Republic of the Philippines

NATIONAL IRRIGATION ADMINISTRATION


LIBMANAN-CABUSAO PUMP IRRIGATION SYSTEM(LCPIS)
Libmanan , Camarines Sur
TIME SUSPENSION REPORT
For the Month of January 4 - March 31, 2010

NAME OF PROJECT: Repair/Rehab of LCPIS - Package A


LOCATION : Libmanan, Camarines Sur
CONTRACTOR: WCS CONSTRUCTION INC.
FUND SOURCE: NDC 5

Time suspension
Day Weather Remarks
Recommended
Jan. 4
to
Jan. 31 24 days
Due to the water delivery schedule for
Feb.01 Dry cropping season, the sections of main
to canal covered by the proposed canal lining
Feb.28 24 days are always full of water from Mondays to
Saturdays of every week.
Mar. 01
to
Mar. 31 27 days

Total Suspension of time recommended this period 75 days


Total suspension of time recommended previously 176 days
Grand Total to Date 251 days
Original Contract Time (Calendar days) 120 days
Date Effectivity of Contract (Date NTP Received) August 14, 2010
Original Expiry Date December 12, 2010
Revised Expiry Date After Suspension and Extension April 22, 2010

Prepared by: Verified and Submitted by:

ARNEL A. NORBERTO NESTOR A. CORTES


Project-in-Charge Officer-in-Charge
Republic of the Philippines
NATIONAL IRRIGATION ADMINISTRATION
LIBMANAN-CABUSAO PUMP IRRIGATION SYSTEM(LCPIS)
Libmanan , Camarines Sur
TIME SUSPENSION REPORT

NAME OF PROJECT: Repair/Rehab of LCPIS - Package G


LOCATION : Libmanan, Camarines Sur
CONTRACTOR: 3RB Construction and Supply
FUND SOURCE: Fund 101

canal
Day Weather Remarks
Recommended

April 1 -18 18 days Water delivery schedule had been re-schedule


from April 1 to April 18 upon request of IA.

April 19 - 30 12 days Location of the work is at lateral A, upstream


of the main canal
May 1-16 16 days the contractor cannot work on these days
since lateral A is utilized as outlet for the
excess water along main canal

May 17 - 31 15 days Land soaking and land preparation


period for Wet Season
water delivery is continous from May 17
June 1 -30 30 days up to June 30, 2010.

Total Suspension of time recommended this period 91 days


Total suspension of time recommended previously 117 days
Grand Total to Date 208 days
Original Contract Time (Calendar days) 120 days
Date Effectivity of Contract (Date NTP Received) August 12, 2009
Original Expiry Date December 10, 2009
Revised Expiry Date After Suspension and Extension July 6, 2010

Prepared by: Verified and Submitted by:

ARNEL A. NORBERTO NESTOR A. CORTES


Project-in-Charge Officer-in-Charge