Академический Документы
Профессиональный Документы
Культура Документы
Un 25m
-in m
GP, F
12C
60 d) Lowering concrete delivered temperature in
summer reduces the temperature differential
Feb
,
50
maximum temperature but not concrete
l
, Ju
20
Total Bleed =
4.2 PLASTIC CRACKING BWH (Hrs) Bleed Rate = B (% free
water/100)
When evaporation loss exceeds the concrete bleed rate Bleed Period = T (Hrs)
water loss from the concrete surface, a volumetric
contraction of the fresh concrete occurs and short, T (Hrs)
irregular plastic cracks result. They can be from few
Pour Height (H)
Evap./Bleed (lt/m2/hr)
3pm Summer
9am Winter
Figure 6 – Settlement vs Pour Height of a Given Pour Rate 1.4
for Concrete with Different Bleeds
3pm
9am
1.0
9.0
0.5 Free Water (W) lt/m3 170
8.0 Bleed Rate Bleed Period (T) hrs 4
1.0 % free 0.6
Pour Rate (P) m/hr 1
7.0 2.0 water
Bleed/Settlement (mm)
3.0 0.2
6.0 Settlement Limit
Sydney Melbourne Perth Brisbane Canberra Hobart Darwin
5.0
4.0
3.0
4.3 ACTIONS BY THE CONTRACTOR
2.0
The Contractor has to know what to expect from the
1.0 concrete supplied so that the pour can be planned
0.0 accordingly. This planing is probably the most
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 important aspect of Hot Weather Concreting. The
Pour Height (m) Consultant can specify that the Contractor provide
an acceptable method statement for Hot Weather
Figure 7 – Settlement vs Pour Height of a Given Bleed for Concreting based on measured properties of the
different Pour Rates concrete (e.g. bleed, setting time) that is to be used.
The method statement would include actions to be
3.5 taken, including pour cancellation, based on
3.0
1 Pour Rate
(m height/hr)
expected ambient conditions. This would ensure that
2
there are steps in place that the Consultant can
Bleed or Settlement (mm)
5
2.5
Settlement Limit
check that are directly relevant to the concrete and
2.0
conditions.
1.5
The principle way of reducing plastic cracking is the
use of aliphatic alcohol but misting over the slab is
1.0 also effective. Polypropylene fibers have been
0.5
Bleed rate (B) %
3
0.6
effective in reducing plastic shrinkage cracking.
Free Water (W) lt/m 170
Bleed Period (T) hrs 4 Other options are to erect wind barriers around the
0.0 pour and to erect sunshades to protect the concrete
surface from heat.
0 0.5 1 1.5 2 2.5 3 3.5 4
Pour Height (m)
30
Water Content (kg/m3)
175
170 20
5MPa 7 28 90 180
165 Age (Days)
Winter w/c=0.45 45
Compressive Strength (MPa)
160
44
180 days
43
42
41
155
40
0 10 20 30 40 39
Temperature (°C)
AS 1379 limit
38
The modifications to the concrete mix to maintain 37
36
Strength drop due to
increasing delivered
slump, w/c ratio, strength and durability are issues for 35 concrete temperature
the concrete company. However, the Contractors 34
33
28 days
Temp (°C)
°C))
Concrete Temperature ((°C
manufacturers recommended admixture dosages
are not exceeded. It is noted that this work relates to 32 35Water
28day strengths and does not consider the longer 30
term affect on durability. 25
28 20
Recognising the high cost of keeping delivered
concrete temperatures down, and as local research 44kg water replaced with ice
had shown that at 38°C retarded concrete did not 24 35
167 kg/m3 Water
suffer strength loss problems, Florida Department of 1839 kg/m3 Aggregate
Transports increased the specified delivered 20 335 kg/m3 Cement at 66°C
20
temperature from 27°C to 38°C as part of a 24 26 28 30 35
specification review of all parts of a project. In (°C))
Aggregate Temperature (°C
essence this accepted that mix design, transport,
placing all played a part in the significance of
delivered temperature. This approach may be Estimated cost of the various methods of reducing
appropriate provided the quality system ensures the concrete temperature are shown in Table 1. Because
Contractor keeps to the requirements of the concrete temperature reduction can have significant
specification and full account is taken of the cost implications specifications should endeavour to
potential for reduced insitu strength and durability. enable the supplier to use higher temperatures where
they can demonstrate it will not lead to poor quality
The use of set retarders in hot weather concrete can concrete. It may well be cheaper for the contractor
give highly extended working times as shown by the to organise for short delivery and placing times than
Foundations for Raffles City ( refer to “Hot Weather reduce the concrete temperature.
Concreting” Singapore Concrete Institute, 1987)
Table 1 – Approximate Cost of Reducing Concrete
where concrete at 30-32°C was retarded for up to
Temperature
8hrs without the use of ice or chilled water. This highly
extended working time becomes necessary in some Method Cost Concrete Implications
large pours and the affect on bleed and settlement implications
must be taken into account. The use of retarders to Shade Negligible Concrete temperature
extend transport times is generally less demanding. aggregates reduced by 3-4°C
Where extended placing times and higher delivered Use of chilled A$0.20/°C Concrete temperature
temperatures are sought by the contractor they may water reduced by 6°C
be accepted based on previous history of the mix or Use of crushed A$2.50/°C Concrete temperature
trial mixes that record slump loss with time and an ice reduced by 6-8°C
appropriate durability parameter. Project mix trials, Use of liquid A$3.00/°C Concrete down to 10°C
undertaken with various retarder dosages, will show nitrogen
how the retarders affect “workability extension time”.
References
Bamforth. P., 1980 “I-situ measurements of the effect of partial
Portland cement replacement using either fly ash or ground
granulated blast furnace slag on the performance of mass
concrete”. Proc. Of Instn. Of Civ. Engrs., Part 2 No. 69.,
September 1980. pp777-800. London.
AS 1379 Manufacture and supply Standards Australia 1997
ACI Committee 305, Hot Weather ACI Manual of Concrete
Practice Construction practices and inspection, pavements
American Concrete Institute, Farmington Hills, USA, 1999.
Mittelacher “Effect of hot weather conditions on the
strength performance of set retarded field concrete” ASTM
STP 858 1992