2018 4th IEEE International Conference on Information Management

Application of BIM Technology in the Construction Management of Shield Tunnel

Peng Zhi, Tianyun Shi, Wanqi Wang and Huilin Wang


Institute of Computing Technology
China Academy of Railway Sciences
Beijing, China
e-mail: 28572322@qq.com

Abstract—Aiming at the current situations of shield tunnel traffic operation safety in the tunnel. This is the one the
construction such as surrounding environment complexity, importance of engineering control.
high risks, severe construction difficulties, high technical
requirements, and urgent project schedules, innovatively using D. Shield Construction Engineering
new technologies of BIM, 3D-based laser scanning, mobile The tunnel is to go through regions which are very close
internet, and WebGL to solve engineering problems is to those multiple sensitive buildings, pipelines, and some
proposed. First, based on the BIM standard distributed by the other risk sources nearby. How to protect the existing lines,
international organization buildingSMART, a BIM application pipelines, and buildings, and how to ensure the existing
and implementation standard and an encoding specification operations and passengers’ safety in the tunnel construction
for railway shield tunnel are proposed to build a visualization process are the key points of the shielding control for the
encoding system for tunnel model elements. Second, refined tunnel boring machine.
BIM-based modeling and information attachment of related
Based on the situations of complex structure and
shield tunnel majors have been achieved by utilizing the
professional modeling software such as Bentley and Revit, as
abnormally complex environmental implication in the shield
well as model assembling, model lightweighting, and separate tunnel engineering mentioned above, it is necessary to
storing of models and data. Last, a self-developed WebGL- introduce the BIM technology to solve a series of problems
based graphics engine is used to achieve the implementation of including the ‘red line’ of the progress, safety risk, quality
progress, quality and safety for the tunnel construction. It has problems in the process of shield tunnel construction so as to
been verified through practical engineering that the BIM achieve the purpose to increasing the work efficiency,
technology can help to increase the collaboration efficiency and reducing safety risks, improving project quality and cutting
the informatization management level for tunnel engineering, down construction costs.
also laying the data and technical foundation for exploring the The overall workflow of the BIM application in the
BIM-based full digital archive of shield tunneling methodology. shield tunnel engineering is shown in Fig. 1. First, a BIM
related application and implementation standard and an
Keywords-Shield tunnel; Building information modeling encoding specification for shield tunnel engineering are
(BIM); 3D laser scanning; BIM application management innovatively proposed, as well as the conduct of unified
platform encoding of tunnel’s relevant model elements to provide a
visualization encoding architecture system for the BIM
I. INTRODUCTION application. Then, the mainstream modeling software
The importance and difficulties of shield tunnel Bentley has been chosen to create the BIM models of shield
construction include: tunnel, tunnel segments, and the geological landform while
another popular modeling software Revit has been used to
A. Vertical Shaft Excavation Engineering build models of vertical shaft pit, surrounding risk sources,
Vertical shafts generally have characteristics such as and monitoring points. All the models have the precision of
great depth, strata instability, easy deformability, and the LOD350 and are attached geometry and attribute data. After
possibility to cause the surrounding strata settlement. These that, based on the modeling software plug-ins and the
are the important points in the engineering control. graphics engine, which are all self-developed, the
interconversion between the two model formats, .dgn
B. Open Excavation Range Engineering and .rvt, as well as the graphical lightweighting with a
Risk sources are relatively concentrated that affect the segment separating method, along with a way of separately
surrounding building structures and environment of the city. storing model and data in database, is utilized to solve the
Therefore, to control the deformation, sedimentation and high threshold difficulties of handling models. Furthermore,
high demand of foundation pit are the emphasis and difficult combined with some new technologies of 3D laser scanning
parts for project control. and internet of things, the informatization implementation of
shield tunnel construction management could be carried out
C. Waterproof Structure to solve practical application difficulties based on the
There are more joints in the tunnel’s main structure independently developed graphics engine platform, which is
which will result in large corrosion on the steel structure if
there is a water leakage and will also influence the future

978-1-5386-6147-5/18/$31.00 ©2018 IEEE 284


Meanwhile, combined with the application requirements
of BIM construction in the late stage of the project, various
unique components of shield tunneling are constructed and
each professional model is modeled quickly according to the
LOD of modeling. Corresponding EBS, IFC, and IFD codes
are also added to provide a visual model and basis for BIM
application [4, 5].
III. MODEL LIGHTWEIGHTING PRINCIPLE OF MULTIPLE
FORMATS
By using the 3D model lightweighting plug-in, BIM
models which originally require large storing and calculating
resources now could be greatly simplified. The process of
lightweighting is shown in Fig. 3, containing 3 purposes,
data compression, data storage, and model presentation.
A. Data Compression
Figure 1. Overall Workflow of the BIM Application in the Shield Tunnel When the lightweighting is done, the model source file is
Engineering simplified and compressed, occupying much less space.

cross-platformed and plug-in-free. With the on-site B. Data Extraction and Storage
engineering verification, from the shield tunnel construction All the attribute data, attribute type information, and the
aspects, such as progress, safety, and quality, the 3D relation between model elements and portions could be
visualized managing and controlling can be achieved, as extracted and stored in a database concentratedly.
well as the improvement of both construction collaboration C. Model Presentation
efficiency and informationalized management level. This
Model exhibition and operation include viewpoint
will lay the data and technical foundation for exploring the
switching, scaling, profiling, border blanking, hyalinizing,
BIM-based full digital archive of shield tunneling labeling, and measuring.
methodology.
IV. RESEARCH OF KEY TECHNOLOGIES FOR BIM
II. RESEARCH ON BIM APPLICATION CRITERIA OF APPLICATION
SHIELD TUNNEL
Key technologies used in BIM-based shield tunnel
According to the "Railway engineering information engineering include 3D visualization, fine-grained progress
modeling technology standard" [1] and "Railway engineering management, visualized early warning for safety risks,
entity structural decomposition guide-EBS(Engineering visualized shielding monitoring, and 3D quality management.
Breakdown Structure)" [2] issued by the China Railway BIM
alliance, combining with the construction situation in the A. 3D Visualization Technology for Tunnel Construction
work field, the BIM application standard in the major of Using the 3D visualization techniques of BIM + GIS to
shield tunnel has been made, including work range division, achieve 3D technical submission, such as key process in
engineering entity structure decomposition and level of detail tunneling, construction solution and specific techniques, can
(LOD) in modeling (as shown in Fig. 2). help to acknowledge the 360°perspective visualization
effect in the important and difficult parts of a project, which
also has advantages in foreseeing the problems, improved
comprehensibility, better comprehensiveness and the
obviousness effect. It not only reduces the difficulty for
construction workers to understand the drawings and to
effectively avoid the understanding mistakes, it also
improves the efficiency and effectiveness of the technical
submission, guaranteeing the construction quality.
Moreover, the application effect of 3d visualization for the

Figure 2. Research and Application of LOD Management Based on BIM.

Figure 3. Flowchart of the Model Lightweighting Principle

285
important and difficult parts of tunnel engineering can be
attained [6-10] (as shown in Fig. 4).

Figure 5. Visualization of Shield Tunnel Progress Control.

Figure 4. BIM Model Application Criteria for Shield Tunnel. 1) Rehearsal schedule
Using 3D visualization and simulation features of the
BIM technology, the dynamic simulation of construction
1) Technological process simulation organization progress through NAVIGATOR software
By loading BIM models using the dynamic simulation technology enables the user to judge the rationality of the
technology, the three-dimensional representation, dynamic construction progress schedule very intuitively, providing the
simulation, and simulation roaming of the starting shaft and most effective help for the next process of the project
starting section can be implemented, which can make it construction.
possible to effectively forecast and identify hazard sources. 2) Schedule analysis
With the accomplishment of the construction risk control and Based on the BIM model to divide the work tasks, the
the solution optimization of both the shield starting shaft and progress information interacts with the BIM model, and the
complicated nodes in the starting section, the goal to improve comparison between the actual and planned progress is made
construction quality and management efficiency can be based on the 3D electronic construction logbook and the
achieved. construction organization plan to determine the advance or
2) Structural visualization for the specific plan lag of the progress in real time, and then getting the reason
Through the BIM model, the spatial geometry, position, [11]. Moreover, a relatively complete progress analysis
and function of the nodes of engineering structure are truly report is provided to the user for the sake of the follow-up
expressed. The design in complex space will become more key operation decision.
intuitive, accomplishing the structural visualization. 3) Schedule early warning
3) Attribute visualization for model elements The key path analysis is used to form the critical path and
Utilizing the characteristics of information completeness mission-critical nodes. The results of real-time analysis of
and visualization of the parametric BIM model, the macro the progress lagging and serious delay are timely pre-warned
information and the microscopic information of the structure based on the BIM model according to the preset warning
of the project can be displayed to the user, helping the user to rules. Through the SMS and E-mail notification function in
grasp the construction information more conveniently and the BIM application platform, warning messages are sent to
accurately. the manager, which apparently improves the immediacy of
the progress warning management.
B. Fine-Grained Progress Management Based on BIM
C. Dynamic Visualized Early Warning for Safety Risks
The BIM technology is used to assist in the progress
management of tunnel construction, and the construction Based on BIM and Internet of Things
progress daily report ("Briefing" system management The safety risk warning is aimed to analyze and early
module) is used to achieve the dynamic management and report safety problems that are discovered in environmental
timely comparative analysis of all parties involved in the risk sources, the construction site, and the surrounding
project, providing follow-up construction staffing, equipment environment monitoring during the construction process and
and equipment deployment, mass material purchase, storage the inspection process. The safety risk warning can help to
yarding material (tunnel segment) admission control, as well improve the risk controlling ability in the construction
as the construction plan of adjacent processes [10]. Providing engineering.
a practical and reliable basis, the construction progress will Based on the information exchange among
be guaranteed as firmly as possible (as shown in Fig. 5). heterogeneous information systems and the data throughout
the different stages of the whole life cycle of the construction
project, the ontology-based heterogeneous exchange model
is proposed to explore the method of mapping both the IFC

286
data and the relationship database with the ontology model,
putting forward the ontology-based reasoning model.
By using the BIM characteristics of 3D visualization,
information relevance and information consistency, the
network sensing technology is widely utilized to achieve the
automatic collection and uploading of risk monitoring data
[12,13]. With the ‘red/orange/yellow’ three-level pre-alarm
mechanism, the early warning information of the analysis
results, along with the real-time status, can be instantly
reflected on the BIM model [14-16], which provides users
with the intuitive and queryable risk warning information
through the mobile network. The information distribution
function in the BIM system generates and delivers the early
warning information to the users through the mobile phone
network, which improves the user’s capability of risk
managing.
In the traditional scheme of risk early warning and
management, people have to carry out the risk controlling
and management by using construction drawings, on-site
verification and manual analysis of monitored data. On one
hand, the data analysis and results are not intuitive enough.
On the other hand, the information transmission is always
delayed. These disadvantages can be resolved by using the
risk early warning module of the BIM system (as shown in
Fig. 6 and Fig. 7).
D. Shielding Visualization Monitoring Based on BIM and
Figure 7. Risk Early Warning Based on BIM.
Big Data
The traditional shield monitoring system mainly focuses
on the video surveillance. The parameters of the tunnel
boring machine can only be viewed, brought to statistics and
analysis in the monitor room. Other people can never be able
to master the tunnel boring machine’s real-time working
status.
The BIM management platform receives real-time
working parameters, machine status, boring parameters and
alarming information from the PLC system in the tunnel
boring machine. The data are used along with the big data
technology to generate all kinds of parameter curves from
multiple aspects for analyzing and decision making. The
tunnel boring machine’s information can be dynamically
demonstrated, located, prewarned based on the 3D
visualization of the BIM model [17], which will help
managers to master the tunnel boring machine’s work status
and to make judgments and decisions (shown in Fig. 8 and
Fig. 9).

Figure 6. Environmental Risk Source Monitoring Based on BIM. Figure 8. Shielding Visualization Monitoring Based on BIM.

287
V. CONCLUSIONS
Combined with the verification of actual engineering
application, the BIM visualization features are used to realize
the key process engineering methods for shield tunnels and
the visualization disclosures of complex nodes. The BIM
simulation characteristics are used to realize the virtual
construction of shield tunnels projects and optimization of
construction organization deduction. The implementation of
collaborative construction of all parties involved in
construction, the dynamic allocation of resources, and the
refinement of construction schedules are achieved through
the coordination and optimization characteristics of BIM.
And then, through the integration of BIM with the internet of
Figure 9. Shielding Efficiency Analysis Based on Big Data.
things and 3D scanning technology, the closed-loop quality
control management and the early warning of safety risk
E. Quality Management Based on 3D Visualization monitoring of the shield tunnel engineering were
The tunnel and segments’ quality data, obtained from the accomplished. Finally, a three-dimensional visualization map
tunnel boring machine’s monitoring system, cloud data of of the construction management for the shield tunnel projects
three-dimensional laser scanning points, and collected data in based on BIM is formed to provide comprehensive auxiliary
a mobile phone, are regularly uploaded to the BIM based decision support for users through full-procedure and
tunnel quality management platform for the sake of 3D comprehensive data analysis from multiple perspectives of
visualized quality analysis of tunneling engineering, engineering construction such as safety, quality, and progress,
including segment assembly quality and influence factors, etc. The technology and data foundation is laid for the
the tunnel axis, the segment ring ovality, the segment further exploration of all digital files for BIM-based shield
damages and hidden dangers, etc. [18-20], which can also tunnel.
provide a practical and reliable information for the next In the actual application process, the size of model files is
step’s shield tunneling, segment assembly, grouting and huge due to the large scale of the tunnel project. During the
other related work. Better than the two-dimension mode, process of model compressing and lightweighting, there are
such as drawings and charts as shown in Fig. 10, the three- problems of information loss and graphics distortion, so it is
dimensional visualization analysis helps managers necessary to further study new graphics algorithms to
comprehensively master the construction quality at the very improve information integrity. Furthermore, the problems of
first moment, containing management of quality issue inconsistent format and poor compatibility exist in the
database, segment assembly quality, hidden project, and process of converting different formats of models. It is
inspection reports [21,22], which is shown in Fig. 11. necessary to further study the international standard of data
storing of IFC format based on BIM to achieve a better
model compatibility. In addition, the current BIM model
cannot adaptively be integrated with the finite element
analysis software for tunnel engineering, which is another
motivation to study the integration pattern and the technical
route in the future work.
ACKNOWLEDGMENT
We gratefully thank the anonymous reviews for their
valuable feedback. This research was supported by the
Science and Technology Research and Development Key
Program of China Railway Corporation (CRC) under grants
Figure 10. 2D Quality Management of Shield Tunnel. No. 2016X002 and No. 2017G001-B. This research was also
supported by the Science and Research Major Program of
China Railway Research Institute (CRRI) under grants No.
2016YJ098. Any opinions, findings, and conclusions
expressed in this material are those of the authors and do not
necessarily reflect the views of the CRC and CRRI.

REFERENCES
[1] China Railway BIM Alliance, “Railway Engineering Information
Classification and Coding Standards (Version 1.0),” Railway
technological innovation, vol. 1, 2015.
Figure 11. 3D Quality Management of Shield Tunnel Based on BIM.

288
[2] China Railway BIM Alliance, “Railway Engineering Entity Structural [13] B. Li, Y. Ma, and L. Wang, “The safety information management and
Decomposition Guide (Version 1.0),” Railway technological Application in Tunnel excavation construction based on BIM
innovation, vol. 6, 2014. technology,” Journal of Dalian Jiaotong University, vol. 35, 2017, pp.
[3] J. Zhu, and F. Tan, “Application of BIM Technology in Project 84-87.
Schedule Management System,” Project Management Technology, [14] Q Wu, W. Shi, H. Qi, and Y. Zou, “The whole process BIM
vol. 5, 2014, pp. 38-42. simulation and analysis research of extra large foundation pit
[4] Y. Rezgui, S. Boddy, M. Wetherill and G. Cooper, “Past, present and construction,” Engineering Construction, vol. 45(5), 2013, pp. 20-24.
future of information and knowledge sharing in the construction [15] S. Zhang, F. Boukamp, and J Teizer, “Ontology-based semantic
industry: Towards semantic service-based construction,” Computer- modeling of constmction safety knowledge 㸸 Towards automated
Aided Design, vol. 43(5), 2011, pp. 502-505. safety planning for job hazard analysis(JHA),” Automation in
[5] Tsinghua University BIM project group, “Research on China Constmction, vol. 52, 2015, pp. 29-41.
Building Information Model Standard Framework,” China [16] A. Yildiz, I. Dikmen, M. Birgonul, K. Ercoskun, and S. Alten, “A
Construction Industry Publishing, Beijing. knowledge-based risk mapping tool for cost estimation of inter-
[6] R. de Laat, and L. Van Berlo, “Integration of BIM and GIS: The national construction projects,” Automation in Construction, vol. 43,
development of the CityGML GeoBIM extension,” Advances in 3D 2014, pp. 144-155.
Geo-Information Sciences, 2011, Heidelberg: Springer-Verlag, pp. [17] J Du, R. He, and L Dai, “Ontology-based Analysis on the Early
211-225. Warning of the Surface Subsidence in the Process of Tunnel Shield
[7] H. Lv, P. Li, S. Tang, Q. Zhu and L. Xu, “Transformation Method Project,” Journal of Information Technology in Civil Engineering and
from BIM Model to GIS Model in Different Levels of Details,” Architecture, vol. 8(4), 2016, pp. 100-108.
Geomatics World, vol. 23(4), 2016, pp. 64-70. [18] H. Zhang, S. Chen, and X Tan, “Research on the mechanical behavior
[8] E. Karan, and J. Irizarry, “Extending BIM interoperability to of a segment of a shield tunnel adjacent to a pile foundation,” Modern
preconstruction operations using geospatial analyses and semantic Tunnelling Technology, vol. 46(6), 2012, pp. 101-107.
web services,” Automation in Construction, vol. 53, 2015, pp. 1-12. [19] J Lai, J Qiu, Y Pan, X Cao, C Liu, and H Fan, “Comprehensive
[9] K. Chmelina, K. Rabensteiner, and G. Krusche, “A Tunnel monitoring and analysis of segment cracking in shield tunnels,”
Information System for the Management and Utilization of Geo- Modern Tunnelling Technology, vol. 52(2), 2015, pp. 186-191.
Engineering Data in Urban Tunnel Projects,” Geotechnical and [20] F. Ye, C. He, S. Wang, “Analysis of mechanical characteristic of
Geological Engineering, vol. 31(3), 2013, pp. 845-859. shield tunnel segments lining and its influence during construction,”
[10] H. Guo, H. Li, G. Chan, and M. Skitmore, “Using game technologies Rock and Soil Mechanics vol. 32(6), 2011, pp. 1801-1807.
to improve the safety of construction plant operations,” Accident [21] L. Zhao, S. Zhai, and F. Chen, “Application of BIM technology in
Analysis and Prevention, vol. 48, 2012, pp. 204-213. railway tunnel construction project,” Construction Technology vol.
[11] M. El-Mekawy, A. Östman, and I. Hijazi, “A unified building model 18, 2016, pp. 10-14.
for 3D urban GIS ISPRS,” International Journal of Geo-Information, [22] G. Yu, M. Hu, and X. Gao, “Three-dimensional visualization system
vol. 1(2), 2012, pp. 120-145. of shield tunnel construction management based on BIM,” Modern
[12] V. Benjaoran, and S. Bhokha, “An integrated safety management Tunnel Technology, vol. 1, 2016, pp. 1-5.
with construction management using 4D CAD model”, Safety
Science, vol. 48(3), 2010, pp. 395-403.