorandum Order No. 202 creating the Executive Committee
or replaced, if there are any. As these matters are factual in nature (EXECOM) to oversee the BOT implementation of solid waste
and it is elementary that this Court is not a trier of facts, remand of management projects, headed by the Chairman of the MMDA and
the case to the execution court would be in order. the Cabinet Officer for Regional Development-National Capital
Region (CORD-NCR). The EXECOM was to oversee and develop
WHEREFORE, the Decision of the Court of Appeals in CA-G.R. CV
waste-to-energy projects for the waste disposal sites in San Mateo,
No. 34971 dated October 18, 2001, which affirmed the Order in
Rizal and Carmona, Cavite under the build-operate-transfer (BOT)
Execution dated November 5, 1990 of the Regional Trial Court of
scheme. The terms of reference for the waste-to-energy projects
Manila, is AFFIRMED with the MODIFICATION that the case
provided that its proponents should have the capability to
be REMANDED to the Regional Trial Court of Manila, Branch 33, for
establish municipal solid waste thermal plants using incineration
further proceedings on the execution of the judgment in Civil Case
technology. This type of technology was selected because of its
No. 135396. Costs against petitioner University Physicians Services,
alleged advantages of greatly reduced waste volume, prolongation
Incorporated.
of the service life of the disposal site, and generation of electricity.
SO ORDERED.
While eleven (11) proponents submitted their pre-qualification
documents, most failed to comply with the requirements under
Section 5.4 of the Implementing Rules and Regulations (IRR) of
Republic Act No. 6957, otherwise known as the Build-Operate-
Transfer Law. On July 21, 1995, the Pre-qualification, Bids and
Awards Committee (PBAC) recommended the pre-qualification of
three proponents, namely: i) JANCOM International Pty. Ltd.; ii)
First Philippine International W-E Managers; and iii) PACTECH
Development Corporation. On July 26, 1995, the EXECOM
approved the recommendation of the PBAC. On July 27, 1995,
MMDA forwarded to the Investment Coordinating Committee
(ICC) Secretariat the pre-feasibility study on the privatization of the
Carmona and San Mateolandfill sites. The project was later
presented to the ICC-Technical Board (ICC-TB) and then endorsed
to the ICC-Cabinet Committee (ICC-CC).

On May 2, 1996, the PBAC conducted a pre-bid conference where


it required the three pre-qualified bidders to submit, within ninety
(90) days, their bid proposals. On August 2, 1996, JANCOM and
First Philippines requested for an extension of time to submit their
bids. PACTECH, on the other hand, withdrew from the bidding.

Subsequently, JANCOM entered into a partnership with Asea


Brown Boveri (ABB) to form JANCOM Environmental Corporation
while First Philippines formed a partnership with OGDEN. Due to
the change in the composition of the proponents, particularly in
their technology partners and contractors, the PBAC conducted a
post pre-qualification evaluation.

During the second bid conference, the bid proposals of First


Philippines for the Carmona site and JANCOM for the San
Mateo site were found to be complete and
responsive. Consequently, on February 12, 1997, JANCOM and
First Philippines were declared the winning bidders, respectively, disregarding the BOT Contract and ii) the acts of MMDA calling for
for the San Mateo and the Carmona projects. bids and authorizing a new contract for Metro Manila waste
management, as illegal, unconstitutional, and void; and for
In a letter dated February 27, 1997, then MMDA Chairman
prohibition to enjoin the Greater Metropolitan Manila Solid Waste
Prospero I. Oreta informed JANCOMs Chief Executive Officer Jay
Management Committee and MMDA from implementing the
Alparslan that the EXECOM had approved the PBAC
assailed resolution and disregarding the Award to, and the BOT
recommendation to award to JANCOM the San Mateo Waste-to-
contract with, JANCOM, and from making another award in its
Energy Project on the basis of the final Evaluation Report declaring
place. On May 29, 2000, the trial court rendered a decision, the
JANCOM International Ltd., Pty., together with Asea Brown Boveri
dispositive portion of which reads:
(ABB), as the sole complying (winning) bidder for the San Mateo
Waste Disposal site, subject to negotiation and mutual approval of WHEREFORE, in view of the foregoing, the Court hereby renders
the terms and conditions of the contract of award. The letter also judgment in favor of petitioners JANCOM ENVIRONMENTAL
notified Alparslan that the EXECOM had created a negotiating CORPORATION, and JANCOM INTERNATIONAL DEVELOPMENT
team composed of Secretary General Antonio Hidalgo of the PROJECTS PTY., LIMITED OF AUSTRALIA, and against respondent
Housing and Urban Development Coordinating Council, Director GREATER METROPOLITAN MANILA SOLID WASTE MANAGEMENT
Ronald G. Fontamillas, General Manager Roberto Nacianceno of COMM., and HON. ROBERTO N. AVENTAJADO, in his Capacity as
MMDA, and Atty. Eduardo Torres of the host local government Chairman of the said Committee, METRO MANILA DEVELOPMENT
unit to work out and finalize the contract award. Chairman Oreta AUTHORITY and HON. JEJOMAR C. BINAY, in his capacity as
requested JANCOM to submit to the EXECOM the composition of Chairman of said Authority, declaring the Resolution of respondent
its own negotiating team. Greater Metropolitan Manila Solid Waste Management Committee
disregarding petitioners BOT Award Contract and calling for bids
Thereafter, after a series of meetings and consultations between
for and authorizing a new contract for the Metro Manila waste
the negotiating teams of EXECOM and JANCOM, a draft BOT
management ILLEGAL and VOID.
contract was prepared and presented to the Presidential Task
Force on Solid Waste Management. Moreover, respondents and their agents are hereby PROHIBITED
and ENJOINED from implementing the aforesaid Resolution and
On December 19, 1997, the BOT Contract for the waste-to-energy
disregarding petitioners BOT Award Contract and from making
project was signed between JANCOM and the Philippine
another award in its place.
Government, represented by the Presidential Task Force on Solid
Waste Management through DENR Secretary Victor Ramos, CORD- Let it be emphasized that this Court is not preventing or stopping
NCR Chairman Dionisio dela Serna, and MMDA Chairman Prospero the government from implementing infrastructure projects as it is
Oreta. aware of the proscription under PD 1818. On the contrary, the
Court is paving the way for the necessary and modern solution to
On March 5, 1998, the BOT contract was submitted to President
the perennial garbage problem that has been the major headache
Ramos for approval but this was too close to the end of his term
of the government and in the process would serve to attract more
which expired without him signing the contract. President Ramos,
investors in the country.
however, endorsed the contract to incoming President Joseph E.
Estrada. (Rollo,p. 159.)

With the change of administration, the composition of the Instead of appealing the decision, MMDA filed a special civil action
EXECOM also changed. Memorandum Order No. 19 appointed the for certiorari with prayer for a temporary restraining order with
Chairman of the Presidential Committee on Flagship Programs and the Court of Appeals which was later docketed therein as CA-G.R.
Project to be the EXECOM chairman. Too, Republic Act No. 8749, SP No. 59021. The appellate court not only required JANCOM to
otherwise known as the Clean Air Act of 1999, was passed by comment on the petition, it also granted MMDAs prayer for a
Congress. And due to the clamor of residents of Rizal province, temporary restraining order. During the pendency of the petition
President Estrada had, in the interim, also ordered the closure of for certiorari, JANCOM moved for the execution of the RTC
the San Mateo landfill. Due to these circumstances, the Greater decision, which was opposed by MMDA. However, the RTC granted
Manila Solid Waste Management Committee adopted a resolution the motion for execution on the ground that its decision had
not to pursue the BOT contract with JANCOM. Subsequently, in a become final since MMDA had not appealed the same to the Court
letter dated November 4, 1999, Roberto Aventajado, Chairman of of Appeals. MMDA moved to declare respondents and the RTC
the Presidential Committee on Flagship Programs and Project judge in contempt of court, alleging that the RTCs grant of
informed Mr. Jay Alparslan, Chairman of JANCOM, that due to execution was abuse of and interference with judicial rules and
changes in policy and economic environment (Clean Air Act and processes.
non-availability of the San Mateo landfill), the implementation of
On November 13, 2001, the Court of Appeals dismissed the
the BOT contract executed and signed between JANCOM and the
petition in CA-G.R. SP No. 59021 and a companion case, CA-G.R. SP
Philippine Government would no longer be pursued. The letter
No. 60303.
stated that other alternative implementation arrangements for
solid waste management for Metro Manila would be considered MMDAs motion for reconsideration of said decision having been
instead. denied, MMDA filed the instant petition, alleging that the Court of
Appeals gravely erred in finding that:
JANCOM appealed to President Joseph Estrada the position taken
by the EXECOM not to pursue the BOT Contract executed and 1) There is a valid and binding contract between the Republic of
signed between JANCOM and the Philippine Government, refuting the Philippines and JANCOM given that: a) the contract does not
the cited reasons for non-implementation. Despite the pendency bear the signature of the President of the Philippines; b) the
of the appeal, MMDA, on February 22, 2000, caused the conditions precedent specified in the contract were not complied
publication in a newspaper of an invitation to pre-qualify and to with; and c) there was no valid notice of award.
submit proposals for solid waste management projects for Metro
Manila. JANCOM thus filed with the Regional Trial Court of Pasig a 2) The MMDA had not seasonably appealed the Decision of the
petition for certiorari to declare i) the resolution of the Greater lower court via a petition for certiorari.
Metropolitan Manila Solid Waste Management Committee
Before taking up the substantive issue in question, we shall first rights of the parties, either on the entire controversy or on some
dispose of the question as to whether it is fatal to petitioners definite and separate branch thereof, and concludes them until it
cause, that rather than appealing the trial courts decision to the is reversed or set aside. Where no issue is left for future
Court of Appeals, it instead filed a petition for certiorari. While consideration, except the fact of compliance or non-compliance
petitioner claims that the trial courts decision never became final with the terms of the judgment or doer, such judgment or order is
by virtue of its having appealed by certiorari to the Court of final and appealable (Investments, Inc. vs. Court of Appeals, 147
Appeals, the trial court ruled that petitioners failure to file an SCRA 334 [1987]).
appeal has made its decision final and executory. At bottom, the
However, instead of appealing the decision, MMDA resorted to the
question involves a determination of the propriety of petitioners
extraordinary remedy of certiorari, as a mode of obtaining reversal
choice of the remedy of certiorari in questioning the decision of
of the judgment. This cannot be done. The judgment was not in
the trial court.
any sense null and void ab initio, incapable of producing any legal
Section 1, Rule 65 of the 1997 Rules of Civil Procedure provides: effects whatever, which could be resisted at any time and in any
court it was attempted. It was a judgment which could or may
Section 1. Petition for certiorari. When any tribunal, board or
have suffered from some substantial error in procedure or in
officer exercising judicial or quasi-judicial functions has acted
findings of fact or of law, and on that account, it could have been
without or in excess of its or his jurisdiction, or with grave abuse of
reversed or modified on appeal. But since it was not appealed, it
discretion amounting to lack or excess of jurisdiction, and there is
became final and has thus gone beyond the reach of any court to
no appeal, or any plain, speedy, and adequate remedy in the
modify in any substantive aspect. The remedy to obtain reversal or
ordinary course of law, a person aggrieved thereby may file a
modification of the judgment on the merits is appeal. This is true
verified petition in the proper court, alleging the facts with
even if the error, or one of the errors, ascribed to the court
certainty and praying that judgment be rendered annulling or
rendering the judgment is its lack of jurisdiction over the subject
modifying the proceedings of such tribunal, board or officer, and
matter, or the exercise of power in excess thereof, or grave abuse
granting such incidental reliefs as law and justice may require.
of discretion in the findings of fact or of law set out in the
The petition shall be accompanied by a certified true copy of the decision. The existence and availability of the right of appeal
judgment, order, or resolution subject thereof, copies of all proscribes a resort to certiorari, because one of the requirements
pleadings and documents relevant and pertinent thereto, and a for availment of the latter remedy is precisely that there should be
sworn certification of non-forum shopping as provided in the third no appeal (Mercado vs. CA, 162 SCRA 75 [1988]). As incisively
paragraph of section 3, Rule 46. observed by the Court of Appeals:

Plain it is from a reading of the above provision that certiorari will The special civil action for certiorari is available only when there is
lie only where a court has acted without or in excess of jurisdiction no appeal nor any plain, speedy and adequate remedy in the
or with grave abuse of discretion. If the court has jurisdiction over ordinary course of law (Sec. 1, rule 65, id.)
the subject matter and of the person, its rulings upon all questions
Admittedly, appeal could have been taken from the assailed RTC
involved are within its jurisdiction, however irregular or erroneous
decision. However, petitioners maintain that appeal is not a
these may be, they cannot be corrected by certiorari. Correction
speedy remedy because the RTC decision prohibiting them from
may be obtained only by an appeal from the final decision.
conducting a bidding for a new waste disposal project has adverse
Verily, Section 1, Rule 41 of the 1997 Rules of Civil Procedure and serious effects on the citys garbage situation.
provides:
Nevertheless, the RTC decision is not immediately executory. Only
SEC. 1. Subject of appeal. An appeal may be taken from a judgment judgments in actions for injunction, receivership, accounting and
or final order that completely disposes of the case or of a support and such other judgments as are now or may hereafter be
particular matter therein when declared by these Rules to be declared to be immediately executory shall be enforced after their
appealable. rendition and shall not be stayed by an appeal therefrom, unless
otherwise ordered by the trial court (Sec. 4, rule 39, id.).
xxx xxx xxx
Since the RTC decision is not immediately executory, appeal would
In all the above instances where the judgment or final order is not have stayed its execution. Consequently, the adverse effects of
appealable, the aggrieved party may file an appropriate special civil said decision will not visit upon petitioners during the appeal. In
action under Rule 65. other words, appeal is a plain, speedy and adequate remedy in the
ordinary course of the law.
There can be no dispute that the trial courts May 29, 2000 decision
was a final order or judgment which MMDA should have appealed, But as no appeal was taken within the reglementary period, the
had it been so minded. In its decision, the trial court disposed of RTC decision had become final and executory.Well-settled is the
the main controversy by declaring the Resolution of respondent rule that the special civil action for certiorari may not be invoked
Greater Metropolitan Manila Solid Waste Management Committee as a substitute for the remedy of appeal (BF Corporation vs. Court
disregarding petitioners BOT Award Contract and calling for bids of Appeals, 288 SCRA 267). Therefore, the extraordinary remedy of
for and authorizing a new contract for the Metro Manila waste certiorari does not lie.
management ILLEGAL and VOID. This ruling completely disposed of
the controversy between MMDA and JANCOM. In BA Finance Moreover, petitioners instituted the instant action without filing a
Corporation vs. CA (229 SCRA 5667 [1994]), we held that a final motion for reconsideration of the RTC decision.Doctrinal is the rule
order or judgment is one which disposes of the whole subject that certiorari will not lie unless a motion for reconsideration is
matter or terminates a particular proceeding or action, leaving first filed before the respondent tribunal to allow it an opportunity
nothing to be done but to enforce by execution what has been to correct its errors (Zapanta vs. NLRC, 292 SCRA 580).
determined. An order or judgment is deemed final when it finally
(Rollo, p. 47-48.)
disposes of the pending action so that nothing more can be done
with it in the trial court. In other words, a final order is that which Admittedly, there are instances where the extraordinary remedy
gives an end to the litigation. A final order or judgment finally of certiorari may be resorted to despite the availability of an
disposes of, adjudicates, or determines the rights, or some right or
appeal. In Ruiz, Jr. vs. Court of Appeals (220 SCRA 490 [1993]), we Admittedly, when petitioners accepted private respondents bid
held: proposal (offer), there was, in effect, a meeting of the minds upon
the object (waste management project) and the cause (BOT
Considered extraordinary, [certiorari] is made available only when
scheme). Hence, the perfection of the contract. In City of Cebu vs.
there is no appeal, nor any plain, speedy or adequate remedy in
Heirs of Candido Rubi (306 SCRA 108), the Supreme Court held that
the ordinary course of the law (Rule 65, Rules of Court, Section
the effect of an unqualified acceptance of the offer or proposal of
1). The long line of decisions denying the petition
the bidder is to perfect a contract, upon notice of the award to the
for certiorari, either before appeal was availed or specially in
bidder.
instances where the appeal period has lapsed, far outnumbers the
instances when certiorari was given due course. The few significant (Rollo, p. 48-49.)
exceptions were: when public welfare and the advancement of
In fact, in asserting that there is no valid and binding contract
public policy dictate; or when the broader interests of justice so
between the parties, MMDA can only allege that there was no
require, or when the writs issued are null . . . or when the
valid notice of award; that the contract does not bear the
questioned order amounts to an oppressive exercise of judicial
signature of the President of the Philippines; and that the
authority.
conditions precedent specified in the contract were not complied
In the instant case, however, MMDA has not sufficiently with.
established the existence of any fact or reason to justify its resort
In asserting that the notice of award to JANCOM is not a proper
to the extraordinary remedy of certiorari. Neither does the record
notice of award, MMDA points to the Implementing Rules and
show that the instant case, indeed, falls under any of the
Regulations of Republic Act No. 6957, otherwise known as the BOT
exceptions aforementioned.
Law, which require that i) prior to the notice of award, an
The Court thus holds that the Court of Appeals did not err in Investment Coordinating Committee clearance must first be
declaring that the trial courts decision has become final due to the obtained; and ii) the notice of award indicate the time within
failure of MMDA to perfect an appeal within the reglementary which the awardee shall submit the prescribed performance
period. security, proof of commitment of equity contributions and
indications of financing resources.
With the foregoing disquisition, it would appear unnecessarily to
discuss and resolve the substantive issue posed before the Court. Admittedly, the notice of award has not complied with these
However, the procedural flaw notwithstanding, the Court deems it requirements. However, the defect was cured by the subsequent
judicious to take cognizance of the substantive question, if only to execution of the contract entered into and signed by authorized
put petitioners mind to rest. representatives of the parties; hence, it may not be gainsaid that
there is a perfected contract existing between the parties giving to
In its second assignment of errors, petitioner MMDA contends that
them certain rights and obligations (conditions precedents) in
there is no valid and binding contract between the Republic of the
accordance with the terms and conditions thereof. We borrow the
Philippines and respondents because: a) the BOT contract does not
words of the Court of Appeals:
bear the signature of the President of the Philippines; b) the
conditions precedent specified in the contract were not complied Petitioners belabor the point that there was no valid notice of
with; and that c) there was no valid notice of award. award as to constitute acceptance of private respondents
offer. They maintain that former MMDA Chairman Oretas letter to
These contentions hold no water.
JANCOM EC dated February 27, 1997 cannot be considered as a
Under Article 1305 of the Civil Code, [a] contract is a meeting of valid notice of award as it does not comply with the rules
minds between two persons whereby one binds himself, with implementing Rep. Act No. 6957, as amended. The argument is
respect to the other, to give something or to render some service. untenable.
A contract undergoes three distinct stages preparation or
The fact that Chairman Oretas letter informed JANCOM EC that it
negotiation, its perfection, and finally, its
was the sole complying (winning) bidder for the San Mateo project
consummation. Negotiation begins from the time the prospective
leads to no other conclusion than that the project was being
contracting parties manifest their interest in the contract and ends
awarded to it. But assuming that said notice of award did not
at the moment of agreement of the parties. The perfection or birth
comply with the legal requirements, private respondents cannot
of the contract takes place when the parties agree upon the
be faulted therefore as it was the government representatives
essential elements of the contract. The last stage is
duty to issue the proper notice.
the consummation of the contract wherein the parties fulfill or
perform the terms agreed upon in the contract, culminating in the In any event, petitioners, as successors of those who previously
extinguishment thereof (Bugatti vs. CA, 343 SCRA 335 acted for the government (Chairman Oreta, et al), are estopped
[2000]). Article 1315 of the Civil Code, provides that a contract is from assailing the validity of the notice of award issued by the
perfected by mere consent. Consent, on the other hand, is latter. As private respondents correctly observed, in negotiating on
manifested by the meeting of the offer and the acceptance upon the terms and conditions of the BOT contract and eventually
the thing and the cause which are to constitute the contract (See signing said contract, the government had led private respondents
Article 1319, Civil Code). In the case at bar, the signing and to believe that the notice of award given to them satisfied all the
execution of the contract by the parties clearly show that, as requirement of the law.
between the parties, there was a concurrence of offer and
While the government cannot be estopped by the erroneous acts
acceptance with respect to the material details of the contract,
of its agents, nevertheless, petitioners may not now assail the
thereby giving rise to the perfection of the contract. The execution
validity of the subject notice of award to the prejudice of private
and signing of the contract is not disputed by the parties. As the
respondents. Until the institution of the original action before the
Court of Appeals aptly held:
RTC, invalidity of the notice of award was never invoked as a
[C]ontrary to petitioners insistence that there was no perfected ground for termination of the BOT contract. In fact, the reasons
contract, the meeting of the offer and acceptance upon the thing cited for terminating the San Mateo project, per Chairman
and the cause, which are to constitute the contract (Arts. 1315 and Aventajados letter to JANCOM EC dated November 4, 1999, were
1319, New Civil Code), is borne out by the records.
its purported non-implementability and non-viability on account of that such approval is required only in infrastructure contracts
supervening events, e.g., passage of the Clean Air Act, etc. involving amounts exceeding the ceilings set in Sec.
58. Significantly, the infrastructure contracts treated in Sec. 58
(Rollo, p. 49-50.)
pertain only to those which may be approved by the Secretaries of
MMDA also points to the absence of the Presidents signature as Public Works and Highways, Transportation and Communications,
proof that the same has not yet been perfected. Not only that, the Local Government (with respect to Rural Road Improvement
authority of the signatories to bind the Republic has even been put Project) and the governing boards of certain government-owned
to question. Firstly, it is pointed out that Memorandum Order No. or controlled corporations. Consequently, the BOT contract in
202 creating the Executive Committee to oversee the BOT question, which was approved by the DENR Secretary and the
implementation of solid waste management projects only charged EXCOM Chairman and Co-Chairman, is not covered by Exec. Order
the officials thereof with the duty of recommending to the No. 292.
President the specific project to be implemented under the BOT
(Rollo, p. 51-52.)
scheme for both San Mateo and Carmona sites. Hence, it is
concluded that the signatories, CORD-NCR Chairman Dionisio dela The provision pertinent to the authority of the Secretary of
Serna and MMDA Chairman Prospero Oreta, had no authority to Environment and Natural Resources would actually be Section 1 of
enter into any waste management project for and in behalf of the Executive Order No. 380, Series of 1989 which provides that The
Government. Secondly, Section 59 of Executive Order No. 292 is Secretaries of all Departments and Governing Boards of
relied upon as authority for the proposition that presidential government-owned or controlled corporations [except the
approval is necessary for the validity of the contract. Secretaries of Public Works and Highways, Transportation and
Communication, and Local Government with respect to Rural Road
The first argument conveniently overlooks the fact that then
Improvement projects] can enter into publicly bidded contracts
Secretary of Environment and Natural Resources Victor Ramos was
regardless of amount (See also Section 515, Government
likewise a signatory to the contract. While dela Serna and Oreta
Accounting and Auditing Manual Volume I). Consequently, MMDA
may not have had any authority to sign, the Secretary of
may not claim that the BOT contract is not valid and binding due to
Environment and Natural Resources has such an authority. In fact,
the lack of presidential approval.
the authority of the signatories to the contract was not denied by
the Solicitor General.Moreover, as observed by the Court of Significantly, the contract itself provides that the signature of the
Appeals, [i]t was not alleged, much less shown, that those who President is necessary only for its effectivity (not perfection),
signed in behalf of the Republic had acted beyond the scope of pursuant to Article 19 of the contract, which reads:
their authority.
This contract shall become effective upon approval by the
In truth, the argument raised by MMDA does not focus on the lack President of the Republic of the Philippines pursuant to existing
of authority of the signatories, but on the amount involved as laws subject to the condition, precedent in Article 18. This contract
placing the contract beyond the authority of the signatories to shall remain in full force and effect for twenty-five (25) years
approve.Section 59 of Executive Order No. 292 reads: subject to renewal for another twenty-five (25) years from the
date of Effectivity. Such renewal will be subject to mutual
Section 59. Contracts for Approval by the President. Contracts for
agreement of the parties and approval of the President of the
infrastructure projects, including contracts for the supply of
Republic of the Philippines.
materials and equipment to be used in said projects, which involve
amounts above the ceilings provided in the preceding section shall (Rollo, p. 94.)
be approved by the President: Provided, That the President may,
Stated differently, while the twenty-five year effectivity period of
when conditions so warrant, and upon recommendation of the
the contract has not yet started to run because of the absence of
National Economic and Development Authority, revise the
the Presidents signature, the contract has, nonetheless, already
aforesaid ceilings of approving authority.
been perfected.
However, the Court of Appeals trenchantly observed in this
As to the contention that there is no perfected contract due to
connection:
JANCOMs failure to comply with several conditions precedent, the
As regards the Presidents approval of infrastructure projects same is, likewise, unmeritorious. Article 18 of the BOT contract
required under Section 59 of Executive Order No. 292, said section reads:
does not apply to the BOT contract in question. Sec. 59 should be
ARTICLE 18
correlated with Sec. 58 of Exec. Order No. 292. Said sections read:
CONDITIONS PRECEDENT
SECTION 58. Ceiling for Infrastructure Contracts. The following
shall be the ceilings for all civil works, construction and other xxx
contracts for infrastructure projects, including supply contracts for
said projects, awarded through public bidding or through 18.2.1. The BOT COMPANY hereby undertakes to provide the
negotiation, which may be approved by the Secretaries of Public following within 2 months from execution of this Contract as an
Works and Highways, Transportation and Communications, Local effective document:
Government with respect to Rural Road improvement Project and
a) sufficient proof of the actual equity contributions from the
governing boards of government-owned or controlled corporations:
proposed shareholders of the BOT COMPANY in a total amount not
xxx xxx xxx less than PHP500,000,000 in accordance with the BOT Law and the
implementing rules and regulations;
Save as provided for above, the approval ceilings assigned to the
departments/agencies involved in national infrastructure and b) sufficient proof of financial commitment from a lending
construction projects shall remain at the levels provided in existing institution sufficient to cover total project cost in accordance with
laws, rules and regulations. the BOT Law and the implementing rules and regulations;

Contrary to petitioners claim that all infrastructure contracts


require the Presidents approval (Petition, p. 16), Sec. 59 provides
c) to support its obligation under this Contract, the BOT COMPANY As regards the projected closure of the San Mateo landfill vis--vis
shall submit a security bond to the CLIENT in accordance with the the implementability of the contract, Art. 2.3 thereof expressly
form and amount required under the BOT Law. states that [i]n the event the project Site is not delivered x x x, the
Presidential task Force on Solid Waste Management (PTFSWM)
xxx
and the Client, shall provide within a reasonable period of time, a
18.2.3 Completion of Documentary Requirements as per Schedule 4 suitable alternative acceptable to the BOT COMPANY.
by the BOT Company
With respect to the alleged financial non-viability of the project
As clearly stated in Article 18, JANCOM undertook to comply with because the MMDA and the local government units cannot afford
the stated conditions within 2 months from execution of the the tipping fees under the contract, this circumstance cannot, by
Contract as an effective document. Since the President of itself, abrogate the entire agreement.
the Philippineshas not yet affixed his signature on the contract, the
Doctrinal is the rule that neither the law nor the courts will
same has not yet become an effective document.Thus, the two-
extricate a party from an unwise or undesirable contract, or
month period within which JANCOM should comply with the
stipulation for that matter, he or she entered into with full
conditions has not yet started to run. It cannot thus be said that
awareness of its consequences (Opulencia vs. CA, 293 SCRA
JANCOM has already failed to comply with the conditions
385). Indeed, the terms and conditions of the subject contract
precedent mandated by the contract. By arguing that failure [of
were arrived at after due negotiations between the parties
JANCOM] to comply with the conditions results in the failure of a
thereto.
contract or prevents the judicial relation from coming into
existence, MMDA reads into the contract something which is not (Rollo, p. 54.)
contemplated by the parties. If the terms of a contract are clear
WHEREFORE, premises considered, the petition is hereby
and leave no doubt upon the intention of the contracting parties,
DISMISSED for lack of merit and the decision of the Court of
the literal meaning of its stipulations shall control (Art. 1370, Civil
Appeals in CA-G.R. SP No. 59021 dated November 13,
Code).
2001 AFFIRMED. No costs.
We, therefore, hold that the Court of Appeals did not err when it
SO ORDERED.
declared the existence of a valid and perfected contract between
the Republic of the Philippines and JANCOM. There being a
perfected contract, MMDA cannot revoke or renounce the same
without the consent of the other. From the moment of perfection,
the parties are bound not only to the fulfillment of what has been
expressly stipulated but also to all the consequences which,
according to their nature, may be in keeping with good faith,
usage, and law (Article 1315, Civil Code). The contract has the
force of law between the parties and they are expected to abide in
good faith by their respective contractual commitments, not
weasel out of them. Just as nobody can be forced to enter into a
contract, in the same manner, once a contract is entered into, no
party can renounce it unilaterally or without the consent of the
other. It is a general principle of law that no one may be permitted
to change his mind or disavow and go back upon his own acts, or
to proceed contrary thereto, to the prejudice of the other
party. Nonetheless, it has to be repeated that although the
contract is a perfected one, it is still ineffective or
unimplementable until and unless it is approved by the President.

Moreover, if after a perfected and binding contract has been


executed between the parties, it occurs to one of them to allege
some defect therein as reason for annulling it, the alleged defect
must be conclusively proven, since the validity and the fulfillment
of contracts cannot be left to the will of one of the contracting
parties. In the case at bar, the reasons cited by MMDA for not
pushing through with the subject contract were: 1) the passage of
the Clean Air Act, which allegedly bans incineration; 2) the closure
of the San Mateo landfill site; and 3) the costly tipping fee. These
reasons are bereft of merit

Once again, we make reference to the insightful declarations of


the Court of Appeals:

Sec. 20 of the Clean Air Act pertinently reads:

SECTION 20. Ban on Incineration. Incineration, hereby defined as


the burning of municipal, bio-chemical and hazardous
wastes, which process emits poisonous and toxic fumes, is hereby
prohibited: x x x.

Section 20 does not absolutely prohibit incineration as a mode of


waste disposal; rather only those burning processes which emit
poisonous and toxic fumes are banned.

Вам также может понравиться