Bill PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III

INSTALLATION CHECK LIST FOR DUCTING WITH


ACCESSORIES & INSULATION

DRAWING NO. REV.


SYSTEM LOCATION
DESCRIPTION

Sr.
Description Yes No Remarks
No.
1 Confirm that the material is approved by Consultant
Route of ducting and duct support hangers are marked and
2 installed at correct spacing/height/locations as per approved
drawings.
Duct support angle edges are ground and painted after
3
cutting to size.

4 All the field joints are sealed properly by approved sealant.

Ducts are cleaned internally prior to fix at high level or in


5
position.

Check all drop rods are correct size, correct entries,


6
adequately fixed and correct length
All the components of duct system such as vanes, splitters,
volume control dampers, fire dampers, sound attenuator,
7
flexible duct connectors are installed with correct
accessories at correct location as per approved drawing.
Access panels are provided as indicated on approved
8
drawings.
Ducts passing through walls are having proper clearance to
9
fill the approved sealant/ fire retardant uniformity.

The flexible connectors to the equipments are installed


10
without any stress/misalignment.
11 Check all fire/smoke dampers/hand balance dampers are
free and open.
12 All Remote control devices etc. are installed
Fixing of approved insulation on external surface of duct
13
surface

DOCUMENT NUMBER ISSUE PAGE NO. DATE

BILT/J-225/QAP/AC-07 REV. 0 1 of 2 16-09-2009


Bill PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III

INSTALLATION CHECK LIST FOR DUCTING WITH


ACCESSORIES & INSULATION

DRAWING NO. REV.


SYSTEM LOCATION
DESCRIPTION

Fixing of rigid insulation between duct support and duct


14 bottom at duct resting area to prevent damaging of
insulation.
Sr.
Description Yes No Remarks
No.
Acoustic insulation is fixed as per the approved method and
15 manufacturer’s recommendations where indicated on
consultant’s approved drawing.
Release as per site measurement all final fix of ducting, such
16
as grills/diffusers, collars, plenum etc.
Incorporate requirement of control and measuring
17
instrument, access doors for maintenance
Leveling and alignment of final fix with architectural
18
finishes.

CONSULTANTS COMMENTS:

ENGINEER/SUPERVISOR (BILT) NAME SIGN.

QA / QC ENGINEER (BILT) NAME SIGN.

CONSULTANT/CLIENT NAME SIGN

DOCUMENT NUMBER ISSUE PAGE NO. DATE

BILT/J-225/QAP/AC-07 REV. 0 1 of 2 16-09-2009