ID Task Name Duration Start Finish % Complete 26 Feb '18 9 Apr '18 21 May '18 2 Jul '18 13 Aug '18 24 Sep '18 5 Nov '18 17 Dec '18 28 Jan '19 11 Mar '19 22 Apr '19 3 Jun '19 15 Jul '19 26 Aug '19 7 Oct '19 18 Nov '19
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M
1 Release Schedule March 2017 354.21 dys 21/08/2017 14/01/2019 3%
2 CR514 Offer Milestones 8 dys 27/06/2018 6/07/2018 0%
3 Offer Submitted 0 dys 27/06/2018 27/06/2018 100% 27/06
4 Offer Review Period 7 dys 28/06/2018 6/07/2018 0% MTM
5 Purchase Order Received 0 dys 6/07/2018 6/07/2018 0% 6/07
6 MTM Milestones 201 dys 4/09/2017 27/06/2018 47%
7 Input Received 201 dys 4/09/2017 27/06/2018 47%
8 Scope of Work 0 dys 6/10/2017 6/10/2017 100%
9 System Architecture Drawing 0 dys 26/06/2018 26/06/2018 0% 26/06
10 Signalling Design Specification 0 dys 26/06/2018 26/06/2018 0% 26/06
11 Signalling Arrangement Plans 0 dys 26/06/2018 26/06/2018 0% 26/06
12 Bit Lists 1 dy 27/06/2018 27/06/2018 0%
13 MCD Bit List 1 dy 27/06/2018 27/06/2018 0%
14 Control Tables 1 dy 27/06/2018 27/06/2018 0%
15 MCD Control Tables 1 dy 27/06/2018 27/06/2018 0%
16 Screen Design Requirements (mock-ups) 1 dy 26/06/2018 26/06/2018 0%
17 Regular Screen mockups 1 dy 26/06/2018 26/06/2018 0%
18 Detailed Screen mockups 1 dy 26/06/2018 26/06/2018 0%
19 Overview Screen mockups 1 dy 26/06/2018 26/06/2018 0%
20 Fringe Box Screen mockups 1 dy 26/06/2018 26/06/2018 0%
21 IL-TCMS ICD 9 dys 26/09/2017 6/10/2017 100%
22 Other ICDs (e.g. TNSI) 0 dys 30/11/2017 30/11/2017 100%
23 Interlocking Data 201 dys 4/09/2017 27/06/2018 0%
24 MCD IFPM Data 1 dy 27/06/2018 27/06/2018 0%
25 CIS, PRIDE Data 1 dy 27/06/2018 27/06/2018 0%
26 Timetables 1 dy 27/06/2018 27/06/2018 0%
27 Paths Data 1 dy 27/06/2018 27/06/2018 0%
28 Trigger Distance Data 0 dys 4/09/2017 4/09/2017 100%
29 Correction Factors 0 dys 15/12/2017 15/12/2017 100%
30 Preliminary Design Submission (T-15) 0 dys 1/02/2018 1/02/2018 0%
31 Detailed Design Submission (T-10) 0 dys 15/02/2018 15/02/2018 0%
32 IFC Design Submission (T-5) 0 dys 1/03/2018 1/03/2018 0% 1/03
33 MTM Simulator Build (T-5) 0 dys 1/03/2018 1/03/2018 0% 1/03
34 Commissioning (T) 0 dys 15/03/2018 15/03/2018 0% 15/03
35 Siemens Release Milestones 292.21 dys 15/11/2017 14/01/2019 0%
36 Project Start 0 dys 25/06/2018 25/06/2018 0% 25/06
37 Input Information Review Complete (Start of Implementation) 0 dys 28/06/2018 28/06/2018 0% 28/06
Project: MTM NEPA Project Schedule Critical Task Baseline Milestone Rolled Up Baseline Group By Summary Manual Summary Rollup
Date: 12/07/2018 Critical Task Progress Summary Rolled Up Baseline Milestone Inactive Task Manual Summary
Critical Rolled Up Task Rolled Up Progress Inactive Milestone Start-only
Critical Split Rolled Up Critical Task Split Inactive Summary Finish-only
Page 1
NEPA Mcleod Stage 2 - Critical Path 12/07/2018
ID Task Name Duration Start Finish % Complete 26 Feb '18 9 Apr '18 21 May '18 2 Jul '18 13 Aug '18 24 Sep '18 5 Nov '18 17 Dec '18 28 Jan '19 11 Mar '19 22 Apr '19 3 Jun '19 15 Jul '19 26 Aug '19 7 Oct '19 18 Nov '19
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M
62 Amend Functional Spec (DD) and Internal Review 2 dys 27/07/2018 30/07/2018 0% Hanu Tirumaleswara
63 Functional Specification Customer Review (DD) 3 dys 31/07/2018 2/08/2018 0% MTM
64 Functional Specification Customer Review (FD) and Internal Review 4 dys 3/08/2018 8/08/2018 0% Local Engineer Data,Local Engineer Test
Project: MTM NEPA Project Schedule Critical Task Baseline Milestone Rolled Up Baseline Group By Summary Manual Summary Rollup
Date: 12/07/2018 Critical Task Progress Summary Rolled Up Baseline Milestone Inactive Task Manual Summary
Critical Rolled Up Task Rolled Up Progress Inactive Milestone Start-only
Critical Split Rolled Up Critical Task Split Inactive Summary Finish-only
Page 2
NEPA Mcleod Stage 2 - Critical Path 12/07/2018
ID Task Name Duration Start Finish % Complete 26 Feb '18 9 Apr '18 21 May '18 2 Jul '18 13 Aug '18 24 Sep '18 5 Nov '18 17 Dec '18 28 Jan '19 11 Mar '19 22 Apr '19 3 Jun '19 15 Jul '19 26 Aug '19 7 Oct '19 18 Nov '19
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M
121 Greensborough Removals (Drawings for existing TD infrastructure) 2 dys 27/06/2018 30/07/2018 0% Adolfo Salazar
Project: MTM NEPA Project Schedule Critical Task Baseline Milestone Rolled Up Baseline Group By Summary Manual Summary Rollup
Date: 12/07/2018 Critical Task Progress Summary Rolled Up Baseline Milestone Inactive Task Manual Summary
Critical Rolled Up Task Rolled Up Progress Inactive Milestone Start-only
Critical Split Rolled Up Critical Task Split Inactive Summary Finish-only
Page 3