GENERAL TUNA CORPORATION

Brgy. Tambler, General Santos City


FACILITIES & ENGINEERING DEPARTMENT
Tel. No. 554-4191 to 93, local 2904

PROJECT TITLE: FABRICATION AND INSTALLATION OF 8-SETS DEAD ROLLERS @ LOCAL SKINNING AREA
LOCATION : MAIN PLANT

SCOPE OF WORKS:

The contractor shall supply labor, materials, consumables, tools, equipment, technical supervision and other related
forms/activities necessary in the completion of the following:

1. Fabrication and Installation of 8 sets dead rollers as per drawing, specifications and instructions
1.1. SS rollers 2ӯ x 620mm Р10 rollers for each set
1.2. SS plate 2mm thk
1.3. SS steel angle bar 1 ½”x1 ½”x2mm thk
1.4. Roller elevation from the floor line is approx. 1.0m

2. Housekeeping, disposal of unused items, and general cleaning.

SPECIFICATIONS AND PROVISIONS:


1. 5 calendar days to finish the project.
2. Install bracket/support as necessary. Use Stainless steel materials
3. Use TIG Welding and provide tigkleen for cleaning of welds.
4. Fabrication and assembly works shall be done in the contractor’s shop. Welding and joinery works shall be of standard
quality and shall be performed by TESDA-certified welders.
5. The contractor shall observe proper safety practices at all times during the entire construction/installation period. All
workers should wear proper PPE.
6. The contractor shall ensure the safety of company’s equipment during the duration of the project.
7. The contractor shall be responsible for the safety of its employees, tools and equipment during the duration of the
project.
8. The contractor shall be responsible for all wastes and garbage disposals in accordance to the plant’s GMP rules and
regulations. The area shall be left cleared and clean after the completion of the project.
9. The contractor shall be required to field out one project engineer/coordinator and one safety officer to supervise the
project at all times.
10. Deadline of submission of quotations shall be on MONDAY, DECEMBER 12, 2016 at 12:00nn. Late submission shall be
considered disqualified.

Prepared by: Manolito E. Nacua Jr.