Академический Документы
Профессиональный Документы
Культура Документы
Ans:
He was helping contractor for his own interest as he wanted to go home in time. It is
against ethics to take money.
Case Study 2
Theory or Practice?
There is a debate in the coatings industry. Some people think inspectors are part of
the application team and should be able to contribute knowledge of how
equipment is set up and operated.
Others think inspectors are independent quality controllers and should be
completely separate from the applicator and his/her problems. In this case, the
inspectors need to understand when work complies with the specified
requirements but don’t need to understand the fine details of how they are applied.
Should the inspector be capable of operating blast cleaning or spray application
equipment? What does your group think?
Answer Yes or No and give at least 3 reasons for your decision. Please write your
answers on a flip chart.
Ans:
Inspector need not be capable of operating blast cleaning or spray application
equipment, but at the same time he should be knowledgeable enough to know
1. how the blasting / painting equipment works,
2. what precautions to be taken to avoid probable defects (ensure proper mixing in
correct proportion, proper induction time, application before pot life, WFT
check)
3. what safety measures to taken to avoid safety hazard (eg deadman valve in
blasting, tip guard for airless, proper PPEs, flameproof fitting)
Case Study 4
Razorback Petroleum, a large, independent oil refiner, was nearing completion of its
$200 million refinery expansion project. For years, the off-loading and crude oil
storage facilities at Razorback’s refinery on the sea coast had been inadequate.
Construction was in its final phase. In fact, the only task remaining was coating the
four new million-gallon crude oil storage tanks.
Completion had originally been scheduled for the previous September. Various
delays had occurred, and it was now early March of the following year.
Razorback had let the coating contract to Black Coatings, Inc., a locally known and
highly respected coating applicator owned by Al Black.
John Simmons stared out over the hood of his pickup truck at the seemingly endless
line of cars in front of him. “Just my luck to get put on assignment at the
Channelside refinery,” he muttered.
John regularly worked at one of Razorback’s manufacturing plants that makes
plastic products from waste byproducts collected from Razorback‘s refineries and
other operations. Several years ago John had worked entirely in manufacturing
quality control. When the plant shut down for major retooling and maintenance, he
had been temporarily assigned to inspect some maintenance painting work.
One thing led to another. John had begun to appreciate the importance of a good
coating job and how coatings could save Razorback thousands of dollars annually.
John had been self-taught until recently, when Razorback sent him to an intensive
training program on coating inspection.
It was no surprise at all to John when Ralph Stone, Razorback’s quality assurance
manager, assigned him to the Channelside project.
John remembered the telephone call as though it were just yesterday. In fact, it was
just yesterday that he found out about his new assignment.
“Ralph always was one for surprises,” John remarked to one of his coworkers. “He
wants me to meet him up at the Channelside refinery tomorrow at eight o’clock
sharp. Says he wants me to inspect the last part of the coating job at that new tank
installation, and he wants me to be at the pre-job meeting.”
6.1 Case Study 1-D Page 2
Coating Inspector Program Level 1
© NACE International, 2003
October 2007
Even though the sun had risen an hour earlier, the morning was still gloomy from a
combination of fog and the air pollution that always seemed to surround the
industries at Channelside. It was exactly 8:00 when John walked into the meeting
room for the pre-job conference.
“Well, Gentlemen and Lady, it’s good to see you here this morning.” Ralph Stone
did not have what could be called a commanding presence, but everyone listened
intently when he brought the meeting to order. As quality assurance manager,
Ralph was smart, tough, and well connected in the company; nobody wanted to get
on his bad side.
“Most of you know each other, but I see some new faces. Let’s take a minute to
introduce ourselves. I’m Ralph Stone, quality assurance manager here at
Razorback’s Channelside Refinery.”
“Stan Layton. I’m Razorback’s lead design engineer on this project. Ralph asked
me to sit in on this meeting in case any clarifications or changes to the coating spec
are necessary. One of my new engineers wrote this spec, so we might have a few
rough spots to iron out.”
“Jim Smith. I’m with Acme Contractors, the company that built the addition.”
“Bob Johnson, production manager. I’ll get to use this facility if it’s ever finished.
These delays are costing Razorback a mint of money.”
“Ann Stevens, safety engineer. We’ve had 457 days without a lost time accident.
I’d like to see us make 500, and I’ll be counting on all of you to follow the safety
rules to help make that happen.”
“John Simmons. I’m with quality assurance at our plant over at Bayview. Ralph has
had me assigned here to be the coating inspector on this job.”
“I’m Nate Beckley. Good to meet all of you! I’m a sales representative for
Maxicoat Systems. We’re supplying all the coatings being used on this job.”
“George Schmidt, purchasing agent here at Channelside. I want to make sure this
project doesn’t go over budget any more than it already has.”
Last to introduce himself was Al Black. “Al Black, here, owner of Black Coatings,
Inc. George, you can count on us to bring this project home for exactly what we
tendered. ‘Black Ink’--that’s our motto. Bob, we’ll have our end of this project
done on schedule. You can count on us.”
1.What problems, if any, do you think may come about on this job as a result of
enforcing the specifications as written?
Ans:
1.Areas to be masked not given.
2. Coating application workmenlike manner: Requalification details not given
3. Surface profile of 75 microns, range not provided
4. Method of checking profile not given
5. Maximum time laps between blasting & painting not mentioned
6. Coaltar product details not given
7 Coating thickness per not given
8. Total coating thickness of 450microns, range not given
9 Coating thickness measurement standard not given
10. Holiday inspection standard, voltage type of instrument to be used not given
11. Inspection stages, hold point, reference standard, inspection format not given
3. What does John need to find out in the pre-job conference in addition to those
points that must be clarified in the specifications?
???
4. What inspection equipment does John need to perform his job?
1. Surface Profile gauge , Testex tape
2. SSPC VIS 1, ISO 8501-1
3. Bresle Patch & conductivity meter
4. Pressure sensitive tape for dust level inspection
5. Thermo hygrometer, Whirling hygrometer psychometric charts
6. Surface Temperature meter
7. WFT gauge
8. DFT meter
9. Holiday detector
Case Study 5
Ans:
1. Coating thickness range not given. Coating thickness range shall be given eg. 5 to 6 mills
2. Holiday detection standard & equipment not mentioned Coating shall be checked for holiday
using Low DC voltage holiday detector in accordance with NACE Standard SP0188
3. Acceptable dust level not given. Ensure blast cleaned surface is free from dust , acceptable
dust level as per ISO 8502-3, rating shall be maximum 2
4. Cleaning water details not given, surface cleanliness details not given. After removing old
coating with chemical stripper ABC, clean the surface with DM water having conductivity <5
micro Siemen/ cm to ensure surface is chemically clean. pH of the cleaned surface shall be
between 7 to 8.
5. Workmanship standard not given. Coating applicator shall be qualified as per ASTM D4227
or ASTM D 4228
Case Study 6
3/4. Patches touch up having overspray & some sanded areas are still visible. To resolve the issue
following steps need to be taken
A. Sample patch touch up to be done as per specification at one location & take approval from
Simon for all future repair.
B. Feathering to be done at touch-up locations to have smooth transition at touch up location &
previous coating.
Simon Peabody of Impeccable Inspections, Inc., arrived for work at his new
assignment at 7:00 a.m. sharp, as scheduled. He recently had been relocated to this
new assignment after political conflicts on a previous job.
Upon arrival on the site, Simon met with representatives of the contractor and the
owner who were constructing a high-pressure gas transmission line on the outskirts
of a large metropolitan area. The pipe on the job had been shop-coated with two
coats of coal-tar epoxy and delivered to the job site with the ends blasted and
covered with plastic. Upon welding, the pipe was 100% ultrasonic tested to ensure
there were no weld porosities or voids. The joints were then coated using miniature,
prepackaged kits of the same coal-tar epoxy that was used to coat the pipe in the
shop.
The contract documents stated there would be weekly inspections of the protective
coating system by an independent NACE-Certified Coating Inspector—Level 3.
Although the job had been underway for almost two months, the contractor had only
recently begun to receive and lay pipe. At this time, the contractor had installed 18
joints of pipe, which were exposed in the ditch and ready for inspection.
The coating specification called for field testing of the coating by high-voltage
holiday test at 2,500 V, thickness testing in accordance with SSPC PA-2, and a
visual inspection for defects such as runs and sags. The specification specifically
noted that destructive tests were not to be performed on the pipe after it had reached
the job site.
Simon performed his thickness tests and found the coating to be within the limits of
the specification. The overall appearance of the protective coating looked good. As
Simon performed the holiday test, however, he noticed as he passed the probe over a
welded joint that the patch material seemed to be disbonded where it feathered out
onto the shop-applied coating. Curious, Simon pulled out his pocket knife and found
that he could run the blade beneath the coating and remove the patch material quite
easily. Upon examination, Simon found that the same condition existed at each
welded joint. Alarmed at this, Simon went to discuss the matter with the contractor
and the owner’s representative.
The reception Simon received was explosive. The owner’s representative had a fit
when Simon told him that he had peeled the patch coating away from every joint.
The contractor told Simon that he has no right to perform destructive tests that were
specifically excluded by the specification. The contractor estimated that he would
incur losses in excess of $25,000 from delays while the joints were recoated and
cured sufficiently for backfill. The contractor further told Simon that he would sue
Impeccable Inspections, Inc. for those and any other losses that were incurred due to
Impeccable Inspections’ “incompetence.”
Ans. I would find out the reason for coating disbondment with photographic
evidence & shall submit the report to customer representative
Case Study 8
You are the inspector (the only inspector) on a crude storage tank coating job. The
specification calls for a thickness of 100 to 150 μm (about 4 to 6 mils) per coat,
with a total of three coats to be applied. The contractor is on a fixed-price contract,
and is required to supply the paint as part of the contract. For some reason,
attaining the specified thickness has been difficult, although after the first coat you
are pleased that the contractor has become less difficult to deal with on this point.
You have been very carefully taking and recording thickness measurements, as per
the specification, after the first and second coat. There have been a number of
areas where the minimum thickness was just barely attained. You have recorded a
number of areas where the thickness is just 200 μm (about 8 mils). The gauge you
are using is the latest microprocessor DFT gauge, which records readings in
memory and can perform a variety of statistical functions, etc.
Retiring to your room for the night, you are making good use of your evening
hours by organizing your field notes. This done, you have taken out your DFT
gauge to check the calibration, and find that you have been using the gauge
incorrectly and that your readings have all been off by at least 50 μm (2 mils) on
the high side. You calculate that the thinnest spots on the tank are not 200 μm
(about 8 mils), but only about 150 μm (about 6 mils).
You know that the contractor, who has been making the painters be quite careful
to check their work frequently with a WFT gauge, is going to want to apply the
coating at a WFT which will give as close to 100 μm (about 4 mils) for the third
pass, which will result in a total thickness of 250 μm (about 10 mils) in most
places, instead of the 12 required by the specification.
How would you deal with the situation?
1. I will inform the contractor/ owner rep. about the actual thickness & error in
the instrument.
2. I will call meeting of Owner rep., Paint manufacturer & contractor. I will
check the paint data sheet for maximum typical thickness that can be achieved
in one coat & if it is possible to achieve total thickness within required range,
In consultation with owner rep. & paint manufacturer’s rep contractor shall be
asked to apply the coating as per paint manufacturers guideline. If typical
thickness per coat is not enough to provide required total DFT, as contractor is
also aware of the fact that it is difficult achieve the thickness I will ask him to
give one more coat to achieve required coating thickness
Case Study 8
It’s Monday morning and John has another new inspection job to start; the
contractor is starting on Wednesday of this week. Arriving at the office he sees
that his boss has laid the specification on his desk with a simple note stating, “Let
me know what you need.”
In reading the specification John notices right away that it is very vague as to what
inspection procedures and documentation are going to be required. Simply put, it
says, new rail car interiors to be lined with two full coats of an amine epoxy
coating of 4 to 6 mils per coat and is to be holiday-free. All work is to be
performed at the fabricators yard in Tulsa, OK, between February 12 and March
15. Surface preparation shall be in accordance with NACE No. 1/SSPC-SP 5 over
a surface accepted by the coating inspector to be adequate for immersion service.
No salts are allowed to be present, the welds are to be rounded, and the humidity
in the cars is to be maintained between 40 to 50% with temperatures held to
coating manufacturers’ requirements until final cure. Hardness readings are to
meet ASTM requirements and pull-off adhesion testing shall be performed to meet
a minimum of 900 pounds per square inch and “X” cuts shall be a minimum
reading of 5. The contractor will touch up all areas where destructive testing is
performed.
There will be a pre-job on Wednesday morning before work begins, and John has
plenty of questions. What does your team consider should be included in John’s
list of standards, reference materials, and equipment required for him to
adequately perform and back up his job with only the information provided?
Please list your team’s response on a flip chart and be ready to present in _____
minutes. It is now _____; be ready to present at ____.
Standards:
1. SSPC VIS 1 –Pictorial STD for blasting
2. ISO 8502-6/9 :Soluble salts by bresle patch
3. ASTM 4417 : Surface Profile
4. ISO 8502-3 – Dust level on blasted surface
5. ASTM D 3359:Crosscut adhesion
6. NACE SP 0188
7. ASM D4541: Pull off adhesion
8. SSPC PA-2
9. ASTM D 4220 – Barcol Hardness
Equipment:
1. Surface profile gauge with testex tape
2. Pressure sensitive tape for dust & crosscut adhesion
3. Pull off adhesion tester, cutter
4. Holiday detector
5. Barcol hardness tester
6. Coating thickness meter
7. Thermohygrometer
8. Surface temp. meter
9. Solvent meter