PROJECTION OF WORK PROGRESS AS AT 12.05.2018 (ORIGINAL MIP REV.

00)

AS AT AS AT
NO ACTIVITY/TASK 05.05.2018 12.05.2018
SCHEDULE % COMPLETE
ACTUAL % COMPLETE
CURRENT % DELAY
WASH WATER COLLECTION & SLUDGE BALANCING TANK
A Partial Backfilling (Drywells Area)
i Partial backfilling & compaction (1st stage) 70.00% 100.00%
B Repair of Cold Joints, Waterproofing & Painting
i Cleanup site 30.00% 75.00%
DEWATERING CONTAINER PLATFORM (GEOTUBE)
A Excavation Works & Hardcore
i To excavate, level & compact ground 50.00% 100.00%
ii To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 25.00% 100.00%
B Drain (Base)
i Install formwork, lay of 50mm thick lean concrete 30.00% 100.00%
ii Erect formwork, install reinforcement 30.00% 75.00%
C Drain (Wall - 2 sides)
i Install formwork, lay of 50mm thick lean concrete 30.00% 50.00%
D Ground Slab
i Install formwork, lay of 50mm thick lean concrete 30.00% 100.00%
ii Erect formwork, install reinforcement 30.00% 50.00%
E Ramp
i Install formwork, lay of 50mm thick lean concrete 30.00% 100.00%
ii Erect formwork, install reinforcement 30.00% 50.00%
POLYMER BUILDING
A Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk)
i Install reinforcement both ground beam & slab 30.00% 100.00%
ii Inspection 0.00% 100.00%
iii Concreting works 0.00% 100.00%
iv Curing works 0.00% 100.00%
v Dismantle formwork 0.00% 100.00%
B Column - 5.5m (0.25mm x 0.25mm)
i Install reinforcement 30.00% 80.00%
ii Erect formwork & bracing 30.00% 80.00%
iii Inspection 0.00% 80.00%
iv Concreting works 0.00% 80.00%
v Curing works 0.00% 53.33%
C Intermediate Beam (0.25mm x 0.5mm)
i Erect scaffold, stagging, t-prox & soffit 30.00% 100.00%
ii Install reinforcement 30.00% 100.00%
iii Erect formwork 30.00% 100.00%
iv Inspection 0.00% 100.00%
iv Concreting works 0.00% 100.00%
v Curing works 0.00% 53.33%
PROJECTION OF WORK PROGRESS AS AT 12.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 05.05.2018 12.05.2018
MECHANICAL WORKS
A Polymer Plant
i Mixing & Service Tank 20.00% 40.00%
ii Hopper, Feeder & Pump Skid 20.00% 40.00%
iii Local Control Panel 20.00% 40.00%
B Miscellaneous Works
Procurement
i Penstock & Valves 80.00% 100.00%
PROJECTION OF WORK PROGRESS AS AT 19.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 12.05.2018 19.05.2018
SCHEDULE % COMPLETE
ACTUAL % COMPLETE
CURRENT % DELAY
WASH WATER COLLECTION & SLUDGE BALANCING TANK
A Partial Backfilling (Drywells Area)
i Partial backfilling & compaction (2nd stage) 0.00% 25.00%
B Water Tightness Testing
i To backfill & compact outer perimeter of WWCT & SBT 0.00% 60.00%
DEWATERING CONTAINER PLATFORM (GEOTUBE)
A Drain (Base)
i Erect formwork, install reinforcement 75.00% 100.00%
ii Inspection 0.00% 100.00%
iii Concreting works 0.00% 100.00%
iv Curing works 0.00% 100.00%
v Dismantle formwork 0.00% 100.00%
B Drain (Wall - 2 sides)
i Erect formwork, install reinforcement 50.00% 80.00%
ii Inspection 0.00% 80.00%
iii Concreting works 0.00% 80.00%
iv Curing works 0.00% 80.00%
v Dismantle formwork & backfilling works 0.00% 80.00%
C Ground Slab
i Erect formwork, install reinforcement 50.00% 100.00%
ii Inspection 0.00% 100.00%
iii Concreting works 0.00% 100.00%
iv Curing works 0.00% 87.50%
D Ramp
i Erect formwork, install reinforcement 50.00% 100.00%
ii Inspection 0.00% 100.00%
iii Concreting works 0.00% 100.00%
iv Curing works 0.00% 87.50%
POLYMER BUILDING
A Column - 5.5m (0.25mm x 0.25mm)
i Install reinforcement 80.00% 100.00%
ii Erect formwork & bracing 80.00% 100.00%
iii Inspection 80.00% 100.00%
iv Concreting works 80.00% 100.00%
v Curing works 53.33% 100.00%
v Dismantle formwork & bracing 0.00% 100.00%
B Intermediate Beam (0.25mm x 0.5mm)
i Curing works 53.33% 100.00%
ii Dismantle scaffold, stagging, t-prox, soffit & formwork 0.00% 12.50%
C Roof Beam (0.25mm x 0.5mm)
i Erect scaffold, stagging, t-prox & soffit 30.00% 100.00%
ii Install reinforcement 30.00% 100.00%
iii Erect formwork 30.00% 100.00%
iv Inspection 0.00% 100.00%
C
PROJECTION OF WORK PROGRESS AS AT 19.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 12.05.2018 19.05.2018
iv Concreting works 0.00% 100.00%
v Curing works 0.00% 100.00%
vi Dismantle scaffold, stagging, t-prox, soffit & formwork 0.00% 12.50%
PROJECTION OF WORK PROGRESS AS AT 19.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 12.05.2018 19.05.2018
D Floor, Wall, Ceiling & Accessories
i Install 225mm thk. brickwall, tie with mortar - Team A & B 0.00% 50.00%
ii External plastering - Team A 0.00% 12.50%
iii Internal plastering - Team B 0.00% 12.50%
E U-Shaped Drain
i Excavation & levelling works 30.00% 100.00%
ii Erect formwork 30.00% 100.00%
iii Install reinforcement 30.00% 100.00%
iv Inspection 0.00% 100.00%
iv Concreting works 0.00% 100.00%
v Curing works 0.00% 100.00%
vi Dismantle formwork 0.00% 75.00%
F Apron & Ramp
i Backfilling, levelling & compaction works 0.00% 100.00%
ii Erect formwork, install reinforcement 30.00% 100.00%
iii Inspection 0.00% 100.00%
iv Concreting works 0.00% 100.00%
iv Curing works 0.00% 100.00%
v Dismantle formwork & cleanup site 0.00% 100.00%
MECHANICAL WORKS
A Polymer Plant
i Mixing & Service Tank 40.00% 50.00%
ii Hopper, Feeder & Pump Skid 40.00% 50.00%
iii Local Control Panel 40.00% 50.00%
B Miscellaneous Works
Procurement
i Submersible Pump (Portable & Gasoline Engine) 90.00% 100.00%
PROJECTION OF WORK PROGRESS AS AT 26.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 19.05.2018 26.05.2018
SCHEDULE % COMPLETE
ACTUAL % COMPLETE
CURRENT % DELAY
WASH WATER COLLECTION & SLUDGE BALANCING TANK
A Partial Backfilling (Drywells Area)
i Reinstate existing sump 0.00% 100.00%
ii Reinstate existing sewer pipes 0.00% 100.00%
iii Partial backfilling & compaction (2nd stage) 25.00% 100.00%
B Water Tightness Testing
i To fill up WWCT & SBT with water 0.00% 100.00%
ii Monitoring 0.00% 100.00%
iii To backfill & compact outer perimeter of WWCT & SBT 60.00% 80.00%
DEWATERING CONTAINER PLATFORM (GEOTUBE)
A Drain (Wall - 2 sides)
i Erect formwork, install reinforcement 80.00% 100.00%
ii Inspection 80.00% 100.00%
iii Concreting works 80.00% 100.00%
iv Curing works 80.00% 100.00%
v Dismantle formwork & backfilling works 80.00% 100.00%
B Ground Slab
i Curing works 87.50% 100.00%
ii Dismantle formwork 0.00% 100.00%
C Ramp
i Curing works 87.50% 100.00%
ii Dismantle formwork 0.00% 100.00%
iii To clean up site condition including levelling & compaction 0.00% 100.00%
POLYMER BUILDING
A Intermediate Beam (0.25mm x 0.5mm)
i Dismantle scaffold, stagging, t-prox, soffit & formwork 12.50% 100.00%
B Roof Beam (0.25mm x 0.5mm)
i Dismantle scaffold, stagging, t-prox, soffit & formwork 12.50% 100.00%
C Roof Truss, Covering & Accessories
i Deliver material for light gauge MS roof trusses on-site 75.00% 100.00%
ii Install prefabricated light gauge MS roof truss & bracing 0.00% 100.00%
iii Install purlins 0.00% 100.00%
iv Inspection 0.00% 100.00%
v Install concrete roof tiles & ridge cap 0.00% 50.00%
PROJECTION OF WORK PROGRESS AS AT 26.05.2018 (ORIGINAL MIP REV.00)

AS AT AS AT
NO ACTIVITY/TASK 19.05.2018 26.05.2018
D Floor, Wall, Ceiling & Accessories
i Install 225mm thk. brickwall, tie with mortar - Team A & B 50.00% 100.00%
ii Electrical wiring works - carry out by specialist team 0.00% 100.00%
iii External plastering - Team A 12.50% 100.00%
iv Internal plastering - Team B 12.50% 100.00%
v Rendering of floor, install tiles & skirting 0.00% 100.00%
E U-Shaped Drain
i Dismantle formwork 75.00% 100.00%
PIPEWORKS
A Installation Works
i Excavation & backfilling works 80.00% 100.00%
ii Pipe laying & jointing 80.00% 100.00%
iii Miscellaneous works 70.00% 80.00%
MECHANICAL WORKS
A Polymer Plant
i Mixing & Service Tank 50.00% 70.00%
ii Hopper, Feeder & Pump Skid 50.00% 70.00%
iii Local Control Panel 50.00% 70.00%
B Pipeworks
i Excavation & backfilling works 0.00% 50.00%
ii Pipe laying & jointing 0.00% 50.00%
ELECTRICAL WORKS
A Switchboard / MCC Panel
i Procurement & Fabrication of Panel 70.00% 75.00%
ii FAT Electrical Control and Switchboards 70.00% 100.00%
B Submain Cabling Works for MCC-SDP-Palong
i Procurement & Delivery of Cable 70.00% 75.00%
ii Installation works 50.00% 80.00%