Вы находитесь на странице: 1из 1

Government of Nepal

Ministry of Physical Infrastructure and Transport


Department of Roads
Division Road Office, Baglung

Comparative Chart

Drilling/Boring for Sub-Soil Investigation of Laxmikunda Bridge, Badigaad Khola, Burtibaang (Burtibaang to 0)
Contract No: DROBLG-3371574-2074/75- Budget Head No: 3371574
Sakhuwa Engineering Sky Star Engineering Social Development &
Estimate Consultancy Pvt. Ltd., Consultancy Pvt. Ltd., Engineering Consultancy
Lalitpur Gothathar, Kathmandu Services Pvt. Ltd.,
SN Particulars Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount
(excluding (excluding (excluding (excluding (excluding (excluding (excluding (excluding
VAT) VAT) VAT) VAT) VAT) VAT) VAT) VAT)
Drilling/Boring for Sub-Soil Investigation of
1
Laxmikunda Bridge, Badigaad Khola, Burtibaang
Drilling/Boring 0 to 16 m gravel,peebles,cobbles &
1.a RM 16 10867.89 173886.24 10,500.00 168000.00 10,600.00 169600.00 10,700.00 171200.00
Boulders, Soft & Hard Rocks (Type_2)
1.b Transportation of Personnel Job 1 16500.00 16500.00 16,000.00 16000.00 16,500.00 16500.00 16,300.00 16300.00
1.c Transportation of Equipment Job 1 22000.00 22000.00 22,000.00 22000.00 22,500.00 22500.00 23,000.00 23000.00
Total excluding VAT 212386.24 206000.00 208600.00 210500.00
VAT 13% 27610.21 26780.00 27118.00 27365.00
Total with VAT 239,996.45 232,780.00 235,718.00 237,865.00
Rank 1 2 3

The lowest evaluated bidder is: M/S Sakhuwa Engineering Consultancy Pvt. Ltd., Lalitpur

Prepared By: Checked By: Approved By: