Вы находитесь на странице: 1из 14

Project: MIDHILLS Details: LANDSCAPE STRUCTURE

Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA

Notes:-
The quantity for excavation for column stump, pile cap,
footing, lift pit, basement and the like shall be stated in
cubic metre without desribing the depth classification.
The excavation, backfilling and subsequent removal of
earth shall not be measured separately but included in
the description.
The slab / bedding and wall / retaining wall are
measured in cubic metre (m3) irrespective of thickness

Excavate, get out and part return; backfilling suitable


selected excavated materials; spreading, levelling and
compacting in layers and ram; removing excavated
material off site to contractor's own tips
A for non suspended slab and walkway, and the like 218 m3

Blinding; Plain insitu concrete (Grade 15)


B 50mm thick underneath slab 1,041 m2

Hardcore & subgrade to be well compacted with


mechanical rammer
C 230mm thick underneath slab 1,041 m2

Approved 0.25mm thick polythene sheet (1000


gauge), damp proof membrane laid in lean concrete
and over a well compacted sub-base
D to underneath of slab 1,041 m2

To Collection
CostX Vincent Tan Associates 1/1
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

Vibrated reinforced concrete (Grade 30) as


described to:-
Planter Box
A Generally 5 m3
Non Suspended Slab
B Generally of various thickness 135 m3
Feature Wall 1& 3
C Generally 11 m3
Feature Pond
D Generally 38 m3
Pump Room
E Generally 9 m3
Disable Ramp
F Generally 2 m3
Walkway
G Generally of various thickness 30 m3
RC Kerb
H Generally 1 m3

To Collection
CostX Vincent Tan Associates 1/2
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

High tensile steel Bar Reinforcement as described


to:-
Planter Box
A 10mm diameter bars 1,287 kg
Non Suspended Slab
B 10mm diameter bars 1,769 kg
Feature Wall
C 10mm diameter bars 287 kg
D 12mm diameter bars 476 kg
Feature Wall 1& 3
E 10mm diameter bars 915 kg
F 12mm diameter bars 2,745 kg
Pump Room
G 10mm diameter bars 899 kg
Disable Ramp
H 10mm diameter bars 277 kg
Walkway
I 10mm diameter bars 1,088 kg
RC Kerb
J 10mm diameter bars 143 kg

Fabric Reinforcement; BRC Steel; measured nett- no


allowance made for laps;
Non Suspended Slab
K Reference A10; 6.16 kg/m2 862 m2
Feature Wall
L Reference A6; 2.22 kg/m2 6 m2
Walkway
M Reference A8; 3.95 kg/m2 194 m2

To Collection
CostX Vincent Tan Associates 1/3
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

Sawn Formwork as described to:


Planter Box
A Sides of planter box 24 m2
Non Suspended Slab
B Edges of floor slabs exceeding 250mm high not 36 m
exceeding 500mm high
Feature Wall
C Sides of feature wall 77 m2
Feature Wall 1& 3
D Sides of feature pond 177 m2
Pump Room
E Sides of pump room 84 m2
Disable Ramp
F Sides and soffit of disable ramp; strutting not exceeing 7 m2
3.50m high
Walkway
G Edges of walkway ; not exceeding 250mm high 58 m
RC Kerb
H Edges of kerd ; not exceeding 250mm high 16 m

To Collection
CostX Vincent Tan Associates 1/4
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

WATERPROOFING SYSTEM
PENTENS T-308 crystallization waterproofing admixture
waterproofing system complete with zero Formaldehyde
and VOC's content <1.21g/L into ready mixed concrete
at the rate of 0.8% of total cement content all as per
manufacturer's detail
A To feature pond 1 &3 38 m3
B To pump room 9 m3

PENTENS T-100 water-based PU bituminous


waterproofing membrane with zero Formaldehyde and
VOC's content <0.53g/L @ 2.25kg/m2 in three (3) layers
complete with T-805 Non-Shrink Grout (Angle Fillet)
25mm x 25mm, treatment to outlet with PENTENS
T-100 water based PU waterproofing membrane @ 2
layers/1.5kg/m2 all as per manufacturer's detail
Internally
C To wall and floor of planter box 26 m2
D To wall and floor of feature pond 1 & 3 117 m2
E To wall and floor of pump room 58 m2

To Collection
CostX Vincent Tan Associates 1/5
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

STAIRCASE CONSTRUCTION
Vibrated reinforced concrete (Grade 30) as
described to:-
Staircase
A Generally to strings, steps, landing beams and landing 6 m3
slabs

High tensile steel Bar Reinforcement as described


to:-
Staircases and strings
B 10mm diameter bars 185 kg

Fabric Reinforcement; BRC Steel; measured nett- no


allowance made for laps;
Staircases and strings
C Reference A8; 3.95 kg/m2 29 m2

Sawn formwork as described to :


D Soffit of staircase; strutting not exceeding 3.50m high 20 m2
E Sides and soffit of landing beam; strutting not exceeding 19 m2
3.50m high
F Edge of stringer; extreme width 300mm 19 m
G Risers; not exceeding 250mm deep 77 m

H ANY OTHER ITEMS


i.).........................................................
ii.).........................................................
iii.).......................................................

To Collection
CostX Vincent Tan Associates 1/6
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

01 OPEN PLAZA (Continued)

COLLECTION
Page 1/1:
Page 1/2:
Page 1/3:
Page 1/4:
Page 1/5:
Page 1/6:
01 OPEN PLAZA
Carried to Summary:

CostX Vincent Tan Associates 1/7


Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

02 SWIMMING POOL

Vibrated reinforced concrete (Grade 30) as


described to:-
Pool Shower
A Generally 3 m3

High tensile steel Bar Reinforcement as described


to:-
Pool Shower
B 10mm diameter bars 109 kg
C 12mm diameter bars 207 kg

Fabric Reinforcement; BRC Steel; measured nett- no


allowance made for laps;
Pool Shower
D Reference A6; 2.22 kg/m2 1 m2
E Reference A8; 3.95 kg/m2 4 m2

Sawn Formwork as described to:


Pool Shower
F Sides of Shower Panel 31 m2

To Collection
CostX Vincent Tan Associates 2/1
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

02 SWIMMING POOL (Continued)

WATERPROOFING SYSTEM
PENTENS T-308 crystallization waterproofing admixture
waterproofing system complete with zero Formaldehyde
and VOC's content <1.21g/L into ready mixed concrete
at the rate of 0.8% of total cement content all as per
manufacturer's detail
A To pool shower 3 m3

PENTENS T-100 water-based PU bituminous


waterproofing membrane with zero Formaldehyde and
VOC's content <0.53g/L @ 2.25kg/m2 in three (3) layers
complete with T-805 Non-Shrink Grout (Angle Fillet)
25mm x 25mm, treatment to outlet with PENTENS
T-100 water based PU waterproofing membrane @ 2
layers/1.5kg/m2 all as per manufacturer's detail
Internally
B To wall and floor of pool shower 31 m2

C ANY OTHER ITEMS


i.).........................................................
ii.).........................................................
iii.).......................................................

To Collection
CostX Vincent Tan Associates 2/2
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

02 SWIMMING POOL (Continued)

COLLECTION
Page 2/1:
Page 2/2:
02 SWIMMING POOL
Carried to Summary:

CostX Vincent Tan Associates 2/3


Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

03 GREEN ARCHWAY ENTRANCE

Notes:-
The quantity for excavation for column stump, pile cap,
footing, lift pit, basement and the like shall be stated in
cubic metre without desribing the depth classification.
The excavation, backfilling and subsequent removal of
earth shall not be measured separately but included in
the description.
The slab / bedding and wall / retaining wall are
measured in cubic metre (m3) irrespective of thickness

Excavate, get out and part return; backfilling suitable


selected excavated materials; spreading, levelling and
compacting in layers and ram; removing excavated
material off site to contractor's own tips
A for non suspended slab, and the like 632 m3

Imported crusher run; spreading, levelling and


compacting in layers
Base courses
B 300mm deep 1,032 m2

Imported sand; spreading, levelling and compacting


in layers
Sub-base courses
C 100mm deep 1,032 m2

To Collection
CostX Vincent Tan Associates 3/1
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

03 GREEN ARCHWAY ENTRANCE (Continued)

Vibrated reinforced concrete (Grade 30) as


described to:-
Non Suspended Slab
A Generally 206 m3

Fabric Reinforcement; BRC Steel; measured nett- no


allowance made for laps;
Non Suspended Slab
B Reference BRC A10; 6.16 kg/m2 2,105 m2

Sawn Formwork as described to:


Non Suspended Slab
C Edges of slab; not exceeding 250mm high 308 m

PRECAST CONCRETE KERB


Kerb; fair finish to exposed surfaces; complete with
outlet holes, dropper kerb and crossing kerb on and
including 250mm thick concrete bedding with haunching
one side; complete with and including all necessary
excavation, formwork, reinforcement, disposal of surplus
materials and backfilling, painting with approved paint
D To road kerb; straight and curved 117 m

E ANY OTHER ITEMS


i.).......................................................
ii.).......................................................
iii.)......................................................

To Collection
CostX Vincent Tan Associates 3/2
Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

03 GREEN ARCHWAY ENTRANCE (Continued)

COLLECTION
Page 3/1:
Page 3/2:
03 GREEN ARCHWAY ENTRANCE
Carried to Summary:

CostX Vincent Tan Associates 3/3


Project: MIDHILLS Details: LANDSCAPE STRUCTURE
Building: GREEN ARCHWAY ENTRANCE

Item Description Quantity Unit Rate Amount (RM)

COLLECTION SUMMARY PAGE NO

01 OPEN PLAZA 1/1 - 1/6


02 SWIMMING POOL 2/1 - 2/2
03 GREEN ARCHWAY ENTRANCE 3/1 - 3/2
Total Amount:

CostX Vincent Tan Associates 3/4

Вам также может понравиться